HSE DEPARTMENT
INCREMENT II PKG I & II
CONTRACT NO. 6600041347, 6600042398
1. The issuer must stop work if ….(Select all 6. Who is responsible for safety at the work
that applies) site after a permit has been extended?
a) The issuer leaves the Job Site. a) The original issuer & receiver
b) More men are working than stated on the b) The person who countersigned the permit
permit. c) The one who originally did the joint site
c) The site was found to be unsafe inspection
d) The issuer loses his copy of the permit d) The issuer and receiver who signed the
extension
2. A pipe fitter cannot work on the same
7. What are the basic precautions for
pieces of equipment using welder’s permit
confined space entry? Select all that apply
because?
a) Assign a standby man, install lightning,
a) Welder’s are usually contractor
install air movers.
b) Gas test are not needed for pipe fitters
b) Take gas test
c) Each type of work involves different
c) Isolate, clean and purge equipment
hazards
d) Use PPE
d) Joint site inspection are not needed for
pipe fitters
8. What’s the purpose of joint site
3. If a work permit is not issued during an inspection?
emergency, what must be done to do the a) To check the availability of equipment and
work? manpower
b) To see the work plan and its
a) Superintendent must approve
implementation
b) All safety precaution must be taken
c) To discuss the work and identify its
c) Joint Site inspection
hazards and risk
d) To meet the worker and observe there
4. The issuer must stop work if ….
activities.
a) He cannot find the issuer
b) The work site becomes unsafe 9. What must be checked during joint site
c) The issuer leaves the site inspection? Select all items that apply.
d) The designated representative must leave
a) Safety devices
b) Equipment conditions
5. What is the purpose of the work permit
c) Gas test
system?
d) Attendance report
a) To insure that hot is not done in restricted
area. 10. Who is a permit issuer?
b) To authorize specific construction or
a) A qualified Saudi ARAMCO employee
maintenance work
b) A person certified to issue permit
c) To document where receiver start work for
c) A person nominated by his supervisor
time keeping
d) A person nominated by his manager
South Dhahran Home Ownership (SDHO) Project
HSE DEPARTMENT
INCREMENT II PKG I & II
CONTRACT NO. 6600041347, 6600042398
11. The safety of work site is a sole 17. Why do we use work permits in
responsibility of permit issuer? hazardous areas?
Note: 80% score must be obtained to be Work Permit Issuer and Work Permit Receiver.