Professional Documents
Culture Documents
PART 1 GENERAL
1.1 REFERENCES
This section applies to certain sections of. This section applies to all
sections of Division 26 and 33, ELECTRICAL and UTILITIES, of this
project specification unless specified otherwise in the individual
sections. This section has been incorporated into, and thus, does not
apply to, and is not referenced in the following sections.
1.3 DEFINITIONS
Page 1
indicate adequate clearance for operation, maintenance, and replacement
of operating equipment devices.
1.7 WARRANTY
Page 2
b. Start up, proper adjustment, operating, lubrication, and
shutdown procedures.
c. Safety precautions.
Not used.
Electrical installations shall conform to IEEE C2, NFPA 70, and IEC
60364 (Electrical Installations of Buildings) and other requirements
specified herein.
PART 2 PRODUCTS
Page 3
2.1 FACTORY APPLIED FINISH
PART 3 EXECUTION
-- End of Section --
Page 4
SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
10/07
PART 1 GENERAL
1.1 REFERENCES
Control Panels
Pumps with Motors Switchgear
Light Fixtures
Motor Control Centers
Switchboards (Floor Mounted)
Solar Heating Units
The Contractor shall design the bracing in accordance with UFC 3-310-04
and additional data furnished by the Contracting Officer. Resistance to
lateral forces induced by earthquakes shall be accomplished without
consideration of friction resulting from gravity loads. UFC 3-310-04
uses parameters for the building, not for the equipment in the building;
therefore, corresponding adjustments to the formulas shall be required.
Loadings determined using UFC 3-310-04 are based on strength design;
therefore, AISC 325 shall be used for the design. The bracing for the
electrical equipment and systems shall be developed by the Contractor.
Page 1
1.3 EQUIPMENT REQUIREMENTS
Engine-Generators
Switch Boards and Switch Gears
Motor Control Centers
1.4 SUBMITTALS
Equipment Requirements
Equipment Requirements; G
Page 1
PART 2 PRODUCTS
Sway bracing materials (e.g. rods, plates, rope, angles, etc.) shall be
as specified in Contractor Designed Bracing
PART 3 EXECUTION
PART 1 GENERAL
1.1 REFERENCES
Page 3
NFPA 780 (2011) Standard for the Installation of
Lightning Protection Systems
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
1.2 DEFINITIONS
1.3 SUBMITTALS
Panelboards[; G]
Cable trays[; G]
Receptacles[; G]
Circuit breakers[; G]
Switches[; G]
Motor controllers[; G]
Page 4
Manual motor starters[; G][; G, [ ]]
Transformer tests[; G]
Page 5
Products manufactured more than 3 years prior to date of delivery to
site shall not be used, unless specified otherwise.
1.5 MAINTENANCE
1.6 WARRANTY
PART 2 PRODUCTS
ANSI C80.1, UL 6.
Page 6
2.2.5 Plastic-Coated Rigid Steel and IMC Conduit
UL 1.
UL 360.
2.2.7 Fittings for Metal Conduit, EMT, and Flexible Metal Conduit
UL 1660.
Page 7
2.5.5 Solid Bottom-Type Cable Trays
2.7.3 Clock Outlet for Use in Other Than Wired Clock System: Not Used
Wires and cables shall meet applicable requirements of NFPA 70 and IEC
60502 for type of insulation, jacket, and conductor specified or
indicated. Wires and cables manufactured more than 12 months prior to
date of delivery to site shall not be used.
2.9.1 Conductors
Page 8
remote-control, alarm and signal circuits, 0.5mm2
a. 380/220V three-phase
2.9.3 Insulation
ASTM B1, solid bare copper wire for sizes 10mm2 and smaller diameter;
ASTM B8, Class B, stranded bare copper wire for sizes 16mm2 and larger
diameter.
2.9.7 Wire and Cable for 400 Hertz (Hz) Circuits: Not Used
Page 9
2.9.13 Cord Sets and Power-Supply Cords
IEC Standards
2.12 SWITCHES
2.14 RECEPTACLES
Page 10
2.14.2 Weatherproof Receptacles
IEC/TSE, duplex type for mounting in standard outlet box. Device shall
be capable of detecting current leak of 10 mA or greater and tripping
per requirements of local wiring regulations. GFI protection shall be
made at branch circuit panels feeding the receptacle
2.14.5 Plugs
2.15 PANELBOARDS
2.15.1 Enclosure
Page 11
Outdoor cabinets shall be of IEC IP54 raintight with[ conduit hubs
welded to the cabinet]. Front edges of cabinets shall be form-flanged
or fitted with structural shapes welded or riveted to the sheet steel,
for supporting the panelboard front. All cabinets shall be so
fabricated that no part of any surface on the finished cabinet shall
deviate from a true plane by more than 3 mm. Holes shall be provided in
the back of indoor surface-mounted cabinets, with outside spacers and
inside stiffeners, for mounting the cabinets with a 15 mm clear space
between the back of the cabinet and the wall surface. Flush doors shall
be mounted on hinges that expose only the hinge roll to view when the
door is closed. Each door shall be fitted with a combined catch and
lock, except that doors over 600 mm long shall be provided with a
three-point latch having a knob with a T-handle, and a cylinder lock.
Two keys shall be provided with each lock, and all locks shall be keyed
alike. Finished-head cap screws shall be provided for mounting the
panelboard fronts on the cabinets.
IEC compliant, and panelboard type shall have been specifically heat
rise tested for use on non-linear loads. Panelboard shall be heat rise
tested in accordance with IEC 61439-3, except with the neutral assembly
installed and carrying 200 percent of the phase bus current during
testing. Verification of the testing procedure shall be provided upon
request. Two neutral assemblies paralleled together with cable is not
acceptable. Nameplates for panelboard rated for use on non-linear loads
shall be marked "SUITABLE FOR NON-LINEAR LOADS"and shall be in
accordance with paragraph FIELD FABRICATED NAMEPLATES. Provide a neutral
label with instructions for wiring the neutral of panelboards rated for
use on non-linear loads.
IEC 60947 and NFPA 70. Provide with "push-to-test" button, visible
Page 12
indication of tripped condition, and ability to detect and trip on
current imbalance of [10mA or greater for personnel protection,][ and][
30mA per equipment protection.]
IEC 60947. Individual molded case circuit breakers with voltage and
continuous current ratings, number of poles, overload trip setting, and
short circuit current interrupting rating as indicated. Enclosure type
as indicated.
2.21 MOTORS
DIN and TSE. Provide the size in terms of kW, or kVA, or full-load
current, or a combination of these characteristics, and other
characteristics, of each motor as indicated or specified. Determine
specific motor characteristics to ensure provision of correctly sized
starters and overload heaters. Motors shall be designed to operate at
full capacity with voltage variation of plus or minus 10 percent of
motor voltage rating. Unless otherwise indicated, motors rated 745 Watts
and above shall be continuous duty type.
Page 13
requirements for premium efficiency electric motors .
Page 14
amperes.][ Provide controllers in hazardous locations with
classifications as indicated].
All control wire shall be stranded tinned copper switchboard wire with
600-volt flame-retardant insulation in accordance with IEC 60332.
Current transformer secondary leads shall be not smaller than 6mm2. The
minimum size of control wire shall be No. 1.5mm2. Power wiring for 380
volt circuits and below shall be of the same type as control wiring and
the minimum size shall be 2.5mm2. Special attention shall be given to
wiring and terminal arrangement on the terminal blocks to permit the
individual conductors of each external cable to be terminated on
adjacent terminal points.
b. Load Type: Load terminal blocks rated not less than 600 volts and
of adequate capacity shall be provided for the conductors for NEMA
Size 3 and smaller motor controllers and for other power circuits,
except those for feeder tap units. The terminals shall be of either
the stud type with contact nuts and locking nuts or of the removable
screw type, having length and space for at least two indented
terminals of the size required on the conductors to be terminated.
For conductors rated more than 50 amperes, screws shall have
hexagonal heads. Conducting parts between connected terminals shall
have adequate contact surface and cross-section to operate without
overheating. Each connected terminal shall have the circuit
designation or wire number placed on or near the terminal in
permanent contrasting color.
Page 15
secondaries wound for correct control circuit voltage. Size
transformers so that 80 percent of rated capacity equals connected
load. Provide disconnect switch on primary side.. One secondary lead
shall be fused; other shall be grounded.
IEC IP Standards
Page 16
protective device].[Main protective device shall be[ molded case
circuit breaker] [ Arrange busing so that control center can be
expanded from both ends.] Interconnecting wires shall be copper.
Terminal blocks shall be plug-in-type so that controllers may be removed
without disconnecting individual control wiring.
Copper ground bus shall be provided full width of motor control center
and shall be equipped with necessary lugs.
Provide disconnecting means capable of being locked out for machines and
other equipment to prevent unexpected startup or release of stored
energy in accordance with 29 CFR 1910.147. Mechanical isolation of
machines and other equipment shall be in accordance with requirements of
Division 23, "Mechanical."
Page 17
trays,] and other accessories for telecommunications outlets and pathway
in accordance with TIA-569 and as specified herein.[ Additional
telecommunications requirements are specified in Section 27 10 00,
BUILDING TELECOMMUNICATIONS CABLING SYSTEM.]
2.27.3 Backboards
UL 467. Ground rods shall be[ sectional type,] copper-clad steel, with
minimum diameter of 19 mm and minimum length[ of 3050 mm]
a. Predrilled copper busbar provided with holes for use with standard
sized lugs,
Page 18
b. Minimum dimensions of 6 mm thick by 100 mm wide for the TMGB[
and 50 mm wide for TGBs] with length as indicated;
Provide warning signs for flash protection in accordance with NFPA 70E
for switchboards, panelboards, industrial control panels, and motor
control centers that are in other than dwelling occupancies and are
likely to require examination, adjustment, servicing, or maintenance
while energized. Provide field installed signs to warn qualified persons
of potential electric arc flash hazards when warning signs are not
provided by the manufacturer. The marking shall be clearly visible to
qualified persons before examination, adjustment, servicing, or
maintenance of the equipment.
Provide parallel type surge protective devices which comply with IEC
60099 at the service entrance [, panelboards] Provide surge protectors
in a [ IP21_] enclosure per IEC Standards. Provide the following modes
of protection:
Page 19
Neutral to ground ( N-G )
Phase to ground ( L-G )
The minimum MCOV (Maximum Continuous Operating Voltage) rating shall be:
EMI/RFI filtering shall be provided for each mode with the capability to
attenuate high frequency noise. Minimum attenuation shall be 20db.
PART 3 EXECUTION
3.1 INSTALLATION
Page 20
3.1.3 Hazardous Locations
3.1.4.1 Labels
Install pull wires in empty conduits. Pull wire shall be plastic having
minimum 890-N force tensile strength. Leave minimum 915 mm of slack at
each end of pull wire.
Unless indicated otherwise, conceal conduit under floor slabs and within
finished walls, ceilings, and floors. Keep conduit minimum 150 mm away
from parallel runs of flues and steam or hot water pipes. Install
conduit parallel with or at right angles to ceilings, walls, and
structural members where located above accessible ceilings and where
conduit will be visible after completion of project.
Page 21
3.1.6.1 Restrictions Applicable to Aluminum Conduit: Not Used
g. Do not use when the enclosed conductors must be shielded from the
effects of High-altitude Electromagnetic Pulse (HEMP).
(5) Do not use above grade, except where allowed in this section
for rising through floor slab or indicated otherwise.
(6) Do not use when the enclosed conductors must be shielded from
the effects of High-altitude Electromagnetic Pulse (HEMP).
Page 22
Plastic-coated rigid steel; plastic-coated steel IMC; PVC, Type EPC-40.
Convert nonmetallic conduit, other than PVC Schedule 40 or 80, to
plastic-coated rigid, or IMC, steel conduit before rising through floor
slab.] Plastic coating shall extend minimum 150 mm above floor.
3.1.6.9 Conduit for Circuits Rated Greater Than 600 Volts: Not Used
Where conduits rise through floor slabs, curved portion of bends shall
not be visible above finished slab.
3.1.6.13 Stub-Ups
Page 23
construction, run conduit above ceiling. Do not support conduit by
ceiling support system. Conduit and box systems shall be supported
independently of both (a) tie wires supporting ceiling grid system, and
(b) ceiling grid system into which ceiling panels are placed.
Supporting means shall not be shared between electrical raceways and
mechanical piping or ducts. Installation shall be coordinated with
above-ceiling mechanical systems to assure maximum accessibility to all
systems. Spring-steel fasteners may be used for lighting branch circuit
conduit supports in suspended ceilings in dry locations.[ Support
exposed risers in wire shafts of multistory buildings by U-clamp hangers
at each floor level and at 3050 mm maximum intervals.] Where conduit
crosses building expansion joints, provide suitable[ watertight]
expansion fitting that maintains conduit electrical continuity by
bonding jumpers or other means. For conduits greater than 63 mm inside
diameter, provide supports to resist forces of 0.5 times the equipment
weight in any direction and 1.5 times the equipment weight in the
downward direction.
Fasten conduits to sheet metal boxes and cabinets with two locknuts
where required by NFPA 70, where insulated bushings are used, and where
bushings cannot be brought into firm contact with the box; otherwise,
use at least minimum single locknut and bushing. Locknuts shall have
sharp edges for digging into wall of metal enclosures. Install bushings
on ends of conduits, and provide insulating type where required by
NFPA 70.
Provide flexible steel conduit between 915 and 1830 mm in length for
recessed and semirecessed lighting fixtures[; for equipment subject to
vibration, noise transmission, or movement; and for motors]. Install
flexible conduit to allow 20 percent slack. Minimum flexible steel
conduit size shall be 16 mm diameter. Provide liquidtight flexible[
nonmetallic] conduit in wet and damp locations[ and in fire pump rooms]
for equipment subject to vibration, noise transmission, movement or
motors. Provide separate ground conductor across flexible connections.
Page 24
TIA-569[ and][ as indicated].
[Install and ground in accordance with NFPA 70. Install cable trays
parallel with or at right angles to ceilings, walls, and structural
members. Support[ in accordance with manufacturer recommendations but
at not more than [1830] mm intervals]. Adjacent cable tray sections
shall be bonded together by connector plates of an identical type as the
cable tray sections. For grounding of cable tray system provide No. 2
AWG bare copper wire throughout cable tray system, and bond to each
section, except use No. 1/0 aluminum wire if cable tray is aluminum.
Terminate cable trays 255 mm from both sides of smoke and fire
partitions. Conductors run through smoke and fire partitions shall be
installed in 103 mm rigid steel conduits with grounding bushings,
extending 305 mm beyond each side of partitions. Seal conduit on both
ends to maintain smoke and fire ratings of partitions. Penetrations
shall be firestopped in accordance with Section 07 84 00, FIRESTOPPING.
Provide supports to resist forces of 0.5 times the equipment weight in
any direction and 1.5 times the equipment weight in the downward
direction. ]
Page 25
supports with wood screws on wood, with bolts and expansion shields on
concrete or brick, with toggle bolts on hollow masonry units, and with
machine screws or welded studs on steel.[ Threaded studs driven in by
powder charge and provided with lockwashers and nuts[ or nail-type nylon
anchors] may be used in lieu of wood screws, expansion shields, or
machine screws.] In open overhead spaces, cast boxes threaded to
raceways need not be separately supported except where used for fixture
support; support sheet metal boxes directly from building structure or
by bar hangers. Where bar hangers are used, attach bar to raceways on
opposite sides of box, and support raceway with approved-type fastener
maximum 610 mm from box. When penetrating reinforced concrete members,
avoid cutting reinforcing steel.
3.1.10.1 Boxes
Boxes for use with raceway systems shall be minimum 40 mm deep, except
where shallower boxes required by structural conditions are approved.
Boxes for other than lighting fixture outlets shall be minimum 100 mm
square, except that 100 by 50 mm boxes may be used where only one
raceway enters outlet. Telecommunications outlets shall be a minimum of
[ 100 mm square by 54 mm deep][ 120 mm square by 54 mm deep][, except
for [wall mounted telephones] [and] [outlet boxes for handicap telephone
stations]]. Mount outlet boxes flush in finished walls.
Extension rings are not permitted for new construction. Use only on
existing boxes in concealed conduit systems where wall is furred out for
new finish.
Page 26
grommets in studs at each point through which cable passes, prior to
installation of cable.
3.1.15 Splices
Page 27
3.1.19 Grounding and Bonding
Provide In accordance with NFPA 70[ and NFPA 780]. Ground exposed,
non-current-carrying metallic parts of electrical equipment, metallic
raceway systems, grounding conductor in metallic and nonmetallic
raceways, telecommunications system grounds, [grounding conductor of
nonmetallic sheathed cables, ]and neutral conductor of wiring systems.[
Make ground connection at main service equipment, and extend grounding
conductor to point of entrance of metallic water service. Make
connection to water pipe by suitable ground clamp or lug connection to
plugged tee. If flanged pipes are encountered, make connection with lug
bolted to street side of flanged connection. Supplement metallic water
service grounding system with additional made electrode in compliance
with NFPA 70.][ Make ground connection to driven ground rods on
exterior of building.][ Interconnect all grounding media in or on the
structure to provide a common ground potential. This shall include
lightning protection, electrical service, telecommunications system
grounds, as well as underground metallic piping systems. Use main size
lightning conductors for interconnecting these grounding systems to the
lightning protection system.] Where ground fault protection is
employed, ensure that connection of ground and neutral does not
interfere with correct operation of fault protection.
Page 28
or pressure-connector type, except that pressure connectors or bolted
connections shall be used for connections to removable equipment.[ For
raised floor equipment rooms in computer and data processing centers, a
minimum of 4, one at each corner, ground buses shall be provided and
connected to the building grounding system. Connections shall be bolted
type in lieu of thermoweld, so they can be changed as required by
additions and/or alterations.]
3.1.19.4 Resistance
Provide power wiring for the connection of motors and control equipment
under this section of the specification. Except as otherwise
specifically noted or specified, automatic control wiring, control
devices, and protective devices within the control circuitry are not
included in this section of the specifications but shall be provided
under the section specifying the associated equipment.
3.1.23.1 Workmanship
Page 29
3.1.23.4 Continuation of Service
Furnish test equipment and personnel and submit written copies of test
results. Give Contracting Officer[ 5] working days notice prior to[
each] test[s].
Test wiring rated 600 volt and less to verify that no short circuits or
accidental grounds exist. Perform insulation resistance tests on wiring
16mm2 and larger diameter using instrument which applies voltage of
approximately 500 volts to provide direct reading of resistance.
Minimum resistance shall be 250,000 ohms.
Page 30
verify that the "line" and "load" leads are not reversed.
-- End of Section --
Page 31
MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS
10/07
PART 1 GENERAL
1.1 REFERENCES
1.2.1 Rules
Page 1
1.2.2 Coordination
1.2.4 Nameplates
c. Switchboards
f. Panelboards
1.3 SUBMITTALS
Page 2
submitted in accordance with the provisions of the Contract.
Drawings; G,
Shop Drawings; G,
Switchboards; G,
Panelboards; G,
Equipment; G,
1.5 MAINTENANCE
Page 3
1.5.1 Accessories and Tools
PART 2 PRODUCTS
2.1 CONNECTIONS
All bolts, studs, machine screws, nuts, and tapped holes shall be in
accordance with ASME B1.1. The sizes and threads of all conduit and
fittings, tubing and fittings, and connecting equipment shall be in
accordance with ASME B1.20.1. All ferrous fasteners shall have
rust-resistant finish and all bolts and screws shall be equipped with
approved locking devices. Manufacturer's standard threads and
construction may be used on small items which, in the opinion of the
Contracting Officer, are integrally replaceable, except that threads for
external connections to these items shall meet the above requirements.
Page 4
Molded case circuit breakers shall conform to the applicable
requirements of NEMA AB 1 and UL 489 and IEC 60947. The circuit
breakers shall be manually-operated, shall be quick-make, quick-break,
common trip type, and shall be of automatic-trip type unless otherwise
specified or indicated on the drawings. All poles of each breaker shall
be operated simultaneously by means of a common handle. The operating
handles shall clearly indicate whether the breakers are in "On," "Off,"
or "Tripped" position and shall have provisions for padlocking in the
"Off" position. Personnel safety line terminal shields shall be
provided for each breaker. The circuit breakers shall be products of
only one manufacturer, and shall be interchangeable when of the same
frame size. Where indicated on the drawings, circuit breakers shall be
provided with shunt trip devices. The contacts shall be suitable for 125
volts dc and shall reset when the breaker is reset.]
Except as otherwise noted, the circuit breakers, of frame sizes and the
trip unit ratings as shown on the drawings, shall be provided with
combination thermal and instantaneous magnetic or solid state trip
units. The Government reserves the right to change the indicated trip
ratings, within frame limits, of the trip devices at the time the shop
drawings are submitted for approval. The breaker trip units shall be
interchangeable and the instantaneous magnetic trip units shall be
adjustable on frame sizes larger than 150 amperes. Nonadjustable
instantaneous magnetic trip units shall be set at approximately 10 times
the continuous current ratings of the circuit breakers.
2.3 WIRING
All control wire shall be stranded tinned copper switchboard wire with
600-volt flame-retardant insulation meeting IEC 60502 standards
Current transformer secondary leads shall be not smaller than No. 6mm2.
The minimum size of control wire shall be No. 14 AWG. Power wiring for
380 volt circuits and below shall be of the same type as control wiring
and the minimum size shall be 2.5mm2. Special attention shall be given
to wiring and terminal arrangement on the terminal blocks to permit the
individual conductors of each external cable to be terminated on
adjacent terminal points.
Page 5
will be acceptable provided they are of the channel or rail-mounted
type. The Contractor shall submit data showing that the proposed
alternate will accommodate the specified number of wires, are of
adequate current-carrying capacity, and are constructed to assure
positive contact between current-carrying parts.
Load terminal blocks rated not less than 600 volts and of adequate
capacity shall be provided for the conductors for NEMA Size 3 and
smaller motor controllers and for other power circuits except those for
feeder tap units. The terminals shall be of either the stud type with
contact nuts and locking nuts or of the removable screw type, having
length and space for at least two indented terminals of the size
required on the conductors to be terminated. For conductors rated more
than 50 amperes, screws shall have hexagonal heads. Conducting parts
between connected terminals shall have adequate contact surface and
cross-section to operate without overheating. Each connected terminal
shall have the circuit designation or wire number placed on or near the
terminal in permanent contrasting color.
Page 6
2.6 MOTOR CONTROL CENTERS
2.6.1 Enclosures
Structure shall have a minimum 300 mm high wireway at the top and a 150
mm minimum wireway at the bottom. Both horizontal wireways shall run the
length of the structure A master terminal block compartment with full
length wireway space shall be provided at the top in all Type C
assemblies. Cover plates shall be provided on the side of the assembly
to permit extension of the horizontal bus and wireway when vertical
sections are added.
Page 7
multiple plug-in components. Vertical wireways shall connect with
horizontal wireways at the top and bottom and be a minimum 100 mm wide.
Barriers shall be provided in sections containing both ac and dc
vertical buses. Doors shall be provided on each vertical wireway. The
exposed surface of any door shall not deviate more than 1.5 mm from a
true plane.
2.6.1.5 Sills
Channel iron foundations, complete with bolts and drilled holes for
grouting and anchoring to the floor, shall be furnished for the complete
length (front and rear) of each motor control center assembly. The
channels shall be designed for flat mounting and maximum channel depth
shall be 38 mm. Additional channel or substantial metal trim shall be
provided flush with the end panels to completely enclose the bases
across the ends of the equipment assemblies.
2.6.1.7 Shutters
Drawout units shall have shutters which close when the unit is withdrawn
to isolate the vertical bus.
2.6.2 Buses
All buses shall be of copper and all bolted splices and connections
between buses and for extensions or taps for equipment shall be tin or
silver-plated. Copper bars and shapes for bus conductors shall conform
to the applicable requirements of ASTM B 187/B 187M. All splices for
field assembly shall be bolted with at least two bolts and shall employ
the use of "Belleville" washers in the connection. The bus ratings
shall be based on a 65 degree Celsius maximumtemperature rise. Bus shall
have a short-circuit current rating of not less than 65,000 RMS
symmetrical amperes. All bus work shall be supported on wet process
porcelain insulators, glass polyester, or suitable molded material.
Page 8
A copper ground bus shall be provided full width at the bottom of the
motor control center line-up. A full clamp-type solderless copper or
copper alloy lug for 70mm2 stranded copper cable shall be provided at
each end of the bus for connection to the station grounding system.
Reduced voltage starters shall be STAR-DELTA type and shall conform with
IEC 61439-1 standards.
Page 9
Except as otherwise indicated, each controller shall be provided three
thermal overload relays with external manual reset. Prior to shipment
of the control centers, the Contracting Officer will furnish the ratings
of the heater elements to be installed in the relays by the Contractor.
Not used.
Page 10
The Contractor's wiring shall be formed into groups, suitably bound
together, properly supported and run straight horizontally or
vertically. There shall be no splices in the wiring. The
manufacturer's standard pressure-type wire terminations for connections
to internal devices will be acceptable. Terminal blocks shall be added
for wiring to devices having leads instead of terminals. Ring tongue
indented terminals shall be used on all wires terminated on control
terminal blocks for external or interpanel connections and at shipping
splits. All stud terminals shall have contact nuts and either locking
nuts or lockwashers.
Power and control cables will enter the control centers at the bottom or
top where shown on the drawings. Where power and control entry points
are not shown, and terminal blocks are not given on the drawings, the
Government will furnish this information to the Contractor after award
of contract.
Page 11
Red and green LED's shall be furnished where shown on the drawings,
indicating contact "open" and "closed" position. The LED's shall be
accessible and replaceable from the front of the control center through
a finished opening in the compartment door. The LED assemblies shall be
of the heavy duty oiltight, watertight, and dusttight type.
2.6.12.2 Ammeters
2.6.12.3 Voltmeters
Page 12
2.6.12.5 Switches
2.7 SWITCHBOARDS
2.7.1 Enclosure
2.7.2 Bus
All buses shall be of copper and all bolted splices and connections
between buses and for extensions or taps for equipment shall be tin or
silver-plated throughout. Copper bars and shapes for bus conductors
shall conform to the applicable requirements of ASTM B 187/B 187M , and
ASTM B 317/B 317M. All splices for field assembly shall be bolted with
at least two bolts and shall employ the use of "Belleville" washers in
Page 13
the connection. Horizontal and vertical power buses have minimum current
ratings as shown on the drawings. The buses shall be insulated for not
less than 600 volts. Shop splices and tap connections shall be brazed,
pressure-welded or bolted. All splices for field assembly shall be
bolted. The buses shall be mounted on insulating supports of wet process
porcelain, glass polyester, or suitable molded material, and shall be
braced to withstand not less than specified on drawings symmetrical
amperes ac.
A copper ground bus, rated not less than 300 amps, extending the entire
length of the assembled structure, shall be mounted near the bottom of
enclosure. A full clamp-type solderless copper or copper alloy lug for
70mm2 stranded copper cable shall be provided at each end of the bus for
connection to the station grounding system.
2.7.4 Components
2.8 PANELBOARDS
2.8.1 Enclosure
Page 14
with paragraph NAMEPLATES. Directory holders, containing a neatly typed
or printed directory under a transparent cover, shall be provided on the
inside of panelboard doors.
2.8.2 Buses
All panelboards shall be of the dead-front type with buses and circuit
breakers mounted on a plate or base for installation as a unit in a
cabinet. All buses shall be of copper. Copper bars and shapes for bus
conductors shall conform to the applicable requirements of
ASTM B 187/B 187M. Suitable provisions shall be made for mounting the
bus within panelboards and adjusting their positions in the cabinets.
Terminal lugs required to accommodate the conductor sizes shown on the
drawing, shall be provided for all branch circuits larger than 6mm2. A
grounding lug suitable for 50mm2 wire shall be provided for each
panelboard.
2.8.3 Components
Each branch circuit, and the main buses where so specified or shown on
the drawings, shall be equipped with molded-case circuit breakers having
overcurrent trip ratings as shown on the drawings. The circuit breakers
shall be of a type designed for bolted connection to buses in a
panelboard assembly, and shall meet the requirements of paragraph MOLDED
CASE CIRCUIT BREAKERS. Circuit breakers of the same frame size and
rating shall be interchangeable.
2.9 PAINTING
Each item of equipment supplied under this contract shall be given the
manufacturer's routine factory tests and tests as specified below, to
insure successful operation of all parts of the assemblies. All tests
required herein shall be witnessed by the Contracting Officer unless
waived in writing, and no equipment shall be shipped until it has been
approved for shipment by the Contracting Officer. The Contractor shall
notify the Contracting Officer a minimum of 14 days prior to the
proposed date of the tests so that arrangements can be made for the
Contracting Officer to be present at the tests. The factory test
equipment and the test methods used shall conform to the applicable NEMA
Standards, and shall be subject to the approval of the Contracting
Officer. Reports of all witnessed tests shall be signed by witnessing
representatives of the Contractor and Contracting Officer. The cost of
performing all tests shall be borne by the Contractor and shall be
included in the prices bid in the schedule for equipment.
Page 15
2.10.1.1 Dielectric Tests
If the unit is not UL labeled for the specified short circuit, the
Contractor may submit design tests demonstrating that satisfactory
short-circuit tests, as specified in NEMA ICS 2, have been made on a
motor control center of similar type of construction and having the same
available short circuit current at the motor terminals, including any
motor contributions, as the motor control centers specified to be
furnished under these specifications.
If the unit is not UL labeled for the specified short circuit, the
Contractor may submit design tests demonstrating that satisfactory
short-circuit tests have been made on a switchboard of similar type of
construction and of the same short-circuit rating as the switchboards
specified to be furnished under these specifications.
Each panelboard shall be assembled with cabinet and front to the extent
necessary to check the fit and provisions for installing all parts in
the field. Each panelboard shall be given a dielectric test in
accordance with NEMA PB 1. All circuit breakers shall be operated to
check mechanical adjustments. All doors and locks shall be checked for
door clearances and fits and the performance of lock and latches.
-- End of Section --
Page 16
LIGHTNING PROTECTION SYSTEM
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
Detail Drawings
SD-07 Certificates
Materials
The Contractor shall become familiar with all details of the work,
verify all dimensions in the field, and shall advise the Contracting
Officer of any discrepancy before performing the work. No departures
shall be made without the prior approval of the Contracting Officer.
Page 1
NFPA 70 and NFPA 780, UL 96 and UL 96A, except where requirements in
excess thereof are specified herein.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.2.1 Copper
Copper conductors used on nonmetallic stacks shall weigh not less than
170 kg/300 m, and the size of any wire in the cable shall be not less
than No. 15 AWG. The thickness of any web or ribbon used on stacks
shall be not less than No. 12 AWG. Counterpoise shall be copper
conductors not smaller than No. 1/0 AWG (50mm2).
2.1.2.2 Aluminum
Not used
Page 2
Rods made of solid copper shall conform to TSE Standards. Ground rods
shall be not less than 20 mm in diameter and 3m in length.
2.1.5 Connectors
PART 3 EXECUTION
Air terminal design and support shall be in accordance with NFPA 780.
Terminals shall be rigidly connected to, and made electrically
continuous with, roof conductors by means of pressure connectors or
crimped joints of T-shaped malleable metal and connected to the air
terminal by a dowel or threaded fitting. Air terminals at the ends of
the structure shall be set not more than 600 mm from the ends of the
ridge or edges and corners of roofs. Spacing of air terminals 600 mm in
height on ridges, parapets, and around the perimeter of buildings with
flat roofs shall not exceed 7.5 m. In specific instances where it is
necessary to exceed this spacing, the specified height of air terminals
shall be increased not less than 50 mm for each 300 mm of increase over
7.5 m. On large, flat or gently sloping roofs, as defined in NFPA 780,
air terminals shall be placed at points of the intersection of imaginary
lines dividing the surface into rectangles having sides not exceeding 15
m in length. Air terminals shall be secured against overturning either
by attachment to the object to be protected or by means of a substantial
tripod or other braces permanently and rigidly attached to the building
or structure. Metal projections and metal parts of buildings,
smokestacks, and other metal objects that do not contain hazardous
materials and that may be struck but not appreciably damaged by
lightning, need not be provided with air terminals. However, these
metal objects shall be bonded to the lightning conductor through a metal
conductor of the same unit weight per length as the main conductor.
Where metal ventilators are installed, air terminals shall be mounted
thereon, where practicable. Any air terminal erected by necessity
Page 3
adjacent to a metal ventilator shall be bonded to the ventilator near
the top and bottom. Where metal ventilators are installed with air
terminals mounted thereon, the air terminal shall not be more than 610 mm
away from the farther edge or corner. If the air terminal is farther
than this distance, an additional air terminal shall be added in order
to meet this requirement. Where metal ventilators are installed with air
terminals mounted adjacent, the air terminal shall not be more than 610
mm away from the farther edge or corner. If the air terminal is farther
than this distance, an additional air terminal shall be added in order
to meet this requirement.
Page 4
Metal doors, windows, and gutters shall be connected directly to the
grounds or down conductors using not smaller than No. 6 copper
conductor, or equivalent. Conductors placed where there is probability
of unusual wear, mechanical injury, or corrosion shall be of greater
electrical capacity than would normally be used, or shall be protected.
The ground connection to metal doors and windows shall be by means of
mechanical ties under pressure, or equivalent.
Page 5
mm.
Wood-Frame Building With Metal Roof and Metal Exterior Walls: The metal
roof and the metal walls shall be bonded and made electrically
continuous and considered as one unit. The air terminals shall be
connected to and made electrically continuous with the metal roof as
well as the roof and down conductors. All connections shall have
electrical continuity and have a surface contact of at least 1935 square
mm.
3.1.5 Ramps
Not used.
Not used
Not used.
Not used.
3.1.8 Stacks
Not used.
Page 6
point of the stack foundation.
Not used.
3.2 RAILROADS
Not used.
Not used.
Page 7
grounded.
3.5 FENCES
Not used.
Not used.
Notused.
3.9 INSPECTION
-- End of Section --
Page 8
INTERIOR LIGHTING
PART 1 GENERAL
1.1 REFERENCES
1.3 DEFINITIONS
b. Average life is the time after which 50 percent will have failed and
50 percent will have survived under normal conditions.
c. Total harmonic distortion (THD) is the root mean square (RMS) of all
the harmonic components divided by the total fundamental current.
1.5 SUBMITTALS
Page 1
Fluorescent lamps; G,
Photocell switch; G,
Local/Regional Materials
Environmental Data]
Energy Efficiency
SD-04 Samples
Operating test
Operational Service
Page 2
1.6.2 Lighting Fixtures, Complete With Lamps and Ballasts
Comply with National Energy Policy Act and Energy Star requirements for
lighting products. [Submit documentation for Energy Star qualifications
for equipment provided under this section. ]Submit data indicating
lumens per watt efficiency and color rendition index of light source.
1.7 WARRANTY
Page 3
period shall not be less than 5 years from the date of manufacture of
the electronic ballast. Ballast assembly in the lighting fixture,
transportation, and on-site storage shall not exceed 12 months, thereby
permitting 4 years of the ballast 5 year warranty to be in service and
energized. The warranty shall state that the malfunctioning ballast
shall be exchanged by the manufacturer and promptly shipped to the using
Government facility. The replacement ballast shall be identical to, or
an improvement upon, the original design of the malfunctioning ballast.
PART 2 PRODUCTS
Page 4
Current crest factor shall be 1.7 (maximum).
j. Ballasts for T-5 and smaller lamps shall have end-of-life protection
circuits as required.
b. Input wattage.
c. Provide two lamp fixtures with one ballasts per fixture where
multilevel switching is indicated.]
Not used.
Page 5
(24 inches), 1300 initial lumens, CRI of 75 (minimum), color
temperature of [3500 K], and an average rated life of 20,000 hours.
Compact
c. fluorescent lamps shall be: CRI 80, minimum, [3500 K], 10,000
hours average rated life, and as follows:
Not used.
Not used.
UL 1598.[ Provide HID fixtures with tempered glass lenses when using
metal-halide lamps.]
Page 6
2.2.2 High-Pressure Sodium (HPS) Lamps
Not used.
Provide type that can be relamped from the bottom. Access to ballast
shall be from the bottom. Trim for the exposed surface of flush-mounted
fixtures shall be as indicated.
2.7 SWITCHES
Not used.
Not used.
Not used.
Page 7
IEC and TSE compliant hermetically sealed cadmium-sulfide or silicon
diode type cell rated 220_ volts ac, 50 Hz with single-throw contacts.
Switch shall turn on at or below 32 lux and off at 22 to 107 lux. A
time delay shall prevent accidental switching from transient light
sources. Provide switch:
UL 924, NFPA 70, and NFPA 101. Exit signs shall be[ self-powered]
type. Exit signs shall use no more than 5 watts.
UL 924, NFPA 70, and NFPA 101. Provide lamps in wattage indicated.[
Provide accessories required for remote-mounted lamps where indicated.
Remote-mounted lamps shall be as indicated.]
Not used.
Page 8
Not used.
Comply with GC-12 and IEC/TSE. Occupancy sensors and power packs shall
be designed to operate on the voltage indicated. Sensors and power packs
shall have circuitry that only allows load switching at or near zero
current crossing of supply voltage. Occupancy sensor mounting as
indicated. Sensor shall have an LED occupant detection indicator.
Sensor shall have adjustable sensitivity and adjustable delayed-off time
range of 5 minutes to 15 minutes. Wall mounted sensors shall[ be white][
match the color of adjacent wall plates as specified in Section 26 20 00
INTERIOR DISTRIBUTION SYSTEM], ceiling mounted sensors shall be white.
Ceiling mounted sensors shall have 6.28 rad coverage unless otherwise
indicated.
[a. Ultrasonic sensor shall be crystal controlled and shall not cause
detection interference between adjacent sensors.]
[b. Infrared sensors shall have a daylight filter. Sensor shall have a
fresnel lens that is applicable to space to be controlled.]
2.18.1 Wires
2.18.3 Straps
2.18.4 Rods
2.19.2 Labels
Page 9
Provide labeled luminaires in accordance with TSE requirements. All
luminaires shall be clearly marked for operation of specific lamps and
ballasts according to proper lamp type. The following lamp
characteristics shall be noted.
a. Lamp diameter code (T-4, T-5, T-8, T-12), tube configuration (twin,
quad, triple), base type, and nominal wattage for fluorescent and
compact fluorescent luminaires.
b. Lamp type, wattage, bulb type (ED17, BD56, etc.) and coating (clear
or coated) for HID luminaires.
c. Start type (preheat, rapid start, instant start) for fluorescent and
compact fluorescent luminaires.
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to the
requirements specified herein.
3.1.1 Lamps
Set lighting fixtures plumb, square, and level with ceiling and walls,
in alignment with adjacent lighting fixtures, and secure in accordance
with manufacturers' directions and approved drawings. Installation
shall meet requirements of NFPA 70. Mounting heights specified or
indicated shall be to the bottom of fixture for ceiling-mounted fixtures
and to center of fixture for wall-mounted fixtures. Obtain approval of
the exact mounting for lighting fixtures on the job before commencing
installation and, where applicable, after coordinating with the type,
style, and pattern of the ceiling being installed. Recessed and
Page 10
semi-recessed fixtures shall be independently supported from the
building structure by a minimum of four wires[ or straps][ or rods] per
fixture and located near each corner of each fixture. Ceiling grid
clips are not allowed as an alternative to independently supported light
fixtures. Round fixtures or fixtures smaller in size than the ceiling
grid shall be independently supported from the building structure by a
minimum of four wires[ or straps][ or rods] per fixture spaced
approximately equidistant around the fixture. Do not support fixtures
by ceiling acoustical panels. Where fixtures of sizes less than the
ceiling grid are indicated to be centered in the acoustical panel,
support such fixtures independently and provide at least two 19 mm (3/4
inch) metal channels spanning, and secured to, the ceiling tees for
centering and aligning the fixture. Provide wires[ or straps][ or rods]
for lighting fixture support in this section. Lighting fixtures
installed in suspended ceilings shall also comply with the requirements
of Section 09 51 00 ACOUSTICAL CEILINGS.
3.1.4 Ballasts
Not used.
Not used.
Wire exit signs and emergency lighting units ahead of the switch to the
normal lighting circuit located in the same room or area.
Page 11
Not used.
Not used.
Not used.
Not used.
Not used.
-- End of Section --
Page 12
BUILDING TELECOMMUNICATIONS CABLING SYSTEM
PART 1 GENERAL
1.1 REFERENCES
1.3 DEFINITIONS
An entrance to the building for both private and public network service
cables (including wireless) including the entrance point at the building
wall and continuing to the equipment room.
Page 1
1.3.7 Open Cable
Cabling that is not run in a raceway as defined by NFPA 70. This refers
to cabling that is "open" to the space in which the cable has been
installed and is therefore exposed to the environmental conditions
associated with that space.
1.3.9 Pathway
1.5 SUBMITTALS
Telecommunications drawings; G,
Patch panels; G,
Page 2
Equipment support frame; G,
Connector blocks; G,
Spare Parts; G,
SD-07 Certificates
Manufacturer Qualifications; G,
Test plan; G,
Record Documentation; G,
Page 3
Provide drawings in accordance with TIA/EIA-606. The identifier for each
termination and cable shall appear on the drawings. Drawings shall
depict final telecommunications installed wiring system infrastructure
in accordance with TIA/EIA-606. The drawings should provide details
required to prove that the distribution system shall properly support
connectivity from the EF telecommunications and ER telecommunications,
CD's, and FD's to the telecommunications work area outlets. The
following drawings shall be provided as a minimum:
Work under this section shall be performed by and the equipment shall be
provided by the approved telecommunications contractor and key
personnel. Qualifications shall be provided for: the
telecommunications system contractor, the telecommunications system
installer, and the supervisor (if different from the installer). A
minimum of 30 days prior to installation, submit documentation of the
experience of the telecommunications contractor and of the key personnel.
Page 4
minimum of three and a maximum of five successful telecommunication
system installations for the telecommunications contractor.
Note that only the key personnel approved by the Contracting Officer in
the successful proposal shall do work on this solicitation's
telecommunications system. Key personnel shall function in the same
roles in this contract, as they functioned in the offered successful
experience. Any substitutions for the telecommunications contractor's
key personnel requires approval from The Contracting Officer.
Page 5
1.6.4 Regulatory Requirements
In each of the publications referred to herein, consider the advisory
provisions to be mandatory, as though the word, "shall" had been
substituted for "should" wherever it appears. Interpret references in
these publications to the "authority having jurisdiction," or words of
similar meaning, to mean the Contracting Officer. Equipment, materials,
installation, and workmanship shall be in accordance with the mandatory
and advisory provisions of NFPA 70 unless more stringent requirements
are specified or indicated.
Provide protection from weather, moisture, extreme heat and cold, dirt,
dust, and other contaminants for telecommunications cabling and
equipment placed in storage.
1.9 WARRANTY
1.10 MAINTENANCE
Page 6
5. Submit operations and maintenance data as specified herein not later
than months prior to the date of beneficial occupancy. In addition to
requirements of Data Package 5, include the requirements of paragraphs
TELECOMMUNICATIONS DRAWINGS, TELECOMMUNICATIONS SPACE DRAWINGS, and
RECORD DOCUMENTATION. Ensure that these drawings and documents depict
the as-built configuration.
PART 2 PRODUCTS
2.1 COMPONENTS
Cabling shall be UL listed for the application and shall comply with
TIA-568-C.0, TIA-568-C.1, TIA-568-C.2, TIA-568-C.3 and NFPA 70. Provide
a labeling system for cabling as required by TIA/EIA-606 and UL 969.
Page 7
Ship cable on reels or in boxes bearing manufacture date for for
unshielded twisted pair (UTP) in accordance with ICEA S-90-661 for all
cable used on this project. Cabling manufactured more than 12 months
prior to date of installation shall not be used.
Provide horizontal copper cable, UTP Cat.6, 100 ohm in accordance with
TIA-568-C.2, UL 444, ANSI/NEMA WC 66, ICEA S-90-661. Provide four each
individually twisted pair, minimum size 24 AWG conductors, Category 6,
with a thermoplastic jacket. Cable shall be imprinted with manufacturers
name or identifier, flammability rating, gauge of conductor,
transmission performance rating (category designation) and length
marking at regular intervals in accordance with ICEA S-90-661. Provide
plenum (CMP), riser (CMR), or general purpose (CM or CMG) communications
rated cabling in accordance with NFPA 70. Substitution of a higher rated
cable shall be permitted in accordance with NFPA 70. Cables installed in
conduit within and under slabs shall be UL listed and labeled for wet
locations in accordance with NFPA 70.
2.4.1 Backboards
Page 8
2.4.4 Patch Panels
Provide ports for the number of horizontal and backbone cables
terminated on the panel plus percent spare. Provide pre-connectorized
optical fiber and patch cords for patch panels. Provide patch cords, as
complete assemblies, with matching connectors as specified. Provide
fiber optic patch cables with crossover orientation in accordance with
TIA-568-C.3. Patch cords shall meet minimum performance requirements
specified in TIA-568-C.1, TIA-568-C.2 for cables, cable length and
hardware specified.
Not used.
Not used
Page 9
2.8 MANUFACTURER'S NAMEPLATE
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Cabling
Use only where specifically indicated on plans for use in cable trays,
Page 10
or below raised floors. Install in accordance with TIA-568-C.1,
TIA-568-C.2. Do not exceed cable pull tensions recommended by the
manufacturer. Copper cable not in a wireway or pathway shall be
suspended a minimum of 200 mm above ceilings by cable supports no
greater than 1.5 m apart. Cable shall not be run through structural
members or in contact with pipes, ducts, or other potentially damaging
items. Placement of cable parallel to power conductors shall be avoided,
if possible; a minimum separation of 300 mm shall be maintained when
such placement cannot be avoided.
Plenum cable shall be used where open cables are routed through plenum
areas. Cable routed exposed under raised floors shall be plenum rated.
Plenum cables shall comply with flammability plenum requirements of
NFPA 70. Install cabling after the flooring system has been installed in
raised floor areas. Cable 1.8 meters long shall be neatly coiled not
less than 300 mm in diameter below each feed point in raised floor areas.
3.1.4.1 Terminations
Page 11
and a unique number to identify cable link in accordance with the
paragraph LABELING in this section.
3.1.4.3 Cables
Unshielded twisted pair and fiber optic cables shall have a minimum of
304 mm of slack cable loosely coiled into the telecommunications outlet
boxes. Minimum manufacturer's bend radius for each type of cable shall
not be exceeded.
3.2 LABELING
3.2.1 Labels
Page 12
be provided using laser printer .
3.2.2 Cable
Cables shall be labeled using color labels on both ends with identifiers
in accordance with TIA/EIA-606.
3.5 TESTING
3.5.1.1 Inspection
Visually inspect UTP and optical fiber jacket materials for UL or third
party certification markings. Inspect cabling terminations in
telecommunications rooms and at workstations to confirm color code for
T568A or T568B pin assignments, and inspect cabling connections to
confirm compliance with TIA-568-C.1, TIA-568-C.2. Visually confirm
Category 6, marking of outlets, cover plates, outlet/connectors, and
patch panels.
Page 13
Perform testing for each outlet and MUTOA as follows:
a. Voice Tests. These tests assume that dial tone service has been
installed. Connect to the network interface device at the
demarcation point. Go off-hook and listen and receive a dial tone.
If a test number is available, make and receive a local, long
distance, and DSN telephone call.
b. Data Tests. These tests assume the Information Technology Staff has
a network installed and are available to assist with testing.
Connect to the network interface device at the demarcation point.
Log onto the network to ensure proper connection to the network.
-- End of Section --
Page 14
COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
PART 1 GENERAL
1.1 REFERENCES
1.3 DEFINITIONS
1.3.1 CATV
1.3.2 Headend
Page 1
1.3.3 Distribution System
1.3.4 Cable
[Trunk and feeder cables are low-loss cables used to transport the
desired signal from the headend equipment to the communications closet
in the area to be served. These cables are used to transport signal
from the [communications closet] into close proximity to a number of
user locations in excess of 200 feet from the [communications closet].
]Drop cables are used to transport the desired signal used from the
[communications closet] to the wall outlet.
1.4.1 Headend
1.4.3 Cable
[Provide trunk cables to transport the desired signal from the headend
equipment to the communications closet in the area to be served.
][Provide [feeder] cables to transport signal from the [communications
closet] to user locations in excess of 200 feet from the [communications
closet].] Provide drop cables to transport the desired signal from the
[communications closet] to the outlet.
Page 2
1.4.5.1 Receiver Termination Signal Level
The system shall not show a serious loss of carrier to noise when the
system levels are lowered 3 dB below normal or a significant distortion
when the levels are increased 3 dB above normal, as observed on a TV set
located at the far end extremities of the system.
1.5 SUBMITTALS
Attenuators; G
Terminators; G
Splitters/combiners; G
Page 3
Line Taps; G
Outlets; G
Connectors; G
System pretest; G
Acceptance tests; G
Connector Installation; G
Calculations shall verify that the system does not exceed the loss
values specified in dBmV at the [input of all active devices and the
receiver terminations]. Provide a drawing displaying all distribution
network calculations. The drawing should accurately show taps,
splitters, outlets, and the type and length of all [trunk, feeder, and
]drop cables. The drawing shall show how many taps, splitters, or
outlets are served by each tap or splitter.
Test plan shall define tests required to ensure that the system meets
technical, operational, and performance specifications. Test plan shall
be based on NCTA RP and be in accordance with FCC proof of performance
requirements. Test plan shall include plan for testing for signal
leakage. Provide test requirements and guidelines.
Page 4
Procedures shall consist of detailed instructions for a test setup,
execution, and evaluation of test results.
PART 2 PRODUCTS
2.2.2 Attenuators
Trunk amplifiers shall have automatic level and slope control features.
Page 5
Cabling shall be UL listed for the application and shall comply with
NFPA 70. Provide a labeling system for cabling as required by UL 969.
Cabling manufactured more than 12 months prior to date of installation
shall not be used.
b. Provide 625 Series cable with an NFPA 70 rating of CATVR and the
following characteristics:NOT USED
d. 75 ohms impedance.
Page 6
d. [Foam FEP] dielectric
g. Maximum attenuation:
2.3.3 Terminators
2.3.4 Splitters/Combiners
Line taps shall have 18 dB minimum isolation from each tap to the
thru-line.Pressure tapoffs are not permitted. Taps shall be rated from
5 to 1000 MHz and shall have a peak to valley not to exceed 1 dB to 1
GHz.
2.3.6 Outlets
2.3.7 Connectors
Provide one piece connectors. [Trunk and feeder cable connectors shall
be pin type. ]Drop cable connectors shall be feed thru type.
2.5 BACKBOARDS
Page 7
Provide void-free, fire rated interior grade plywood, 3/4 inch thick,[
as indicated]. Backboards shall be painted with a gray, nonconductive
fire-resistant overcoat.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1.1 Raceway
Provide the grounding block [at the main CATV backboard]. Ground this
device according to the requirements of IEEE C2 and NFPA 70.
Page 8
system. Deficiencies revealed by the testing shall be corrected
[outlets] sampled as well as on the [outlets] not sampled ]and
revalidated by follow-up testing. Contractor shall conduct testing at
each of the following points in the system:
-- End of Section --
Page 9
INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
PART 1 GENERAL
1.2 REFERENCES
Page 1
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
1.3 DEFINITIONS
Page 2
equipment, devices, and functions shall be defined as follows:
1.4.1 Scope
c. Where remote fire alarm control units are needed, they shall be
provided at a terminal cabinet location.] Each remote fire alarm
control unit shall be powered from a wiring riser specifically for
that use or from a local emergency power panel located on the same
floor as the remote fire alarm control unit. Where remote fire
control units are provided, equipment for notification appliances
Page 3
may be located in the remote fire alarm control units.
1.4.3 Keys
Keys and locks for equipment shall be identical. Provide not less than
six keys of each type required. [Master all keys and locks to a single
key as required by the [Installation Fire Department]
1.5 SUBMITTALS
Wiring Diagrams[; G]
System Layout[; G]
System Operation[; G]
Notification Appliances[; G]
Amplifiers[; G]
Page 4
Technical Data And Computer Software[; G]
Fire Alarm Control Unit and Mass Notification Control Unit (FMCP)
; G
LCD, LED Display Unit (VDU)[; G]
Terminal cabinets[; G]
Manual stations[; G]
Smoke sensors[; G]
Heat detectors[; G]
Notification appliances[; G]
Addressable interface devices[; G]
Amplifiers[; G]
Battery power[; G]
SD-07 Certificates
Installer
Formal Inspection and Tests
Final Testing
System Operation[; G]
Fire Alarm/Mass Notification System
As-Built Drawings
Page 5
c. Devices and equipment for fire alarm service shall be listed by UL
Fire Prot Dir or approved by FM APP GUIDE.
1.6.1 Qualifications
1.6.1.2 Supervisor
1.6.1.3 Technician
1.6.1.4 Installer
Page 6
1.6.1.6 Manufacturer's Representative
1.6.1.7 Manufacturer
Page 7
a . Operating manual outlining step-by-step procedures required
for system startup, operation, and shutdown. The manual shall
include the manufacturer's name, model number, service manual,
parts list, and complete description of equipment and their basic
operating features.
Repair services and replacement parts for the system shall be available
for a period of 10 years after the date of final acceptance of this work
by the Contracting Officer. During guarantee period, the service
technician shall be on-site within 24 hours after notification. All
repairs shall be completed within 24 hours of arrival on-site.
Page 8
Software, connecting cables and proprietary equipment, necessary for the
maintenance, testing, and reprogramming of the equipment shall be
furnished to the Contracting Officer.
PART 2 PRODUCTS
2.1.2 Nameplates
a. FMCPs
All fire alarm and mass notification equipment shall be listed for use
under the applicable reference standards. Interfacing of Listed UL 864
or similar approved industry listing with Mass Notification Panels
listed to UL 2017 shall be done in a laboratory listed configuration, if
the software programming features cannot provide a listed interface
control. If a field modification is needed, such as adding equipment
like relays, the manufacturer of the panels being same or different
brand from manufacturer shall provide the installing contractor for
review and confirmation by the installing contractor. As part of the
submittal documents, provide this information.
Page 9
The Addressable Interior Fire Alarm and Mass Notification System shall
be a complete, supervised, noncoded, analog/addressable fire alarm and
mass notification system conforming to NFPA 72, UL 864 , and UL 2017.
The system shall be activated into the alarm mode by actuation of any
alarm initiating device. The system shall remain in the alarm mode
until the initiating device is reset and the control panel is reset and
restored to normal. The system may be placed in the alarm mode by local
microphones, LOC, or remotely from authorized locations/users.
c. The system shall operate in the alarm mode upon actuation of any
alarm initiating device or a mass notification signal. The system
shall remain in the alarm mode until initiating device(s) or mass
notification signal is/are reset and the control panel is manually
reset and restored to normal. Audible, and visual appliances and
systems shall comply with NFPA 72 and as specified herein. Fire
alarm system/mass notification system components requiring power,
except for the control panel power supply, shall operate on 24 Volts
dc.
The system shall provide the following functions and operating features:
b. For Class "A" or "X" circuits with conductor lengths of 3m (10 feet)
or less, the conductors shall be permitted to be installed in the
same raceway in accordance with NFPA 72.
Page 10
for Class "X"). The trouble signal shall also operate upon loss of
primary power (AC) supply, absence of a battery supply, low battery
voltage, or removal of alarm or supervisory panel modules. Provide
a trouble alarm silence feature that shall silence the audible
trouble signal, without affecting the visual indicator. After the
system returns to normal operating conditions, the trouble signal
shall again sound until the trouble is acknowledged. A smoke sensor
in the process of being verified for the actual presence of smoke
shall not initiate a trouble condition.
Page 11
(8) Operation of a smoke sensor in an elevator lobby or other
location associated with the automatic recall of elevators,
shall recall the elevators in addition to other requirements of
this paragraph.
(1) Visual indication of the system trouble on the FACP, [VDU,] and
on the graphic annunciator, and sound the audible alarm at the
respective panel.
(3) Recording of the event in the history log of the control unit.
2.4.1 Valves
Page 12
including automatic sprinkler control valves, standpipe control valves,
sprinkler service entrance valve, valves at fire pumps, isolating valves
for pressure type waterflow or supervision switches, and valves at
backflow preventers, whether supplied under this contract or existing,
shall be electrically monitored to ensure its proper position. Provide
each tamper switch with a separate address[, unless they are within the
same room, then a maximum of five can use the same address].
2.5.2 Strobes
The Wide Area MNS system (if available) in the area of the building
shall not be activated by the in-building MNS.
Page 13
control unit of the installation-wide system. The autonomous control
unit shall receive commands/messages from the central control unit and
provide status information.
Digital and analog inputs and outputs shall be protected against surges
induced by sensor wiring installed outdoors and as shown. The inputs
and outputs shall be tested with the following waveform[s]:
Page 14
configured as a Class "B" notification appliance circuits. The system
shall be capable of supervising, audible, visual and dry contact
circuits. The control module shall have both an input and output
address. The supervision shall detect a short on the supervised circuit
and shall prevent power from being applied to the circuit. The control
model shall provide address setting means compatible with the control
panel's SLC supervision and store an internal identifying code. The
control module shall contain an integral LED that flashes each time the
control module is polled and is visible through the device cover
plate. Control Modules shall be located in environmental areas that
reflect the conditions to which they were listed.
e. The sensor address shall identify the particular unit, its location
within the system, and its sensitivity setting. Sensors shall be of
the low voltage type rated for use on a 24 VDC system.
Page 15
Provide addressable ionization type smoke sensors as follows:
d. Provide twist lock bases for the sensors. The sensors shall
maintain contact with their bases without the use of springs.
Provide companion mounting base with screw terminals for each
conductor. Terminate field wiring on the screw terminals. The
sensor shall have a visual indicator to show actuation.
e. The sensor address shall identify the particular unit, its location
within the system, and its sensitivity setting. Sensors shall be of
the low voltage type rated for use on a 24 VDC system.]
a. Sampling tubes shall run the full width of the duct. The duct
detector package shall conform to the requirements of NFPA 90A,
UL 268A, and shall be UL listed for use in air-handling systems.
Page 16
The control functions, operation, reset, and bypass shall be
controlled from the fire alarm control panel.
b. Lights to indicate the operation and alarm condition; and the test
and reset buttons shall be visible and accessible with the unit
installed and the cover in place. Remote indicators shall be
provided where required by NFPA 72 and these shall be provided with
test and reset switches.
c. Remote lamps and switches as well as the affected fan units shall
be properly identified in etched plastic placards. Detectors shall
provide for control of auxiliary contacts that provide control,
interlock, and shutdown functions specified in Section [23 09 23 to
LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL
SYSTEMS][28 31 74.00 20 INTERIOR FIRE DETECTION AND ALARM SYSTEM][
28 31 63.00 20 ANALOG/ADDRESSABLE INTERIOR FIRE ALARM SYSTEM].
Auxiliary contacts provide for this function shall be located within
1 m of the controlled circuit or appliance. The detectors shall be
supplied by the fire alarm system manufacturer to ensure complete
system compatibility.
Page 17
detectors shall be rated for 15 by 15 m.
An operator at the control panel, having the proper access level, shall
have the capability to manually access the following information for
each heat sensor:
a. Primary status
b. Device type
d. Sensor range
An operator at the control panel, having the proper access level, shall
have the capability to manually control the following information for
each heat sensor:
Page 18
2.14.1 Primary Power
Power shall be 220VAC service for the FMCP from the AC service to the
building in accordance with NFPA 72.
2.15.1 Batteries
2.15.1.1 Capacity
Page 19
Provide a solid state, fully automatic, variable charging rate battery
charger. The charger shall be capable of providing 120 percent of the
connected system load and shall maintain the batteries at full charge.
In the event the batteries are fully discharged (20.4 Volts dc), the
charger shall recharge the batteries back to 95 percent of full charge
within 48 hours after a single discharge cycle as described in paragraph
CAPACITY above. Provide pilot light to indicate when batteries are
manually placed on a high rate of charge as part of the unit assembly if
a high rate switch is provided.
2.16 FIRE ALARM CONTROL UNIT AND MASS NOTIFICATION CONTROL UNIT (FMCP)
2.16.1 Cabinet
Page 20
Provide power and control modules to perform all functions of the FACP.
Provide audible signals to indicate any alarm, supervisory, or trouble
condition. The alarm signals shall be different from the trouble
signal. Connect circuit conductors entering or leaving the panel to
screw-type terminals with each terminal marked for identification.
Locate diodes and resistors, if any, on screw terminals in the FACP.
Circuits operating at 24 VDC shall not operate at less than the UL
listed voltage at the sensor or appliance connected. Circuits operating
at any other voltage shall not have a voltage drop exceeding 10 percent
of nominal voltage
Provide an alarm silencing switch at the FMCP that shall silence the
audible and visual. This switch shall be overridden upon activation of
a subsequent alarm.
Provide supervisory and trouble silencing switch that shall silence the
audible trouble and supervisory signal, but not extinguish the visual
indicator. This switch shall be overridden upon activation of a
subsequent alarm, supervision, or trouble condition. Audible trouble
indication must resound automatically every 24 hours after the silencing
feature has been operated.
2.16.4 Non-Interfering
Power and supervise each circuit such that a signal from one device does
not prevent the receipt of signals from any other device. Circuits
shall be manually reset by switch from the FACP after the initiating
device or devices have been restored to normal.
Page 21
b. The Mass Notification functions shall override the manual or
automatic fire alarm notification or Public Address (PA) functions.
Other fire alarm functions including transmission of a signal(s) to
the fire department shall remain operational. The system shall have
the capability of utilizing LOC with redundant controls of the
notification system control panel. Notification Appliance Circuits
(NAC) shall be provided for the activation of strobe appliances.
The activation of the NAC Circuits shall follow the operation of the
speaker NAC circuits. Audio output shall be selectable for line
level. Amplifier outputs shall be not greater than 100 watts RMS
output. The strobe NAC Circuits shall provide at least 2 amps of 24
VDC power to operate strobes and have the ability to synchronize all
strobes. A hand held microphone shall be provided and, upon
activation, shall take priority over any tone signal, recorded
message or PA microphone operation in progress, while maintaining
the strobe NAC Circuits activation.
(2) "May I have your attention please. May I have your attention
please. An fire emergency has been reported in the building.
Please leave the building by the nearest exit or exit stairway.
Do not use the elevators." (Provide a [2] second pause.) "May I
have your attention please, (repeat the message)."
(3) "May I have your attention please. May I have your attention
please. [insert installation specific message here]" (Provide a
[2] second pause.) (repeat the message)
(4) "May I have your attention please. May I have your attention
please. [insert installation specific message here]" (Provide a
[2] second pause.) (repeat the message)
(5) "May I have your attention please. May I have your attention
please. [insert installation specific message here]" (Provide a
[2] second pause.) (repeat the message)
(6) "May I have your attention please. May I have your attention
please. [insert installation specific message here]" (Provide a
[2] second pause.) (repeat the message)
Page 22
prerecorded messages. The unit shall be fully supervised from the
control panel. The housing shall contain a latch (not lock).
f. When an installation has more than one LOC, the LOC's shall be
programmed to allow only one LOC to be available for page or
messaging at a time. Once one LOC becomes active, all other LOC's
will have an indication that the system is busy (Amber Busy
Light)and cannot be used at that time. This is to avoid two messages
being given at the same time. Also, it must be possible to override
or lockout the LOC's from the Master Command Panel (in accordance
with NFPA 72.)
2.16.6 Memory
Provide each control unit with non-volatile memory and logic for all
functions. The use of long life batteries, capacitors, or other
age-dependent devices shall not be considered as equal to non-volatile
processors, PROMS, or EPROMS.
Provide control units and control panels that are fully field
programmable for control, initiation, notification, supervisory, and
trouble functions of both input and output. The system program
configuration shall be menu driven. System changes shall be password
protected and shall be accomplished using personal computer based
equipment. Any proprietary equipment and proprietary software needed by
qualified technicians to implement future changes to the fire alarm
system shall be provided as part of this contract.
The FMCP shall contain features that allow the bypassing of input
devices from the system or the modification of system outputs. These
control features shall consist of a panel mounted keypad[ and a
keyboard]. Any bypass or modification to the system shall indicate a
trouble condition on the FMCP.
2.16.9 Resetting
2.16.10 Instructions
Page 23
show those steps to be taken by an operator when a signal is received as
well as the functional operation of the system under all conditions,
normal, alarm, supervisory, and trouble. The instructions shall be
approved by the Contracting Officer before being posted.
The FACP shall have a walk test feature. When using this feature,
operation of initiating devices shall result in limited system outputs,
so that the notification appliances operate for only a few seconds and
the event is indicated on the system printer, but no other outputs occur.
In addition to the required printer output, the control panel shall have
the ability to store a minimum of 400 events in a log. These events
shall be stored in a battery-protected memory and shall remain in the
memory until the memory is downloaded or cleared manually. Resetting of
the control panel shall not clear the memory.
Page 24
that the amplifiers have sufficient capacity to simultaneously drive all
notification speakers at the maximum rating plus 50 percent spare
capacity. Annotate data for each circuit on the drawings.
2.18.1 Operation
The system shall automatically operate and control all building speakers
except those installed in the stairs and within elevator cabs. The
speakers in the stairs and elevator cabs shall operate only when the
microphone is used to deliver live messages.
2.18.2 Construction
Amplifiers shall utilize computer grade solid state components and shall
be provided with output protection devices sufficient to protect the
amplifier against any transient up to 10 times the highest rated voltage
in the system.
2.18.3 Inputs
Equip each system with separate inputs for the tone generator,
digitalized voice driver and panel mounted microphone [Public Address
Paging Function (where allowed)]. Microphone inputs shall be of the low
impedance, balanced line type. Both microphone and tone generator input
shall be operational on any amplifier.
The tone generator shall be of the modular, plug-in type with securely
attached labels to identify the component as a tone generator and to
identify the specific tone it produces. The tone generator shall
produce a code 3 temporal tone and shall be constantly repeated until
interrupted by either the digitalized voice message, the microphone
input, or the alarm silence mode as specified. The tone generator shall
be single channel with an automatic backup generator per channel such
that failure of the primary tone generator causes the backup generator
to automatically take over the functions of the failed unit and also
causes transfer of the common trouble relay.
2.20 ANNUNCIATOR
Page 25
their programmed address to facilitate their physical location from the
LCD display information.
2.20.2 Programming
Page 26
manufacturer shall have the color lens tested to the full UL 1971 polar
plotting criteria, voltage drop, and temperature rise as stated in
1971. [Fire Alarm Notification Appliances shall have clear high
intensity optic lens, xenon flash tubes, and be marked ["Fire"] in red
letters.][Fire Alarm/Mass Notification Appliances shall have [amber]
high intensity optic lens, xenon flash tubes, and output white light and
be marked "ALERT" in red letters.] The light pattern shall be disbursed
so that it is visible above and below the strobe and from a 90 degree
angle on both sides of the strobe. Strobe flash rate shall be 1 flash
per second and a minimum of [15][30][75][ ] candela (actual output
after derating for tinted lens) based on the UL 1971 test. Strobe shall
be [surface][semi-flush] mounted. [Where more than two appliances are
located in the same room or corridor or field of view, provide
synchronized operation.] Devices shall use screw terminals for all
field wiring.
2.22.3 Chimes
2.24 INTERFACE TO THE BASE WIDE MASS NOTIFICATION NETWORK: Not Used
2.26 WIRING
The SLC wiring shall be [solid copper] cable in accordance with the
manufacturers requirements.Copper signaling line circuits and
initiating device circuit field wiring shall be No. [16] AWG size
twisted and shielded solid conductors at a minimum. Visual notification
appliance circuit conductors, that contain audible alarm appliances,
shall be solid copper No. 14 AWG size conductors at a minimum.[ Speaker
circuits shall be copper No. [16] AWG size twisted and shielded
conductors at a minimum.] Wire size shall be sufficient to prevent
voltage drop problems. Circuits operating at 24 VDC shall not operate at
less than the UL listed voltages for the sensors and/or appliances.
Power wiring, operating at 220 VAC minimum, shall be a minimum No. 12
AWG solid copper having similar insulation. Acceptable power-limited
cables are FPL, FPLR or FPLP as appropriate with red colored covering.
Nonpower-limited cables shall comply with NFPA 70.
Page 27
PART 3 EXECUTION
3.1.1 FMCP
Locate the FMCP [where indicated on the drawings]. [Surface mount] the
enclosure with the top of the cabinet 2 m above the finished floor or
center the cabinet at [1.5] m, whichever is lower. Conductor
terminations shall be labeled and a drawing containing conductors, their
labels, their circuits, and their interconnection shall be permanently
mounted in the FMCP.
Locate sensors [as indicated] on a 100 mm mounting box. Locate smoke and
heat sensors on the ceiling. Install heat sensors not less than 100 mm
from a side wall to the near edge. Heat sensors located on the wall
shall have the top of the sensor at least 100 mm below the ceiling, but
not more than 300 mm below the ceiling. Smoke sensors are permitted to
be on the wall no lower than 300 mm from the ceiling with no minimum
distance from the ceiling. In raised floor spaces, install the smoke
sensors to protect 21 square meters per sensor. Install smoke sensors no
closer than 1.5 m from air handling supply outlets.
3.1.5 Annunciator
Page 28
3.2 SYSTEM FIELD WIRING
Page 29
Labeling of conductors at terminal blocks in terminal cabinets, FMCP,
and remote FMCP and the LOC shall be provided at each conductor
connection. Each conductor or cable shall have a shrink-wrap label to
provide a unique and specific designation. Each terminal cabinet, FMCP,
and remote FMCP shall contain a laminated drawing that indicates each
conductor, its label, circuit, and terminal. The laminated drawing shall
be neat, using 12 point lettering minimum size, and mounted within each
cabinet, panel, or unit so that it does not interfere with the wiring or
terminals. Maintain existing color code scheme where connecting to
existing equipment.
Maintain existing fire alarm equipment fully operational until the new
equipment has been tested and accepted by the Contracting Officer. As
new equipment is installed, label it "NOT IN SERVICE" until the new
equipment is accepted. Once the new system is completed, tested, and
accepted by the Government, it shall be placed in service and connected
to the station fire alarm system. Remove tags from new equipment and
tag the existing equipment "NOT IN SERVICE" until removed from the
building.
b. Disconnect and remove the existing fire alarm and smoke detection
systems where indicated and elsewhere in the specification.
The following new system connections shall be made during the last phase
of construction, at the beginning of the preliminary tests. New system
connections shall include:
Once these connections are made, system shall be left energized and new
audio/visual devices deactivated. Report immediately to the Contracting
Officer, coordination and field problems resulting from the connection
of the above components.
3.5 FIRESTOPPING
Page 30
3.6 PAINTING
Paint exposed electrical, fire alarm conduit, and surface metal raceway
to match adjacent finishes in exposed areas. Paint junction boxes red in
unfinished areas and conduits and surface metal raceways shall be
painted with a 25 mm wide red band every 3 m in unfinished areas..
Painting shall comply with Section 09 90 00 PAINTS AND COATINGS.
e. Provide space to identify the date and time of each test. Provide
space to identify the names and signatures of the individuals
conducting and witnessing each test.
Page 31
preliminary tests. The Contractor and an authorized representative from
each supplier of equipment shall be in attendance at the preliminary
testing to make necessary adjustments.
When tests have been completed and corrections made, submit a signed,
dated certificate with a request for formal inspection and tests to the
[Contracting Offices Designated Representative (COR)].
Notify the Contracting Officer in writing when the system is ready for
final acceptance testing. Submit request for test at least 15 calendar
days prior to the test date. The tests shall be performed in accordance
with the approved test procedures in the presence of the Contracting
Officer. Furnish instruments and personnel required for the tests. A
final acceptance test will not be scheduled until the following are
provided at the job site:
[In existing buildings, the transfer of devices from the existing system
to the new system and the permission to begin demolition of the old fire
alarm system will not be permitted until the as-built drawings and O&M
Page 32
manuals are received.]
Test the system in accordance with the procedures outlined in NFPA 72,
ISO 7240-16, IEC 60268-16. The required tests are as follows:
a. Megger Tests: After wiring has been installed, and prior to making
any connections to panels or devices, wiring shall be megger tested
for insulation resistance, grounds, and/or shorts. Conductors with
300 volt rated insulation shall be tested at a minimum of 250 VDC.
Conductors with 600 volt rated insulation shall be tested at a
minimum of 500 VDC. The tests shall be witnessed by the Contracting
Officer and test results recorded for use at the final acceptance
test.
g. Test both primary power and secondary power. Verify, by test, the
secondary power system is capable of operating the system for the
time period and in the manner specified.
k. Verify that software control and data files have been entered or
programmed into the FACP. Hard copy records of the software shall
be provided to the Contracting Officer.
Page 33
n. Measure voltage readings for circuits to ensure that voltage
drop is not excessive.
b. Ensure that a CIS value greater than the required minimum value is
provided in each area where building occupants typically could be
found. The minimum required value for CIS is [.7] [.8].
c. Areas of the building provided with hard wall and ceiling surfaces
(such as metal or concrete) that are found to cause excessive sound
reflections may be permitted to have a CIS score less than the
minimum required value if approved by the DOD installation, and if
building occupants in these areas can determine that a voice signal
is being broadcast and they must walk no more than 10 m to find a
location with at least the minimum required CIS value within the
same area.
e. Take measurements near the head level applicable for most personnel
in the space under normal conditions (e.g., standing, sitting,
sleeping, as appropriate).
f. The distance the occupant must walk to the location meeting the
minimum required CIS value shall be measured on the floor or other
walking surface as follows:
Page 34
intelligibility score at each test location.
3.8.1 Instructor
-- End of Section --
Page 35
SECTION 31 00 00
EARTHWORK
07/06
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.5 Overhaul
Page 1
Overhaul is the product of the quantity of materials hauled beyond the
free-haul limit, and the distance such materials are hauled beyond the
free-haul limit, expressed in station meters.
1.2.6 Topsoil
1.2.8 Rock
Unstable material are too wet to properly support the utility pipe,
conduit, or appurtenant structure.
63 mm 100
4.75 mm 40 - 85
2.00 mm 20 - 80
425 micrometers 10 - 60
75 micrometers 5 - 25
Page 2
1.2.11 Initial Backfill Material
As used herein, a structure where both the foundation and floor slab are
pile supported.
1.3 MEASUREMENT
1.3.1 Excavation
The unit of measurement for excavation and borrow will be the cubic
meter, computed by the average end area method from cross sections taken
before and after the excavation and borrow operations, including the
excavation for ditches, gutters, and channel changes, when the material
is acceptably utilized or disposed of as herein specified. The
measurements will include authorized excavation of rock (except for
piping trenches that is covered below), authorized excavation of
unsatisfactory subgrade soil, and the volume of loose, scattered rocks
and boulders collected within the limits of the work; allowance will be
made on the same basis for selected backfill ordered as replacement.
The measurement will not include the volume of subgrade material or
other material that is scarified or plowed and reused in-place, and will
not include the volume excavated without authorization or the volume of
any material used for purposes other than directed. The volume of
overburden stripped from borrow pits and the volume of excavation for
ditches to drain borrow pits, unless used as borrow material, will not
be measured for payment. The measurement will not include the volume of
any excavation performed prior to the taking of elevations and
measurements of the undisturbed grade.
Measure and pay for rock excavation by the number of cubic meters of
Page 3
acceptably excavated rock material. Measure the material in place, but
base volume on a maximum 750 mm width for pipes 300 mm in diameter or
less, and a maximum width of 400 mm greater than the outside diameter of
the pipe for pipes over 300 mm in diameter. Provide the measurement to
include all authorized overdepth rock excavation as determined by the
Contracting Officer. For manholes and other appurtenances, compute
volumes of rock excavation on the basis of 300 mm outside of the wall
lines of the structures.
1.4 SUBMITTALS
Shoring ; G
Page 4
Testing
Borrow Site Testing
SD-07 Certificates
Testing
Page 5
PART 2 PRODUCTS
Test offsite soils brought in for use as backfill for Total Petroleum
Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX)
and full Toxicity Characteristic Leaching Procedure (TCLP) including
ignitability, corrosivity and reactivity. Backfill shall contain a
maximum of 100 parts per million (ppm) of total petroleum hydrocarbons
(TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl
Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH
concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX
concentrations by using EPA SW-846.3-3 Method 5030/8020.Perform TCLP
in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site
Testing for TPH, BTEX and TCLP from a composite sample of material from
the borrow site, with at least one test from each borrow site. Do not
bring material onsite until tests have been approved by the Contracting
Officer.
Red: Electric
Yellow: Gas, Oil; Dangerous Materials
Orange: Telephone and Other
Communications
Blue: Water Systems
Green: Sewer Systems
White: Steam Systems
Gray: Compressed Air
Page 6
12 AWG.
2.4.2 Grout
2.4.3 Rock
ASTM A 139/A 139M, Grade B, or ASTM A 252, Grade 2, smooth wall pipe.
Match casing size to the outside diameter and wall thickness as
indicated on the drawings. Protective coating is not required on casing
pipe.
Page 7
PART 3 EXECUTION
Page 8
leaving a smooth, solid, undisturbed surface to receive the concrete or
masonry.
3.2.3 Drainage
Provide for the collection and disposal of surface and subsurface water
encountered during construction. Completely drain construction site
during periods of construction to keep soil materials sufficiently dry.
Construct storm drainage features (ponds/basins) at the earliest stages
of site development, and throughout construction grade the construction
area to provide positive surface water runoff away from the construction
activity and or provide temporary ditches, swales, and other drainage
features and equipment as required to maintain dry soils. When
unsuitable working platforms for equipment operation and unsuitable soil
support for subsequent construction features develop, remove unsuitable
material and provide new soil material as specified herein. It is the
responsibility of the Contractor to assess the soil and ground water
conditions presented by the plans and specifications and to employ
necessary measures to permit construction to proceed.
3.2.4 Dewatering
Page 9
support for the bottom quadrant of each section of the pipe. Excavate
bell holes to the necessary size at each joint or coupling to eliminate
point bearing. Remove stones as recommended by the pipe manufacturer,
whichever is smaller, to avoid point bearing.
Ensure that footing subgrades have been inspected and approved by the
Contracting Officer prior to concrete placement. Excavate to bottom of
pile cap prior to placing or driving piles, unless authorized otherwise
by the Contracting Officer. Backfill and compact over excavations and
changes in grade due to pile driving operations to 95 percent of
ASTM D 698 maximum density.
Page 10
3.3 SELECTION OF BORROW MATERIAL
3.5 SHORING
Page 11
and required backfills. Do not haul satisfactory material excavated in
one grading area to another grading area except when so directed in
writing. Place and grade stockpiles of satisfactory, unsatisfactory and
wasted materials as specified. Keep stockpiles in a neat and well
drained condition, giving due consideration to drainage at all times.
Clear, grub, and seal by rubber-tired equipment, the ground surface at
stockpile locations; separately stockpile excavated satisfactory and
unsatisfactory materials. Protect stockpiles of satisfactory materials
from contamination which may destroy the quality and fitness of the
stockpiled material. If the Contractor fails to protect the stockpiles,
and any material becomes unsatisfactory, remove and replace such
material with satisfactory material from approved sources.
Page 12
stream, endanger a partly finished structure, impair the efficiency or
appearance of any structure, or be detrimental to the completed work in
any way.
Provide buried utility lines with utility identification tape. Bury tape
300 mm below finished grade; under pavements and slabs, bury tape 150 mm
below top of subgrade.
Place backfill adjacent to any and all types of structures, and compact
to at least 100 percent laboratory maximum density for cohesive
materials or 100 percent laboratory maximum density for cohesionless
materials, to prevent wedging action or eccentric loading upon or
against the structure. Prepare ground surface on which backfill is to
be placed as specified in paragraph GROUND SURFACE PREPARATION. Provide
compaction requirements for backfill materials in conformance with the
applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish
compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled
rollers, vibratory compactors, or other approved equipment.
Backfill trenches to the grade shown. Backfill the trench above the top
of pipe prior to performing the required pressure tests. Leave the
joints and couplings uncovered during the pressure test. Do not backfill
the trench until all specified tests are performed.
Replace unyielding material removed from the bottom of the trench with
select granular material or initial backfill material.
Provide bedding of the type and thickness shown. Place initial backfill
material and compact it with approved tampers to a height of at least
300 mm above the utility pipe or conduit. Bring up the backfill evenly
on both sides of the pipe for the full length of the pipe. Take care to
ensure thorough compaction of the fill under the haunches of the pipe.
Page 13
Except as specified otherwise in the individual piping section, provide
bedding for buried piping in accordance with AWWA C600, Type 4, except
as specified herein. Compact backfill to top of pipe to 95 percent of
ASTM D 698 maximum density. Provide plastic piping with bedding to
spring line of pipe. Provide materials as follows:
b. Class II: Coarse sands and gravels with maximum particle size of
40 mm, including various graded sands and gravels containing
small percentages of fines, generally granular and noncohesive,
either wet or dry. Soil Types GW, GP, SW, and SP are included
in this class as specified in ASTM D 2487.
Fill the remainder of the trench, except for special materials for
roadways, railroads and airfields, with satisfactory material. Place
backfill material and compact as follows:
Page 14
Excavate trenches to a depth as shown from the existing ground surface,
or from the indicated finished grade, whichever is lower, to the top of
the pipe. For fire protection yard mains or piping, an additional cover
is required.
Provide new smooth wall steel pipeline casing under new or existing
pavement in a trench. Provide each new pipeline casing, where indicated
and to the lengths and dimensions shown, complete and suitable for use
with the new piped utility as indicated. Install pipeline casing by dry
boring and jacking method as follows:
Mechanically bore holes and case through the soil with a cutting head on
a continuous auger mounted inside the casing pipe. Weld lengths of pipe
together in accordance with AWS D1.1/D1.1M. Do not use water or other
fluids in connection with the boring operation.
3.12.3.2 Cleaning
Clean inside of the pipeline casing of dirt, weld splatters, and other
foreign matter which would interfere with insertion of the piped
utilities by attaching a pipe cleaning plug to the boring rig and
passing it through the pipe.
Page 15
with finer material. Provide at least one "weep hole" through grouted
rip-rap for every 4.65 square meters of finished surface. Provide weep
holes with columns of bedding material, 100 mm in diameter, extending up
to the rip-rap surface without grout.
3.12.4.3 Grouting
3.13 EMBANKMENTS
Page 16
select material.
3.14.2 Construction
3.14.3 Compaction
3.15 FINISHING
Page 17
3.15.2 Capillary Water Barrier
Place a capillary water barrier under concrete floor and area-way slabs
grade directly on the subgrade and compact with a minimum of two passes
of a hand-operated plate-type vibratory compactor.
Construct areas within 1.5 m outside of each building and structure line
true-to-grade, shape to drain, and maintain free of trash and debris
until final inspection has been completed and the work has been accepted.
3.17 TESTING
a. One test per 200 m², or fraction thereof, of each lift of fill
or backfill areas compacted by other than hand-operated machines.
b. One test per 200 m², or fraction thereof, of each lift of fill
or backfill areas compacted by hand-operated machines.
a. One check test per lift for each 200 m² square meters, or
fraction thereof, of each lift of fill or backfill compacted by
Page 18
other than hand-operated machines.
b. One check test per lift for each 100 m², of fill or backfill
areas compacted by hand-operated machines.
After other required tests have been performed and the trench backfill
compacted to first 0.5 meters above the top of the pipe then to the
finished grade surface , inspect the pipe to determine whether
significant displacement has occurred.Conduct this inspection in the
presence of the Contracting Officer. While inspecting pipes use
shining a light or laser between manholes or manhole locations, or by
the use of television cameras passed through the pipe. If, in the
judgement of the Contracting Officer, the interior of the pipe shows
poor alignment or any other defects that would cause improper
functioning of the system, replace or repair the defects as directed at
no additional cost to the Government.
-- End of Section --
Page 19