Daily flow rate m3/d 1000 1000 500 500

Peak flow rate m3/h 69 69 34 34


kg DOB5/d 600 600 300 300
Input load kg SM/d 660 660 330 330
kg N/d 132 132 66 66
Volume of pool m3 1800 1800 1800 1800
Sludge concentration g DM/L 4 6 2 4
Mass loading kg DOB5/m3/d 0.1 0.1 0.1 0.1
Reference biological mass kg DM 7200 10800 3600 7200
Sludge production kg DM/d
Nitrogen in sludge kg/d 0 0 0 0
Nitrogen rejection kg/d 10 10 5 5
Oxygen demand for biomass kg O2/d 428.4 642.6 214.2 428.4
Oxygen demand for DOB5 kg O2/d 420 420 210 210
Oxygen demand for nitrogen removal kg O2/d 264 264 132 132
Total demand kg O2/d
Peak demands kg O2/h 67 76 33 42
Power for turbine kW 62 70 31 39
Aeration time h/d
AERATION ELECTRICAL CONSUMPTION kWh/d
Mixing power kW 18 18 18 18
Running time h/d 24.0 24.0 24.0 24.0
ELECTRICAL MIXING CONSUMPTION kWh/d
TOTAL ELECTRICAL CONSUMPTION kWh/d
% Overconsumption %
Specific ratio (aeration + mixing) kWh/kg DOB5
Discharge station Pump flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Screening Power kW
Running time h/d
Consumption kWh/d
Grit and FOG removal Power kW
Running time h/d
Consumption kWh/d
Aeration & mixing Consumption kWh/d
Clarifier Power kW
Running time h/d
Consumption kWh/d
Recirculation Pump flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Pumping to thickening processes Pump flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Dynamic thickening processes Pump flow rate kW
Running time h/d
Consumption kWh/d
Other Consumption kWh/d
Total electrical consumption kWh/d
Specific ratio kWh/kgDOB5
69
8

14.5

0.6875
14.5

0.48
14.5

0
0.34
24

63
3
0.9375
0.0

15
4
0.3
0.0

0
0.0

0.0
Exercise N°7

ENERGY CONSUMPTION POST PARAMETERS UNITS


Discharge station Pumping flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Screening Power kW
Running time h/d
Consumption kWh/d
Grit and FOG removal Power kW
Running time h/d
Consumption kWh/d
Bacterial bed Pumping flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Clarifier Power kW
Running time h/d
Consumption kWh/d
Recirculation Pumping flow rate m3/h
TDH m
Power kW
Running time h/d
Consumption kWh/d
Pumping to thickener Pumping flow rate m3/h
TDH m
Power kW
Running time h/j
Consumption kWh/d
Dynamic thickening processes Power kW
Running time h/j
Consumption kWh/d
Other Consumption kWh/d
Total electrical consumption kWh/d
Specific ratio kWh/kgDOB5
DATA SHARE (en %)
69
8

14.5

0.6875
14.5

0.48
14.5

370.0
7.0

24.0

0.34
24

63
3
0.9375
0.0

15
4
0.3
0.0

0
0.0