You are on page 1of 4

PRELIMINARY AND GENERAL

Item Description Unit Qty Material Cost

1 PRELIMINARY AND GENERAL

1.1 FIXED-CHARGE ITEMS

Contractual Requirements (Specify) sum 1 R -

Establishment of Facilities on Site


2 Site Office and Camp Facilities
(a) Office / Meeting Facilities sum 1 R -
(b) Material Store Facilities sum 1 R -
(c) Ablution facilities sum 1 R -
(d) Approved Construction Board Signage sum 1 R -

Other applicable fixed-charge obligations (Specify)

i) __________________________
sum 1

ii) __________________________
sum 1

iii) __________________________
sum 1

Removal of Contractor's establishment on completion sum 1

Occupational Health and Safety

Compliance with Occupational Health and Safety


Act (Act 85 of 1993) and its regulations and with
the Employers Health and Safety Specification sum 1 R -

1.2 TIME-RELATED ITEMS

Contractual requirements (Specify) sum 1 R -

Supervision for duration of construction sum 1 R -

Company and head office overhead costs for the


duration of the contract sum 1 R -

Other applicable fixed-charge obligations (Specify)

i) __________________________
sum 1

ii) __________________________
sum 1

iii) __________________________
sum 1
Occupational Health and Safety

Compliance with Occupational Health and Safety


Act (Act 85 of 1993) and its regulations and with the
Employers Health and Safety Specification sum 1 R -

Total : Schedule 1
Preliminary and General
Carried forward to Summary of Schedules
Amount (R)
Labour Cost Excluding
VAT

R - R -

R - R -
R - R -
R - R -
R - R -

R - R -

R - R -

R - R -

R - R -
R - R -

R -