Professional Documents
Culture Documents
Liang Ge, Chaoran Fu, Mingming Wu, Yutong Wang are with State
Grid Shanghai Municipal Electric Power Company Pudong Supply Company,
Shanghai 200120, China (e-mail: fuchaoran617@163.com). Linkun Man is
with State Grid Liaoning Economic Research Institute.
and m
c (t )
is the price of electricity purchased/sold by the
pm(t ) 0, Power transmission from large-
grid to micro-grid at time t microgrid to the large grid at time t.
pm(t ) 0,
Power transmission from micro-grid B. Time Series Dynamic Characteristics of Energy Storage
to large-grid at time t In this paper, the two variables of charging power and
discharge power are used to describe the energy storage and
pl (t ) 0,
Power transmission from AC subsystem discharge process. Because of the loss in the charging and
to DC subsystem at time t
discharging process, the optimization model can ensure that
pl (t ) 0,
Power transmission from DC subsystem the charging and discharging of the energy storage battery
to AC subsystem at time t will not occur at the same time. The charging and discharging
process of the energy storage battery is shown in Figure 2.
III. SOURCE-STORAGE COORDINATIVE
OPTIMIZATION CONFIGURATION MODEL
In the AC/DC hybrid microgrid, the AC subsystem is
connected to the large grid through the grid-connected
interface unit, and the AC/DC subsystem is interconnected
with the bidirectional AC/DC converter through the AC/DC
link. In the case of the power of AC/DC tie-line, considering
the following factors like dynamic timing characteristics of
Figure 2 the charging and discharging process of energy storage battery
energy storage battery, dynamic timing characteristics of
Considering the charging and discharging efficiency of the
conventional power supply, dynamic timing characteristics of
load, the power balance of AC subsystem in microgrid, the energy storage battery, the charging and discharging process
power balance of DC subsystem and power constraint of can be expressed as:
AC/DC tie-line, the following source-storage collaborative s(t 1) s(t ) pch (t ) t ch pdch (t ) t / dch (3)
optimization configuration model is constructed. Where: s(t) and s(t+1) are the state of charge of the energy
A. Objective Function storage battery at time t and time t+1, respectively.
pch (t )
Minimum Investment Cost
1914
pdch (t ) are the charging power and discharge power of subsystem to the DC subsystem. Figure 4 shows the power
and transfer of the AC and DC subsystem.
the energy storage battery at time t, ch and dch are the
charging efficiency and discharge efficiency of the energy
storage battery, respectively. t is the unit time interval and is Figure 4 Schematic diagram of AC and DC subsystem power transmission
Considering the power transmission efficiency( ) of tie-
usually set to 1 hour.
The energy storage battery should not exceed its maximum
lines between AC and DC, the power transmission on the AC
charge and discharge power during the corresponding process.
side and the power transmission on the DC side can be
pch (t ) pch,max expressed as:
(4)
pdch (t ) pdch,max pac pl
(5)
In order to avoid damaging the energy storage battery, the pdc ( pl ) pl (1 ( pl )) pl (10)
charging state must be kept in the upper and lower limits: Where: ( ) is a step function, the function value is 1 when
y Smin s(t ) y Smax (6) the input variable is greater than or equal to 0, and the
function value is 0 when the input variable is less than 0.
Where: y is the energy storage investment decision. Smax For the AC subsystem, the power balance equation is:
and Smin are the upper and lower limits of the storage pg (t ) pres (t ) pdch (t ) pm (t ) pch (t ) pd (t ) pac (t )
(11)
capacity of the energy storage battery, respectively. For the DC subsystem, the power balance equation is:
pg (t ) pres (t ) pdch (t ) pdc (t ) pch (t ) pd (t )
(12)
pg (t )
Where: is the normal power output at time t,
Figure.3 Energy storage battery period
pres (t ) is the renewable energy output at time t, pch (t ) and
After a complete period of time (such as one day), the state pdch (t ) are the charging power and discharge power of the
of charge of the energy storage battery should return to the
initial value, as shown in Figure 3.
energy storage battery at time t, respectively. m is the
p (t )
s((n 1)T ) s(nT ) (7) power flow from the large grid to the AC subsystem at time t,
Where: T represents a complete period, n is a natural p (t )
number. and d is the load at time t.
C. Time Series Dynamic Characteristics of Power Supply E. Power Constraint of Tie-line
For a conventional power supply, the upper and lower The power transmitted by the large power grid to the
limits of the output are: microgrid should meet the upper and lower limits.
x pmin pg (t ) x pmax pm (t ) pm,max
(8) (13)
Where: x is the conventional power investment decision, p (t ) is the power transmitted from the large
Where: m
pmax and pmin are the upper and lower limits of the normal
pm,max
power output. power grid to the microgrid at t time, and is the upper
In order to adapt to the intermittent output of renewable limit of transmission power.
energy and meet the load peak and valley requirements, the The transmission power of AC and DC tie-lines should
climbing rate needs to meet a certain range. conform to the upper and lower constraints.
pdowm pg (t 1) pg (t ) pup pl (t ) pl ,max
(9) (14)
pg (t ) pg (t 1) p (t ) is the AC and DC tie-line power at time t,
Where: and are the state of charge of the Where: l
pup pl ,max
energy storage battery at time t and t +1 respectively. and is the tie-line power limit.
p
and dowm are the upper and lower limits of the climbing rate,
respectively. IV. SOLVING ALGORITHM
D. Power Balance Constraints Equations (1) to (14) can come down to a Mixed Integer
Linear Programming (MILP) problem, and the matrix form is
p
Define l as the AC/DC tie-line power (based on the AC as shown in equations (13) to (15).
side), with the positive direction flowing from the AC min(CTg x CTs y bT z )
(15)
1915
Ax By Cz d (16)
If UB LB , the algorithm terminates, otherwise
continue to the next step.
Gx Hy Mz h (17) Add the following constraints to the slack problem of
Where: z is a column vector consisting of all operating the main problem and return to step 2).
pg (t )
variables, including conventional power output , η (d Ax By )T π*k (h Gx Hy )T λ *k (23)
energy storage battery state s(t ) , charging power pch (t ) , Equation (23) is the optimal cut of the Benders
p (t ) , large grid Injection power pm (t ) , decomposition algorithm. In the practical calculation,
discharge power dch a penalty is added to the lower level problem, so that
and AC/DC tie-line power l
p (t ) . the optimal solution can be guaranteed, as a result the
feasible cut can be omitted [15].
Among those expressions, the objective function formula
(15) is composed of the formulas (1) and (2), and the formula V. EXAMPLE ANALYSIS
(16) represents the inequality constraints (4)-(6), (8)-(9), (13)-
(14), Equation (15) represents equation constraints (3), (7), A. Example System
(11), and (12). In order to improve the speed of MILP In the AC/DC hybrid microgrid structure shown in Figure
solution, the Benders decomposition [14] algorithm can usually 1, each power supply and energy storage is connected to the
be used to solve the layered iterative solution. In this paper, corresponding busbar according to its output force, and
based on the Benders decomposition algorithm, the above supplies power to the AC and DC load. The micro gas turbine
MILP is solved, and the faster solution speed is obtained is used as a conventional power source to access the AC
under the condition of guaranteeing the global optimal subsystem, the fan is connected to the AC subsystem, and the
solution. photovoltaic and energy storage batteries are connected to the
Based on the Benders decomposition algorithm, we can DC subsystem. The AC and DC loads are respectively
divide the integer problem into the upper level problem, and connected to the AC and DC subsystems. The unit time
the continuous variable problem is divided into the lower period is t for 1 hour and the battery operation period is 1
level problem. The upper level problem is: day. Table 1 gives the parameters of the system, and Table 2
min(cTg x cTs y η) shows the time-of-use tariffs for the transactions between the
(18) large grid and the microgrid.
η (d Ax By)T π* (h Gx Hy)T λ* , l k (19)
Based on the dual theory, the lower level problem can be Parameter Value Parameter value
expressed as: name name
pm,max 50 kW Smin 50 kWh
max(d Ax* By* )T π (h Gx* Hy* )T λ (20)
pl ,max 40 kW Smax 10 kWh
CT π MT λ b (21)
π0 0.95 pch,max 20%Smax / h
(22)
Where:
η is the upper problem slack variable, λ and π pmax 60 kW pdch,max 20%Smax / h
are the dual variables corresponding to constraints (16) and
(17), respectively. pmin 12 kW ch 0.9
The solution steps are as follows: pup 10 kW dch 0.9
pdown 3 kW cg ¥3100/kW
Let the number of iterations k 0, the upper boundary
UB , the lower boundary LB . s(nT ) 30 kWh cs ¥1300/kW
k=k+1, solve the upper problem (18)-(19), and get the Table 1 system parameters
x y η
optimal solution of the upper problem k , k , k ,
purchase selling
η
and let LB k .
Time period
price price
/(yuan/kW
/(yuan/kW
Substituting the optimal solution of the upper level h)
h)
x y
problem k and k into the lower level problems peak 10:00-14:00 , 18:00- 0.83 0.65
(20)-(22) and solving them with the assumed optimal 21:00
valley 00:00-7:00 , 23:00- 0.17 0.14
solution
πk , λ k , then 24:00
UB min UB, (d Ax*k By*k ) π*k (h Gx*k Hy*k )T λ *k
T
average The rest 0.49 0.38
(22)
Table 2 Grid time-of-use electricity tariff
1916
This paper selects four typical day scenes to consider the cost is 1.029 million yuan and 1.371 million yuan, when only
random characteristics of wind power, photovoltaic, AC and the power supply investment or the energy storage investment
DC loads. The wind power sunrise curve, the photovoltaic is considered. When the power supply and energy storage are
sunrise force curve, and the AC/DC daily load curve are coordinated, the investment cost is 0.697 million yuan and the
shown in Figure 5. operation cost is 0.938 million yuan. Obviously, among the 3
schemes, the investment cost of scheme 2 is the lowest, but
the total cost of the scheme 2 is 1.956 million yuan after the
operation cost is added, which is the worst economic scheme.
This shows that only considering energy storage construction
can effectively accept renewable energy and meet the
requirement of load peak valley, but it is overly dependent on
purchasing electricity from the large power grid, which
makes the operation cost too high. Comparing scheme 3 and
scheme 1, the investment cost of the scheme 3 is 0.047
million yuan less than that of the scheme 1, and the operating
(a) Wind power output diurnal curve cost is 0.091 million yuan less than that of the scheme 1.
Therefore, the source storage cooperative configuration can
effectively save the cost of the investment and construction of
the power supply, and improve the operation economy of the
AC/DC hybrid microgrid.
VI. CONCLUSION
In this paper, a coordinated optimization configuration
model of source and storage in AC/DC hybrid microgrids
established by considering the dynamic characteristics of the
power storage and the power transmission limit and loss of
(b) Photovoltaic output diurnal curve
AC / DC tie line, and the optimal solution can be obtained by
the mathematical optimization algorithm which is guaranteed
to get the global optimal solution. The validity of the
proposed model is verified by the analysis of the results of the
example. The shortcoming of this paper is that it fails to take
into account the fact that the capacity of the energy storage
battery decreases as the number of charge and discharge
cycles increases. In addition, the AC/DC hybrid microgrid is
only connected to two microgrids. The next research direction
can focus on the multi-AC/DC microgrid hybrid, and take
into account the attenuation characteristics of the energy
(c) AC and DC diurnal load curve storage system.
Fig.5 Renewable energy output and load curve
ACKNOWLEDGMENT
B. Example Result The authors gratefully acknowledge the contributions of
State Grid Shanghai Municipal Electric Power Company
Table 3 shows the optimal configuration results of the Pudong Supply Company and State Grid Liaoning Economic
AC/DC hybrid microgrid under the three-category scheme. Research Institute.
The schemes 1 and 2 are separately configured for the power
supply and the storage, and the scheme 3 is the coordinated
REFERENCES
configuration of the power storage.
Conventional Investment Operation Total cost [1] Ming Meng, Shichao Chen, Shujun Zhao, et al. Overview on Research
Energy
scheme power supply
storage cost cost of Renewable Energy Microgrid[J]. Modern Electric Power,
amount
amount /million 2017,34(1):1-7.
/million /million [2] Parhizi S,Lotfi H,Khodaei A,et al.State of the Art in Research
1 4 0 0.744 1.029 1.773 on Microgrids:A Review[J].IEEE Access,2015,3:890-925.
[3] Ming Ding, Longgang Tian, Hao Pan, et al.Research on Control
2 0 9 0.585 1.371 1.956
Strategy of Hybrid AC/DC Microgrid[J]. Power System Protection and
3 2 5 0.697 0.938 1.635 Control,2015(9):1-8.
[4] Guodong Xu, Haozhong Cheng, Zifeng Ma, et al. An Overview of
Table 3 Optimal configuration results of AC/DC hybrid microgrid
Operation and Configuration of Energy Storage Systems for Smoothing
Wind Power Outputs[J]. Power System Technology, 2017, 41(11):
It can be seen from table 3 that the cost of investment is 3470-3479.
0.744 million yuan and 0.585 million yuan, and the operating
1917
[5] Xun Dou, Shiqing Ji, Yang Li, et al.Capacity Optimization of Energy [11] Xiangjin Wang, Bo Zhao, Hongbin Wu, et al. Optimal Sizing Analysis
Storage Devices in Wind Farm[J]. Modern Electric of Grid-connected Hybrid AC-DC Microgrid[J]. Automation of Electric
Power,2015,32(5):42-47. Power Systems,2016,40(13):55-62.
[6] Xin Ai, Chunfa Dong. Review on the Application of Energy Storage [12] Ming Meng, Yafan Wu, Yahui Su. The Optimization of Hybrid Energy
Technology in Power System with Renewable Energy Sources[J]. Storage Capacity Considering the Utilization Rate of Tie Lines in
Modern Electric Power,2015,32(5):1-9. Microgrid[J]. Modern Electric Power,2018(1).
[7] Liu X,Wang P,Loh P C.A Hybrid AC/DC Microgrid and Its [13] Lotfi H,Khodaei A.Static hybrid AC/DC microgrid planning[C]//
Coordination Control[J].IEEE Transactions on Smart Grid,2011, Innovative Smart Grid Technologies Conference.IEEE,2016:1-
2(2):278-286. 5.
[8] Keren He, Huan Teng, Hongjun Gao. Capacity Optimized [14] Geoffrion A M . Generalized Benders decomposition[J]. Journal of
Configuration of Multi-source Standalone Microgrid by Considering Optimization Theory & Applications,1972,10(4):237-260.
Seasonal Characteristics[J]. Modern Electric Power,2017,34(1):8-14. [15] Bertsimas D , Litvinov E , Sun X A , et al . Adaptive Robust
[9] Bahramirad S, Reder W, Khodaei A. Reliability-Constrained Optimal
Optimization for the Security Constrained Unit Commitment
Sizing of Energy Storage System in a Microgrid[J]. IEEE Transactions
Problem[J].IEEE Transactions on Power Systems,2013,28(1):
on Smart Grid,2012,3(4):2056-2062.
[10] Xingjie Liu, Zhe Du, Xiao Yan. Optimal Allocation of Power Supply in 52-63.
AC/DC Hybrid Stand-Alone Microgrid[J]. Electric Power
Construction,2016,37(10):16-23.
1918