Professional Documents
Culture Documents
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
And it is because of these needs for speed and ‘certainty’ that construction
contracts usually include a fixed completion date. Without it, the contractor
would be left to undertake the work without a deadline, or more accurately
within “a reasonable time”.
Keating on Building Contracts 5th edition2 explained, “If no time is specified for
completion of the contract a reasonable time for completion will normally be
implied. What is a reasonable time is a question of fact to be considered in
relation to circumstances which existed at the time when the contractual
services were performed”.
The need for speed however also means that contractors are usually asked to
start work before the design is fully complete and/or before the employer knows
its final requirements, and often before the employer is fully ready to fully
accommodate the supply of the works. There are also always other unknowns
when the parties agree the contract, some of which it is fair (or most
commercially practicable) for the employer to take responsibility for.
The parties therefore accept that the agreed period will need to be adjusted for
additional periods in respect of any matters which were unaccounted for when
the parties agreed the contract and the contract period, and for which the
1 This paper does not contain legal advice. This paper does not contain advice or guidance. It
is a discussion paper which expresses a point of view or potential point of view, and is not
intended to be relied upon
2 (page 218): Keating on Building Contracts 5th edition , Vivian Ramsey, Sweet & Maxwell 1991
1
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
employer took the risk under the contract. This is where the extension of time
clause comes in. It provides for an adjustment of the fixed and agreed period, to
take into account unknown or ‘unaccounted for’ employer risk events.
Just as the original contract period is taken to represent a reasonable period for
undertaking the contract works, the job of the extension of time clause is
(subject to any further agreement between the parties for an additional period in
respect of any particular employer risk event) to evaluate a reasonable
additional period for completion by reference to the employer risks which
eventuated.
A fit for purpose extension of time clause therefore adds to the completion date
stated in the contract, a reasonable time for employer risk events, and the
contractor’s obligation should be to complete within that revised period.
In the case of Dodd v Churton (1897)3 Lord Esher and Lord Justice Chitty held
(on the basis of a centuries old legal principle that a party may not take
advantage of or rely upon its own wrong), “if the building owner has ordered
extra work beyond that specified by the original contract which has necessarily
increased the time requisite for finishing the work, he is thereby disentitled to
claim the penalties for non-completion provided by the contract”. This is the
‘prevention principle’ in the construction industry, or more generally in
contracts which provide a fixed time for performance.
It can be said that the extension of time clause in one sense cured the mischief
identified by Lords Esher and Chitty, by enabling the employer to measure an
increase in the, “time requisite for finishing the work” and refix the completion
obligation accordingly.
The logic in all of the prevention principle judgements (up to 2011) is the same.
Without an applicable extension of time provision in the contract, there is no
mechanism for calculating date from which the damages can start other than the
original completion date stated in the contract, and the damages can not start
from the unextended original contract completion date because that original
fixed period can no longer be asserted by the Employer once by its actions it has
made that date unachievable, or has extended the necessary period for
undertaking the work beyond that date.
Once a matter which falls within the domain of the employer, extends (beyond
the contract completion date) the time reasonably needed by the contractor to
3 1 QB 562
2
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
complete the Works4 then the completion date falls away. Time becomes ‘at
large’, i.e. the contractor’s obligation reverts to completing in an (undefined)
reasonable time.
The reason why adding an extension of time clause keeps the damages alive, is
that it effectively changes the obligation from one to finish by date A to one to
finish by date B or C, where B and C represents the agreed contract period, plus
the additional period of events for which the employer is responsible. In that
way, the obligation (and therefore damages) can be enforced to the extent that
delays to the original date were not on account of the employer’s acts.
When looked at from the point of view of the prevention principle, the
extension of time clause fulfils the same requirement as from the point of view
of the fit for purpose model, i.e. to add a reasonable period in respect of
employer risk events. Whichever way you look at it, contractor ‘delays’ or
‘events’ are irrelevant to the assessment of extension of time entitlement.
In this way, the extension of time clause is measuring the period in which the
contractor could have finished (without accelerating through employer delay).
But this is also the period in which the contractor would have finished, but for
its own delays.
By any sensible measure this has to be how extensions of time, and damages
payments to the employer have to be calculated.
The only alternative which might conceivably have some logical merit, would
be to say let’s forget about the employer delay completely, and just measure the
extent to which the contractor breached its obligation to perform as agreed5. In
other words an assessment of when the contractor would have finished the
4 Unless there is float or spare capacity in the original period, this extension beyond the completion date will
occur as soon as the employer act extends the works programme,
5 As discussed in The Wrong Path, the contractor is prima facie responsible for performance whichever party
was to ‘blame’ for the delay but this does not need further consideration here, and contractor and employer
delay is discussed in the normally perceived sense.
3
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Works but for the employer’s delays. By this approach, an extension of time
would only be given for any additional delay to the project caused by the
employer on top of any delays which the contractor in any event caused itself
or ‘extra over’ employer delay, so:
i) In practice, the formula given above is not the approach which the
contract would actually take. Why go to all the trouble of adding up
the employer delay and adding up the contractor delay, taking them
away from one another and taking the result away from something
else (which is the only purpose an extension of time clause could
serve), when all that you have to do is simply add up the delay for
which the contractor was itself responsible? Damages period =
Contractor delay. You wouldn’t in reality have an extension of time
clause at all. Irrespective, it is strikingly obvious that neither
approach is what any standard form construction contract provides for.
Standard form construction contracts contain extension of time clauses
which add to the original contract period, periods for employer risks.
ii) From a damages point of view, the employer has suffered no loss to
the extent that the contractor caused delay does not exceed employer
caused delay6. The project would have been finished no earlier than
the aggregate of the employer delay, even if the contractor delay
didn’t exist. It’s a fundamental principle of almost any legal
jurisdiction, that a contracting party can only recover damages in
respect of loss incurred as a result of the other party’s non-
performance7. In English law the principle goes back at least 170 years
and has been enforced on multiple occasions in both the House of
Lords, and its successor the Supreme Court in the 21st century alone.
4
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
8 Aside from the fact that the paper starts at page 338, the structure of the paper is quite confusing, and the
chronology of events hard to establish from various citations scattered around the document. It’s also noted
that the reader has to notice a footnote on page 375 (effectively page 38 of the paper) in order to find out
that, “ ‘extended duration claim’ as used in this article refers to a contractor’s affirmative claim for delay
costs”, i.e. not extensions of time. If the reader misses the footnote, then much of the paper can appear to
have an entirely different meaning. This reader got the personal impression was that the paper may not have
intended to deliver a clear understanding (much like his conclusion on the 2002 Society of Construction Law
Hong Kong paper on concurrent delay – See The Wrong Path).
5
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
First let’s just check what critical path analysis/critical path method means. A
good place to start is the definition which was provided by the UK’s Society of
Construction Law in its Protocol on Delay and Disruption of 2002, which
defined critical path in the following terms:
This is the accepted definition of the critical path today. This author understands
that that is what critical path method has actually always measured, since its
‘invention’ in the 1950s as a planning tool, although it would appear that the
meaning of the term, particularly when it is applied to the assessment of
entitlement arising out of delays, has not always been fully understood - See
Appendix B.
The approach which critical path analysis takes to 35 very simple and
rudimentary hypothetical delay scenarios, is analysed in Appendix A to this
paper.
Appendix A demonstrates that the critical path analysis measures one of the
following, depending on the circumstances in which the delay events arose:
• The total delay caused by the employer irrespective of contractor delay,
i.e. delay ‘but for’ contractor delay (the fit for purpose or prevention
principle –properly so called – approach described in Section 1 above), or
• The additional delay caused by the employer on top of contractor delay,
or the ‘extra over’ employer delay, the delay ‘but for’ employer delay, or
the total delay caused by the contractor irrespective of employer delay.
The situations in which the analysis takes the fit for purpose approach, are those
where either i) the as-planned situation had the activity which was in fact hit by
the contractor event, sufficiently in float9 so as to exceed (or match) the period
by which the contractor event in fact preceded the employer event, or ii) the
employer delay event happened first.
9The only ‘exceptions’ are examples 33-35 where there was one path of events only, and the author analysed
concurrency on the basis of creating entitlement where there are parallel competing causes of delay.
6
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
What other justification has been provided for using CPM or critical path
analysis for assessing extension of time entitlement?
The authors of the ABA paper state (page 368) that a case by the name of
“Blackhawk Heating & Plumbing Co., Inc”10 (1975), found that there was no
entitlement to extension of time, because the Contractor had not demonstrated
that the employer’s delays were on the critical path. The author quotes the court
in that case (now on Page 380): “Since liquidated damages are only imposed for
delays in project completion, it is manifest that only those delays should be
considered which actually affect project completion. By their nature the delayed
activities involved must necessarily lie on the critical path as it was actually
completed”.
To the extent that this is taken to be intended to validate a critical path approach
(as it is understood today) to assessing extension of time entitlement, then this
would be based on unsound logic. The judge appears to be effectively stating
that it is axiomatic that extension of time entitlement is assessed on the basis of
delays which drive project completion, because delay damages are determined
by reference to project completion. But the reality is that an extension of time
clause is measuring neither liquidated damages nor the project completion date.
7
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
8
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
9
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Society of Construction Law Lord Justice Coulson since attributing meaning to other judges which appeared to
10
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Justice Hamblen then states that the same principle which he has (it is submitted
wrongly attributed to the prevention principle) also applies to extensions of
time. He says (in relation to what appears to be the correct position, which he
has attributed to Adyard), “It is wrong in principle…It is wrong as a matter of
authority because it is contrary to the principles laid down in the authorities
dealing with both extensions of time and the prevention principle”.
Again this appears to be incorrect. We’ve seen above (Section 1) that it is an
incorrect conclusion in principle. In terms of authorities, we’ve seen that it is an
incorrect conclusion in relation to the prevention principle (page 10 above). As
analysed in ‘The Wrong Path’ and ‘A History of Extension of Time’ by this
author, it is not accurate either (or not fully accurate) in regards to the
authorities on extensions of time.
In those other papers by this author, it is concluded that the English cases never
took a critical path approach to extension of time prior to 1999. Since 1999 and
up to the Adyard case, this author identifies 4 judgements which do not take a
critical path approach, 3 which clearly do, and 4 in which it is unclear whether a
critical path approach (in the sense which we understand it today and as defined
by the Society of Construction Law) is advocated21. Furthermore, there are
multiple Supreme Court and House of Lords cases which advise as to how
damages should be assessed, and they do not do so in the manner which would
be achieved by following Justice Hamblen’s approach (discussed further in ‘The
Wrong Path’).
Furthermore, Justice Hamblen seems to be striving for a ‘but for employer
delay’ or ‘extra-over employer delay’ approach to extensions of time as
discussed in Section 2 of this paper above, which asides from being
conceptually invalid (as explained in Section 2 above), is not something which
critical path method in any case provides (as explained in Section 4 above).
Justice Hamblen (as he then was) refers to the critical path method or treats the
critical path method as being the “prevention” approach (See Appendix C). But
it is an illusion of prevention; an illusion of logic. Justice Hamblen states that
Adyard’s argument was turning the prevention principle on its head. The truth is
that it is Justice Hamblen who has turned the prevention principle on its head,
and turned logic on its head at the same time.
Nowhere does Justice Hamblen provide any reasoning for taking an approach
which creates a hybrid between the ‘extra-over employer delay’ outcome and a
fit for purpose outcome, as in fact critical path analysis does (as explained
this author on the face of it to be the plain opposite of the statements or findings which the applicable judges
had made, in support of similar principles to those being proposed by Justice Hamblen – See The Wrong Path.
21 There may be other judgements which this author has missed
11
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
As mentioned in Appendix B of the current paper, the author of the ABA paper
refers (on page 363) to an American judgement, “Santa Fe Inc”22 (1984), and
states that,
The findings of the court on this argument never appear to be revealed in the
paper (it immediately jumps to a different point considered), however the
authors give their own thoughts on the proposition saying, “Because a project
extends beyond the contract completion date, this does not mean that the
longest chain of activities through the network in terms of time and the delays
which affect that chain cannot be determined”,
Path
12
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
25 See The Wrong Path or A History of Extension of Time’ by the author of this paper
26 As discussed in ‘The Wrong Path’ it is not clear that FIDIC requires a critical path approach
27 Discussed further in The Wrong Path
28 Discussed further in The Wrong Path
13
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
7. Conclusions
As a planning tool, critical path analysis has likely been very useful to the
construction industry. When applied to delay claims, this paper suggests that it
does not work.
The critical path approach fundamentally changes the task of assessing
extension of time, from one of measuring the extent to which employer delay
exceeds the fixed period for undertaking the works, to one of measuring -
seemingly inexplicably and randomly - employer delay when it impacts upon
what happens to be (at the particular point in the project which coincides with
the timing of the employer delay event) the then longest path to the completion
of the Works.
It could be viewed as a hugely resource intensive, charter for disputes. Without
wishing to be rude, it is a logical nonsense based upon a fallacy. Fundamentally
it does not fulfil the basic requirements of the task which it has been given. It
doesn’t provide a predictable entitlement or the ‘right’ entitlement. It calculates
a subjective and highly complex answer, to the wrong question.
No sensible and meaningful justification for the approach appears ever to be
been provided. It is submitted there is none which can be provided. Yet
somehow this method has been bought by and/or imposed upon the construction
and real estate industries which pay for it.
It may be that there has been a deliberate plan of ‘illusion’ or ‘slight of hand’ of
sorts, (or, depending how you look at it, quite legitimate strategic
gamesmanship) by clever people somewhere at the top of the chain. Conversely,
its adoption may simply be due to genuine confusion and misunderstanding,
including on the part of the judiciary.
Either way, as this author sees it (and he is perfectly happy and willing to stand
corrected if appropriate) the construction and real estate industries have been
sold a dummy, and left (arguably encouraged) to fight each other like cats and
dogs over the critical path, racking up vast bills in the process, ultimately to no
purpose at all other than having something to argue about.
Robert Tustin 11 December 2022*
*With slight adaptions to a paper with a similar title dated 9 December.
rob_tustin@yahoo.co.uk
THIS PAPER DOES NOT CONTAIN LEGAL ADVICE. THIS PAPER DOES NOT
PROVIDE ADVICE OR GUIDANCE, IT IS A DISCUSSION PAPER, AND IS NOT
INTENDED TO BE RELIED UPON. THIS PAPER EXPRESSES A POINT OF VIEW
OR POTENTIAL POINT OF VIEW, WHICH OTHERS MAY DISAGREE WITH.
14
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
APPENDICES
15
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
16
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
• The total delay caused by the employer irrespective of contractor delay, i.e.
delay but for contractor delay (the fit for purpose or prevention – properly so
called – approach described above), or
• The additional delay caused by the employer on top of contractor delay, or
the ‘extra over’ employer delay, or the delay but for employer delay, or the
total delay caused by the contractor irrespective of employer delay.
The situations in which the analysis takes the fit for purpose approach, are those
where either i) the as-planned situation had the activity which was in fact hit by the
contractor event, sufficiently in float so as to exceed (or match) the period by which
the contractor event in fact preceded the employer event, or ii) the employer delay
event happened first.
The only ‘exceptions’ to these rules are in examples 33-35 where there was one path
of events only, and the author analysed concurrency on the basis of creating
entitlement where there are parallel competing causes of delay.
Critical path analysis gives full fit for purpose extension of time entitlement for all
employer delay beyond the completion date, where the period that the employer
event starts earlier than a contractor event, exceeds the period of float belonging to
the employer event. In other circumstances, it gives entitlement based on the ‘extra
over’ delay caused by the employer, i.e. delay ‘but for’ employer delay.
On most construction projects, where there are multiple delays by both parties,
critical path analysis takes the approach shown in examples 31 and 32, which is a
hybrid between the two approaches.
The extent to which the overall result leans towards one method or the other will
depend randomly upon the float which affected activities had on an as-planned
basis, and completely randomly upon the order in which the delay events arose.
Some other points to note are:
• In 6 examples an assessment was done on both a sequential time basis and
on a sequential event basis. In 2 cases the analysis gave the same result. In 3
cases the analysis gave more entitlement for the sequential time assessment.
In one case (example 28), where the employer affected event was in float and
where a contractor event occurred during the employer event, the sequential
event approach gave more entitlement.
• In 4 of the 6 cases, a situation of concurrent delay occurred when using the
sequential time approach (highlighted in blue on the summary page and in the
example). In none of the cases did concurrent delay arise when using the
sequential event approach. This supports the author’s conclusion that the
Society of Construction Law’s method means that concurrent delay will not
arise, other than in single path scenarios.
• The ‘extra over’ period of delay is always the Employer delay beyond
completion less the Contractor delay beyond completion.
The table of results is set out below, followed by the worked examples (as noted, for
examples 1 and 2 please see Section 5 of The Wrong Path):
17
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
18
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
19
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
For examples 1 and 2, please see Part 5 of the paper The Wrong Path.
Examples 3,4,5,6
As-Planned (for examples 3-6, and 29-32):
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Structure A
Structure B
EXAMPLE 3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Structure A
Contractor delay
Structure B
Employer delay
20
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Examples 7-22
As-planned, for examples 7-22:
1 2 3 4 5 6 7 8 9 10
Activity 1
Activity 2
EXAMPLE 7
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 8
1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
EXAMPLE 9
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 10
1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
21
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
EXAMPLE 11
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 12 1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
EXAMPLE 13 1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 14 1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
22
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
EXAMPLE 15
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 16
1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
EXAMPLE 17
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 18
1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
EXAMPLE 19
1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay E
Activity 2
Contractor delay
EXAMPLE 20 1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay E
Activity 2
Employer delay
23
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
EXAMPLE 21 1 2 3 4 5 6 7 8 9 10
Activity 1
Employer delay
Activity 2
Contractor delay
EXAMPLE 22 1 2 3 4 5 6 7 8 9 10
Activity 1
Contractor delay
Activity 2
Employer delay
Examples 23-28
As-planned, for examples 23-26:
1 2 3 4 5 6 7 8 9 10
Activity 1
Activity 2
PLEASE NOTE: FOR EXAMPLES 23-28 THERE IS AN ANALYSIS DONE BASED ON SEQUENTIAL EVENTS
(PER SCL) AND AN ANALYSIS DONE PER SEQUENTIAL TIME (see Part 5 of The Wrong Path)
Activity 1
Employer delay
Activity 2
Contractor delay
Activity 1
Employer delay
Activity 2
Contractor delay
24
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Activity 1
Contractor delay
Activity 2
Employer delay
Activity 1
Contractor delay
Activity 2
Employer delay
Activity 1
Employer delay
Activity 2
Contractor delay
Activity 1
Employer delay
Activity 2
Contractor delay
Activity 1
Contractor delay
Activity 2
Employer delay
Activity 1
Contractor delay
Activity 2
Employer delay
25
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
1 2 3 4 5 6 7 8 9 10
Activity 1
Activity 2
Activity 1
Employer delay
Activity 2
Contractor delay
Activity 1
Employer delay
Activity 2
Contractor delay
Activity 1
Contractor delay
Activity 2
Employer delay
Activity 1
Contractor delay
Activity 2
Employer delay
26
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Examples 29,30,31,32
EXAMPLE 29
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 30
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 31
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Structure A
Contractor delay
Structure B
Employer delay
EXAMPLE 32
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Structure A
Contractor delay
Structure B
Employer delay
27
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Examples 33,34,35
EXAMPLE 33
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Contractor delay
Employer delay
EXAMPLE 34
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Contractor delay
Employer delay
EXAMPLE 35
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Contractor delay
Employer delay
28
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
The author of the paper presented by the American Bar Association, refers (on page
363) to an American judgement referred to as “Santa Fe Inc” (1984), and states that
“the contractor asserted that any work sequence or CPM path of activities that
ran past the contractually required completion date is critical and delays on these
work sequences due to changes are on the critical path”.
The author gives his own thoughts upon this proposition saying, “Because a project
extends beyond the contract completion date, this does not mean that the longest
chain of activities through the network in terms of time and the delays which affect
that chain cannot be determined”, however he doesn’t seem to disclose what the
court’s conclusion was on the point, and continues the discussion of the case (on
page 363) by reference to the critical path without explaining the court’s definition of
the term.
A similar assumption to the contractor’s in the Sante Fe case was made in the UK
publication “The Presentation and Settlement of Construction Claims”, 198329, stated
(page 242) with regards to the JCT80 form, “in forming his view (as to extension of
time entitlement, the Architect) will need to consider whether the delay is on a
critical element and the effect of float in the Contractor’s programme”. The reader is
then referred to page 30 of the book for more information, where it’s stated, “…the
Architect is first required to form an opinion as to whether the delay is likely to
affect (or has affected) the completion date. A simple delay in progress during
the contract is not sufficient…it must be of such size or on such an element of
the works as will have an effect upon the completion date.”
29The author, Geoffrey Trickey, was a Partner of Davis, Belfield and Everest (later Senior Partner of Davis
Langdon)
29
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
The point made in Trickey is that in order to create entitlement, it’s not enough for
the directly affected activity to be delayed, but the delay must also use up all free
float for that activity (period Y) and use up Total float (“an effect on the completion
date”). There’s no reference (expressly or implicitly) to a critical path in today’s
sense. This was the argument put forward by the contractor (seemingly in
connection with a contract which expressly linked extension of time entitlement to the
critical path), in the Santa Fe case.
It's just worth bearing this in mind, particularly when the first United Kingdom case
which approved of a “critical path” approach (Henry Boot Construction (UK) Ltd v
Malmaison Hotel (Manchester) Ltd (1999)30) did so in brief passing without any
discussion of what the term meant or how it applied.
30 (1999) 70 Con LR 32
30
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
THIS PAPER DOES NOT CONTAIN LEGAL ADVICE. THIS PAPER DOES NOT
PROVIDE ADVICE OR GUIDANCE, IT IS A DISCUSSION PAPER, AND IS NOT
INTENDED TO BE RELIED UPON.
THIS PAPER EXPRESSES A POINT OF VIEW OR POTENTIAL POINT OF VIEW,
WHICH OTHERS MAY DISAGREE WITH.
31
The Nonsensical Application of Critical Path Method to Extensions of Time December 2022
Robert Tustin MRICS MSc (King’s College) FCIArb THIS PAPER IS NOT INTENDED TO BE RELIED UPON
Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm) 9-12,31
Blackhawk Heating & Plumbing Co., Inc (1975) SBCA No. 2432, 76-1 BCA 11
11,649 7
Dodd v Churton (1897) 1 QB 562 2,10
Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70
Con LR 32 30
Holme v Guppy (1836) 3 M. & W. 387 10
CM. Shupe, Inc. v. United States, 5 Cl. Ct. 662, 728 (1984) 8
Peak Construction (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 111
10
Percy Bilton Ltd v Greater London Council [1982] 1 WLR 794 10
Santa Fe Inc (1984) 4-2 BCA 11 17,341. 12,30
Roberts v The Bury Improvement Commissioner [1870] LR 5 C P 310 10
Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973] 2 AII
ER 260 10
32