You are on page 1of 80

4 14.11.

2022 Revised as per client comments AP SB KCM


3 19.07.2022 Revised as per client comments AP SB KCM
2 22.04.2022 Revised as per client comments AP SB KCM
1 13.01.2022 Revised as per client comments AP SB KCM
0 10.08.2021 Issued for Information AP SB PKP
Rev. Date Description Prepared Checked Approved
PLACE RESERVED FOR STAMPS: Date :
Prev. CS No. :
Prev. CS Date :
28-11-2022

PROJECT COMPANY: SOUTH JEDDAH NOOR PV ENERGY COMPANY LLC,


2540 AL ISKANDARIYYAH – AL HAMRA DIST,
23212 – 6999 JEDDAH
SAUDI ARABIA

OWNER’S ENGINEER:
NATIONAL INSPECTION & TECHNICAL TESTING CO LTD
(FAHSS TUV NORD)

CONTRACTOR: LARSEN AND TOUBRO LIMITED,


INDUSTRIAL CREATIVITY CENTRE BUILDING
DABAB STREET, RIYAD - 11351,
KINGDOM OF SAUDI ARABIA
TEL : +966 11 4793777
SUB CONTRACTOR:

PROJECT:
CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA
NAME DATE SIGN TITLE:
PREPARED AP 06.08.2021
SCADA I/O SIGNAL LIST
CHECKED SB 09.08.2021
APPROVED KCM 10.08.2021

DRAWING /DOCUMENT NUMBER REVISON NO SHEET NO

20PKSA001-LNT-SPV-I-LST-1301 4 1 OF 80
CONTENTS
1 Equipment .......................................................................................................... 3
2 Location ............................................................................................................. 4
2.1 Climate and site conditions ........................................................................... 5
3 Attachment ......................................................................................................... 6

SCADA I/O SIGNAL LIST Page 2 of 80


20PKSA001-LNT-SPV-I-LST-1301
1 Equipment

Description

SCADA I/O SIGNAL LIST

SCADA I/O SIGNAL LIST Page 3 of 80


20PKSA001-LNT-SPV-I-LST-1301

Sensitivity: LNT Construction Internal Use


2 Location
The Site is in the Third Jeddah Industrial City, 50 km south-east of Jeddah and about 50
km south-west of Mecca in the Makkah region. The size of the available area is
approximately 7.9 km².

FIGURE 1 Overview Map Include Site Location

FIGURE 2 General View of the site

SCADA I/O SIGNAL LIST Page 4 of 80


20PKSA001-LNT-SPV-I-LST-1301

Sensitivity: LNT Construction Internal Use


2.1 Climate and site conditions

As Indicated on EPC - 01 - Project Company's Requirements - Part II , climate and site


conditions of site location are following:

Parameter Unit Data


Highest recorded
°C 51.6
temperature
Lowest recorded
°C 12.4
temperature
Ultimate design wind
m/s 44
speed
Maximum precipitation in
mm 73
24hrs
Yearly average soiling rate %/day 0.47
Table1. Climate and site conditions
Site climate conditions such as Time Series, TMY and Albedo have been received and
summarized as per the following table:

Document File
T-Series (30 min) - SG-63941-1908-10-1_TSmin_15_REP.pdf
SolarGis SG-63941-1908-10-1_TSmin_15.csv
TMY ( P50, P75, P90) SA-Jed-TMY_P50_2018-07-10.xlsx
ALBEDO Data Albedo_CSPS_Jeddah_KSA.csv

SCADA I/O SIGNAL LIST Page 5 of 80


20PKSA001-LNT-SPV-I-LST-1301

Sensitivity: LNT Construction Internal Use


3 Attachment
Description Page No
SCADA IO SIGNAL LIST FOR IDT STATION 8
SCADA IO SIGNAL LIST AT O&M BUILDING 59

SCADA I/O SIGNAL LIST Page 6 of 80


20PKSA001-LNT-SPV-I-LST-1301

Sensitivity: LNT Construction Internal Use


ATTACHMENTS

SCADA I/O SIGNAL LIST Page 7 of 80


20PKSA001-LNT-SPV-I-LST-1301

Sensitivity: LNT Construction Internal Use


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Breaker Open Status to SCADA Indication 1 - - - -


Breaker Close Status to SCADA Indication 1 - - - -
Local Mode Status to SCADA Indication 1 - - - -
Remote Mode Status to SCADA Indication 1 - - - -
O/C Trip Status (Trip output over current) Alarm 1 - - - -
33kV Breaker E/F Trip Status (Trip output earth Fault) Alarm 1 - - - - RMU Vendor Drawings & Technical data sheet (20PKSA001-
1 (Ring Main Unit at Inverter Duty
DC Supply Unhealthy Status to SCADA Alarm 1 - - - - LNT-SPV-V-DSH-1709)
Transformer station)
Motor is enabled to SCADA Indication 1 - - - -
Gas density monitor- Closed When Pressure Low to SCADA Alarm 1 - - - -
Gas density monitor- Closed When Pressure Ok to SCADA Indication 1 - - - -
Breaker Open Command from SCADA Command - 1 - - -
Breaker Close Command from SCADA Command - 1 - - -

Disconnector Disconnector Switch at Earth position Indication 1 - - - -


RMU Vendor Drawings & Technical data sheet (20PKSA001-
2 (Ring Main Unit at Inverter Duty Disconnector Switch at Off position Indication 1 - - - -
LNT-SPV-V-DSH-1709)
Transformer station)
Disconnector Switch at On position Indication 1 - - - -
Data for current measurement on I1 Value to SCADA Measurement - - - 1 -
Data for current measurement on I2 Value to SCADA Measurement - - - 1 -
Numerical Relay Data for current measurement on I3 Value to SCADA Measurement - - - 1 - 1. RMU Vendor Drawings & Technical data sheet (20PKSA001-
3 (Ring Main Unit at Inverter Duty LNT-SPV-V-DSH-1709)
Transformer station) Data for current measurement on I0 Value to SCADA Measurement - - - 1 - 2. Annexure-1 – Numerical relay Mapping list
Phase Trip Status to SCADA Alarm - - - 1 -
Earth Trip Status to SCADA Alarm - - - 1 -
Earth Fault Indication (EFI)/Fault I>> short-circuit in phase L1/L2/L3 (Fault direction A↑) Alarm - - - 1 -
passage indicator (FPI) I>> short-circuit in phase L1/L2/L3 (Fault direction B↓) Alarm - - - 1 -
4 Annexure-7 – EFI/FPI Mapping List
(Ring Main Unit at Inverter Duty IES> earth fault (Fault direction A↑) Alarm - - - 1 -
Transformer station) IES> earth fault (Fault direction B↓) Alarm - - - 1 -
Load Break Switch (LBS) Load Break Switch at Earth position Status to SCADA Indication 1 - - - -
RMU Vendor Drawings & Technical data sheet (20PKSA001-
5 (Ring Main Unit at Inverter Duty Load Break Switch at Open position Status to SCADA Indication 1 - - - -
LNT-SPV-V-DSH-1709)
Transformer station) Load Break Switch at Close position Status to SCADA Indication 1 - - - -
LV Winding-1 High Temperature Alarm Status to SCADA Alarm 1 - - - -
LV Winding-2 High Temperature Alarm Status to SCADA Alarm 1 - - - -
HV Winding High Temperature Alarm Status to SCADA Alarm 1 - - - -
Oil High Temperature Alarm Status to SCADA Alarm 1 - - - -
Buchholz Relay Alarm Status to SCADA Alarm 1 - - - -
Inverter Duty Transformer
Magnetic Oil Gauge (MOG) Alarm Status to SCADA Alarm 1 - - - - RMU Vendor Drawings & Technical data sheet (20PKSA001-
6 (From Ring Main Unit at Inverter Duty
LV Winding-1 High Temperature Trip Status to SCADA Alarm 1 - - - - LNT-SPV-V-DSH-1709)
Transformer station)
LV Winding-2 High Temperature Trip Status to SCADA Alarm 1 - - - -
HV Winding High Temperature Trip Status to SCADA Alarm 1 - - - -
Oil High Temperature Trip Status to SCADA Alarm 1 - - - -
Buchholz Relay Trip Status to SCADA Alarm 1 - - - -
Pressure Release Valve (PRV) Trip Status to SCADA Alarm 1 - - - -
LV Winding-1 Temperature Value to SCADA Measurement - - 1 - -
Inverter Duty Transformer LV Winding-2 Temperature Value to SCADA Measurement - - 1 - - Inverter Duty Transformer
(From marshalling box of Inverter Duty
7 HV Winding Temperature Value to SCADA Measurement - - 1 - - Drawings & Technical data sheet (20PKSA001-LNT-SPV-V-DSH-
Transformer at Inverter Duty
Magnetic Oil Gauge Level Value to SCADA Measurement - - 1 - - 1710)
Transformer station)
Oil Temperature Value to SCADA Measurement - - 1 - -

# Sensitivity: Unclassified Page 1 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Incomer Breaker ON status to SCADA Indication 1 - - - -


LT Panel Incomer OFF status to SCADA Indication 1 - - - - LV Panel Drawings & Data sheet
8
at Inverter Duty Transformer station Incomer Trip status to SCADA Alarm 1 - - - - (20PKSA001-LNT-SPV-V-DSH-1712)

Incomer Sparing charged status to SCADA Indication 1 - - - -


L1 Phase Voltage Value to SCADA Measurement - - - 1 -
L2 Phase Voltage Value to SCADA Measurement - - - 1 -
L3 Phase Voltage Value to SCADA Measurement - - - 1 -
Average Voltage Value to SCADA Measurement - - - 1 -
L1 Phase Current Value to SCADA Measurement - - - 1 -
L2 Phase Current Value to SCADA Measurement - - - 1 -
L3 Phase Current Value to SCADA Measurement - - - 1 -
Neutral Current Value to SCADA Measurement - - - 1 -
Average Current Value to SCADA Measurement - - - 1 - 1. LV Panel Drawings & Data sheet
Multi Function Meter (MFM)
Frequency Value to SCADA Measurement - - - 1 - (20PKSA001-LNT-SPV-V-DSH-1712)
9 (Associated with LT Panel at Inverter
Duty Transformer station) Avg power factor Value to SCADA Measurement - - - 1 - 2. Annexure-2 – LT Panel MFM Data sheet
Active Power Value to SCADA Measurement - - - 1 -
Apparent Power Value to SCADA Measurement - - - 1 -
Reactive power Value to SCADA Measurement - - - 1 -
Active import/ export energy Value to SCADA Measurement - - - 1 -
Reactive import/ export energy Value to SCADA Measurement - - - 1 -
Net active energy (Active Import – Active export energy) Value to
Measurement - - - 1 -
SCADA
Gross active import/ export energy (Sum of all import/ export energy)
Measurement - - - 1 -
Value to SCADA

Auxiliary Transformer Aux Transformer Drawings &


10 Winding Temperature Trip Status to SCADA Alarm 1 - - - -
(At Inverter Duty Transformer station) Technical data sheet (20PKSA001-LNT-SPV-V-DSH-1711)

DC Current Value to SCADA Measurement - - - 1 -


DC Voltage Value to SCADA Measurement - - - 1 -
DC Power Value to SCADA Measurement - - - 1 -
Phase Value to SCADA Measurement - - - 1 -
AC Input Voltage Value to SCADA Measurement - - - 1 -
AC Input Current Value to SCADA Measurement - - - 1 -
AC Input Frequency Value to SCADA Measurement - - - 1 -
UPS
11 AC Input True Power Value to SCADA Measurement - - - 1 - Annexure-3 – UPS Mapping List
(At Inverter Duty Transformer station)
AC Input Apparent Power Value to SCADA Measurement - - - 1 -
AC Output Voltage Value to SCADA Measurement - - - 1 -
AC Output Current Value to SCADA Measurement - - - 1 -
AC Output Frequency Value to SCADA Measurement - - - 1 -
AC Output True Power Value to SCADA Measurement - - - 1 -
AC Output Apparent Power Value to SCADA Measurement - - - 1 -
Temperature Value to SCADA Measurement - - - 1 -
L1 Phase Voltage Value to SCADA Measurement - - - 1 -
L2 Phase Voltage Value to SCADA Measurement - - - 1 -
L3 Phase Voltage Value to SCADA Measurement - - - 1 -
L1 Phase Current Value to SCADA Measurement - - - 1 -
L2 Phase Current Value to SCADA Measurement - - - 1 -
Multi Function Meter (MFM) L3 Phase Current Value to SCADA Measurement - - - 1 - 1. IDT station Auxiliary Panel (400V ACDB)
(Associated with Auxiliary Panel (400V (20PKSA001-LNT-SPV-E-DSH-1265)
12 Frequency Value to SCADA Measurement - - - 1 -
ACDB) at Inverter Duty Transformer
station Avg power factor Value to SCADA Measurement - - - 1 - 2. Annexure-8 – IDT Auxiliary Panel MFM Data sheet

# Sensitivity: Unclassified Page 2 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

Multi Function Meter (MFM) I/O Quantity Per Equipment 1. IDT station Auxiliary Panel (400V ACDB)
S.12
No. (Associated with Auxiliary
Equipment Name Panel (400V Signal Description Signal Type (20PKSA001-LNT-SPV-E-DSH-1265)
Reference
ACDB) at Inverter Duty Transformer DI DO AI MODBUS RS 485 Modbus TCP/IP
station 2. Annexure-8 – IDT Auxiliary Panel MFM Data sheet
Active Power Value to SCADA Measurement - - - 1 -
Apparent Power Value to SCADA Measurement - - - 1 -
Reactive power Value to SCADA Measurement - - - 1 -
Active import/ export energy Value to SCADA Measurement - - - 1 -
Reactive import/ export energy Value to SCADA Measurement - - - 1 -
All Inverters Power on setting (The data field can only be 0 for Annexure-11 – SmartLogger ModBus Interface Definitions
Command - - - - 1
poweringon all inverters.)
All Inverters Power off setting (The data field can only be 0 for powering
Command - - - - 1
off all inverters.)

All Inverters Power on/off Command - - - - 1

Transfer trip (The device shuts down when it stops due to faults and
Command - - - - 1
does not respond to the startup request.)
Array reset Command - - - - 1
All Inverters Active adjustment Command - - - - 1
All Inverters Reactive adjustment Command - - - - 1
All Inverters Active power adjustment by percentage Command - - - - 1
All Inverters Power factor adjustment Command - - - - 1
Total input DC current of all inverters Measurement - - - - 1
Total input power of all inverters Measurement - - - - 1
Total CO2 reduction of all inverters Measurement - - - - 1
Total active output power of all inverters Measurement - - - - 1
Total power factor of all inverters Measurement - - - - 1
Total reactive output power of all inverters Measurement - - - - 1
Total CO2 reduction of all inverters (Maximum value) Measurement - - - - 1
Total input DC current of all inverters (Maximum value) Measurement - - - - 1
Total energy yield generatedby all inverters Measurement - - - - 1
Daily energy yield generated by all inverters Measurement - - - - 1
Duration of daily power generation Measurement - - - - 1
Sum of phase A currents of all inverters Measurement - - - - 1
Sum of phase B currents of all inverters Measurement - - - - 1
Sum of phase C currents of all inverters Measurement - - - - 1
Phase A-B Voltage Measurement - - - - 1
Phase B-C Voltage Measurement - - - - 1
Phase C-A Voltage Measurement - - - - 1
Max. reactive adjustment Measurement - - - - 1
Min. reactive adjustment Measurement - - - - 1
Max. active adjustment Measurement - - - - 1
System reset Indication - - - - 1
Fast device access Indication - - - - 1
Device operation Indication - - - - 1
Smart Array Controller (At Inverter Duty Device access status Indication - - - - 1
13
Transformer station) Active power control mode Indication - - - - 1
Active power scheduling target value Measurement - - - - 1
Reactive power control mode Indication - - - - 1
Reactive power scheduling curve mode Indication - - - - 1
Reactive power scheduling target value Measurement - - - - 1
Active scheduling percentage Measurement - - - - 1

# Sensitivity: Unclassified Page 3 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
Smart Array Controller (At Inverter Duty
13
Transformer station) SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

CO2 emission reduction coefficient Measurement - - - - 1


PV module capacity Measurement - - - - 1
Rated plant capacity Measurement - - - - 1
Total rated capacity of grid-connected inverters Measurement - - - - 1
Conversion coefficient Measurement - - - - 1
Communication status Indication - - - - 1
Communication abnormal shutdown Measurement - - - - 1
Communication anbormal detection time Measurement - - - - 1
Auto start upon communication recovery Measurement - - - - 1
Current error during scanning Measurement - - - - 1
Inspection Indication - - - - 1
IV curve scanning Indication - - - - 1
Abnormal Active Schedule Indication - - - - 1
Abnormal Reactive Schedule Indication - - - - 1
MCB Disconnect Indication - - - - 1
Abnormal Cubicle Indication - - - - 1
Device Address Conflict Indication - - - - 1
AC SPD fault Indication - - - - 1
24V power failure Indication - - - - 1
Inverter Active power Measurement - - - - 42
Inverter Reactive power Measurement - - - - 42
Inverter Total DC input current Measurement - - - - 42
Inverter Total input power Measurement - - - - 42
Insulation resistance Measurement - - - - 42
Power factor Measurement - - - - 42
Inverter status Measurement - - - - 42
Cabinet temperature Measurement - - - - 42
Rated power (Pn) Measurement - - - - 1 Annexure-4 – String Inverter Mapping List

Maximum active power (Pmax) Measurement - - - - 1


Maximum apparent power (Smax) Measurement - - - - 1
Maximum reactive power (Qmax, fed to the power grid) Measurement - - - - 1
Maximum reactive power (Qmax, absorbed from the power grid) Measurement - - - - 1
Inverter standby Indication - - - - 1
Inverter grid connection Indication - - - - 1
Inverter normal grid connection Indication - - - - 1
Inverter grid connection with derating due to power rationing Indication - - - - 1
Inverter grid connection with derating due to inverter internal causes Indication - - - - 1
Inverter normal stop Indication - - - - 1
Inverter stop due to faults Alarm - - - - 1
Inverter stop due to power rationing Alarm - - - - 1
Inverter shutdown Alarm - - - - 1
Inverter spot check Indication - - - - 1

# Sensitivity: Unclassified Page 4 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Inverter locking status Indication - - - - 1


Inverter PV connection status Indication - - - - 1
Inverter DSP data collection Indication - - - - 1
Inverter High String Voltage Indication - - - - 1
Inverter DC Arc Fault Alarm - - - - 1
Inverter String Reversed Indication - - - - 1
Inverter PV String Backfeed Indication - - - - 1
Inverter Abnormal String Indication - - - - 1
Inverter AFCI Self-test Fault Indication - - - - 1
Inverter Short circuit between phase to PE Indication - - - - 1
Inverter Power Grid Failure Indication - - - - 1
Inverter Grid Undervoltage Indication - - - - 1
Inverter Grid Overvoltage Indication - - - - 1
Inverter Unbalanced Grid Voltage Indication - - - - 1
Inverter Grid Overfrequency Indication - - - - 1
Inverter Grid Underfrequency Indication - - - - 1
Inverter Grid Frequency Instability Indication - - - - 1
Inverter Output Overcurrent Indication - - - - 1
Inverter Large DC of Output current Measurement - - - - 1
Inverter Abnormal Leakage Current Measurement - - - - 1
Inverter Abnormal Ground. Indication - - - - 1
Inverter Low Insulation Res. Indication - - - - 1
Inverter High Temperature Indication - - - - 1
Inverter Abnormal Equipment Indication - - - - 1
Inverter Upgrade Failed Indication - - - - 1
Inverter Abnormal Monitor Unit Indication - - - - 1
Inverter High String Voltage to Ground Indication - - - - 1
Inverter PV1 Voltage (14 / 16 String) Measurement - - - - 16
Inverter PV1 Current (14 / 16 String) Measurement - - - - 16
Inverter Input power Measurement - - - - 1
Inverter voltage phases A and B Measurement - - - - 1
Inverter voltage phases B and C Measurement - - - - 1
Inverter voltage phases C and D Measurement - - - - 1
Inverter Phase A current Measurement - - - - 1
String Inverter(At Inverter Duty
14 Inverter Phase B current Measurement - - - - 1
Transformer station)
Inverter Phase C current Measurement - - - - 1
Inverter Active power peak of current day Measurement - - - - 1
Inverter Active power Measurement - - - - 1
Inverter Reactive power Measurement - - - - 1
Inverter Power factor Measurement - - - - 1
Inverter Frequency Measurement - - - - 1
Inverter Inverter efficiency Measurement - - - - 1

# Sensitivity: Unclassified Page 5 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA
String Inverter(At Inverter Duty
14
Transformer station) Document Title L&T Document No. Rev. No.
20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Inverter Cabinet temperature Measurement - - - - 1


Inverter Insulation resistance Measurement - - - - 1
Inverter Idle:Initializing Measurement - - - - 1
Inverter Idle:Detecting ISO Measurement - - - - 1
Inverter Idle:Detecting irradiation Measurement - - - - 1
Inverter Idle:Grid detecting Measurement - - - - 1
Inverter Starting Measurement - - - - 1
Inverter On-grid Measurement - - - - 1
Inverter On-grid: Power limit Measurement - - - - 1
Inverter On-grid:self derating Measurement - - - - 1
Inverter Shutdown: Fault Alarm - - - - 1
Inverter Shutdown:Command Command - - - - 1
Inverter Shutdown: OVGR Indication - - - - 1
Inverter Shutdown: Communication disconnected Indication - - - - 1
Inverter Shutdown: Power limit Indication - - - - 1
Inverter Shutdown: Start manually Indication - - - - 1
Inverter Shutdown: DC switch OFF Indication - - - - 1
Inverter Grid dispatch: cos(Phi)-P curve Indication - - - - 1
Inverter Grid dispatch: QU curve Indication - - - - 1
Inverter Idle: No irradiation Indication - - - - 1
Inverter Spot-check Indication - - - - 1
Inverter Spot-checking Indication - - - - 1
Inverter Inspecting Indication - - - - 1

Inverter AFCI self-check Indication - - - - 1

Inverter IV scanning Indication - - - - 1

Inverter DC input detection Indication - - - - 1

Inverter Startup time Measurement - - - - 1

Inverter Shutdown time Measurement - - - - 1

Inverter Total energy yield Measurement - - - - 1

Inverter Energy yield of current day Measurement - - - - 1

Inverter Energy yield of current month Measurement - - - - 1

Inverter Energy yield of current year Measurement - - - - 1

Inverter System Time Measurement - - - - 1

Inverter Active power derating Measurement - - - - 1

Inverter Reactive power compensation (PF) Measurement - - - - 1

Inverter Reactive power compensation(Q/S) Measurement - - - - 1

Inverter Active power derating percent(0.1%) Measurement - - - - 1

Inverter Power on Indication - - - - 1

Inverter Power off Indication - - - - 1

# Sensitivity: Unclassified Page 6 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Global Horizontal Pyranometer-1 Irradiation Measurement - - - - 1


Global Horizontal Pyranometer-1 Calculated Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-2 Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-2 Calculated Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-3 Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-3 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-1 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-1 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-2 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-2 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-3 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-3 Calculated Irradiation Measurement - - - - 1
Wind Speed Measurement - - - - 1
Wind Direction Measurement - - - - 1
Weather Monitoring Station - Type-1
15 Ambient Temperature Measurement - - - - 1 Annexure-5 – Weather Monitoring Station Mapping List
(At Inverter Duty Transformer station)
Relative Humidity Measurement - - - - 1
Rain Measurement - - - - 1
Air Pressure Measurement - - - - 1
PV Module Temperature-1 Measurement - - - - 1
PV Module Temperature-2 Measurement - - - - 1
PV Module Temperature-3 Measurement - - - - 1
PV Module Temperature-4 Measurement - - - - 1
PV Module Temperature-5 Measurement - - - - 1
PV Module Temperature-6 Measurement - - - - 1
Albedo (Horizontal) Measurement - - - - 1
Diffuse Horizontal Irradiation (W/m2) Measurement - - - - 1
Direct Normal irradiance (W/m2) Measurement - - - - 1
Soiling Loss (%) Measurement - - - - 1
Global Horizontal Pyranometer-1 Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-1 Calculated Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-2 Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-2 Calculated Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-3 Irradiation Measurement - - - - 1
Global Horizontal Pyranometer-3 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-1 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-1 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-2 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-2 Calculated Irradiation Measurement - - - - 1
Plane of Array Pyranometer-3 Irradiation Measurement - - - - 1
Plane of Array Pyranometer-3 Calculated Irradiation Measurement - - - - 1
Wind Speed Measurement - - - - 1
Wind Direction Measurement - - - - 1
Weather Monitoring Station - Type-2 Ambient Temperature Measurement - - - - 1
16 Annexure-5 – Weather Monitoring Station Mapping List
(At Inverter Duty Transformer station) Relative Humidity Measurement - - - - 1
Rain Measurement - - - - 1
Air Pressure Measurement - - - - 1

# Sensitivity: Unclassified Page 7 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22
Weather Monitoring Station - Type-2
16 Annexure-5 – Weather Monitoring Station Mapping List
(At Inverter Duty Transformer station) I/O Quantity Per Equipment
S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

PV Module Temperature-1 Measurement - - - - 1


PV Module Temperature-2 Measurement - - - - 1
PV Module Temperature-3 Measurement - - - - 1
PV Module Temperature-4 Measurement - - - - 1
PV Module Temperature-5 Measurement - - - - 1
PV Module Temperature-6 Measurement - - - - 1
Albedo (Horizontal) Measurement - - - - 1
Soiling Loss (%) Measurement - - - - 1
Albedo-1 (Plane of Array) Measurement - - - - 1
Albedo-2 (Plane of Array) Measurement - - - - 1
Albedo-3 (Plane of Array) Measurement - - - - 1
Year Local Feedback - - - - 1 Local year
Month Local Feedback - - - - 1 Local month
Day Local Feedback - - - - 1 Local day
Hour Local Feedback - - - - 1 Local 24 hour
Minute Local Feedback - - - - 1 Local minute
Second Local Feedback - - - - 1 Local second
Sun Azimuth Feedback - - - - 1 Sun Azimuth

Sun Zenith Feedback - - - - 1 Sun Zenith

Sun Angle Feedback - - - - 1 Sun Angle

Sun tracking setpoint for trackers in auto mode in degrees from


Global Auto Elevation Target Feedback - - - - 1
horizonta

Global Wind Direction EW Feedback - - - - 1 Stow Control Mode:

Backtracking Status Feedback - - - - 1 Status of Backtracking

Night Setpoint Feedback - - - - 1 Setpoint defined for the Night possition


Tracker - Plant Data
17
(TBOX to SCADA RIO panel) Night Mode Feedback - - - - 1 Status of Night Mode

Wind Direction Feedback - - - - 1 Numeric value of wind direction


Wind Speed Feedback - - - - 1 Numeric value of wind speed
WindAlarm Feedback - - - - 1 Status of Wind Speed Alarm
If Wind_Speed is 0 during more than 24 hours,
Wind In activity Alarm Feedback - - - - 1
WindIncativityAlarm get's TRUE
UPS Alarm Status. If UpsAlarm is TRUE, it is alarmed. Check
UpsAlarm Feedback - - - - 1
the UPS

Ups Battery Feedback - - - - 1 If UpsBattery is TRUE, UPS is the TBOX power supply

If UpsCharging is TRUE, Auxiliary Services is the TBOX power


Ups Charging Feedback - - - - 1
supply
Count of active anemometers considering all MBoxes and
Anemometer Active Number Feedback - - - - 1
TBoxes anemometers

# Sensitivity: Unclassified Page 8 of 10


Tracker - Plant Data
17
(TBOX to SCADA RIO panel)

Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16


REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Count of total anemometers considering all MBoxes and TBoxes


Anemometer Total Number Feedback - - - - 1
anemometers
Warning rised when at least one anemometer is not
Anemometer Warning Feedback - - - - 1 communicating with the TBoxes considering all MBoxes and
TBoxes anemometers.
Diffuse State Feedback - - - - 1 Diffuse Control State Machine state
Internal Diffuse Sensor Value Feedback - - - - 1 Diffuse-Global irradiance ratio internal value
Applicable Diffuse Sensor Value Feedback - - - - 1 Diffuse-Global irradiance ratio applicable value

Auto incremented counter when a message is processed by the


TBox. It does not mean that the message is sent to or received
Global Message Counter Control - - - - 1 by the DBox since LoRa communications are not inmediate.
Status or setpoint feedback will be available once the DBox
sends its state.

Wind Alarm Trigger Control - - - - 1 Signal to send all trackers a global wind alarm

Tracker - Plant control from plant Stop Alarm Trigger Control - - - - 1 Signal to send all trackers a global stop alarm
18 SCADA
(TBOX to SCADA RIO panel)
Manual Elevation Target Trigger Control - - - - 1 Signal to send all trackers a global manual setpoin

Manual Elevation Target Control - - - - 1 Global manual setpoint to be sent

Set Auto Control Trigger Control - - - - 1 Signal to send all trackers a set to auto signal

Construction Trigger Control - - - - 1 Signal to send all trackers a set to construction position signa

Trigger Counter FEEDBACK - - - - 1 Feeback from Trigger messages


Tracker - AUTO MODE SETTINGS
19 Diffuse Enable CONTROL - - - - 1 Enable Diffuse control algorithm
(TBOX to SCADA RIO panel)
Diffuse Is Enabled FEEDBACK - - - - 1 Feeback from Diffuse Enable

Writable register for receiving global irradiance values from


Global Irradiance From SCADA CONTROL - - - - 1
SCADA in Watts per square mete

Writable register for receiving diffuse irradiance values from


Diffuse Irradiance From SCADA CONTROL - - - - 1
Tracker - INPUT DATA SCADA in Watts per square mete
20
(TBOX to SCADA RIO panel)
Selector to use diffuse data from SCADA (value 1) or internal
Select SCADA Diffuse Data CONTROL - - - - 1
data (value 0

SCADA Diffuse Data Is Selected FEEDBACK - - - - 1 Feedback from Diffuse selected

Auto incremented counter when a message is processed by the


TBox. It does not mean that the message is sent to or received
Global Message Counter CONTROL - - - - 1 by the DBox since LoRa communications are not inmediate.
Status or setpoint feedback will be available once the DBox
sends its state.

Wind Alarm Trigger CONTROL - - - - 1 Flag signal to send all trackers a global wind alarm

Tracker - GENERAL BLOCK CONTROL Stop Alarm Trigger CONTROL - - - - 1 Flag signal to send all trackers a global stop alarm
21
(TBOX to SCADA RIO panel)
Manual Elevation Target Trigger CONTROL - - - - 1 Flag signal to send all trackers a global manual setpoint

# Sensitivity: Unclassified Page 9 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION Prepared Checked Approved Date
AP SB KCM 06-Oct-22

Tracker - GENERAL BLOCK CONTROL I/O Quantity Per Equipment


21
(TBOX to SCADA RIO panel)
S. No. Equipment Name Signal Description Signal Type Reference
DI DO AI MODBUS RS 485 Modbus TCP/IP

Manual Elevation Target CONTROL - - - - 1 Global manual setpoint to be sent

Set Auto Control Trigger CONTROL - - - - 1 Flag signal to send all trackers a set to auto signal

Flag signal to send all trackers a set to construction position


Construction Trigger CONTROL - - - - 1
signal

Wind Speed 3s Feedback - - - - 1 Average numeric value of wind speed of the last 3 seconds

Wind Direction 3s Feedback - - - - 1 Average numeric value of wind direction of the last 3 seconds

Wind Speed 30s Feedback - - - - 1 Average numeric value of wind speed of the last 30 seconds

Wind Direction 30s Feedback - - - - 1 Average numeric value of wind direction of the last 30 seconds
Tracker - MBOX BLOCK X
22
(TBOX to SCADA RIO panel)
Battery Level Feedback - - - - 1 Battery level
Alarms:
Alarms Feedback - - - - 1 - Bit 0: Anemometer Fault
- Bit 1: Charger Fault

Numeric value average of wind direction east/west each 3


Ew3s Feedback - - - - 1
seconds 1 - East 2 - West

Numeric value average of wind direction east/west each 30


Ew30s Feedback - - - - 1
seconds 1 - East 2 - West

Notifications Feedback - - - - 1 Notifications - Bit 0: Outdated


Control Triggers Word CONTROL - - - - 1
Manual Elevation Target CONTROL - - - - 1
Operation Mode FEEDBACK - - - - 1
Elevation Setpoint FEEDBACK - - - - 1
Elevation Position FEEDBACK - - - - 1
Tracker - DBOX
23 Battery Level FEEDBACK - - - - 1
(TBOX to SCADA RIO panel)
Alarms FEEDBACK - - - - 1
Max Motor Current FEEDBACK - - - - 1
Warnings FEEDBACK - - - - 1
Position Code FEEDBACK - - - - 1
Notifications FEEDBACK - - - - 1

Feedback from Gateway state


1 – No communication
Tracker - Gateway
24 Status FEEDBACK - - - - 1 2 – No credentials
(TBOX to SCADA RIO panel)
3 – Login error
4 - OK
Note:
(i) This I/O list shall be updated based on the vendor document of electrical equipment's in case of any change.
(ii) Please refer following documents for Tracker communication.

1. SOLAR PLANT: SINGLE LINE DIAGRAM (DC & AC) - (20PKSA001-LNT-SPV-E-DWG-1201)


2. Tracker Communication Architecture Diagram (20PKSA001-LNT-SPV-M-DWG-1403)
3. Annexure-6 – Tracker controller system Mapping List

# Sensitivity: Unclassified Page 10 of 10


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP

I PLC RTU/RIO Panel at IDTS-01

1 IDTS-01_36kV Breaker-1 10 2 -- -- --

2 IDTS-01_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-01_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-01_36kV EFI/FPI -- -- -- 4 --

5 IDTS-01_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-01_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-01_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-01_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-01_LT Panel-1 4 -- -- -- --

10 IDTS-01_LT Panel-2 4 -- -- -- --

11 IDTS-01_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-01_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-01_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-01_UPS -- -- -- 15 --

15 IDTS-01_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-01_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-01_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-01 40 2 5 74 5258

# Sensitivity: Unclassified Page 1 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
II PLC RTU/RIO Panel at IDTS-02

1 IDTS-02_36kV Breaker-1 10 2 -- -- --

2 IDTS-02_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-02_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-02_36kV EFI/FPI -- -- -- 4 --

5 IDTS-02_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-02_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-02_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-02_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-02_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-02_LT Panel-1 4 -- -- -- --

11 IDTS-02_LT Panel-2 4 -- -- -- --

12 IDTS-02_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-02_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-02_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-02_UPS -- -- -- 15 --

16 IDTS-02_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-02_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-02_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-02 43 2 5 74 5258

# Sensitivity: Unclassified Page 2 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
III PLC RTU/RIO Panel at IDTS-03

1 IDTS-03_36kV Breaker-1 10 2 -- -- --

2 IDTS-03_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-03_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-03_36kV EFI/FPI -- -- -- 4 --

5 IDTS-03_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-03_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-03_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-03_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-03_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-03_LT Panel-1 4 -- -- -- --

11 IDTS-03_LT Panel-2 4 -- -- -- --

12 IDTS-03_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-03_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-03_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-03_UPS -- -- -- 15 --

16 IDTS-03_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-03_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-03_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

19 IDTS-03_Weather Monitoring Station_Type1 -- -- -- -- 28

Total I/O for PLC RTU/RIO Panel at IDTS-03 43 2 5 74 5286

# Sensitivity: Unclassified Page 3 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
IV PLC RTU/RIO Panel at IDTS-04

1 IDTS-04_36kV Breaker-1 10 2 -- -- --
2 IDTS-04_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-04_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-04_36kV EFI/FPI -- -- -- 4 --
5 IDTS-04_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-04_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-04_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-04_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-04_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
10 IDTS-04_LT Panel-1 4 -- -- -- --
11 IDTS-04_LT Panel-2 4 -- -- -- --
12 IDTS-04_LT Panel-1_MFM -- -- -- 18 --
13 IDTS-04_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-04_Auxiliary Transformer Panel 1 -- -- -- --
15 IDTS-04_UPS -- -- -- 15 --
16 IDTS-04_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-04_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.
18 IDTS-04_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

IDTS- 1 (D-BOX : 280 Nos),


IDTS- 2 (D-BOX : 280 Nos),
IDTS- 3 (D-BOX : 280 Nos), (M-BOX : 1 No),
19 IDTS-04_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 15643
IDTS- 4 (D-BOX : 294 Nos),
IDTS- 7 (D-BOX : 280 Nos)
and 3 Nos of M-BOX in Boundary

# Sensitivity: Unclassified Page 4 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
Total I/O for PLC RTU/RIO Panel at IDTS-04 43 2 5 74 21161

V PLC RTU/RIO Panel at IDTS-05

1 IDTS-05_36kV Breaker-1 10 2 -- -- --
2 IDTS-05_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-05_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-05_36kV EFI/FPI -- -- -- 4 --
5 IDTS-05_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-05_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-05_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
8 IDTS-05_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
9 IDTS-05_LT Panel-1 4 -- -- -- --
10 IDTS-05_LT Panel-2 4 -- -- -- --
11 IDTS-05_LT Panel-1_MFM -- -- -- 18 --
12 IDTS-05_LT Panel-2_MFM -- -- -- 18 --
13 IDTS-05_Auxiliary Transformer Panel 1 -- -- -- --
14 IDTS-05_UPS -- -- -- 15 --
15 IDTS-05_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
16 IDTS-05_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
17 IDTS-05_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

# Sensitivity: Unclassified Page 5 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP

IDTS- 5 (D-BOX : 280 Nos),


IDTS- 6 (D-BOX : 280 Nos),
IDTS- 8 (D-BOX : 294 Nos), (M-BOX : 1 No),
IDTS- 9 (D-BOX : 280 Nos),
18 IDTS-05_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 21977
IDTS- 10 (D-BOX : 280 Nos),
IDTS- 11 (D-BOX : 280 Nos), (M-BOX : 1 No),
IDTS- 12 (D-BOX : 294 Nos)
and 4 Nos of M-BOX in Boundary

Total I/O for PLC RTU/RIO Panel at IDTS-05 40 2 5 74 27235

VI PLC RTU/RIO Panel at IDTS-06

1 IDTS-06_36kV Breaker-1 10 2 -- -- --

2 IDTS-06_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-06_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-06_36kV EFI/FPI -- -- -- 4 --

5 IDTS-06_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-06_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-06_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-06_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-06_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-06_LT Panel-1 4 -- -- -- --

11 IDTS-06_LT Panel-2 4 -- -- -- --

12 IDTS-06_LT Panel-1_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 6 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
13 IDTS-06_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-06_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-06_UPS -- -- -- 15 --

16 IDTS-06_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-06_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-06_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-06 43 2 5 74 5258

VII PLC RTU/RIO Panel at IDTS-07

1 IDTS-07_36kV Breaker-1 10 2 -- -- --

2 IDTS-07_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-07_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-07_36kV EFI/FPI -- -- -- 4 --

5 IDTS-07_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-07_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-07_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-07_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-07_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-07_LT Panel-1 4 -- -- -- --

11 IDTS-07_LT Panel-2 4 -- -- -- --

12 IDTS-07_LT Panel-1_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 7 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
13 IDTS-07_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-07_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-07_UPS -- -- -- 15 --

16 IDTS-07_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-07_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-07_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-07 43 2 5 74 5258

VIII PLC RTU/RIO Panel at IDTS-08

1 IDTS-08_36kV Breaker-1 10 2 -- -- --

2 IDTS-08_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-08_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-08_36kV EFI/FPI -- -- -- 4 --

5 IDTS-08_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-08_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-08_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-08_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-08_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-08_LT Panel-1 4 -- -- -- --

11 IDTS-08_LT Panel-2 4 -- -- -- --

12 IDTS-08_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-08_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 8 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-08_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-08_UPS -- -- -- 15 --

16 IDTS-08_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-08_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-08_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-08 43 2 5 74 5518

IX PLC RTU/RIO Panel at IDTS-09

1 IDTS-09_36kV Breaker-1 10 2 -- -- --

2 IDTS-09_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-09_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-09_36kV EFI/FPI -- -- -- 4 --

5 IDTS-09_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-09_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-09_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-09_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-09_LT Panel-1 4 -- -- -- --

10 IDTS-09_LT Panel-2 4 -- -- -- --

11 IDTS-09_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-09_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 9 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
13 IDTS-09_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-09_UPS -- -- -- 15 --

15 IDTS-09_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-09_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-09_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-09 40 2 5 74 5258

X PLC RTU/RIO Panel at IDTS-10

1 IDTS-10_36kV Breaker-1 10 2 -- -- --

2 IDTS-10_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-10_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-10_36kV EFI/FPI -- -- -- 4 --

5 IDTS-10_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-10_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-10_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-10_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-10_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-10_LT Panel-1 4 -- -- -- --

11 IDTS-10_LT Panel-2 4 -- -- -- --

12 IDTS-10_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-10_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 10 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-10_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-10_UPS -- -- -- 15 --

16 IDTS-10_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-10_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-10_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-10 43 2 5 74 5258

XI PLC RTU/RIO Panel at IDTS-11

1 IDTS-11_36kV Breaker-1 10 2 -- -- --

2 IDTS-11_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-11_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-11_36kV EFI/FPI -- -- -- 4 --

5 IDTS-11_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-11_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-11_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-11_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-11_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-11_LT Panel-1 4 -- -- -- --

11 IDTS-11_LT Panel-2 4 -- -- -- --

12 IDTS-11_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-11_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 11 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-11_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-11_UPS -- -- -- 15 --

16 IDTS-11_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-11_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-11_String Inverter (Total 40 Number) -- -- -- -- 4880 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-11 43 2 5 74 5258

XII PLC RTU/RIO Panel at IDTS-12

1 IDTS-12_36kV Breaker-1 10 2 -- -- --

2 IDTS-12_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-12_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-12_36kV EFI/FPI -- -- -- 4 --

5 IDTS-12_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-12_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-12_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-12_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-12_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-12_LT Panel-1 4 -- -- -- --

11 IDTS-12_LT Panel-2 4 -- -- -- --

12 IDTS-12_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-12_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 12 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-12_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-12_UPS -- -- -- 15 --

16 IDTS-12_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-12_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-12_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-12 43 2 5 74 5518

XIII PLC RTU/RIO Panel at IDTS-13

1 IDTS-13_36kV Breaker-1 10 2 -- -- --

2 IDTS-13_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-13_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-13_36kV EFI/FPI -- -- -- 4 --

5 IDTS-13_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-13_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-13_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-13_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-13_LT Panel-1 4 -- -- -- --

10 IDTS-13_LT Panel-2 4 -- -- -- --

11 IDTS-13_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-13_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-13_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-13_UPS -- -- -- 15 --

# Sensitivity: Unclassified Page 13 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
15 IDTS-13_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-13_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-13_String Inverter (Total 15 Number) -- -- -- -- 1830 14 Nos. of String per String Inverter

18 IDTS-13_String Inverter (Total 25 Number) -- -- -- -- 3150 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-13 40 2 5 74 5358

XIV PLC RTU/RIO Panel at IDTS-14

1 IDTS-14_36kV Breaker-1 10 2 -- -- --

2 IDTS-14_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-14_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-14_36kV EFI/FPI -- -- -- 4 --

5 IDTS-14_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-14_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-14_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-14_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-14_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-14_LT Panel-1 4 -- -- -- --

11 IDTS-14_LT Panel-2 4 -- -- -- --

12 IDTS-14_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-14_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-14_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-14_UPS -- -- -- 15 --

# Sensitivity: Unclassified Page 14 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
16 IDTS-14_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-14_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-14_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-14 43 2 5 74 5418

XV PLC RTU/RIO Panel at IDTS-15

1 IDTS-15_36kV Breaker-1 10 2 -- -- --
2 IDTS-15_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-15_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-15_36kV EFI/FPI -- -- -- 4 --
5 IDTS-15_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-15_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-15_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-15_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-15_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
10 IDTS-15_LT Panel-1 4 -- -- -- --
11 IDTS-15_LT Panel-2 4 -- -- -- --
12 IDTS-15_LT Panel-1_MFM -- -- -- 18 --
13 IDTS-15_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-15_Auxiliary Transformer Panel 1 -- -- -- --
15 IDTS-15_UPS -- -- -- 15 --
16 IDTS-15_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-15_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
18 IDTS-15_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

# Sensitivity: Unclassified Page 15 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP

IDTS- 13 (D-BOX : 305 Nos),


IDTS- 14 (D-BOX : 320 Nos),
IDTS- 15 (D-BOX : 320 Nos),
19 IDTS-15_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 20178 IDTS- 16 (D-BOX : 294 Nos),
IDTS- 19 (D-BOX : 294 Nos), (M-BOX : 1 No),
IDTS- 20 (D-BOX : 294 Nos)
and 2 Nos of M-BOX in Boundary

Total I/O for PLC RTU/RIO Panel at IDTS-15 43 2 5 74 25596

XVI PLC RTU/RIO Panel at IDTS-16

1 IDTS-16_36kV Breaker-1 10 2 -- -- --

2 IDTS-16_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-16_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-16_36kV EFI/FPI -- -- -- 4 --

5 IDTS-16_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-16_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-16_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-16_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-16_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-16_LT Panel-1 4 -- -- -- --

11 IDTS-16_LT Panel-2 4 -- -- -- --

12 IDTS-16_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-16_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 16 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-16_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-16_UPS -- -- -- 15 --

16 IDTS-16_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-16_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-16_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

19 IDTS-16_Weather Monitoring Station_Type2 -- -- -- -- 29

Total I/O for PLC RTU/RIO Panel at IDTS-16 43 2 5 74 5547

XVII PLC RTU/RIO Panel at IDTS-17

1 IDTS-17_36kV Breaker-1 10 2 -- -- --

2 IDTS-17_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-17_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-17_36kV EFI/FPI -- -- -- 4 --

5 IDTS-17_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-17_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-17_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-17_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-17_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-17_LT Panel-1 4 -- -- -- --

11 IDTS-17_LT Panel-2 4 -- -- -- --

12 IDTS-17_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-17_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 17 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-17_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-17_UPS -- -- -- 15 --

16 IDTS-17_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-17_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-17_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-17 43 2 5 74 5418

XVIII PLC RTU/RIO Panel at IDTS-18

1 IDTS-18_36kV Breaker-1 10 2 -- -- --

2 IDTS-18_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-18_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-18_36kV EFI/FPI -- -- -- 4 --

5 IDTS-18_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-18_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-18_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-18_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-18_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-18_LT Panel-1 4 -- -- -- --

11 IDTS-18_LT Panel-2 4 -- -- -- --

12 IDTS-18_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-18_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 18 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-18_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-18_UPS -- -- -- 15 --

16 IDTS-18_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-18_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-18_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-18 43 2 5 74 5418

XIX PLC RTU/RIO Panel at IDTS-19

1 IDTS-19_36kV Breaker-1 10 2 -- -- --

2 IDTS-19_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-19_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-19_36kV EFI/FPI -- -- -- 4 --

5 IDTS-19_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-19_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-19_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-19_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-19_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-19_LT Panel-1 4 -- -- -- --

11 IDTS-19_LT Panel-2 4 -- -- -- --

12 IDTS-19_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-19_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 19 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-19_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-19_UPS -- -- -- 15 --

16 IDTS-19_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-19_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-19_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-19 43 2 5 74 5518

XX PLC RTU/RIO Panel at IDTS-20

1 IDTS-20_36kV Breaker-1 10 2 -- -- --

2 IDTS-20_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-20_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-20_36kV EFI/FPI -- -- -- 4 --

5 IDTS-20_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-20_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-20_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-20_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-20_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-20_LT Panel-1 4 -- -- -- --

11 IDTS-20_LT Panel-2 4 -- -- -- --

12 IDTS-20_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-20_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 20 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-20_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-20_UPS -- -- -- 15 --

16 IDTS-20_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-20_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-20_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-20 43 2 5 74 5518

XXI PLC RTU/RIO Panel at IDTS-21

1 IDTS-21_36kV Breaker-1 10 2 -- -- --

2 IDTS-21_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-21_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-21_36kV EFI/FPI -- -- -- 4 --

5 IDTS-21_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-21_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-21_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-21_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-21_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-21_LT Panel-1 4 -- -- -- --

11 IDTS-21_LT Panel-2 4 -- -- -- --

12 IDTS-21_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-21_LT Panel-2_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 21 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
14 IDTS-21_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-21_UPS -- -- -- 15 --

16 IDTS-21_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-21_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-21_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-21 43 2 5 74 5518

XXII PLC RTU/RIO Panel at IDTS-22


1 IDTS-22_36kV Breaker-1 10 2 -- -- --
2 IDTS-22_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-22_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-22_36kV EFI/FPI -- -- -- 4 --
5 IDTS-22_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-22_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-22_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
8 IDTS-22_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
9 IDTS-22_LT Panel-1 4 -- -- -- --
10 IDTS-22_LT Panel-2 4 -- -- -- --
11 IDTS-22_LT Panel-1_MFM -- -- -- 18 --
12 IDTS-22_LT Panel-2_MFM -- -- -- 18 --
13 IDTS-22_Auxiliary Transformer Panel 1 -- -- -- --
14 IDTS-22_UPS -- -- -- 15 --
15 IDTS-22_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
16 IDTS-22_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
17 IDTS-22_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

# Sensitivity: Unclassified Page 22 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP

IDTS- 17 (D-BOX : 320 Nos),


IDTS- 18 (D-BOX : 320 Nos), (M-BOX : 1 No),
IDTS- 21 (D-BOX : 294 Nos),
IDTS- 22 (D-BOX : 320 Nos),
18 IDTS-22_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 24454
IDTS- 23 (D-BOX : 320 Nos),
IDTS- 35 (D-BOX : 320 Nos),
IDTS- 26 (D-BOX : 320 Nos) (M-BOX : 1 No),
and 3 Nos of M-BOX in Boundary

19 IDTS-22_Weather Monitoring Station_Type2 -- -- -- -- 29

Total I/O for PLC RTU/RIO Panel at IDTS-22 40 2 5 74 29901

XXIII PLC RTU/RIO Panel at IDTS-23

1 IDTS-23_36kV Breaker-1 10 2 -- -- --

2 IDTS-23_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-23_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-23_36kV EFI/FPI -- -- -- 4 --

5 IDTS-23_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-23_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-23_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-23_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-23_LT Panel-1 4 -- -- -- --

10 IDTS-23_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 23 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
11 IDTS-23_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-23_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-23_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-23_UPS -- -- -- 15 --

15 IDTS-23_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-23_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-23_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-23 40 2 5 74 5418

XXIV PLC RTU/RIO Panel at IDTS-24

1 IDTS-24_36kV Breaker-1 10 2 -- -- --

2 IDTS-24_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-24_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-24_36kV EFI/FPI -- -- -- 4 --

5 IDTS-24_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-24_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-24_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-24_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-24_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-24_LT Panel-1 4 -- -- -- --

11 IDTS-24_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 24 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-24_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-24_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-24_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-24_UPS -- -- -- 15 --

16 IDTS-24_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-24_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-24_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-24 43 2 5 74 5418

XXV PLC RTU/RIO Panel at IDTS-25

1 IDTS-25_36kV Breaker-1 10 2 -- -- --

2 IDTS-25_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-25_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-25_36kV EFI/FPI -- -- -- 4 --

5 IDTS-25_36kV Load Break Switch-1 3 -- -- -- --


6 IDTS-25_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-25_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-25_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-25_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
10 IDTS-25_LT Panel-1 4 -- -- -- --
11 IDTS-25_LT Panel-2 4 -- -- -- --
12 IDTS-25_LT Panel-1_MFM -- -- -- 18 --

# Sensitivity: Unclassified Page 25 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
13 IDTS-25_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-25_Auxiliary Transformer Panel 1 -- -- -- --
15 IDTS-25_UPS -- -- -- 15 --
16 IDTS-25_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-25_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-25_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

19 IDTS-25_Weather Monitoring Station_Type1 -- -- -- -- 28

Total I/O for PLC RTU/RIO Panel at IDTS-25 43 2 5 74 5446

XXVI PLC RTU/RIO Panel at IDTS-26

1 IDTS-26_36kV Breaker-1 10 2 -- -- --

2 IDTS-26_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-26_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-26_36kV EFI/FPI -- -- -- 4 --

5 IDTS-26_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-26_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-26_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-26_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-26_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-26_LT Panel-1 4 -- -- -- --

11 IDTS-26_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 26 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-26_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-26_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-26_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-26_UPS -- -- -- 15 --

16 IDTS-26_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-26_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-26_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-26 43 2 5 74 5418

XXVII PLC RTU/RIO Panel at IDTS-27

1 IDTS-27_36kV Breaker-1 10 2 -- -- --

2 IDTS-27_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-27_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-27_36kV EFI/FPI -- -- -- 4 --

5 IDTS-27_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-27_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-27_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-27_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-27_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-27_LT Panel-1 4 -- -- -- --

11 IDTS-27_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 27 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-27_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-27_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-27_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-27_UPS -- -- -- 15 --

16 IDTS-27_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-27_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-27_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-27 43 2 5 74 5418

XXVIII PLC RTU/RIO Panel at IDTS-28

1 IDTS-28_36kV Breaker-1 10 2 -- -- --

2 IDTS-28_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-28_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-28_36kV EFI/FPI -- -- -- 4 --

5 IDTS-28_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-28_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-28_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-28_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-28_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-28_LT Panel-1 4 -- -- -- --

11 IDTS-28_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 28 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-28_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-28_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-28_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-28_UPS -- -- -- 15 --

16 IDTS-28_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-28_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-28_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-28 43 2 5 74 5418

XXIX PLC RTU/RIO Panel at IDTS-29

1 IDTS-29_36kV Breaker-1 10 2 -- -- --

2 IDTS-29_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-29_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-29_36kV EFI/FPI -- -- -- 4 --

5 IDTS-29_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-29_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-29_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-29_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-29_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-29_LT Panel-1 4 -- -- -- --

11 IDTS-29_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 29 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-29_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-29_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-29_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-29_UPS -- -- -- 15 --

16 IDTS-29_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-29_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-29_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-29 43 2 5 74 5518

XXX PLC RTU/RIO Panel at IDTS-30

1 IDTS-30_36kV Breaker-1 10 2 -- -- --

2 IDTS-30_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-30_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-30_36kV EFI/FPI -- -- -- 4 --

5 IDTS-30_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-30_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-30_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-30_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-30_LT Panel-1 4 -- -- -- --

10 IDTS-30_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 30 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
11 IDTS-30_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-30_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-30_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-30_UPS -- -- -- 15 --

15 IDTS-30_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-30_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-30_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-30 40 2 5 74 5418

XXXI PLC RTU/RIO Panel at IDTS-31

1 IDTS-31_36kV Breaker-1 10 2 -- -- --
2 IDTS-31_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-31_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-31_36kV EFI/FPI -- -- -- 4 --
5 IDTS-31_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-31_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-31_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-31_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-31_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
10 IDTS-31_LT Panel-1 4 -- -- -- --
11 IDTS-31_LT Panel-2 4 -- -- -- --
12 IDTS-31_LT Panel-1_MFM -- -- -- 18 --
13 IDTS-31_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-31_Auxiliary Transformer Panel 1 -- -- -- --

# Sensitivity: Unclassified Page 31 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
15 IDTS-31_UPS -- -- -- 15 --
16 IDTS-31_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-31_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
18 IDTS-31_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

IDTS- 24 (D-BOX : 320 Nos),


IDTS- 27 (D-BOX : 320 Nos),
IDTS- 28 (D-BOX : 320 Nos), (M-BOX : 1 No),
19 IDTS-31_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 20924 IDTS- 29 (D-BOX : 294 Nos),
IDTS- 30 (D-BOX : 320 Nos),
IDTS- 31 (D-BOX : 320 Nos)
and 3 Nos of M-BOX in Boundary

Total I/O for PLC RTU/RIO Panel at IDTS-31 43 2 5 74 26342

XXXII PLC RTU/RIO Panel at IDTS-32

1 IDTS-32_36kV Breaker-1 10 2 -- -- --

2 IDTS-32_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-32_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-32_36kV EFI/FPI -- -- -- 4 --

5 IDTS-32_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-32_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-32_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

8 IDTS-32_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-32_LT Panel-1 4 -- -- -- --

# Sensitivity: Unclassified Page 32 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
10 IDTS-32_LT Panel-2 4 -- -- -- --

11 IDTS-32_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-32_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-32_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-32_UPS -- -- -- 15 --

15 IDTS-32_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-32_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-32_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-32 40 2 5 74 5418

XXXIII PLC RTU/RIO Panel at IDTS-33

1 IDTS-33_36kV Breaker-1 10 2 -- -- --

2 IDTS-33_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-33_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-33_36kV EFI/FPI -- -- -- 4 --

5 IDTS-33_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-33_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-33_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-33_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-33_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

# Sensitivity: Unclassified Page 33 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
10 IDTS-33_LT Panel-1 4 -- -- -- --

11 IDTS-33_LT Panel-2 4 -- -- -- --

12 IDTS-33_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-33_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-33_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-33_UPS -- -- -- 15 --

16 IDTS-33_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-33_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-33_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-33 43 2 5 74 5418

XXXIV PLC RTU/RIO Panel at IDTS-34


1 IDTS-34_36kV Breaker-1 10 2 -- -- --
2 IDTS-34_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-34_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-34_36kV EFI/FPI -- -- -- 4 --
5 IDTS-34_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-34_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-34_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-34_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-34_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --
10 IDTS-34_LT Panel-1 4 -- -- -- --
11 IDTS-34_LT Panel-2 4 -- -- -- --

# Sensitivity: Unclassified Page 34 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
12 IDTS-34_LT Panel-1_MFM -- -- -- 18 --
13 IDTS-34_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-34_Auxiliary Transformer Panel 1 -- -- -- --
15 IDTS-34_UPS -- -- -- 15 --
16 IDTS-34_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-34_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
18 IDTS-34_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

IDTS- 32 (D-BOX : 320 Nos),


IDTS- 33 (D-BOX : 320 Nos), (M-BOX : 1 No),
IDTS- 34 (D-BOX : 320 Nos),
19 IDTS-34_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 16193
IDTS- 35 (D-BOX : 294 Nos),
IDTS- 38 (D-BOX : 294 Nos), (M-BOX : 1 No),
and 2 Nos of M-BOX in Boundary

Total I/O for PLC RTU/RIO Panel at IDTS-34 43 2 5 74 21611

XXXV PLC RTU/RIO Panel at IDTS-35

1 IDTS-35_36kV Breaker-1 10 2 -- -- --

2 IDTS-35_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-35_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-35_36kV EFI/FPI -- -- -- 4 --

5 IDTS-35_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-35_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-35_36kV Load Break Switch-3 3 -- -- -- --

8 IDTS-35_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

# Sensitivity: Unclassified Page 35 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
9 IDTS-35_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-35_LT Panel-1 4 -- -- -- --

11 IDTS-35_LT Panel-2 4 -- -- -- --

12 IDTS-35_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-35_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-35_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-35_UPS -- -- -- 15 --

16 IDTS-35_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-35_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-35_String Inverter (Total 42 Number) -- -- -- -- 5208 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-35 43 2 5 74 5602

XXXVI PLC RTU/RIO Panel at IDTS-36

1 IDTS-36_36kV Breaker-1 10 2 -- -- --

2 IDTS-36_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-36_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-36_36kV EFI/FPI -- -- -- 4 --

5 IDTS-36_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-36_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-36_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

# Sensitivity: Unclassified Page 36 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
8 IDTS-36_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-36_LT Panel-1 4 -- -- -- --

10 IDTS-36_LT Panel-2 4 -- -- -- --

11 IDTS-36_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-36_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-36_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-36_UPS -- -- -- 15 --

15 IDTS-36_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-36_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-36_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-36 40 2 5 74 5418

XXXVII PLC RTU/RIO Panel at IDTS-37

1 IDTS-37_36kV Breaker-1 10 2 -- -- --

2 IDTS-37_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-37_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-37_36kV EFI/FPI -- -- -- 4 --

5 IDTS-37_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-37_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-37_36kV Load Break Switch-3 3 -- -- -- --

# Sensitivity: Unclassified Page 37 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
8 IDTS-37_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-37_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-37_LT Panel-1 4 -- -- -- --

11 IDTS-37_LT Panel-2 4 -- -- -- --

12 IDTS-37_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-37_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-37_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-37_UPS -- -- -- 15 --

16 IDTS-37_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-37_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

18 IDTS-37_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-37 43 2 5 74 5418

XXXVIII PLC RTU/RIO Panel at IDTS-38

1 IDTS-38_36kV Breaker-1 10 2 -- -- --

2 IDTS-38_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-38_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-38_36kV EFI/FPI -- -- -- 4 --

5 IDTS-38_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-38_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-38_36kV Load Break Switch-3 3 -- -- -- --

# Sensitivity: Unclassified Page 38 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
8 IDTS-38_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

9 IDTS-38_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

10 IDTS-38_LT Panel-1 4 -- -- -- --

11 IDTS-38_LT Panel-2 4 -- -- -- --

12 IDTS-38_LT Panel-1_MFM -- -- -- 18 --

13 IDTS-38_LT Panel-2_MFM -- -- -- 18 --

14 IDTS-38_Auxiliary Transformer Panel 1 -- -- -- --

15 IDTS-38_UPS -- -- -- 15 --

16 IDTS-38_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

17 IDTS-38_SACU -- -- -- -- 394 42 Nos. of String Inverter connected.

18 IDTS-38_String Inverter (Total 42 Number) -- -- -- -- 5124 14 Nos. of String per String Inverter

Total I/O for PLC RTU/RIO Panel at IDTS-38 43 2 5 74 5518

XXXIX PLC RTU/RIO Panel at IDTS-39

1 IDTS-39_36kV Breaker-1 10 2 -- -- --
2 IDTS-39_36kV Disconnector Break Switch-1 3 -- -- -- --
3 IDTS-39_36kV Numerical Relay-1 -- -- -- 6 --
4 IDTS-39_36kV EFI/FPI -- -- -- 4 --
5 IDTS-39_36kV Load Break Switch-1 3 -- -- -- --
6 IDTS-39_36kV Load Break Switch-2 3 -- -- -- --
7 IDTS-39_36kV Load Break Switch-3 3 -- -- -- --
8 IDTS-39_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --
9 IDTS-39_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

# Sensitivity: Unclassified Page 39 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
10 IDTS-39_LT Panel-1 4 -- -- -- --
11 IDTS-39_LT Panel-2 4 -- -- -- --
12 IDTS-39_LT Panel-1_MFM -- -- -- 18 --
13 IDTS-39_LT Panel-2_MFM -- -- -- 18 --
14 IDTS-39_Auxiliary Transformer Panel 1 -- -- -- --
15 IDTS-39_UPS -- -- -- 15 --
16 IDTS-39_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --
17 IDTS-39_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.
18 IDTS-39_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

IDTS- 36 (D-BOX : 320 Nos), (M-BOX : 1 No),


IDTS- 37 (D-BOX : 320 Nos),
19 IDTS-39_Tracker system signals (D-BOX,M-BOX, T-BOX & Gateway) -- -- -- -- 10857 IDTS- 39 (D-BOX : 320 Nos),
IDTS- 40 (D-BOX : 320 Nos)
and 3 Nos of M-BOX in Boundary

20 IDTS-39_Weather Monitoring Station_Type1 -- -- -- -- 28

Total I/O for PLC RTU/RIO Panel at IDTS-39 43 2 5 74 16303

XXXX PLC RTU/RIO Panel at IDTS-40

1 IDTS-40_36kV Breaker-1 10 2 -- -- --

2 IDTS-40_36kV Disconnector Break Switch-1 3 -- -- -- --

3 IDTS-40_36kV Numerical Relay-1 -- -- -- 6 --

4 IDTS-40_36kV EFI/FPI -- -- -- 4 --

5 IDTS-40_36kV Load Break Switch-1 3 -- -- -- --

6 IDTS-40_36kV Load Break Switch-2 3 -- -- -- --

7 IDTS-40_Inverter Duty Transformer-1 (From RMU) 12 -- -- -- --

# Sensitivity: Unclassified Page 40 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.


20PKSA001-LNT-SPV-I-LST-1301 4
SCADA I/O SIGNAL LIST FOR INVERTER DUTY TRANSFORMER STATION (IDTS) Prepared Checked Approved Date
AP SB KCM 06-Oct-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI
RS485 TCP/IP
8 IDTS-40_Inverter Duty Transformer-1 (Marshalling box) -- -- 5 -- --

9 IDTS-40_LT Panel-1 4 -- -- -- --

10 IDTS-40_LT Panel-2 4 -- -- -- --

11 IDTS-40_LT Panel-1_MFM -- -- -- 18 --

12 IDTS-40_LT Panel-2_MFM -- -- -- 18 --

13 IDTS-40_Auxiliary Transformer Panel 1 -- -- -- --

14 IDTS-40_UPS -- -- -- 15 --

15 IDTS-40_Auxiliary Panel (400V ACDB)_MFM -- -- -- 13 --

16 IDTS-40_SACU -- -- -- -- 378 40 Nos. of String Inverter connected.

17 IDTS-40_String Inverter (Total 40 Number) -- -- -- -- 5040 16 Nos. of String per String Inverter

18 IDTS-40_Weather Monitoring Station_Type1 -- -- -- -- 28

Total I/O for PLC RTU/RIO Panel at IDTS-40 40 2 5 74 5446

# Sensitivity: Unclassified Page 41 of 41


Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC
1.O&M building – Technical Details
Mains failure alarm status to SCADA Alarm - - - 1 - -
for UPS (20PKSA001-LNT-SPV-V-DSH-1267)
Rectifier. fuse failure alarm status to SCADA Alarm - - - 1 - -
2. Annexure-9 – UPS at O&M Building Mapping
Max. rectifier voltage alarm status to SCADA Alarm - - - 1 - - List

Min. rectifier voltage alarm status to SCADA Alarm - - - 1 - -

Battery Circuit Breaker open alarm status to SCADA Alarm - - - 1 - -

Battery discharging alarm status to SCADA Alarm - - - 1 - -

3rd battery discharge level alarm status to SCADA Alarm - - - 1 - -

Inverter overload alarm status to SCADA Alarm - - - 1 - -

Inverter out of tolerance alarm status to SCADA Alarm - - - 1 - -

Bypass not OK alarm status to SCADA Alarm - - - 1 - -

Common alarm status to SCADA Alarm - - - 1 - -

Inverter feeds load status to SCADA Status - - - 1 - -

Bypass feeds load status to SCADA Status - - - 1 - -

Mains voltage phase L1 value to SCADA Measurement - - - 1 - -

Mains voltage phase L2 value to SCADA Measurement - - - 1 - -

Mains voltage phase L3 value to SCADA Measurement - - - 1 - -

Mains current phase L1 value to SCADA Measurement - - - 1 - -


UPS
1 Mains current phase L2 value to SCADA Measurement - - - 1 - -
(At O&M Building)
Mains current phase L3 value to SCADA Measurement - - - 1 - -

Mains frequency value to SCADA Measurement - - - 1 - -

Bypass voltage phase L1 value to SCADA Measurement - - - 1 - -

Bypass voltage phase L2 value to SCADA Measurement - - - 1 - -

Bypass voltage phase L3 value to SCADA Measurement - - - 1 - -

Bypass frequency value to SCADA Measurement - - - 1 - -

Rectifier output voltage Measurement - - - 1 - -

Battery voltage Measurement - - - 1 - -

Rectifier output current Measurement - - - 1 - -

Battery current Measurement - - - 1 - -

Inverter voltage phase L1 value to SCADA Measurement - - - 1 - -

Inverter voltage phase L2 value to SCADA Measurement - - - 1 - -

Inverter voltage phase L3 value to SCADA Measurement - - - 1 - -

Inverter current phase L1 value to SCADA Measurement - - - 1 - -

Inverter current phase L2 value to SCADA Measurement - - - 1 - -

Inverter current phase L3 value to SCADA Measurement - - - 1 - -

Inverter frequency value to SCADA Measurement - - - 1 - -


20PKSA001-LNT-SPV-V-DSH-1903-R3-SCADA
GPS-1 Fault status to SCADA Indication 1 - - - - -
2 SCADA Contol Panel (At O&M Building) System - DS & draw., BOM
GPS-2 Fault status to SCADA Indication 1 - - - - -

Sensitivity: Unclassified
#
Page 1 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

L1 Phase Voltage Value to SCADA Measurement - - - 1 - - Annexure-10 – O&M Auxiliary Panel MFM Data
sheet
L2 Phase Voltage Value to SCADA Measurement - - - 1 - -

L3 Phase Voltage Value to SCADA Measurement - - - 1 - -

Average Voltage Value to SCADA Measurement - - - 1 - -

L1 Phase Current Value to SCADA Measurement - - - 1 - -

L2 Phase Current Value to SCADA Measurement - - - 1 - -


Multi Function Meter (MFM) L3 Phase Current Value to SCADA Measurement - - - 1 - -
3 (Associated with ACDB at O&M
Building) Average Current Value to SCADA Measurement - - - 1 - -

Frequency Value to SCADA Measurement - - - 1 - -

Avg power factor Value to SCADA Measurement - - - 1 - -

Active Power Value to SCADA Measurement - - - 1 - -

Apparent Power Value to SCADA Measurement - - - 1 - -

Reactive power Value to SCADA Measurement - - - 1 - -

Active import/ export energy Value to SCADA Measurement - - - 1 - -


This vendor document is awaited from vendor
Smoke detector activates trouble signal to SCADA Alarm 1 - - - - -
same will be submitted.

Fire Alarm Panel Manual fire alarm box activates trouble signal to SCADA Alarm 1 - - - - -
4
(O&M Building)
General Alarm Signal to SCADA Alarm 1 - - - - -

General Trouble Signal to SCADA Alarm 1 - - - - -

PPC Local/Remote Mode status to SCADA Indication - - - - 1 -

Active Power Mode status to SCADA Indication - - - - 1 -

Automatic Voltage Regulation Mode status to SCADA Indication - - - - 1 -

Reactive Mode status to SCADA Indication - - - - 1 -

Power Factor Mode status to SCADA Indication - - - - 1 -

PV Plant Active Power Set Point Feedback Value to SCADA Measurement - - - - 1 -

Ramp Up Rate Set Point Feedback Value to SCADA Measurement - - - - 1 -

Ramp Down Rate Set Point Feedback Value to SCADA Measurement - - - - 1 -

Over frequency Droop Set Point Feedback Value to SCADA Measurement - - - - 1 -

Under frequency Droop Set Point Feedback Value to SCADA Measurement - - - - 1 -

Automatic Voltage regulation Set Point Feedback Value to SCADA Measurement - - - - 1 -

PV Plant Reactive Set Point Feedback Value to SCADA Measurement - - - - 1 -

Power Factor Set Point Feedback Value to SCADA Measurement - - - - 1 -

PV plant Active power set point command feedback value to SCADA Measurement - - - - 1 -

Ramp up rate set point command feedback value to SCADA Measurement - - - - 1 -

Ramp down rate set point command feedback value to SCADA Measurement - - - - 1 -

PV plant Reactive power set point command feedback value to SCADA Measurement - - - - 1 -

Generation Stop/Start Command to PPC Command

Set Active Power Mode to PPC Command - - - - 1 -

PV Plant Active Power Set Point to PPC Command - - - - 1 -

Ramp Up Rate Set Point to PPC Command - - - - 1 -

Sensitivity: Unclassified
#
Page 2 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Ramp Down Rate Set Point to PPC Command - - - - 1 -

Over frequency Droop Set Point to PPC Command - - - - 1 -

Under frequency Droop Set Point to PPC Command - - - - 1 -

Set Automatic Voltage Regulation Mode to PPC Command - - - - 1 -

Avr Set Point to PPC Command - - - - 1 -

Set Reactive mode to PPC Command - - - - 1 -

PV plant Reactive power set point to PPC Command - - - - 1 -

Set Power factor mode to PPC Command - - - - 1 -

Power factor set point to PPC Command - - - - 1 -

PQ Meter -1 Voltage phase L1 Measurement - - - - 1 -

PPC System signals PQ Meter -1 Voltage phase L2 Measurement - - - - 1 -


(PPC to PV SCADA)
PQ Meter -1 Voltage phase L3 Measurement - - - - 1 -

PQ Meter -1 Line current I1 Measurement - - - - 1 -

PQ Meter -1 Line current I2 Measurement - - - - 1 -

PQ Meter -1 Line current I3 Measurement - - - - 1 -

PQ Meter -1 Line current I4 Measurement - - - - 1 -

PQ Meter -1 Active power Measurement - - - - 1 -

PQ Meter -1 Reactive power Measurement - - - - 1 -

PQ Meter -1 Apparent power Measurement - - - - 1 -

PQ Meter -1 Power factor Measurement - - - - 1 -

PQ Meter -1 Frequency Measurement - - - - 1 -

PQ Meter -1 Active Energy Import Measurement - - - - 1 -

PQ Meter -1 Active Energy Export Measurement - - - - 1 -

PQ Meter -1 Reactive Energy Import Measurement - - - - 1 -

PQ Meter -1 Reactive Energy Export Measurement - - - - 1 -

PQ Meter -1 Apparent Energy Measurement - - - - 1 -

PQ Meter -2 Voltage phase L1 Measurement - - - - 1 -

PQ Meter -2 Voltage phase L2 Measurement - - - - 1 -

PQ Meter -2 Voltage phase L3 Measurement - - - - 1 -

PQ Meter -2 Line current I1 Measurement - - - - 1 -

PQ Meter -2 Line current I2 Measurement - - - - 1 -

PQ Meter -2 Line current I3 Measurement - - - - 1 -

PQ Meter -2 Line current I4 Measurement - - - - 1 -

PQ Meter -2 Active power Measurement - - - - 1 -

PQ Meter -2 Reactive power Measurement - - - - 1 -

PQ Meter -2 Apparent power Measurement - - - - 1 -

PQ Meter -2 Power factor Measurement - - - - 1 -

PQ Meter -2 Frequency Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 3 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

PQ Meter -2 Active Energy Import Measurement - - - - 1 -

PQ Meter -2 Active Energy Export Measurement - - - - 1 -

PQ Meter -2 Reactive Energy Import Measurement - - - - 1 -

PQ Meter -2 Reactive Energy Export Measurement - - - - 1 -

PQ Meter -2 Apparent Energy Measurement - - - - 1 -

PCC voltage Uab Measurement - - - - 1 -

PCC voltage Ubc Measurement - - - - 1 -

PCC voltage Uca Measurement - - - - 1 -

PCC current Ia Measurement - - - - 1 -

PCC current Ib Measurement - - - - 1 -

PCC current Ic Measurement - - - - 1 -

Bus bar voltage Uab Measurement - - - - 1 -

Bus bar voltage Ubc Measurement - - - - 1 -

Bus bar voltage Uca Measurement - - - - 1 -

Bus bar current Ia Measurement - - - - 1 -

Bus bar current Ib Measurement - - - - 1 -

Bus bar current Ic Measurement - - - - 1 -

SVG current Ia Measurement - - - - 1 -

5 SVG current Ib Measurement - - - - 1 -

SVG current Ic Measurement - - - - 1 -

System frequency Measurement - - - - 1 -

System power factor Measurement - - - - 1 -

System active power Measurement - - - - 1 -

System reactive power Measurement - - - - 1 -

SVG reactive power Measurement - - - - 1 -

Locking status word - grid over voltage locking Status - - - - 1 -

Locking status word - grid under voltage locking Status - - - - 1 -

Locking status word - grid over frequency locking Status - - - - 1 -

Locking status word - grid under frequency locking Status - - - - 1 -

Locking status word - output over current locking Status - - - - 1 -

Locking status word - output over load locking Status - - - - 1 -

Locking status word - module fault locking Status - - - - 1 -

Locking status word - hardware over currrent locking Status - - - - 1 -

Locking status word - water-cooling system fault locking Status - - - - 1 -

Warning status word - grid over voltage alarm Alarm - - - - 1 -

Warning status word - grid under voltage alarm Alarm - - - - 1 -

Warning status word - output over load alarm Alarm - - - - 1 -

Warning status word - control cabinet AC alarm Alarm - - - - 1 -

Sensitivity: Unclassified
#
Page 4 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Warning status word - control cabinet DC alarm Alarm - - - - 1 -

Warning status word - extend box AC alarm Alarm - - - - 1 -

Warning status word - extend box DC alarm Alarm - - - - 1 -

Fault status word 1 - grid over voltage fault Fault - - - - 1 -

Fault status word 1 - grid under voltage fault Fault - - - - 1 -

Fault status word 1 - grid over frequency fault Fault - - - - 1 -

Fault status word 1 - grid under frequency fault Fault - - - - 1 -

Fault status word 1 - output over current fault Fault - - - - 1 -

Fault status word 1 - output over load fault Fault - - - - 1 -

Fault status word 2 - soft-start charging timeout trip Fault - - - - 1 -

Fault status word 2 - locking number exceed limit trip Fault - - - - 1 -

Fault status word 2 - hardware detecting over current Fault - - - - 1 -


Statcom-1 signals from PPC to PV
Fault status word 2 - module bypass failure fault Fault - - - - 1 - Annexure-12 – Statcom Modbus Interface list
SCADA
Fault status word 2 - bypass module over limit Fault - - - - 1 -

Fault status word 5 - breaker opening failure trip Fault - - - - 1 -

Fault status word 5 - soft-start closing failure trip Fault - - - - 1 -

Fault status word 5 - soft-start opening failure trip Fault - - - - 1 -

Fault status word 5 - control power supply fault Fault - - - - 1 -

Fault status word 5 - extend box power supply fault Fault - - - - 1 -

Fault status word 5 - disconnector opening fault Fault - - - - 1 -

Fault status word 5 - ground switch closing fault Fault - - - - 1 -

Warning status word 1 - module over TEMP alarm Status - - - - 1 -

A phase1#~14# module status - Normal or Failure Status - - - - 14 -

A phase15#~28# module status - Normal or Failure Status - - - - 14 -

A phase29#~42# module status - Normal or Failure Status - - - - 14 -

B phase1#~14# module status - Normal or Failure Status - - - - 14 -

B phase15#~28# module status - Normal or Failure Status - - - - 14 -

B phase29#~42# module status - Normal or Failure Status - - - - 14 -

C phase1#~14# module status - Normal or Failure Status - - - - 14 -

C phase15#~28# module status - Normal or Failure Status - - - - 14 -

C phase29#~42# module status - Normal or Failure Status - - - - 14 -

Control mode Command - - - - 1 -

Reactive power setting value Command - - - - 1 -

Power factor setting value Command - - - - 1 -

Constant voltage setting value Command - - - - 1 -

Sensitivity: Unclassified
#
Page 5 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Load compensation reactive power setting Command - - - - 1 -

phase A 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

Redundancy margin for each phase Measurement - - - - 1 -

Redundancy loss of phase A Measurement - - - - 1 -

Redundancy loss of phase B Measurement - - - - 1 -

Redundancy loss of phase C Measurement - - - - 1 -

PCC voltage Uab Measurement - - - - 1 -

PCC voltage Ubc Measurement - - - - 1 -

PCC voltage Uca Measurement - - - - 1 -

PCC current Ia Measurement - - - - 1 -

PCC current Ib Measurement - - - - 1 -

PCC current Ic Measurement - - - - 1 -

Bus bar voltage Uab Measurement - - - - 1 -

Bus bar voltage Ubc Measurement - - - - 1 -

Bus bar voltage Uca Measurement - - - - 1 -

Bus bar current Ia Measurement - - - - 1 -

Bus bar current Ib Measurement - - - - 1 -

Bus bar current Ic Measurement - - - - 1 -

SVG current Ia Measurement - - - - 1 -

SVG current Ib Measurement - - - - 1 -

SVG current Ic Measurement - - - - 1 -

System frequency Measurement - - - - 1 -

System power factor Measurement - - - - 1 -

System active power Measurement - - - - 1 -

System reactive power Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 6 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

SVG reactive power Measurement - - - - 1 -

Locking status word - grid over voltage locking Status - - - - 1 -

Locking status word - grid under voltage locking Status - - - - 1 -

Locking status word - grid over frequency locking Status - - - - 1 -

Locking status word - grid under frequency locking Status - - - - 1 -

Locking status word - output over current locking Status - - - - 1 -

Locking status word - output over load locking Status - - - - 1 -

Locking status word - module fault locking Status - - - - 1 -

Locking status word - hardware over currrent locking Status - - - - 1 -

Locking status word - water-cooling system fault locking Status - - - - 1 -

Warning status word - grid over voltage alarm Alarm - - - - 1 -

Warning status word - grid under voltage alarm Alarm - - - - 1 -

Warning status word - output over load alarm Alarm - - - - 1 -

Warning status word - control cabinet AC alarm Alarm - - - - 1 -

Warning status word - control cabinet DC alarm Alarm - - - - 1 -

Warning status word - extend box AC alarm Alarm - - - - 1 -

Warning status word - extend box DC alarm Alarm - - - - 1 -

Fault status word 1 - grid over voltage fault Fault - - - - 1 -

Fault status word 1 - grid under voltage fault Fault - - - - 1 -

Fault status word 1 - grid over frequency fault Fault - - - - 1 -

Fault status word 1 - grid under frequency fault Fault - - - - 1 -

Fault status word 1 - output over current fault Fault - - - - 1 -

Fault status word 1 - output over load fault Fault - - - - 1 -


Statcom-2 signals from PPC to PV
6 Fault status word 2 - soft-start charging timeout trip Fault - - - - 1 - Annexure-12 – Statcom Modbus Interface list
SCADA
Fault status word 2 - locking number exceed limit trip Fault - - - - 1 -

Fault status word 2 - hardware detecting over current Fault - - - - 1 -

Fault status word 2 - module bypass failure fault Fault - - - - 1 -

Fault status word 2 - bypass module over limit Fault - - - - 1 -

Fault status word 5 - breaker opening failure trip Fault - - - - 1 -

Fault status word 5 - soft-start closing failure trip Fault - - - - 1 -

Fault status word 5 - soft-start opening failure trip Fault - - - - 1 -

Fault status word 5 - control power supply fault Fault - - - - 1 -

Fault status word 5 - extend box power supply fault Fault - - - - 1 -

Fault status word 5 - disconnector opening fault Fault - - - - 1 -

Fault status word 5 - ground switch closing fault Fault - - - - 1 -

Warning status word 1 - module over TEMP alarm Status - - - - 1 -

A phase1#~14# module status - Normal or Failure Status - - - - 14 -

A phase15#~28# module status - Normal or Failure Status - - - - 14 -

Sensitivity: Unclassified
#
Page 7 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

A phase29#~42# module status - Normal or Failure Status - - - - 14 -

B phase1#~14# module status - Normal or Failure Status - - - - 14 -

B phase15#~28# module status - Normal or Failure Status - - - - 14 -

B phase29#~42# module status - Normal or Failure Status - - - - 14 -

C phase1#~14# module status - Normal or Failure Status - - - - 14 -

C phase15#~28# module status - Normal or Failure Status - - - - 14 -

C phase29#~42# module status - Normal or Failure Status - - - - 14 -

Control mode Command - - - - 1 -

Reactive power setting value Command - - - - 1 -

Power factor setting value Command - - - - 1 -

Constant voltage setting value Command - - - - 1 -

Load compensation reactive power setting Command - - - - 1 -

phase A 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase A 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase B 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT1 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT2 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT3 junction temperature Measurement - - - - 42 -

phase C 1# ~ 42# module IGBT4 junction temperature Measurement - - - - 42 -

Redundancy margin for each phase Measurement - - - - 1 -

Redundancy loss of phase A Measurement - - - - 1 -

Redundancy loss of phase B Measurement - - - - 1 -

Redundancy loss of phase C Measurement - - - - 1 -

STATCOM-1 FEEDER H01 REACTIVE POWER Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT Measurement - - - - 1 -

STATCOM-1 FEEDER H01 POWER FACTOR Measurement - - - - 1 -

STATCOM-1 FEEDER H01 FREQUENCY Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT R-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT Y-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT B-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE R-PH Measurement - - - - 1 -

Sensitivity: Unclassified
#
PSS SAS system signals from PV Page 8 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

STATCOM-1 FEEDER H01 VOLTAGE Y-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE B-PH Measurement - - - - 1 -


PSS SAS system signals from PV
7
SCADA to PPC
STATCOM-2 FEEDER H11 REACTIVE POWER Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT Measurement - - - - 1 -

STATCOM-2 FEEDER H11 POWER FACTOR Measurement - - - - 1 -

STATCOM-2 FEEDER H11 FREQUENCY Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT R-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT Y-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT B-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE R-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE Y-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE B-PH Measurement - - - - 1 -

UPS AC Supply Fail Fault 1 - - - - -


Non-UPS AC Supply Fail Fault 1 - - - - -
Monitor AC Supply Fail Fault 1 - - - - - 20PKSA001-LNT-SPV-I-SPC-1312 (BASIC
MDA A Server Supply Fail Fault 1 - - - - - DESIGN, GA & SCHEMATIC FOR MDA & PASS
MDA B Server Supply Fail Fault 1 - - - - - SYSTEM)
8 Meter Data Acquisition System (MDA) Firewall A Supply Fail Fault 1 - - - - -
Firewall B Supply Fail Fault 1 - - - - -
20PKSA001-LNT-SPV-I-SPC-1313 (OFFINE
SERVER SYSTEM AND FUNCTIONAL DESIGN
Net Energy Exported Measurement - - - - - 1
SPECIFICATION (FDS) OF MDA & PASS
SYSTEM)
UPS AC Supply Fail Fault 1 - - - - -
Non-UPS AC Supply Fail Fault 1 - - - - - 20PKSA001-LNT-SPV-I-SPC-1312 (BASIC
Monitor AC Supply Fail Fault 1 - - - - - DESIGN, GA & SCHEMATIC FOR MDA & PASS
PASS Server AC Supply Fail Fault 1 - - - - - SYSTEM)

MY Cloud server Supply Fail Fault 1 - - - - -


Plant Accounting & Settlement system Irradiance to PASS Measurement - - - - - 1
9
(PASS)
Wind Speed to PASS Measurement - - - - - 1
20PKSA001-LNT-SPV-I-SPC-1313 (OFFINE
Temperature to PASS Measurement - - - - - 1 SERVER SYSTEM AND FUNCTIONAL DESIGN
Generated Power to PASS Measurement - - - - - 1 SPECIFICATION (FDS) OF MDA & PASS
Atmospheric Pressure to PASS Measurement - - - - - 1 SYSTEM)

Solar Tracking to PASS Measurement - - - - - 1


Enable/Disable Robot SCADA end Clean Cmd Command - - - - 1 -
Robot SCADA end Start Cmd to One Area's Robots Command - - - - 6 -
Robot SCADA end Stop Cmd to One Area's Robots Command - - - - 6 -
Robot SCADA end Return Cmd to One Area's Robots Command - - - - 6 -
Robot SCADA end Start Cmd to One Robot Command - - - - 308 -
Robot SCADA end Stop Cmd to One Robot Command - - - - 308 -
Robot SCADA end Return Cmd to One Robot Command - - - - 308 -
Read Daily availability of All Robots Measurement - - - - 1 -
Read Monthly availability of All Robots Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 9 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Read Annual availability of All Robots Measurement - - - - 1 -


Read Online status of Robot 1·16 in AA 1 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 1 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 1 Status - - - - 16 -
Read Online status of Robot 49·50 in AA 1 Status - - - - 2 -
Read Online status of Robot 1·16 in AA 2 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 2 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 2 Status - - - - 16 -
Read Online status of Robot 49·50 in AA 2 Status - - - - 2 -
Read Online status of Robot 1·16 in AA 3 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 3 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 3 Status - - - - 16 -
Read Online status of Robot 49·50 in AA 3 Status - - - - 2 -
Read Online status of Robot 1·16 in AA 4 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 4 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 4 Status - - - - 16 -
Read Online status of Robot 49·50 in AA 4 Status - - - - 2 -
Read Online status of Robot 1·16 in AA 5 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 5 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 5 Status - - - - 16 -
Read Online status of Robot 49·50 in AA 5 Status - - - - 2 -
Read Online status of Robot 1·16 in AA 6 Status - - - - 16 -
Read Online status of Robot 17·32 in AA 6 Status - - - - 16 -
Read Online status of Robot 33·48 in AA 6 Status - - - - 16 -
Read Online status of Robot 49·58 in AA 6 Status - - - - 10 -
Read Fault status of Robot 1·16 in AA 1 status - - - - 16 -
Read Fault status of Robot 17·32 in AA 1 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 1 status - - - - 16 -
Read Fault status of Robot 49·50 in AA 1 status - - - - 2 -
Read Fault status of Robot 1·16 in AA 2 status - - - - 16 -
Read Fault status of Robot 17·32 in AA 2 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 2 status - - - - 16 -
Read Fault status of Robot 49·50 in AA 2 status - - - - 2 -
Read Fault status of Robot 1·16 in AA 3 status - - - - 16 -
Read Fault status of Robot 17·32 in AA 3 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 3 status - - - - 16 -
Read Fault status of Robot 49·50 in AA 3 status - - - - 2 -
Read Fault status of Robot 1·16 in AA 4 status - - - - 16 -
Read Fault status of Robot 17·32 in AA 4 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 4 status - - - - 16 -
Read Fault status of Robot 49·50 in AA 4 status - - - - 2 -
Read Fault status of Robot 1·16 in AA 5 status - - - - 16 -
Read Fault status of Robot 17·32 in AA 5 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 5 status - - - - 16 -
10 Module cleaning system (Robot) Annexure-15 ARCS points table
Read Fault status of Robot 49·50 in AA 5 status - - - - 2 -

Sensitivity: Unclassified
#
Page 10 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
10 Module cleaning system (Robot) Annexure-15 ARCS points table
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Read Fault status of Robot 1·16 in AA 6 status - - - - 16 -


Read Fault status of Robot 17·32 in AA 6 status - - - - 16 -
Read Fault status of Robot 33·48 in AA 6 status - - - - 16 -
Read Fault status of Robot 49·58 in AA 6 status - - - - 10 -
Read Working status of Robot 1·16 in AA 1 status - - - - 16 -
Read Working status of Robot 17·32 in AA 1 status - - - - 16 -
Read Working status of Robot 33·48 in AA 1 status - - - - 16 -
Read Working status of Robot 49·50 in AA 1 status - - - - 2 -
Read Working status of Robot 1·16 in AA 2 status - - - - 16 -
Read Working status of Robot 17·32 in AA 2 status - - - - 16 -
Read Working status of Robot 33·48 in AA 2 status - - - - 16 -
Read Working status of Robot 49·50 in AA 2 status - - - - 2 -
Read Working status of Robot 1·16 in AA 3 status - - - - 16 -
Read Working status of Robot 17·32 in AA 3 status - - - - 16 -
Read Working status of Robot 33·48 in AA 3 status - - - - 16 -
Read Working status of Robot 49·50 in AA 3 status - - - - 2 -
Read Working status of Robot 1·16 in AA 4 status - - - - 16 -
Read Working status of Robot 17·32 in AA 4 status - - - - 16 -
Read Working status of Robot 33·48 in AA 4 status - - - - 16 -
Read Working status of Robot 49·50 in AA 4 status - - - - 2 -
Read Working status of Robot 1·16 in AA 5 status - - - - 16 -
Read Working status of Robot 17·32 in AA 5 status - - - - 16 -
Read Working status of Robot 33·48 in AA 5 status - - - - 16 -
Read Working status of Robot 49·50 in AA 5 status - - - - 2 -
Read Working status of Robot 1·16 in AA 6 status - - - - 16 -
Read Working status of Robot 17·32 in AA 6 status - - - - 16 -
Read Working status of Robot 33·48 in AA 6 status - - - - 16 -
Read Working status of Robot 49·58 in AA 6 status - - - - 10 -
Read Battery charging status of Robot 1·16 in AA 1 status - - - - 16 -
Read Battery charging status of Robot 17·32 in AA 1 status - - - - 16 -
Read Battery charging status of Robot 33·48 in AA 1 status - - - - 16 -
Read Battery charging status of Robot 49·50 in AA 1 status - - - - 2 -
Read Battery charging status of Robot 1·16 in AA 2 status - - - - 16 -
Read Battery charging status of Robot 17·32 in AA 2 status - - - - 16 -
Read Battery charging status of Robot 33·48 in AA 2 status - - - - 16 -
Read Battery charging status of Robot 49·50 in AA 2 status - - - - 2 -
Read Battery charging status of Robot 1·16 in AA 3 status - - - - 16 -
Read Battery charging status of Robot 17·32 in AA 3 status - - - - 16 -
Read Battery charging status of Robot 33·48 in AA 3 status - - - - 16 -
Read Battery charging status of Robot 49·50 in AA 3 status - - - - 2 -
Read Battery charging status of Robot 1·16 in AA 4 status - - - - 16 -
Read Battery charging status of Robot 17·32 in AA 4 status - - - - 16 -
Read Battery charging status of Robot 33·48 in AA 4 status - - - - 16 -
Read Battery charging status of Robot 49·50 in AA 4 status - - - - 2 -
Read Battery charging status of Robot 1·16 in AA 5 status - - - - 16 -

Sensitivity: Unclassified
#
Page 11 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Read Battery charging status of Robot 17·32 in AA 5 status - - - - 16 -


Read Battery charging status of Robot 33·48 in AA 5 status - - - - 16 -
Read Battery charging status of Robot 49·50 in AA 5 status - - - - 2 -
Read Battery charging status of Robot 1·16 in AA 6 status - - - - 16 -
Read Battery charging status of Robot 17·32 in AA 6 status - - - - 16 -
Read Battery charging status of Robot 33·48 in AA 6 status - - - - 16 -
Read Battery charging status of Robot 49·58 in AA 6 status - - - - 10 -

Kindly refer “SIGNAL LIST BETWEEN PV SCADA


& WRCC - 20PKSA001-LNT-SPV-I-LST-1002”
11 WRCC Signals through Grid RTU panel WRCC signals - - - - - - -
document for signals between PV SCADA system
& WRCC through Grid RTU panel.

PTR-01 URGENT - ALARM / NORMAL Alarm - - - - 1 -


PTR-01 PROT - FAULTY / NORMAL Alarm - - - - 1 -
PTR-01 PROT - OPERATE / NORMAL Alarm - - - - 1 -
PTR-01 MECH PROT - OPERATE / NORMAL Alarm - - - - 1 -
EAT-01 PROT - OPERATE / NORMAL Alarm - - - - 1 -
EAT-01 PROT - FAULTY / NORMAL Alarm - - - - 1 -
EAT-01 MECH PROT - OPERATE / NORMAL Alarm - - - - 1 -
PTR-02 URGENT - ALARM / NORMAL Alarm - - - - 1 -
PTR-02 PROT - FAULTY / NORMAL Alarm - - - - 1 -
PTR-02 PROT - OPERATE / NORMAL Alarm - - - - 1 -
PTR-02 MECH PROT - OPERATE / NORMAL Alarm - - - - 1 -
Pooling Substation (PSS) signals from EAT-02 PROT - OPERATE / NORMAL Alarm - - - - 1 -
12 PSS SAS system to PV SCADA
110kV Alarm EAT-02 PROT - FAULTY / NORMAL Alarm - - - - 1 -
EAT-02 MECH PROT - OPERATE / NORMAL Alarm - - - - 1 -
CB 205B URGENT - ALARM/ NORMAL Alarm - - - - 1 -
BAY E02B PROT - FAULTY/ NORMAL Alarm - - - - 1 -
CB 205B CB LOCKOUT - ALARM/ NORMAL Alarm - - - - 1 -
BAY E02B PROT - FAULTY/ NORMAL Alarm - - - - 1 -
BAY E02B PROT - OPERATE/ NORMAL Alarm - - - - 1 -
CB 105A URGENT - ALARM/ NORMAL Alarm - - - - 1 -
BAY E01A PROT - FAULTY/ NORMAL Alarm - - - - 1 -
CB 105A CB LOCKOUT - ALARM/ NORMAL Alarm - - - - 1 -
BAY E01A PROT - FAULTY/ NORMAL Alarm - - - - 1 -
BAY E01A PROT - OPERATE/ NORMAL Alarm - - - - 1 -
PTR-01 AVC STATUS - AUTO / MANUAL Indication - - - - 1 -
PTR-01 OLTC POSITION - LOCAL / REMOTE Indication - - - - 1 -
PTR-01 TAP CHANGER - RAISE / LOWER Indication - - - - 1 -
Pooling Substation (PSS) signals from PTR-02 AVC STATUS - AUTO / MANUAL Indication - - - - 1 -
13 PSS SAS system to PV SCADA
110kV Indications PTR-02 OLTC POSITION - LOCAL / REMOTE Indication - - - - 1 -
PTR-02 TAP CHANGER - RAISE / LOWER Indication - - - - 1 -
205B BREAKER - CLOSE/ OPEN Indication - - - - 1 -
105A BREAKER - CLOSE/ OPEN Indication - - - - 1 -

Sensitivity: Unclassified
#
Page 12 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

E02B UG FEEDER - BCU - ACTIVE POWER Measurement - - - - 1 -

E02B UG FEEDER - BCU - REACTIVE POWER Measurement - - - - 1 -

E02B UG FEEDER - BCU - VOLTAGE Measurement - - - - 1 -


Pooling Substation (PSS) signals from E02B UG FEEDER - BCU - CURRENT Measurement - - - - 1 -
14 PSS SAS system to PV SCADA
110kV Measurements E01A UG FEEDER - BCU - ACTIVE POWER Measurement - - - - 1 -

E01A UG FEEDER - BCU - REACTIVE POWER Measurement - - - - 1 -


E01A UG FEEDER - BCU - VOLTAGE Measurement - - - - 1 -
E01A UG FEEDER - BCU - CURRENT Measurement - - - - 1 -
H01 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H01 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H01 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H01 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H01-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H01 REMOTE - OFF/ON Alarm - - - - 1 -
H02 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H02 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H02 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H02 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H02-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H02 REMOTE - OFF/ON Alarm - - - - 1 -
H03 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H03 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H03 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H03 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H03-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H03 REMOTE - OFF/ON Alarm - - - - 1 -
H04 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H04 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H04 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H04 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H04-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H04 REMOTE - OFF/ON Alarm - - - - 1 -
H05 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H05 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H05 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H05 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H05-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H05 REMOTE - OFF/ON Alarm - - - - 1 -
H07 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H07 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H07 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H07 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H07-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H07 REMOTE - OFF/ON Alarm - - - - 1 -

Sensitivity: Unclassified
#
Page 13 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

H08 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -


H08 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H08 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H08 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H08-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H08 REMOTE - OFF/ON Alarm - - - - 1 -
H10 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H10 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
Pooling Substation (PSS) signals from H10 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
15 PSS SAS system to PV SCADA
33kV Alarm H10 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H10-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H10 REMOTE - OFF/ON Alarm - - - - 1 -
H11 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H11 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H11 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H11 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H11-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H11 REMOTE - OFF/ON Alarm - - - - 1 -
H13 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H13 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H13 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H13 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H13-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H13 REMOTE - OFF/ON Alarm - - - - 1 -
H15 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H15 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H15 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H15 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H15-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H15 REMOTE - OFF/ON Alarm - - - - 1 -
H16 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H16 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H16 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H16 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H16-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H16 REMOTE - OFF/ON Alarm - - - - 1 -
H17 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H17 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H17 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H17 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H17-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H17 REMOTE - OFF/ON Alarm - - - - 1 -
H18 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H18 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H18 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -

Sensitivity: Unclassified
#
Page 14 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

H18 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -


H18-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -
H18 REMOTE - OFF/ON Alarm - - - - 1 -
H19 URGENT ALARM - ALARM/ NORMAL Alarm - - - - 1 -
H19 PROT FLTY ALARM - FAULTY/ NORMAL Alarm - - - - 1 -
H19 CB LOCKOUT - ALARM / NORMAL Alarm - - - - 1 -
H19 CBF PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -

H19-33kV PROT OPTD - OPERATE / NORMAL Alarm - - - - 1 -

H19 REMOTE - OFF/ON Alarm - - - - 1 -

H01 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H01 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H01 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H02 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H02 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H02 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H03 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H03 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H03 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H04 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H04 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H04 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H05 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H05 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H05 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H07 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H07 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H07 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H08 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H08 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H08 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H10 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H10 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H10 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H09 Q10-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -


Pooling Substation (PSS) signals from
16 PSS SAS system to PV SCADA H09 Q10-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -
33kV Indication
BUS-A Q61-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

BUS-A Q61-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H11 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H11 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H11 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

BUS-B Q61-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

Sensitivity: Unclassified
#
Page 15 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA
Pooling Substation (PSS) signals from
16 PSS SAS system to PV SCADA Document Title L&T Document No. Rev. No.
33kV Indication
20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

BUS-B Q61-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H13 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H13 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H13 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H15 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H15 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H15 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H16 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H16 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H16 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H17 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H17 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H17 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H18 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H18 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H18 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H19 Q0 BREAKER - CLOSE / OPEN Indication - - - - 1 -

H19 Q1-S1 ISOLATOR - CLOSE / OPEN Indication - - - - 1 -

H19 Q1-S5 E/SW - CLOSE / OPEN Indication - - - - 1 -

H01 BREAKER - CLOSE / OPEN Command - - - - 1 -

H02 BREAKER - CLOSE / OPEN Command - - - - 1 -

H03 BREAKER - CLOSE / OPEN Command - - - - 1 -

H04 BREAKER - CLOSE / OPEN Command - - - - 1 -

H05 BREAKER - CLOSE / OPEN Command - - - - 1 -

H07 BREAKER - CLOSE / OPEN Command - - - - 1 -

H08 BREAKER - CLOSE / OPEN Command - - - - 1 -


Pooling Substation (PSS) signals from
17 PSS SAS system to PV SCADA H10 BREAKER - CLOSE / OPEN Command - - - - 1 -
33kV Command
H11 BREAKER - CLOSE / OPEN Command - - - - 1 -

H13 BREAKER - CLOSE / OPEN Command - - - - 1 -

H15 BREAKER - CLOSE / OPEN Command - - - - 1 -

H16 BREAKER - CLOSE / OPEN Command - - - - 1 -

H17 BREAKER - CLOSE / OPEN Command - - - - 1 -

H18 BREAKER - CLOSE / OPEN Command - - - - 1 -

H19 BREAKER - CLOSE / OPEN Command - - - - 1 -

STATCOM-1 FEEDER H01 REACTIVE POWER Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT Measurement - - - - 1 -

STATCOM-1 FEEDER H01 POWER FACTOR Measurement - - - - 1 -

STATCOM-1 FEEDER H01 FREQUENCY Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT R-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT Y-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 CURRENT B-PH Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 16 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

STATCOM-1 FEEDER H01 VOLTAGE R-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE Y-PH Measurement - - - - 1 -

STATCOM-1 FEEDER H01 VOLTAGE B-PH Measurement - - - - 1 -

INVERTER BLOCK-01 FEEDER H02 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-01 FEEDER H02 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-02 FEEDER H03 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-02 FEEDER H03 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-03 FEEDER H04 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-03 FEEDER H04 REACTIVE POWER Measurement - - - - 1 -

TRANSFORMER GT PTR-01 (E01) TAP POSITION Measurement - - - - 1 -

TRAFO. OUTGOING-1 FEEDER H05 ACTIVE POWER Measurement - - - - 1 -

TRAFO. OUTGOING-1 FEEDER H05 REACTIVE POWER Measurement - - - - 1 -

TRAFO. OUTGOING-1 FEEDER H05 VOLTAGE Measurement - - - - 1 -

TRAFO. OUTGOING-1 FEEDER H05 CURRENT Measurement - - - - 1 -

INVERTER BLOCK-04 FEEDER H07 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-04 FEEDER H07 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-05 FEEDER H08 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-05 FEEDER H08 REACTIVE POWER Measurement - - - - 1 -

BUS SECTION FEEDER H10 CURRENT Measurement - - - - 1 -

STATCOM-2 FEEDER H11 REACTIVE POWER Measurement - - - - 1 -


Pooling Substation (PSS) signals from
18 PSS SAS system to PV SCADA STATCOM-2 FEEDER H11 VOLTAGE Measurement - - - - 1 -
33kV Measurement
STATCOM-2 FEEDER H11 CURRENT Measurement - - - - 1 -

STATCOM-2 FEEDER H11 POWER FACTOR Measurement - - - - 1 -

STATCOM-2 FEEDER H11 FREQUENCY Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT R-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT Y-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 CURRENT B-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE R-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE Y-PH Measurement - - - - 1 -

STATCOM-2 FEEDER H11 VOLTAGE B-PH Measurement - - - - 1 -

TRANSFORMER GT PTR-01 (E02) TAP POSITION Measurement - - - - 1 -

TRAFO. OUTGOING-2 FEEDER H13 ACTIVE POWER Measurement - - - - 1 -

TRAFO. OUTGOING-2 FEEDER H13 REACTIVE POWER Measurement - - - - 1 -

TRAFO. OUTGOING-2 FEEDER H13 VOLTAGE Measurement - - - - 1 -

TRAFO. OUTGOING-2 FEEDER H13 CURRENT Measurement - - - - 1 -

INVERTER BLOCK-06 FEEDER H15 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-06 FEEDER H15 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-07 FEEDER H16 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-07 FEEDER H16 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-08 FEEDER H17 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-08 FEEDER H17 REACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-09 FEEDER H18 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-09 FEEDER H18 REACTIVE POWER Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 17 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

INVERTER BLOCK-10 FEEDER H19 ACTIVE POWER Measurement - - - - 1 -

INVERTER BLOCK-10 FEEDER H19 REACTIVE POWER Measurement - - - - 1 -

BUS RISER + BUS-A VT H09 VOLTAGE- BBA Measurement - - - - 1 -

BUS RISER + BUS-A VT H09 FREQUENCY- BBA Measurement - - - - 1 -

BUS-B VT H12 VOLTAGE- BBB Measurement - - - - 1 -

BUS-B VT H12 FREQUENCY- BBB Measurement - - - - 1 -

PCC voltage Uab Measurement - - - - 1 -

PCC voltage Ubc Measurement - - - - 1 -

PCC voltage Uca Measurement - - - - 1 -

PCC current Ia Measurement - - - - 1 -

PCC current Ib Measurement - - - - 1 -

PCC current Ic Measurement - - - - 1 -

Bus bar voltage Uab Measurement - - - - 1 -

Bus bar voltage Ubc Measurement - - - - 1 -

Bus bar voltage Uca Measurement - - - - 1 -

Bus bar current Ia Measurement - - - - 1 -

Bus bar current Ib Measurement - - - - 1 -

Bus bar current Ic Measurement - - - - 1 -

SVG current Ia Measurement - - - - 1 -

SVG current Ib Measurement - - - - 1 -

SVG current Ic Measurement - - - - 1 -

System frequency Measurement - - - - 1 -

System power factor Measurement - - - - 1 -

System active power Measurement - - - - 1 -

System reactive power Measurement - - - - 1 -

SVG reactive power Measurement - - - - 1 -

Locking status word - grid over voltage locking Status - - - - 1 -

Locking status word - grid under voltage locking Status - - - - 1 -

Locking status word - grid over frequency locking Status - - - - 1 -

Locking status word - grid under frequency locking Status - - - - 1 -

Locking status word - output over current locking Status - - - - 1 -

Locking status word - output over load locking Status - - - - 1 -

Locking status word - module fault locking Status - - - - 1 -

Locking status word - hardware over currrent locking Status - - - - 1 -

Locking status word - water-cooling system fault locking Status - - - - 1 -


Statcom-1 signals from PV SCADA to
19 Warning status word - grid over voltage alarm Alarm - - - - 1 - Annexure-12 – Statcom Modbus Interface list
PSS SAS
Warning status word - grid under voltage alarm Alarm - - - - 1 -

Warning status word - output over load alarm Alarm - - - - 1 -

Warning status word - control cabinet AC alarm Alarm - - - - 1 -

Sensitivity: Unclassified
#
Page 18 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date
Statcom-1 signals from PV SCADA to
19 AP SB KCM Annexure-12 – Statcom Modbus Interface list
14-Nov-22
PSS SAS

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Warning status word - control cabinet DC alarm Alarm - - - - 1 -

Warning status word - extend box AC alarm Alarm - - - - 1 -

Warning status word - extend box DC alarm Alarm - - - - 1 -

Fault status word 1 - grid over voltage fault Fault - - - - 1 -

Fault status word 1 - grid under voltage fault Fault - - - - 1 -

Fault status word 1 - grid over frequency fault Fault - - - - 1 -

Fault status word 1 - grid under frequency fault Fault - - - - 1 -

Fault status word 1 - output over current fault Fault - - - - 1 -

Fault status word 1 - output over load fault Fault - - - - 1 -

Fault status word 2 - soft-start charging timeout trip Fault - - - - 1 -

Fault status word 2 - locking number exceed limit trip Fault - - - - 1 -

Fault status word 2 - hardware detecting over current Fault - - - - 1 -

Fault status word 2 - module bypass failure fault Fault - - - - 1 -

Fault status word 2 - bypass module over limit Fault - - - - 1 -

Fault status word 5 - breaker opening failure trip Fault - - - - 1 -

Fault status word 5 - soft-start closing failure trip Fault - - - - 1 -

Fault status word 5 - soft-start opening failure trip Fault - - - - 1 -

Fault status word 5 - control power supply fault Fault - - - - 1 -

Fault status word 5 - extend box power supply fault Fault - - - - 1 -

Fault status word 5 - disconnector opening fault Fault - - - - 1 -

Fault status word 5 - ground switch closing fault Fault - - - - 1 -

Control mode Command - - - - 1 -

Reactive power setting value Command - - - - 1 -

Power factor setting value Command - - - - 1 -

Constant voltage setting value Command - - - - 1 -

Load compensation reactive power setting Command - - - - 1 -

PCC voltage Uab Measurement - - - - 1 -

PCC voltage Ubc Measurement - - - - 1 -

PCC voltage Uca Measurement - - - - 1 -

PCC current Ia Measurement - - - - 1 -

PCC current Ib Measurement - - - - 1 -

PCC current Ic Measurement - - - - 1 -

Bus bar voltage Uab Measurement - - - - 1 -

Bus bar voltage Ubc Measurement - - - - 1 -

Bus bar voltage Uca Measurement - - - - 1 -

Bus bar current Ia Measurement - - - - 1 -

Bus bar current Ib Measurement - - - - 1 -

Bus bar current Ic Measurement - - - - 1 -

Sensitivity: Unclassified
#
Page 19 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

SVG current Ia Measurement - - - - 1 -

SVG current Ib Measurement - - - - 1 -

SVG current Ic Measurement - - - - 1 -

System frequency Measurement - - - - 1 -

System power factor Measurement - - - - 1 -

System active power Measurement - - - - 1 -

System reactive power Measurement - - - - 1 -

SVG reactive power Measurement - - - - 1 -

Locking status word - grid over voltage locking Status - - - - 1 -

Locking status word - grid under voltage locking Status - - - - 1 -

Locking status word - grid over frequency locking Status - - - - 1 -

Locking status word - grid under frequency locking Status - - - - 1 -

Locking status word - output over current locking Status - - - - 1 -

Locking status word - output over load locking Status - - - - 1 -

Locking status word - module fault locking Status - - - - 1 -

Locking status word - hardware over currrent locking Status - - - - 1 -

Locking status word - water-cooling system fault locking Status - - - - 1 -

Warning status word - grid over voltage alarm Alarm - - - - 1 -

Warning status word - grid under voltage alarm Alarm - - - - 1 -


Statcom-2 signals from PV SCADA to
20 Annexure-12 – Statcom Modbus Interface list
PSS SAS Warning status word - output over load alarm Alarm - - - - 1 -

Warning status word - control cabinet AC alarm Alarm - - - - 1 -

Warning status word - control cabinet DC alarm Alarm - - - - 1 -

Warning status word - extend box AC alarm Alarm - - - - 1 -

Warning status word - extend box DC alarm Alarm - - - - 1 -

Fault status word 1 - grid over voltage fault Fault - - - - 1 -

Fault status word 1 - grid under voltage fault Fault - - - - 1 -

Fault status word 1 - grid over frequency fault Fault - - - - 1 -

Fault status word 1 - grid under frequency fault Fault - - - - 1 -

Fault status word 1 - output over current fault Fault - - - - 1 -

Fault status word 1 - output over load fault Fault - - - - 1 -

Fault status word 2 - soft-start charging timeout trip Fault - - - - 1 -

Fault status word 2 - locking number exceed limit trip Fault - - - - 1 -

Fault status word 2 - hardware detecting over current Fault - - - - 1 -

Fault status word 2 - module bypass failure fault Fault - - - - 1 -

Fault status word 2 - bypass module over limit Fault - - - - 1 -

Fault status word 5 - breaker opening failure trip Fault - - - - 1 -

Sensitivity: Unclassified
#
Page 20 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

I/O Quantity Per Equipment


S. No. Equipment Name Signal Description Signal Type Remarks
DI DO AI MODBUS RS 485 Modbus TCP/IP ODBC

Fault status word 5 - soft-start closing failure trip Fault - - - - 1 -

Fault status word 5 - soft-start opening failure trip Fault - - - - 1 -

Fault status word 5 - control power supply fault Fault - - - - 1 -

Fault status word 5 - extend box power supply fault Fault - - - - 1 -

Fault status word 5 - disconnector opening fault Fault - - - - 1 -

Fault status word 5 - ground switch closing fault Fault - - - - 1 -

Control mode Command - - - - 1 -

Reactive power setting value Command - - - - 1 -

Power factor setting value Command - - - - 1 -

Constant voltage setting value Command - - - - 1 -

Load compensation reactive power setting Command - - - - 1 -

Note: This I/O list shall be updated based on the vendor document of electrical equipment's in case of any change.

Sensitivity: Unclassified
#
Page 21 of 21
Project: CONTRACT NO: 0047390-0000108EU01:2000735990.16
REPDO ROUND 2 JEDDAH 300 MWAC PV SOLAR PROJECT AT JEDDAH, KSA

Document Title L&T Document No. Rev. No.

20PKSA001-LNT-SPV-I-LST-1301 4

SCADA I/O SIGNAL LIST AT O&M BUILDING Prepared Checked Approved Date

AP SB KCM 14-Nov-22

SCADA I/O Summary


I/O Quantity
S. No. Field Equipment Name Modbus Modbus Remarks
DI DO AI ODBC
RS485 TCP/IP
I PV PLANT CONTROL BUILDING

1 UPS -- -- -- 35 -- --

2 GPS 2 -- -- -- -- --

3 ACDB_MFM -- -- -- 14 --

4 Fire Alarm panel 4 -- -- -- --

Statcom signals are considered with maximum 42


5 PPC (PPC + PQ meter + Statcom 1 &2 + SAS) -- -- -- 1474 -- Modules in 1 statcom. But the actual IO quantity
will get reduced based on actual module quantity

6 Plant Accounting & Settlement system (PASS) 5 -- -- -- -- 6

7 Meter Data Acquisition System (MDA) 7 -- -- -- -- 1

8 Module cleaning system (Robot) -- -- -- -- 2178 --

Substation SAS system


9 (i) Substation signals from PSS SAS to PV SCADA -- -- -- -- 371 --
(ii) Statcom signals from PV SCADA to PSS SAS

Kindly refer “SIGNAL LIST BETWEEN PV


SCADA & WRCC - 20PKSA001-LNT-SPV-I-LST-
10 Western Regional Control Center (WRCC) -- -- -- -- -- --
1002” document for signals between PV SCADA
system & WRCC through Grid RTU panel.

# Sensitivity: Unclassified Page 1 of 1