You are on page 1of 1

Home » Projects » Central Asia-South Asia (CASA-1000) Electricity Transmission Project

Central Asia-South Asia (CASA-1000) Electricity


Transmission Project
POWER TRANSMISSION AND DISTRIBUTION POWER CABLE

Project Type : Location :


Power transmission Afghanistan, Kyrgyzstan, Pakistan, and Tajikistan

Capacity
MORE  : Estimated Investment :
1,300MW $1.17bn
Central Asia-South Asia (CASA-1000) electricity transmission project is a 1,227km-long cross-border
Start of Construction
transmission :
project being developed in Central Asia. Start of Operations :
2019 2022
The project aims to establish an electricity trade involving the transfer of surplus hydropower available in
Major
Central Financier :
Asia to electricity-deficient countries in South Asia. Surplus energy available with Kyrgyzstan and
Tajikistan will be sold to Afghanistan and Pakistan, under the project.
World Bank
Estimated to cost approximately $1.17bn, the project is being developed by the participating countries under an
inter-governmental agreement (IGA) signed in 2008. The four nations established an Inter-Governmental
Council (IGC) for the project development.

The main aim of the transmission project is to facilitate the transfer of surplus summer power (approximately
1.3GW) from Kyrgyzstan and Tajikistan to Pakistan via Afghanistan. An estimated 1GW of power will be
transmitted to Pakistan, while up to 300MW will be delivered to Afghanistan.

PROJECT GALLERY

 

d Pakistan will receive 1GW of the total power transported, while Afghanistan will receive the remaining. Image Th
courtesy of World Bank.
  
The CASA-1000 project received approval in March 2014, while commercial operations are expected to be
started in 2022.

Central Asia-South Asia (CASA-1000) electricity


transmission project details
The CASA-1000 project involves the construction of a 477km-long, 500kV AC line from Datka sub-station in
Kyrgyz Republic to Khudjand sub-station in Tajikistan. The line will be in the Kyrgyz Republic for 450km,
while the rest will be in Tajikistan.

The project also involves the construction of three convertor stations to convert the power from alternating
current (AC) into direct current (DC) and vice versa. The stations will be located at Sangtuda (1.3GW) in
Tajikistan, Peshawar (1.3GW) in Pakistan, and Kabul (300MW) in Afghanistan.

The connecting AC systems shall be of 500kV, 50Hz in Tajikistan and Pakistan, while Afghanistan will use
220kV, 50Hz systems.

A 120km-long, 500kV single-circuit AC line will also be constructed in Tajikistan between Regar and Sangtuda
substations. The line will transfer export power from Tajikistan and Kyrgyz to the Sangtuda converter station.

Furthermore, a 750km, 500kV high-voltage DC (HVDC) line will be laid from Sangtuda (Tajikistan) to
Nowshera (Pakistan). The line will have a transmission capacity of 1.3GW in either direction, using a bipolar
and earth-return configuration.

It will run for 120km in Tajikistan, 560km in Afghanistan, and 70km in Pakistan.

Financing
The CASA-1000 project is financed by seven institutions, with the majority being financed by the World Bank
through International Development Association (IDA).

The World Bank Group is providing $526.5m financing, while the other lenders include Islamic Development
Bank (IsDB, $155m), European Bank for Reconstruction and Development (EBRD, $110m), European
Investment Bank (EIB, $180m), UK Department for International Development, Afghanistan Reconstruction
Trust Fund (ARTF, $40m), and the US Government.

The United States Agency for International Development and the UK Department for International
Development are providing bilateral financing of $11.5m and $46m, respectively. The remaining funding of
$101m is provided by Pakistan, one of the recipient countries.

Contractors involved
Monenco Iran Consulting Engineers was engaged to provide construction supervision services for the HVAC
transmission lines and associated substations in Tajikistan and Kyrgyz Republic.

In December 2017, Kalpataru Power Transmission was awarded a $66.9m contract for conducting civil works
at the 500kV HVDC line in Tajikistan border to intermediate point 1.

KEC International is conducting civil works for the 500kV HVDC line from intermediate point 1 to
intermediate point 2 and from intermediate point 2 to Pakistan border.

WAPCOS is providing consulting services with regard to the commissioning of two terminal HVDC converter
stations in Pakistan and Tajikistan. The contractual scope also includes the construction of HVDC line from
Sangtud.

The consortium of ABB and Cobra Instalaciones Y Servicios secured a contract worth approximately $330m, in
September 2018, for installing two HVDC converter stations in Tajikistan and Pakistan.

SNC-Lavalin prepared the feasibility study for the project in February 2011, while Integrated Environment
(IEL) prepared the ESIA and ESMP reports in September 2011.

Normandeau Associates conducted the Avian Risk Assessment and Management study for the project in May
2012.

    

RELATED PROJECTS

TransWest Express Transmission Project,


US

Tyrrhenian Link Project,


Italy

Ten West Link Transmission Line Project,


US

RELATED NEWS

NGET, SSEN get planning consent for 2GW Eastern Green Link 2
project

SSEN selects preferred bidders for Western Isles and Spittal-Peterhead


links

Construction begins on £2.4bn NeuConnect interconnector


project

RELATED COMPANY INSIGHT

TENEX – winner of the Mitsubishi Research Institute’s


tender

About us Contact
Advertise with us – Advertising enquiries: Roy Morris,
roy.morris@progressivemediainternational.com, +44 (0) 20 7406 6613
Privacy Policy Terms and Conditions

You might also like