You are on page 1of 4

Executive Summary

Background
Tackling the large global infrastructure gap remains The Global Infrastructure Hub (GI Hub) has led the
a priority for governments to drive inclusive growth development of this Reference Tool on Governmental
and reduce poverty. The Global Infrastructure Outlook Processes Facilitating Infrastructure Project Preparation
report prepared by the Global Infrastructure Hub (hereinafter referred to as the ‘reference tool’) to
(GI Hub) estimates that the global infrastructure support the operationalisation of the aforementioned
investment needed between 2015 and 2040 is G20 Principles.
approximately US $94 trillion. Past studies peg project This reference tool is intended as a guidance
preparation costs at between 5-12% of investment document for governments and practitioners involved
needs, and even if the lower end of this range is in infrastructure project preparation, and is built on
considered, financing needs for project preparation a detailed country-lens review of project preparation
translate to US $4.7 trillion over this period, or US $188 practices in 15 countries. The reference tool seeks
billion annually. to address challenges faced by governments in early-
In 2018, the G20’s Infrastructure Working Group (IWG) stage project preparation through providing guidance
identified the key elements for infrastructure growth in five areas, as shown in the following diagram:
under a strategic roadmap, “Developing infrastructure
as an asset class”, organised under three overarching
pillars, the first of which is improving project
development. In July 2018, the G20 Finance Ministers
and Central Bank Governors endorsed the G20
Principles for the Infrastructure Project Preparation
Phase developed by the IWG.

Enabling environment for project preparation


Policy framework and public institutional capacity
(Chapter 2)

Financing project preparation


PPFs | PDFs | Government budget (Chapter 3)

Infrastructure planning and project prioritisation Project Project


Planning | Prioritised projects pipeline (Chapter 4) procurement implementation

Project feasibility, reviews and approvals


Project concept and pre-feasibility | Feasibility
| Reviews, audit and approval (Chapter 5)

Project communication
Stakeholder engagement | Market sounding
(Chapter 6)

Leading Practices in Governmental Processes Facilitating Infrastructure Project Preparation | 3


Outline of guidance areas Financing project preparation
Enabling environment for project preparation As noted, infrastructure project preparation costs
A conducive enabling environment for infrastructure in developing countries typically range from 5-10%
investment is often a key differentiator between of the total project investment, and about 3-5% of
countries that successfully scale up infrastructure and project costs in developed countries. While financing
those that face challenges in doing so, and nurturing for project preparation has, in the past, been largely
such an environment is largely the responsibility of addressed through government budgetary allocations,
governments. The reference tool identifies leading increasing use is now being made of national and
practices in two dimensions of government action: sub-national Project Development Funds (PDFs), and
of Project Preparation Facilities (PPFs) developed
1. A robust policy framework: that signals clarity, by the MDBs and other multilateral entities. Key
consistency and stability of government actions, considerations for governments in utilising each of
while providing for agility to adapt and manage these three financing sources are summarised below:
changes in the wider infrastructure ecosystem.
In developing such a framework, governments 1. Project Development Funds (PDFs): Many
should: governments have set up PDFs as a means to
provide dedicated financing and bridge capacity
• Establish a stable policy and legislative gaps faced by GCAs in project preparation.
framework guiding development and private PDFs can be set up at the national and sub-
participation in infrastructure that is agile and national level, either with government funding
responsive to tackle evolving infrastructure or structured so as to recover costs. They may
development needs; have a thematic focus (e.g. climate mitigation)
• Develop guidelines, standards and processes or a sectoral focus. Critical considerations in
to make the policy framework actionable, together the creation of PDFs are summarised below:
with an aligned cascading of policies at the sub- • Ensure clarity of PDF objectives, scope of
national government and government contracting operation, and interface with GCAs;
authority (GCA) level; and
• Support PDFs with effective governance,
• Formulate allied sector-specific policies as institutional capacity and sustainable financing;
necessary to drive infrastructure project
preparation. • Institutionalise project preparation financing
support for sub-national governments; and
2. Well-governed public institutions: with a clear
role, mandate, and commensurate capacity to • Develop allied mechanisms, standards and
operationalise policy into effective and smooth processes for effective operationalisation.
project preparation and implementation. 2. Project Preparation Facilities (PPFs): PPFs are
Key ‘leading practices’ include the following: a response by the MDBs and other multilateral
• Establish and empower centralised agencies entities to address the scarcity of bankable,
to institutionalise project preparation capacity investment-ready project pipelines in many
and standards; Emerging Market and Developing Economies
(EMDEs), and to provide financing support
• Create sector-specific agencies where investment for project preparation. Many of these PPFs
and/or transformation needs are significantly have been set up with different arrangements
large; and regional focuses. Apart from financing
• Develop commensurate capacity and project preparation activities, PPFs provide
mechanisms to address conflicts of interest; technical assistance and capacity building
support. To effectively utilise PPFs, the following
• Create distinct structures for preparing large considerations are crucial:
complex projects; and
• Alignment of government objectives with relevant
• Build complementary capacity to equip GCAs PPF aims;
with skills and capabilities to manage project
preparation. • Seek support from PPFs for the upstream
enabling environment and improving public
investment efficiency; and

4 | GLOBAL INFRASTRUCTURE HUB


• View PPF support as a ‘stepping stone’ to build • Update infrastructure plans periodically to reflect
and accelerate local capacity creation, and not lessons learned and build credibility in planning;
just as a financing mechanism. and

3. Government budgets: Notwithstanding the • Create linkages of the plan with downstream
growth of PDFs and PPFs, a dominant portion actions, to operationalise the plans.
of project preparation is financed by public
2. Translate these plans into a prioritised and
spending from budgetary allocations of GCAs.
actionable projects pipeline: Once long-term
Even in Africa, where many PPFs are active,
plans are in place, they should be translated into
70-80% of project preparation funding comes
a credible and prioritised pipeline of programs
from government budgets. Given the scale of
and projects:
budgetary spending on project preparation,
governments should pay close attention to • Encourage GCAs to prepare master plans,
improving the efficacy and impact of these which can serve as useful starting points to build
expenditures. The following actions should a project pipeline database;
be considered:
• Create mechanisms to track and monitor projects
• Direct a portion of budgets to project preparation of national and strategic importance; and
while tracking expenditure and outcomes
• Move to evidence-based analysis to prioritise
continually;
projects, including through the use of tools such
• Implement GCA-level reporting and disclosure as the World Bank’s Infrastructure Prioritization
on project preparation spending; and Framework.

• Set and enforce guidelines with which GCAs must Project feasibility, reviews and approvals
comply to secure budgetary funding.
Translating a concept into a bankable project requires
Infrastructure planning and project prioritisation rigorous evaluation and appraisal of the project’s
feasibility, and often requires a multi-stage evaluation,
Well-planned and prioritised infrastructure investment
starting with a strategic case or concept definition,
improves productivity, engenders competitiveness
and moving through to pre-feasibility assessment and
and contributes to long-term sustainable economic
detailed feasibility evaluation. A structured approach
growth. Effective project preparation starts with
to project feasibility evaluation typically involves three
putting in place upstream mechanisms to formulate
steps:
long-term infrastructure plans, and translating those
plans into prioritised project pipelines. 1. Early-stage pipeline screening and pre-feasibility
assessment: Key actions required by central
1. Formulate medium- and long-term infrastructure
government agencies and GCAs at this stage
plans: This involves a systematic assessment
include the following:
of critical infrastructure gaps, identification of
priorities to drive socioeconomic transformation, • Strengthen planning processes and capacity of
setting actionable goals around these priorities, GCAs to translate development priorities into well-
and identifying projects to realise the agreed-upon scoped project concepts;
goals. The formulation of medium- and long-term
• Implement structured processes and guidelines
plans to drive greater focus and commitment to
for early stage screening, project identification
infrastructure development priorities calls for the
and scoping; and
following set of actions from governments:
• Create institutional support for independent
• Prepare long-term infrastructure plans that
unbiased pre-feasibility studies and early stage
translate a systematic baseline assessment into
project evaluation.
a committed articulation of priorities, goals and
pipeline of projects;

• Anchor accountability for infrastructure planning


within capable and empowered public institutions;

• Cascade infrastructure planning down to the level


of GCAs and sub-national governments;

Leading Practices in Governmental Processes Facilitating Infrastructure Project Preparation | 5


2. Rigour in feasibility evaluation: This step appropriate communication actions to inform and
involves a detailed evaluation of the project’s engage them; and fosters a supportive environment
feasibility and seeks to comprehensively facilitate through the course of project preparation and
decisions regarding the investment and financing implementation. Governments should:
of projects. The following elements should be
1. Formulate and deliver a stakeholder
considered:
engagement action plan to:
• Governments should develop harmonised
• Map stakeholders and their preferences, and
standards and guidelines for quality feasibility
assess the intensity of communication efforts
evaluations and build capacity in GCAs to perform
required;
them, using external consultants as appropriate.
• Assess stakeholders’ behaviour, influence
• While evaluating project feasibility, tools such as
and importance while identifying their needs,
the World Bank’s PPP Project Screening Tool can
expectations and concerns; and
help in building comprehensiveness of evaluation
and suitability for implementation using the PPP • Develop and deliver an appropriate
model of procurement. communication plan to address the various
stakeholder groups.
• Governments need to strike the right balance
between qualitative and quantitative approaches 2. For potential PPP projects, evaluate market
in determining which model of procurement to interest early in the project preparation phase
use, especially in the early stages where there is through the market sounding of projects to
limited data to inform assumptions, even though potential developers and investors. To prepare for
they ultimately seek to integrate comprehensive market soundings, the GCA should:
Value for Money analyses into overall public
• Identify and engage as wide a set of potential
investment planning.
bidders as possible; and
3. Periodic review and approvals: Mechanisms
• Identify positive aspects of the project that
to consistently build robust project reviews
position it as an attractive investment opportunity,
and appraisals in a multi-stage manner can
and position the GCA as a credible partner in the
help to avoid missing key requirements early
PPP transaction.
on and getting blindsided by challenges later in
the project preparation process. The following Concluding remarks
elements should be built into project reviews.
The reference tool synthesises lessons and
• Implementing well-defined and time-bound practices from global, national, and sub-national level
work flows to balance rigour and efficiency experiences to support governments in making project
considerations; preparation processes more effective. The reference
tool has been finalised with inputs and contributions
• Embedding a process audit into project
from government officials in over 15 countries,
preparation to build transparency, accountability
multilateral agencies, and private organisations,
and efficiency; and
who have helped to inform its final development.
• Ensuring that key stakeholders are involved
The reference tool blends conceptual inputs with
during project preparation and reviews.
country case examples and best practices, distilled
Project communication from the country-lens reviews undertaken during
the preparation of this tool, and also includes a
Stakeholder engagement during infrastructure
referencing of other tools and frameworks used
project preparation assumes tremendous significance
in project preparation.
given the multi-faceted nature of large infrastructure
projects and the complex stakeholder interfaces The reference tool is designed to complement the G20
they tend to cut across. Communication during the IWG Principles for the Infrastructure Project Preparation
course of infrastructure project preparation should be Phase and the MDB Guidance Note on Project
viewed as a strategic action that takes into account Preparation Facilities (PPF): Structure and Operations.
the importance and disposition of all key stakeholder
groups towards the project; tailors timely and

6 | GLOBAL INFRASTRUCTURE HUB

You might also like