Professional Documents
Culture Documents
The cost incurred to date can also be used to estimate the work progress.
For example, if an activity was budgeted to cost $20,000 and the cost incurred at a
particular date was $
p $10,000,
, , then the estimated p
percentage
g complete
p under the cost ratio
method would be 10,000/20,000 = 0.5 or fifty percent.
This method provides no independent information on the actual percentage
complete or any possible errors in the activity budget: the cost forecast will
always be the budgeted amount.
Consequently, managers must use the estimated costs to complete an activity
derived from the cost ratio method with extreme caution.
Cost Loaded Schedule
While the cost loaded schedule reflects the cost of each work component, it is also
essential that it has to be time phased. So it must show you not only how much
project activities will cost, but when these costs will be incurred.
Cost Baseline is a time‐phased budget which can be used to monitor and measure
cost performance throughout project life cycle. It is the product of the approved
schedule and the project budget (BAC). Using the schedule, you need to identify
when,
h andd for
f how
h long,
l eachh activity is planned.
l d You then
h align
l the
h aggregated
d costs
you've calculated with the time durations in which they fall.
The BAC includes the allocated project budget and the budget contingency to
accommodate
d t the
th risk
i k off incurring
i i unidentifiable
id tifi bl but
b t normally
ll occurring
i costs.
t The
Th
key elements that should be present in any cost baseline are work package costs,
subproject costs, a total project cost, as well as their due dates and contingency
reserves.
Cost Baseline
Cost Loaded Schedule – Advantages.
g
BACC iss p
prepared
epa ed at p planning
a g stage be
before
o e tthee
execution takes place.
BAC is calculated byy aggregation
gg g method. Bottom‐
up estimating is the most accurate.
Estimating should be based on WBS to improve
accuracy.
Contingency reserve is included and Management
reserve is
i excluded
l d d in
i BAC.
BAC
Your BAC becomes your cost baseline.
Project
j Cost Budgeting
g g
COSTING
Cost Baseline – Time Phased Budget
g
Project
j Performance
The basis:
The Earned Value Analysis provides a third reference which is the earned
value of the physical work completed which gives an objective view of the
status of the project, i.e. the value of the work completed to date.
This can be compared with both planned and actual cost to determine the
performance to date which will give an early indication of problems.
problems
Earned Value Analysis (EVA) is an industry standard method of measuring a
project’s progress at any given point in time, forecasting the project
completion
l d
date andd final
f l cost and d also
l analyzing
l variances in the
h schedule
h d l
and budget as the project proceeds.
Earned value Management
g
Earned value Management
g
EVM – BENEFIT.
At the
h end d off the
h project, is it likely
l k l that
h the
h cost willll
be less than or equal to or greater than the original
estimate or the budget?
Cost Performance Index (CPI):‐ It is the ratio between the work accomplished versus
the actual cost incurred for a specified time period. It can be stated as an efficiency
rating for the work accomplished for the resources expended.
Cost Variance (CV):‐ It is the difference between the Earned Value and the actual
cost incurred for a specified time period. It can be stated as a measure of the
spending variance.
Schedule Performance Index (SPI):‐ It is the ratio between the work accomplished
versus the value of the planned work for a specified time period. It can be stated as
an efficiency rating for the work accomplished against the original plan.
Schedule Variance (SV):‐ It is the difference between the Earned value of the work
accomplished and the planned versus the value of the planned work. It can be stated
as an efficiency of the project performance.
Cost Performance Indicator (CPI)
( )
CPI is the ratio of earned value and the actual cost of completed works.
CPI represents the amount of work produced by the project for every unit of cost
spent.
No. Description Remarks
1 C t Performance
Cost P f I d (CPI) = 1
Index O Budget
On B d t
2 Cost Performance Index (CPI) < 1 Over Budget
Cost Variance is the difference between the Earned Value and the Actual Cost
of the works.
works
CV = BCWP – ACWP
CV = EV ‐ AC
SPI is the ratio of earned value and the planned value of completed works.
SPI represents the amount of time being utilized on a project for every unit hour
spent
N
No. D
Description
i ti R
Remarks
k
1 Schedule Performance Index (SPI) = 1 On Schedule
2 Schedule Performance Index (SPI) < 1 Behind Schedule
3 Schedule Performance Index (SPI) > 1 Ahead of Schedule
Schedule Variance (SV).
( )
It is the difference between the Earned Value and the planed value.
SV = BCWP – BCWS
SV = EV ‐ PV
Estimate At Completion (EAC): It is the estimate or the amount of money will be spend on
the project and it depend on judgment.
Independent Estimate At Completion (IEAC): is the projected final cost of the project,
based on the performance so far. It takes into account the original budget (BAC).
IEAC = BAC / CPI
BAC is the Budget at completion
Independent Schedule At Completion (ISAC): is the projected duration of the project based
on the performance so far.
far
ISAC = SAC / SPI
SAC is the schedule at completion
Variance AT Completion(VAC): is the forecast of final cost variance.
variance
VAC = BAC – IEAC or BAC ‐ EAC
The above analysis and the forecasted values will give an indication, whether the project is
in crises or not and also the type
yp of crises if there is.
Project
j Status
Project
j Forecasting.
g
TCPI is the required productivity to complete the scope within the available budget.
TCPI = (Budget – BCWP) / (Budget – ACWP)
TCPI is an indication of how one has to perform for the project duration in order to meet
the desired cost goal.
If TCPI is greater than 1, one must perform better than planed to meet the goal.
If TCPI is less than 1, one can get by with performing under the plan.
Project
j Forecasting.
g
TCSPI is the required work rate to complete the scope within the available schedule. It gives
the idea how to utilize the remaining time period of the project.
TCSPI is an indication of how we have to perform for the project duration in order to meet
the desired schedule goal.
Inference of result:
If TCSPI is grater than 1, one must perform better than planned in order to meet the goal.
If TCSPI is less than 1, one can get by with performing under the plan.
EVM measures p
project
j p performance
Project Cost Control – Tools & Techniques
PV Planned Value What is the estimated value of the work planned to be done ?
BAC Budget At Completion How much did we BUDGET for the TOTAL project effort?
EAC Estimate At Completion What do we currently expect the TOTAL project to cost?
ETC Estimate to Complete From this point on, how much MORE do we expect it to cost
to finish the project?
VAC Variation to Complete How much
Ho m ch over
o er or under
nder b
budget
dget do we
eeexpect
pect to be at the
end of the project?
Calculations Example
Earned quantity = (allowed credit) x (summary qty) x [(qty to date) / (total qty)]
Earned Ton Beams = (0.11) x (520 tons) x (45 each /859each) = 3.0 tons
E
Earned
d value
l =P Percentage
t Completed
C l t dxbbudget
d t ffor th
thatt accountt
Percentage Completed = (earned work hours or dollars all accounts) / (budgeted
work hours or dollars all accounts)
For our earlier example:
– Percentage Complete = 82.5/520 tons = 15.87%
Productivityy
Credit WH
• Like earned WH are derived quantity that
provide a vehicle for handling quantity
variations between budgeted and actual WH’s
without distorting crew productivity figures
figures.
• CWH = budgeted productivity unit WH rate X
actuall WH
Productivityy
Productivity Index
• PI= (Sum of credit WH) / (Sum of actual WH)