KONTRAK PERIODE LALU PERIODE SAAT INI PERIODE S/D SAAT INI

ADD-01 ADD-02
NO. URAIAN PEKERJAAN SAT AWAL
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
VOLUME VOLUME VOLUME BOBOT
1 Pekerjaan Persiapan Preboring Ø 70 cm Ls 1,00 1,00 1,00 1,13% 1,00 1,13% 1,00 1,13%
2 Mobilisasi Demobilisasi Alat Bor + Excavator + Genset + Kelly Set 1,00 1,00 1,00 3,78% 1,00 3,78% 1,00 3,78%
3 Preboring Ø 70 cm, Kedalaman 40 x 51 Titik m' 2.040,00 2.040,00 2.280,00 51,65% 2.280,00 51,65% 2.280,00 51,65%
4 Pasang & Cabut Temporary Casing Ø 70 cm m' 1.020,00 1.020,00 1.042,00 11,80% 1.042,00 11,80% 1.042,00 11,80%
5 Buang Tanah/Lumpur Di sekitar Lokasi Proyek m' 2.040,00 2.040,00 2.280,00 12,91% 2.280,00 12,91% 2.280,00 12,91%
6 Pekerjaan Persiapan Pancang Spunpile Ø 45 cm Ls 1,00 1,00 1,00 1,13% 1,00 1,13% 1,00 1,13%
7 Mobilisasi Demobilisasi Alat Pancang + Service Crane + Set 1,00 1,00 1,00 3,78% 1,00 3,78% 1,00 3,78%
Hammer DD45
8 Pancang Spunpile 45 cm, Kedalaman 54 x 51 Titik m' 2.754,00 2.754,00 3.005,00 11,35% 3.005,00 11,35% 3.005,00 11,35%
9 Handling Pile m' 2.754,00 2.754,00 3.005,00 1,70% 3.005,00 1,70% 3.005,00 1,70%
10 Joint Pile Joint 153,00 153,00 169,00 0,77% 169,00 0,77% 169,00 0,77%

100,00% 100,00% 100,00%