Technical Information

Handling of Switching order documentation


for MV_HV switching operations

Area of application
This document applies to: Country, company, department

Mechanical Induction Installation Update Precast concrete tower – Installation


Electrical Rotor blade Grid connection Concrete repair Precast concrete tower – Prestressing

E-10 E-26 E-40/6.44 E2 E-66 E-82 E-112


E-12 E-30 E-40/6.44 E3 E-66/18.66 E-82 E2 E-115
E-15 E-30/3.30 E-44 E-66/18.70 E-82 E3 E-115 E2
E-16 E-32 E-48 E-66/20.70 E-82 E4 E-126
E-17 E-33 E-53 E-70 E4 E-92 E-126 E2
E-18 E-40 E-58/10.58 E-70 E4-2 E-101 E-126 EP4
E-20 E-40/6.44 E1 E-58/12.58 E-70 E4-3 E-101 E2

Battery Charging System HV_Sub MewaCt1 PDI_1 SCADA_ESLD


CLC HYDRO MSpg.-Erf PDI_2 SI
Display MCU MV_Dis RTU SOLAR
FCU METEO MV_Spc SAI STATCOM
GDA MewaBI1 MV_Sub SCADA_DOS HV_Sub

Document details

© ENERCON GmbH. All rights reserved.


Document ID TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV
switching operations

Confidentiality INTERNAL

Date Language DCC Plant/department


2016-02-25 en DD Service Deutschland GmbH/Grid Operation

Revision table
Revision Date Section Change
000 2016-02-25 - Document created

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations i of ii
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

Table of contents
1 General information ...............................................................................................................1
1.1 When to carry out work......................................................................................................1
1.2 Reason for the information ................................................................................................ 1
2 Preparatory work ....................................................................................................................2
3 Required work steps ..............................................................................................................2
3.1 Switching order documentation .........................................................................................2
3.2 Filling out the “Switching order documentation” form .........................................................2
3.3 Filing the report .................................................................................................................5
4 Contact....................................................................................................................................5

© ENERCON GmbH. All rights reserved.

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations ii of ii
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

1 General information
This document replaces Technical Instruction document TD-GO-01-ger-xxx-14-027. Its content has
been updated according to the most recent findings.

1.1 When to carry out work


The tasks described in this information must be carried out when obtaining a switching order from
the switching authorisation dispatcher of the Grid Operation department. This applies to line
switching and for any switching operations in HV substations.

1.2 Reason for the information


Documenting switching orders prevent mix-ups and misunderstandings after the order is obtained.
During the switching conversation the order must be documented in writing by using the form
“Switching order documentation”.

© ENERCON GmbH. All rights reserved.

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations 1 of 5
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

2 Preparatory work
Before obtaining and documenting the switching order, attention should be paid to the procedure
instruction “Performing of switching operations” (TD-GO-05-xx-006).
Also the information for safe use “Working in medium-voltage and high-voltage areas”
(BA_bl_1040) and the technical information “MV+HV switching authorisations”
(TD-esc-02-de-xx-15-017) must be known and understood.

3 Required work steps

3.1 Switching order documentation


Contact a switching authorisation dispatcher of the Grid Operation department using the respective
telephone number (as per TD-esc-02-de-xx-15-017 MV+HV switching authorisation) and obtain the
switching order.
The document number from the header of the report has to be communicated to the switching
authorisation dispatcher, because it has to be entered on the system.
Document the switching order in the “Switching order documentation” form
(TD-esc-03-de-xx-16-036).

3.2 Filling out the “Switching order documentation” form

© ENERCON GmbH. All rights reserved.


Location:
e.g. - Name of the wind farm
- Name of the transmission substation

Reason for the switching operation:


e.g. - Disconnection for repair of the medium-voltage switchgear WEC xxx
- Reconnection after connection of new WEC xxx
- Reconnection after tripping of substation circuit breaker

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations 2 of 5
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

Nominated person in control of electrical installation during work activity


Nominated person in control of the work activity:
Coordinate with the switching authorisation dispatcher of the Grid Operation Department, if
the responsibility for the electrical installation and / or the work activity lies at ENERCON or
on the customer side.
Are switching operations to be carried out, where obtaining a switching order is necessary,
the ENERCON Grid Operation coordinator is mostly responsible for the electrical
installation. But in single cases it could be also that e.g. that the project manager is
responsible. Customer responsibility for the electrical installation exists e.g. at grid works
outside of ENERCON WEC’s, if the switch-off-point is not operated by ENERCON.
The nominated person in control of the work activity is usually the ENERCON technician
who is carrying out the switching operations, but could also lay in few cases e.g. on the
customer side. The responsibilities lay in normal cases either both at ENERCON or both on
the customer side.
Afterwards enter the names of the nominated person in control of the electrical installation

© ENERCON GmbH. All rights reserved.


during work activity as well as the nominated person in control of the work activity in the
lines.
If the responsibility is on customer side, the name doesn’t need to be entered if not known.

Date and time:


Enter the date and time when the switching order has been obtained

Name:
Document the full name of the switching authorisation dispatcher of the Grid Operation
department issuing the switching order. The current list of switching authorisation
dispatcher is stored in the ISI database in the MV+HV switching authorisation
(TD-esc-02-de-xx-15-017).

To:
Fill in full name and the personnel ID number of the receiver of the switching order. Confirm
with the signature afterwards the receipt of the switching order. This information is required
for assigning the form at a later time.

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations 3 of 5
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

Location:
Fill in the location of the switching operation.
- Serial number of the wind turbine
- Substation
- Exact designation of the switchgear (for switching operations in HV substations)
e.g. - E1

© ENERCON GmbH. All rights reserved.


- H1

Panel:
Fill in the panel of the switchgear in this line.
e.g. - Panel 1
- Panel 2
Or for switching operations in transmission substations:
e.g. - Q01
- Q03

Measure:
Fill in the individual switching operations in this field.
e.g. - Switch off CB
- Switch off DC
- Switch on ES

Completed:
Once the switching operations of the respective line have been done,
this field has to be ticked.

All switching operations of one panel can be noted in one line.


To do so, the abbreviations as per the report can be used for
the designations of the switching devices.

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations 4 of 5
Technical Information
Handling of Switching order documentation
for MV_HV switching operations

Comments:
Fill in important additional information for the switching operation.
e.g. - Issue permit to work after disconnection
- Provide instruction after disconnection

3.3 Filing the form


After the switching operations have been completed, file the form in the “Grid Operation
instructions + forms” folder for a period of one year.

© ENERCON GmbH. All rights reserved.


4 Contact
Switching authorised employees Switching authorised Grid Operation coordinators
Switching authorised Grid Operation coordinators Operational Administration at Grid Operation

TD-esc-02-de-en-16-004 Rev000 Handling of Switching order documentation for MV_HV switching operations 5 of 5