Saudi Aramco Work Permit System (G.I. 2.

100)
Pre-Certification Examination

3.
T
Name: Badge Number:

Position: Company:

Department: Signature:

Date: Score ( % )

Instruction: Read carefully the following questions, he issuer left the jobsite
4. The job site was found to be unsafe
review all the multiple choices and encircle the number
of the best answer. Passing grade: (85%)

1. What happens if work must continue past the time the


original permit was to expire?
1. Work can continue until the job is complete
2. Keep working, but tell the issuer
3. Stop work and come back next day
4. Renew the permit 7. What must the issuer do with the permit after he stops
work?
2. Who is the responsible for safety at the work after 1. Close, then extend the permit
permit has been extended? 2. Give his copy to the receiver
1. The original issuer and receiver 3. Get a countersignature
2. The old issuer, because he did the joint site inspection 4. Write the reason on the permit
3. The issuer and the receiver who sign the extension
4. No one after permit has been extended 8. A pipe fitter cannot work on the same piece of
equipment using a welder’s work permit because:
3. Work permits can be issued up to 30 days if: 1. Each type of work involves different hazard
1. Is highly unlikely that conditions will change 2. Joint site inspection are not needed for pipe fitters
2. Only cold work will be done 3. Welders are usually contractor.
3. The work site is far away 4. Gas tests are not needed for pipe fitter
4. The receiver cannot close the work permit
9. Work permit can be issued up to
4. Who must sign the work permit issued for up to 30 1. To receiver shift
days? 2. One operational shift
1. Receiver and designated representative 3. 24 consecutive hours
2. The designated representative 4. Two - ten hour shift
3. Operations and maintenance division head
4. Operation foreman, issuer and recover
10. Who must sign a work permit to extend it?
5. If the work permit is not issued during the emergency, 1. Then new area foreman and new issuer
what must be done to do the work? 2. Superintendent's countersignature is required
1. Superintendent must approve 3. The new issuer and receiver
2. Wear Scott air - packs 4. The new issuer, receiver and gas tester
3. Joint site inspection
4. All safety precaution must be taken 11. When must be work permit closed?
1. Before another permit is issued
6. The issuer must stop work if: 2. When the work is finished or crew leaves
1. More men working than stated on the permit 3. After gas test taken
2. The issuer lost his copy of the permit 4. When the issuer leaves the jobsite
Saudi Aramco Work Permit System (G.I. 2.100)
Pre-Certification Examination

12. Who must sign the work permit to close it? 20. What can the designated representative do?
1. Competent person 1. Sign the work permit
2. Gas tester, issuer and receiver 2. Authorize the receivers responsibilities
3. Designated representative 3. Accept the receiver's responsibilities
4. Issuer and receiver 4. Inspect the work site

13. Why must work permit be closed?


1. To allow gas test to be taken 21. What joint responsibility does Issuer and Receiver
2. To allow the permit to be extended Share?
3. To communicate the status of the work 1. Taking gas tests
4. To stop all hot work 2. Naming the designated representative
3. During the work.
14. What is one hazard with doing hot work? 4. Safety at the work site.
1. Vapor pressure
2. Ignition source 22. When can an issuer decide a work permit is not needed
3. Flash point in a restricted area?
4. Cold work 1. They are always required a work permit in restricted area.
2. When the work is cold work
15. The use of air compressor in an operating-area 3. When he decides the work is low risk
requires which work permit? 4. When a joint site inspection is not needed
1. Release
2. Entry 23. Examples of low risk work could include?
3. Hot 1. Spray painting, water-washing, & turbine work
4. Cold 2. Brush painting, abrasive blasting, & sweeping
3. Cold work, light work & nondestructive testing
16. Why do we install tags as well as locks? 4. Sweeping, visual inspection & minor cleaning.
1. To record a gas test
2. To explain why the lock is installed 24. When would the issuer make sure equipment have
3. To lists safety precaution been properly prepared for maintenance work?
4. To record purging cycle 1. When the permit is closed
2. After issuing a WP?
17. Who from the work crew, install lock? 3. During the JSI
1. One member from each work crew 4. After getting counter signatures
2. Every member of the crew
3. The foreman and the receiver 25. Why do receivers go on the joint site inspection with
4. The issuer and the gas tester issuer?
1. For the receiver to take gas tests
18. The issuer must try to start - up equipment at the field 2. To start the work
switch after it has been isolated and before work starts to 3. To check the fire watch's certification
make sure: 4. To discuss hazard and risks.
1. It has been purged and cleaned
2. There is no gas in the area 26. When a fire watch be assigned?
3. The receiver's tag in installed 1 When gas tests are over 0.0% LEL
4. It cannot accidentally start 2 For any hot works
3 For high-risk jobs.
19. Why is designated representative sometimes used? 4 Whenever a fire could occur.
1. The receiver did not come to work
2. The issuer may be busy and need help 27. What are the (2) important reasons for using work
3. The gas tester .found high LEL readings permits?
4. Too many safety problems were found 1. To designate representatives & communicate
Saudi Aramco Work Permit System (G.I. 2.100)
Pre-Certification Examination

2. To track contractors & manage emergencies 3. Fire Watch, Fire Extinguisher & Work Permit
3. To track work hours & contractor names 4. Fire Watch, Fire Extinguisher & Fire Blanket
4. To communicate & control work.
36. What would the issuer requires when welding or in
28. A work permit lists.
service hydrocarbon equipment.
1. Minimum safety precaution.
1. Fire watch
2. Maximum safety precaution.
2. Fire department
3. Government safety precaution.
3. Fire blanket
4. OSHA safety precaution.
4. Fire station

29. Work permits must be issued for:


37. What must the fire watch be?
1. Specific tools and general locations
1. As issuer
2. Specific work at a specific locations
2. Trained
3. General work at a general location
3. Certified
4. General equipment at small work sites
4. A receiver
30. A restricted area requires:
38. A Fire watch has to know how to?
1. That work permits are issued.
1. Take a gas test
2. That receiver's respond to emergencies.
2. Operate process equipment
3. That extension is short time.
3. Be a receiver
4. That certificates are issued.
4. Operate fire equipment given to him
31. What is a fire triangle?
39. What do we call a person who is required to be at a job
1. Oxygen, Heat & Fuel site because of a special skill he has?
2. Heat and Fuel 1. Competent person
3. Fuel and Oxygen 2. Designated Rep
4. None of the above 3. Standby Man
32. Choose three (3) things that are needed before 4. Certified
allowing entry into confined space?
1. Gas tests, fire extinguisher and barricade 40. Is a firewatcher assigned in a welding activity can
2. Lighting, standby man and air mover leave the area while the work is going on without any
3. Fire watch, air mover and gas tests information?
4. Air mover, respirator and countersignature
1. NO
33. What are the three (3) type of gas we take? 2. YES
1. Flammable gas, inert gas, heavy gas 3. NO PROBLEM
2. Oxyacetylene, flash point, sulfides
3. Flash point, vapor pressure, specific gravity 41. What type of fire extinguisher is used to extinguish
4. Oxygen, flammable gas, toxic materials Class-C fires (Electrical Fire)?
1. Dry chemical powder
34. What is oxygen deficiency? 2. Water
1. A lower than normal amount of oxygen 3. CO2 (carbon dioxide)
2. A higher than normal level of hydrogen sulfide 4. Foam
3. Too much oxygen
4. Oxygen that is not pure 42. What happen to the operations locks and tags installed
on equipment when operators change shifts?
35. What are the three (3) major requirements needed 1. The keys are usually transferred to the new shift
before a Hot Work activity can start? 2. The locks and tags must be removed
1. Water, Fire Extinguisher & Work Permit 3. The tags must be destroyed
2. Fire Blanket, Water & Fire Watch 4. The locks must be replace
Saudi Aramco Work Permit System (G.I. 2.100)
Pre-Certification Examination

2. Take gas tests and check Scott Air Pack


43. The reason equipment must be de-energized and 3. Train the Fire watch and renew the permit
depressurized before work is started is because: 4. Read the permit and agree to all conditions.
1. Electricity can be wasted
2. People can be injured
3. Locks and tags will be lost
4. Gas can be wasted

44. What would be a good example of when the receiver


must stop work?
1. Materials have not yet arrive
2. He cannot wait for the countersignature
3. He hear an emergency alarm
4. The back hoe run out of fuel

45. What might happen if the safety problem arises and


the receiver does not stop work?
1. A fire, injury or accident
2. Countersignature become void
3. His certificate expires
4. The work permit expires
46. Flammable liquids, oil, grease, gases are examples of:
1. Class A fires
2. Class B fires
3. Class C fires
4. Class D fires
47. A nonflammable materials commonly used to purge
process equipment is.
1. Nitrate
2. Nitrite
3. Nitrous oxide
4. Nitrogen
48. Two common methods of cleaning process equipment
methods
1. Streaming and gas testing
2. Treating and clarifying
3. Purging and gas testing
4. Water washing and streaming

49. Equipment is isolated to make sure it cannot be.


1. Started-up, leak or cause electric shock
2. Shut down by accident
3. Slip, trip or fall
4. Taken to stop for repairs

50. What 2 things must the receiver do before receiving a


WP?
1. Extend the permit and take gas tests

You might also like