Professional Documents
Culture Documents
Project Name Nakheel Mall Project Number UPR377 Managing Office: ISG
Satisfactory
(please tick)
Ref RAMS Considerations
Yes No/NA
1 Work activity detailed within the Risk Assessments / Method Statements fully representative of the actual tasks to be undertaken
2 Sequence of work activity listed in a logical order
3 Site specific content included with the site actually named and the date / time of the tasks also detailed if relevant
4 Risks associated with the work activity clearly identified e.g. working at height, dust, exposure to noise / vibration etc
5 Supporting issue specific risk assessments included as necessary e.g. manual handling, COSHH and MSDS etc
6 Classification of persons exposed to the risks identified e.g. contractors, client employees, members of public etc
7 Suitable control measures to mitigate the risks stipulated – e.g. use of scaffolding tower, use of PPE, use of lifting equipment etc
8 Quoted types of plant and equipment suitable and available on-site with statutory inspection evidence provided where required
9 Quoted types of materials and / or substances to be used suitable and available on-site
10 Required competencies of operatives who will be undertaking the work activity identified
11 Competent persons named, certificates submitted to ISG, i.e. erection, dismantling, inspection of mobile towers
12 Specific arrangements for the delivery, storing and movement of plant and material considered and planned accordingly
13 Emergency / rescue plans considered as necessary e.g. work from height / confined spaces
14 Details of communication outlined within the documentation
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 1 of 17
Risk Assessment, Method Statement (RAMS)
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 2 of 17
Risk Assessment, Method Statement (RAMS)
Note: To be submitted at least 5 working Days prior to commencement of work
Other Trade Contractors to receive a copy of RAMS for information, coordination and interface purposes
Name Name
Company Name Company Name
Proposed Start
1.0 Proposed Start Date: 24 Jan 2024 09.00 AM
Time:
1.1 Expected Duration: 1 Day
Exact Location (S):
1.2 Nakheel Mall, Basement 2,B1,LG,GF,L1 & L2
Attach Plan (if necessary)
1.3 Document Prepared By: Bibin
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 3 of 17
Risk Assessment, Method Statement (RAMS)
SITE PREPARATION
All safety permits shall be obtained before the commencement of any works.
All workers or site staff shall undergo must undergo daily safety toolbox talk and risk briefing
prior to the initiation of any site activity.
Material shifting shall be done with sufficient manpower and in compliance safe lifting
procedure.
Dilapidation report citing the site conditions and the condition of existing MEP services shall be
submitted in advance to ISG.
It shall be ensured that the source of Electricity, Water and drainage is approved by the
Landlord prior to commencement of connection to the existing services.
The Supervising Engineer / Supervisor / Team leaders shall confirm that all necessary
documentation is in place to proceed with the works.
Site works shall proceed only after the receipt of instruction from the Site Engineer/Project
Manager after ensuring compliance to the project specific requirements.
After the civil clearance advice to proceed with MEP installations, ensure that area is clean and
ready to commence the work.
Contractor shall ensure that the materials are free of any damage or deformity of any kind.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 4 of 17
Risk Assessment, Method Statement (RAMS)
Podium Ladder
For light duty works low level works EMKAY shall utilise podium ladders
Ladders shall be propped on level surfaces only. Aluminium or metal ladders shall not be used
near the live electrical services in areas exposed to chances of electrocution.
EMKAY will ensure that ladder shall never be placed on a box, bricks or any other thing to
reach the height and that the podium ladders are fully opened and locked before use.
Swing guard is in close position when operatives on the podium working platform.
Proper PPE to be used when working on the top of a ladder.
Ladder inspection tags will be obtained from ISG after submitting ladder inspection report. For
scaffolding inspection tags shall be provided by trained EMKAY employee. PASMA
Certificate of scaffolding inspector will be available at site.
METHOD OF INSTALLATION
Conduits and trunking shall connect to the Distributions Board by adaptors glands, after the
cables, wires are pulled to the DB, through the containment as per the drawings and load
schedules, Further the cables and wires dressed properly and terminated to the assigned
breakers.
Individual circuit wires shall be then grouped properly, and neat dressing shall be done and
then terminated to a particular breaker using proper size Sleeve number ferules / lugs. Each
outgoing will be labelled to identify the circuit number.
Distribution board serving the site temporary loads shall be connected to the spare breaker
facilitated by the Landlord as per the load demand.
Necessary PTW and Isolations will be obtained prior to the connection to existing facility. All
energisations will be carried out in the presence of landlord representative.
On receipt of confirmation from the landlord/main contractor on the feeding point, necessary
isolation permits will be obtained to connect to the existing LV network
Obtain a valid access permit for the electrical room and electrical cabinet located in
Basement 2, basement 1, LG, L1 & L2 prior to start the cable pulling works.
Extra care should be taken before pulling the wires and cables; testing will be carried out
before pulling the cable for damage of insulation, continuity of the conductor by Megger. Wires
shall be arranged according to the size and color mentioned in the load schedule for lighting
and power circuits. All wiring of multi-point circuits in a “loop-in” system, and do not use joints
or connections, other than those required for the connection of switches, fuses, socket outlets.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 5 of 17
Risk Assessment, Method Statement (RAMS)
Entire wire roll shall be kept in a safe stand to rotate as free. Wire size, color and quantity shall
be as per the load schedule and tie with insulation tape to the pulling spring and pull from the
other side. Technician will ensure the neutral wire should not come to the switch boxes. If any
difficulties found during pulling apply a small amount of lubricant to the wire. All the boxes and
points are wired with earth continuity conductor.
A slack of at least 200mm of wire will be left at each outlet and 300 mm for lighting points
wherever there is no false ceiling, but inside DB the length is around 800 mm. Put proper
identification for the wires in DB for connection purposes and continuity testing.
The cables and wires shall be in accordance with the approved load schedules and shop
drawings. During installation technician shall pull the cable from one side and push from other
side in a uniform manner until reach the destination.
ECC (Earth Continuity Conductor) of green yellow color equal to half the size of phase
conductor shall be laid with the cable for size including and above 25 Sq.mm2 and of
same for cable equal and below 16 sq.mm.
Leave around a length of 1 meter in DB’s and 2 meter in SMDB’s as loop when pulling the
cable.
Site office cable will tie to the existing power cable tray and Supports in Basement level 2.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 6 of 17
Risk Assessment, Method Statement (RAMS)
Ensure the pulled cable is free from any damages and conduct a megger test to validate.
Ensure the Cable Pulling works Completed and terminated in the Site office temporary
SMDB.
Ensure valid Shutdown permit (S1B-L02-SMDB-RT1 Located level 2 Electrical Room)
from IMDAAD prior to start the termination works.
Expected duration for the shutdown was 3 hours.
Once the Shutdown received from M/s IMDAAD, ensure shutdown tag provided on the LV
panel respective breaker.
we will ensure the S1B-L02-SMDB-RT1 is free from Voltage by using a multi meter.
Remove the existing connected cable from DB-RT-E03 (125A) and connect our temporary
cable with required Gland and Lugs.
After terminating the cable, we will ensure all the terminations are properly tighten and
safe manner with an IMDAAD representative.
Once the termination approved by the IMDAAD. We will close all the shrouds and closed
the SMDB prior to energize the panel.
Once the Panel Energized, we will ensure the voltage between each phases and Phase
to neutral and earth prior to turn on the temporary site office SMDB.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 7 of 17
Risk Assessment, Method Statement (RAMS)
S1B-L02-SMDB-RT1 RYB3- 125A(DB-RT-E03) Existing breaker will used for our 59kW load
PERSONNEL RESPONSIBILITIES
PROJECT MANAGER
The Contractor / Subcontractor Project Manager is responsible for implementing this method
statement and its associated safety precautions in compliance to the risk assessment.
Project Manager shall be responsible for planning, scheduling and managing the onsite
activities including the arrangement of necessary manpower and equipment’s.
Responsible for ensuring compliance to the project QHSE requirements.
Manages subcontractors/vendors and acts as the single point of management contact between
the main and the subcontractor.
Liaises and coordinates with the Main Contractor/Consultant for commercial and contractual
matters.
Responsible for managing the project schedule, cost baselines and ensuring compliance to
project KPI’s and Metrics.
PROJECT/SITE ENGINEER
QA/QC ENGINEER
He will be overall responsible for the implementations of this procedure and will carry out the
material inspection to ensure that materials received on site are approved materials submittal.
He will monitor the installation works according to the approved shop drawing &method
statement.
Coordinate with the Consultant to carry out the inspection/testing of the completed works.
Responsible for monitoring the work and ensure that all installation or construction works will
be carried out in accordance with the specification’s requirements, approved drawings and
good engineering practice. QA QC Engineer will carry out internal/preliminary, inspection of
work completed prior to raise an inspection/testing to the Consultant.
He will maintain comprehensive records of inspection and test record (ITP’s) for the purpose of
reference and documentation.
SAFETY OFFICER
He will be overall responsibility for the implementations of the Safety procedure at site.
Safety officer shall be responsible for maintaining the Safety Documentation, Reports.
Audits the site on regular intervals for compliance to HSSE requirements.
Implements control measures in coordination with the site engineer and supervisors.
Leads the implementation of all safety related activities on sites.
SITE SUPERVISOR
Ensure that the construction work is carrying out properly and according to instructions
received from the site engineer.
Coordinating with the site team and subcontractors for the work to be done.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 9 of 17
Risk Assessment, Method Statement (RAMS)
2.3 NOISE: During drilling the soffit for supports with power tools
What activities will generate noise? How Noisy area can be defined though: -
will you minimise noise? How will you Sound pressure, time for distribution sound power and its
define noisy areas? Will you undertake a frequency.
noise assessment?
See Appendix: 4
Noise shall be reduced by using: -
Ear plug if found excessive and zoning of noisy work areas.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 10 of 17
Risk Assessment, Method Statement (RAMS)
Training Certs/Qualifications:
Supervisor (with contact No):
or person in charge of site
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 11 of 17
Risk Assessment, Method Statement (RAMS)
4.1 WASTE Management Housekeeping Waste will be removed to the pre-arranged waste collection.
and Storage REMOVAL:
How will waste be removed from the site?
Consider the location of skips, provision of
bins and what collection arrangements will
be put in place.
Disposal of controlled waste?
4.2 HOUSEKEEPING and STORAGE: Site Supervisor shall ensure the works areas are maintained
How will materials be stored on-site?
Ensure that materials are properly stacked and stored.
How will you maintain the required standard
of housekeeping? Excess materials shall be returned to contractors store.
6.0 MANDATORY SITE PPE (AS PER Safety Hard Hat / Safety Shoes / Hi- Visible Vest / Gloves, Eye
BRITISH AND EUROPEAN Protection, Mask
STANDARDS):
6.1 TASK-SPECIFIC PPE: Hearing protection for high noisy activities > 85dB
Identified as per risk assessment.
Respiratory protection (Safety masks)
State grade and standard. Note:
Consideration of working environments will Hand protection, Safety Goggles
need to be included and additional PPE
may be required e.g. cut resistant arm
protection for work in ceiling voids etc.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 12 of 17
Risk Assessment, Method Statement (RAMS)
8.0 RESPONSIBILITY FOR TASK Task lighting for temporary works shall be provided.
LIGHTING:
Consideration should be given to site
hours; this may immediately highlight the
need for artificial lighting if work starts
before the first light or continues after dusk.
Additionally, the requirement for general
site lighting and specific task lighting would
be inserted here
NO PORTABLE HALOGEN LIGHTS
ALLOWED
9.0 TO WHOM THE INFORMATION All the personnel involved in this works shall be briefed prior to
WILL BE COMMUNICATED AND works. Briefing shall be recorded on RAMS briefing sheet, copy given
HOW? to Main Contractor HSE. For Non–English speaking personnel,
(to include non-English speaking provide translation in to the local language familiar to the employee.
operatives)
9.1 CONFIRMATION OF OPERATIVES Signed briefing sheets are to be submitted prior to the commencement of
BRIEFING: works
10.0 PERSON RESPONSIBLE FOR Jagath.M Phone No: 050 365 3569
MONITORING/REVIEW OF THE
SAFE SYSTEM OF WORK AND
ENSURING COMPLIANCE:
Show here who is responsible for this
operation/task, and their contact
numbers.
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS- 001 HSQE Manager HSE February 2023 04 Page 13 of 17
APPENDIX 1
Risk Assessment
Please refer to Document Reference:
HSQE-RAMS-006 Risk Assessment Template with Guide List
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HSQE Manager HSE February 2023 04 Page 14 of 17
Risk Assessment
Severity
>3 day Injury 3 Possible 4 20 16 12 8 4
Project Name and/or Address: Permit to Work Reference Numbers Major Injury 4 Probable 3 15 12 9 6 3
Death 5 Frequently 2 10 8 6 4 2
1 5 4 3 2 1
Nakheel Refurbishment
Persons 1. Employees 2. Contractors 1. ISG 2. TC Supervisor
Responsibility
Affected 3. Client Employees 4. Public 3. TC Operator 4. TC Workforce
3 Work at Height - Damaged scaffold parts; Fall from height, scaffold 2 5 4 20 - Double width towers must be given preference – narrow width towers only to be used in areas where it is 5 2 10 2,3,4
more than 3m - incompetent persons; collapse, property not possible to place a double width or in very limited spaces
- Assembly, dismantling or altering must be carried out by PASMA trained person/s
Mobile Scaffold - uneven surfaces; damage.
- The ratio of the minimum base dimension to the height of the working platform shall not exeed 1:3 ratio.
(Working at height - uninspected scaffolding; - Access up and down from working platforms should never be from outside the scaffold, only by the internal
on mobile - Failure to erect as per Serious injury, fatality, ladder frame and through the trap doors.
aluminium tower manufacturers multiple fatalities. - Trap doors must be closed when using the platform.
recommendations - PASMA trained inspector must inspect and tag tower from first use, at 7-day intervals and when major
scaffold (more than
alterations have been made
3m) - All brakes deployed and functional prior to work is carried out on the platform
- If complete guardrails have been correctly installed, It is recommended NOT to use a safety harness when
working on lightweight aluminium mobile towers (in line with PASMA recommendations).
- Constructed as per manufacturer’s instructions
- 3T (Through the Trap) method implemented when assembling/dismantling towers
- ISG Visual Standards should be posted on all towers
- Towers must meet the requirements of EN1004
- Narrow width towers 2.4m and above must deploy 4 stabilisers
- Double width towers 3m and above must deploy 4 stabilisers
- Where the deployment of stabilisers in the manufacturer’s instructions is more stringent than stated above,
the manufacturer's instructions will be followed.
- Should the scaffold require repositioning, this must be done when no personnel are on the working
platform.
- Exclusion zones deployed with physic barriers prior to work commencement
- All tools must be tethered when working at height.
- A fiberglass mobile tower must be used for electrical work being completed at height as it is non-conducted
and spark resistant.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 1 of 3
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
4 Manual Handling - Wrong body posture - Major or minor body 1,2,3 4 4 16 - All involved persons for the activity of manual handling needs to undergo safety induction, task briefing, 4 1 4 2, 3, 4
- Uneven Surfaces injuries TBT and awareness training before starting the task;
- All activities involving manual handling must have appropriate planning;
- Poor housekeeping - Fracture
- Pre-check of the route to be taken to identify and clear any obstructions;
- Sharp edges - Hand injuries - Ensure that the work area is free from any obstruction before starting any manual handling activity;
- Failure of lifting - Head and eye injuries - All materials to be lifted must be assessed and checked before starting any manual lift;
- Lack of physical space - Foot and leg injuries - Appropriate manual handling technique must be followed accordingly to avoid back injuries;
- Repetitive movements - Bruises and cuts - Use the power of your legs rather than you back to avoid any back injuries;
- Poor workplace design - Strains and Sprains - If doing manual tandem lift, assess and do trial lift first for the material before proceeding;
- Back injuries - Ensure that the manual handling activity is competently supervised;
- Do not overexpose a person to a manual handling activity. Plan the activity and assign a workers rotation;
- Ensure that all sharp edges have been safely covered or protected before starting any manual lifts;
- Assess the work space if needed before starting manual handling. Do not push through the activity if the
space or access is obstructed with unwanted materials;
- Conduct regular housekeeping around the work area before and after the task;
- Ensure that all operatives who are involved in manual handling are using the standard 5-point PPEs and
task specific PPEs.
5 Use of Hand Tools A- Misuse of hand tools Damaged Tools, 2 3 3 9 - Hand tools shall not be kept on walkways. 3 1 3 2, 3, 4
B- Improper maintenance Improvised Tools, Sharp - Hand tools shall be kept in tool boxes, specific & designated areas for storage whenever not in use &
should not be kept unattended at any time.
C- Homemade handtools Edges, Fall of Tools
- All tools shall be inspected for any damages on daily basis and at regular intervals.
from Height - Tie off tools with a tool teather to prevent their fall while working at height.
- Ensure that no homemade/makeshift or any altered tools are used at the site.
A- Cuts, lacerations, - Ensure the operatives are wearing hand gloves during the activity.
bruises - Ensure to isolate the area below scaffolding when using hand tools on at height.
B- Frequent / prolonged - Ensure hand tools are in good condition when received from store or supplier.
use of hand tools can - Provide Appropriate PPE.
- Choose the Safest Tools for the task.
cause soreness, aches,
- Conduct regularly training and workshops on the safe use of Hand Tool
pains, and fatigue. - Never carry sharp tools with a pointy end in pocket.
- Always be aware of people around you when using hand tools
- Always use the right tools for the job
- Only operate tools according to manufacture instructions
6 Housekeeping - Scattered Materials - Major and minor Head 1,2,3,4 3 4 12 - Provision of approved, dedicated and secured materials storage area. 3 1 3 2, 3, 4
- Dust Injuries - Training and awareness to all workforce and staff regarding the importance of housekeeping;
- Ensure that material storage entry and exit points are visible and free from any obstruction;
- Accumulated cut materials - Eye Irritation
- Cut small materials must be stored in safe designated area or inside a safe skip box;
- Combustible Materials - minor/ major Eye - Appropriate segregation of materials must be done as per item and away from open access;
- COSHH Materials Injuries - Waste management and segregation must be as per approved site plan;
- Fumes - Fire - Designated COSHH/ chemical room must be established on site;
- Spills/ stagnant water - Asphyxiation - All COSHH materials must be segregated as per item with visible labeling;
- Obstructed Access - Shortness of breath - Used COSHH materials must be securely covered and stored in designated safe area only;
- minor or major Head - Provide the MSDS and COSHH assessment for all available Chemicals on site, and ensure the availability
when needed;
Injuries
- Liquid chemicals must be stored on top of a portable drip tray or might be provided with a dedicated storage
area, safe and secured 110% Fireproof bund to avoid any spillage.
- Chemical waste must be disposed and be collected by approved collection local authority;
- If all combustible materials cannot be collected immediately, it must be initially secured or identified with
visible barrier and warning signage;
- Ensure the availability of Spill kits nearby works involving chemicals;
- Avoid accumulation of combustible materials and secure it on separate collection skip for further removal;
- No Brooms are to be used when cleaning floor, vacuum cleaners must be used to avoid accumulation of
dust and airborne particles.
- Conduct regular housekeeping and removal of unwanted materials before and after the task.
- Adopt a 'clean as you go' policy at all times.
26 Scaffolding - Poor workmanship - Falling from height, 1,2,3 5 3 15 - All tube and fitting scaffolds are to be designed in line with the requirements of NASC guidance TG20. 5 1 5 2,3,4
Erection and - untrained erector, - Collision with - All types / brands of system scaffolding used shall conform to the relevant BS EN 12810/12811 standards,
- All scaffolds are to be designed by a competent person, in accordance with the ISG Temporary works
Dismantling - Poor standard of lighting, scaffolding,
procedure
- Weather condition. - Collapse of the - Ensure the scaffolding is erected and dismantled by trained and competent persons
- Lack of edge protection, platform, - All scaffolds shall be erected, modified or dismantled in accordance with the requirements of NASC
- Unstable ground surface. - Cuts/severe injuries. guidance SG4
- Where scaffolding works are to be completed over public areas, these shall be subject to a robust
exclusion zone with interconnected red pedestrian barriers and clear warning signage, with a marshal to
secure the zone.
- Where an exclusion zone cannot be provided, a climbing fan shall be employed and shall rise and lower
with the erection or dismantling respectively.
- All tools shall be tethered. Materials shall be tethered in high-risk environments.
- A separate documented safe system of work for dismantling shall be in place. This shall clearly detail the
striking sequence, methodology and works-specific rescue plan.
- Only electric winch or braked pulley wheels are permitted and shall be subject to a lifting plan.
- Lapped boards are not permitted without justification.
- Gaps are not permitted between boards (including between inside standards).
- Twisted boards are not permitted.
- Horizontal protruding tubes are not permitted.
- Materials may only be stored vertically when restrained and the scaffold has been designed to
accommodate the load.
- Scaffold sheeting and debris netting shall be branded wherever possible and shall be fire retardant to the
LPS 1215 specification for external materials;
- Scaffolding must be erected on level or smooth ground; avoid sloping, uneven surfaces, overhead wires or
other obstructions when erecting scaffolding.
- Adequate guardrails must be fitted on the scaffold to prevent personnel from falling.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 2 of 3
RA RISK RATING RESIDUAL RISK
Risk & Persons
Item Activity Hazard Control Measures Required Responsibility
Concequences Affected Severity Likelihood Risk Severity Likelihood Risk
No.
27 Cabling - Untrained personnel, - Severe injuries 1,2,3 4 2 8 - The operative must be trained and competent. 4 1 4 2,3,4
- Working at height, - Death to the personnel, - Ensure complete isolation of connected live services before such cabling activity.
- Proper or appropriate working at height equipment, such as podium step, and mobile tower, must be
- Cable pulling, - Fall from height,
selected for such cabling activity.
- Working at height, - Cut/abrasion, - The cables must be adequately managed to prevent trips of fall hazards.
- Damaged hand tools. - Shock/electrocution. - Appropriate PPE must be thoroughly worn by the operatives engaged in the activity.
- Energised system. - Do not leave the hand tools unattended on the ground when not in use.
- Hand tools to be stored directly in a toolbox when not in use.
- All tool used during work at height needs to be tethered and secured to avoid a sudden drop.
- Tools shall be of good quality and replaced if the fault is broken.
- No homemade tools shall be used. Tools shall only be used for the purpose they are designed for.
28 DB Installation - Working at height, - Back injury, 1,2,3 4 3 12 - Don’t work on live equipment; isolation and multi-lock system shall be followed. 4 1 4 2,3,4
- Shifting of materials, - Hand injuries/cuts, - Don’t hang cloth or any material on electrical equipment.
- Electrical DB or switchgear should not be handled with wet hands or bodies.
- Manual handling, - Flying debris,
- Electrical switches or access to them shall not block by any material.
- Cable pulling, - Fire and explosion. - Use appropriate PPE while working on electrical DB.
- Overloading, - Use safe work practices every time electrical equipment is used.
- Energised System. - Know the location and how to operate shut-off switches and/or circuit breaker panels. Use these devices to
shut off the equipment during a fire or electrocution.
- Limit the use of extension cords. Use only for temporary operations and then only for short periods. In all
other cases, request installation of a new electrical outlet.
- Place exposed electrical conductors (such as those sometimes used with electrophoresis devices) behind
shields.
27 Cabling - Untrained personnel, - Severe injuries 1,2,3 4 2 8 - The operative must be trained and competent. 4 1 4 2,3,4
- Working at height, - Death to the personnel, - Ensure complete isolation of connected live services before such cabling activity.
- Proper or appropriate working at height equipment, such as podium step, and mobile tower, must be
- Cable pulling, - Fall from height,
selected for such cabling activity.
- Working at height, - Cut/abrasion, - The cables must be adequately managed to prevent trips of fall hazards.
- Damaged hand tools. - Shock/electrocution. - Appropriate PPE must be thoroughly worn by the operatives engaged in the activity.
- Energised system. - Do not leave the hand tools unattended on the ground when not in use.
- Hand tools to be stored directly in a toolbox when not in use.
- All tool used during work at height needs to be tethered and secured to avoid a sudden drop.
- Tools shall be of good quality and replaced if the fault is broken.
- No homemade tools shall be used. Tools shall only be used for the purpose they are designed for.
15 Testing and Energized system, Electrocution, 1,2,3 4 4 16 - Ensure that the testing activity is only as per the approved plan. 4 2 8 2,3,4
commissioning Untrained personnel, Poor quality, - Conduct task briefing and TBT to all involved persons before starting any testing and commissioning works
on site.
Activity Un-authorized persons, Severe burns,
- Additional awareness will be given to all operatives and staff regarding the testing activity.
PPE, False alarm, - PTW and NOC (if required) must be issued and available on site for verification.
Working at height, Falling from height, - Team involved for the testing needs to identify the location of the testing and source panel/ operation board
Working with a rotating Cuts or severe injury, or DB to ensure that everybody is aware of the planned testing.
machine Open and unsecured - Ensure that the area of testing and commissioning is having exclusion zone, isolation and identified entry
panels, point with warning signage to avoid any un-authorized entry.
Noise - Implement the LOTO (Lockout/ Tagout) system to ensure safe process of testing (minimum two locks)
- All panel sources must have dedicated supervision to avoid un-authorized operation.
- Inform the building premises about the test to be done as an additional awareness.
- Ensure that all persons involved are using the mandatory 5-point PPEs and task specific PPE (e.g. earplug,
etc.) with facemask while or during the operation.
- Only suitably experienced or qualified competent personnel to be used to carry out testing
- Suitable height equipment must be selected, such as fibreglass podium step to avoid electrocution.
FORM REF: HSQE-FOR-045a AUTHORISED BY: HSQE Manager | DEPARTMENT: HSQE | DATE OF ISSUE: November 2023 | ISSUE NUMBER: 06 Page 3 of 3
APPENDIX 3
10 Nov 2023
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 14 of 15
APPENDIX 3
FORM REF AUTHORISED BY DEPARTMENT DATE OF ISSUE ISSUE NUMBER PAGE NUMBER
HSQE-RAMS-001 HQSE Manager HSE February 2023 04 Page 15 of 15