No PUNCH LIST POINT DETAILS PICTURES

1 project documents All documents have


been delivered to the
managers of the
facilities.
please find the
uploaded documents

2 GX GSM modem The installation was


done in the south, as
for the north, it will be
handed over to the
UNOPS

3 connection bolts Grease added to all


connection bolts for all
lots.
please find the
uploaded documents
4 Ventilation fans Power supplied and
turned on/off switch in
all lots.
please find the
uploaded documents

5 Drawings we did all drawing


inside all boxes
(Combiner - MDB-etc).

please find the


uploaded documents

6 connection bolts we used Torque


wrench shell be used
To check of all bolts.
7 Data sheets and O&M manuals All leaflets
(Datasheets- Catalogs-
O&M manuals....)
Available in all rooms
in lastic files.
please find the
uploaded documents

8 VRM Activation We activated all


monitoring systems in
VRM web for both
systems (victron and
Outback) in all Lots.

9 Earthing And Lighting pits All earthing and


lightning pits
measured resistance
more than 5 Ohm it
was reduce.

10 Fire extinguisher All fire extinguishers in


all facilities (All Lots)
are carrying third party
inspection label for
date of inspection (and
refilling if required).
please find the
uploaded documents

11 Outback Charge Controller All charge controller


checked they are
inside of service.

12 Charge Controller (Outback) Ground fault fuses of


charger controllers
replaced with same
rating 1A-600VDC for
all outback in all lots.
13 Shunt for battery motoring and All shunt and battery
battery bus bar rack bus bar of the
battery monitoring
Protected by
fiberglass in all sites.
please find the
uploaded documents

14 Entrance holes to battery rooms All cable tray entrance,


Air conditioning and
ventilation fans holes
are sealed and plugged
against dust, water,
and insects in all
facilities for all lots.
please find the
uploaded documents

15 Photocell for Outdoor Lighting we replaced photocell


for outdoor lighting
for
AI-Khansa School,
Haeel School.
14 October Hospital.
AI-Zahra'a School.
AI-Shahidah Eqbal
School
AI-Faroq-Rosod School,
Salem Saleh School, AI-
Waseti School,
AI-Faroq-Sebah School,
AI-Saeed School,
Mousa Awadh School,
Motherhood & Child
Center -Qatabah and
AI-Salam Hospital.
Please find the
uploaded documents.
16 Protection cover for Outback inverters All outback inverters
bottom side covered
by in all lots.

Please find the


uploaded documents.
17 Spare cable gland Holes All cable gland holes
plugged.

18 Lightning Arrester Lightning Arrester


cover PV modules area
and place to the
highest point in facility
rooftop in following
ABU-MUSA SCHOOL,
DHALMA H.
AI-Wahdah School,
Saeed Ali Hospital, AI-
Khatwah school and
Al-Ershad School.
19 Indoor Lighting We Completed indoor
lighting installing in:-
Dhebah Health center.
Thee Ata Health
center.
AI-Ershad School.
20 Monitoring system firmware's update All monitoring system
firmware updated for
all site in all Lots.
21 AC SPD The activated AC SPD
replaced in:-
AI-Maidan Health
Center.
Dhebah HC.
Thee Ata'a HC.
Saeed Ali Hospital.
Maryam School.
Please find the
uploaded documents.
22 Blocking Diode Burned blocking diode
was replaced in
Saeed Ali Hospital.
AI-Mawaset Rural
Hospital
Ali Abdullah School
Wa'lan HC.
Please find the
uploaded documents.
23 Smoke Detector We replaced all Smoke
detector which was
malfunctioned in:-
AI-Khatwah School, AI-
Jeel AI-Jadeed School.
Zinab School, Sumaia
School, Khadejah
School, Hadhar HC.
Dhebah HC. Asma
School.

Please find the


uploaded documents.
24 Tagging and Labeling Tag of strings, PV
modules, cables &
chargers completed
in:-
Haifan Hospital &
Da'an HC, AI-Jeel AI-
Jadeed School, Saeed
Ali Hospital, AI-
Mawaset Rural
Hospital.
AI-Zahra'a School, AI-
Saqaf School, Khadejah
School, AI- Shahidah
Eqbal School, Tur AI-
Bahah Hospital.
AL-ESHRAQSCHOOL,
SOUQAI-RABUA H.C,
Sumaia
School Arwa AI-Fawz
School
25 Batteries connection bolts Some batteries
connection bolts
changed in:
AI-Jeel AI-Jadeed
School, AI-Wahdah
School,
AI-Naser Adhalem
School, AI-Shaheed AI-
Eryani School, And
Hadhar HC
26 Alternator operation and temperature The alternator
control unit operation and
temperature control
unit pot
are working in:-
khadejah School
27 Sign Board relocation We Relocated
signboard to the
correct place
Saeed Ali Hospital
AI-Mawaset Rural
Hospital
14 October Hospital,
AI-Zahra'a School,
Aisha School,
Zinab School, Tur AI-
Bahah Hospital.

28 Battery monitoring System (BMV) BMV is working in:-


-Tur AI-Bahah Hospital
-DAR HABA H.C,
AL-ESHRAQ SCHOOL
-A I-Khatwah &
AI-Ershad School.

Please find the


uploaded documents
29 BMV Shunt base The base of battery
shunt replaced in:-
AI-Khansa School,
Khadejah School,
Bait AI-Hojaini HC
Please find the
uploaded documents

30 Battery rack We fixed the Missing


parts of the battery
rack and installed it in:-
-Arwa AI-Fawz School.
-Asma Schoof.
31 Mounting structure We fixed the Missing
parts and bolt of the
mounting structure
and installed it :-
AI-Naser Adhalem
School
Aisha School,
Zainab School &
Az-Zahra'a Schooi-
Yafe'e
32 Concrete block grout Concrete block
grouting completed
in:-
AI-Khatwah, AI-
Tahreer & AI-Ershad
School & Haifan
Hospital.
AI-Faroq-Rosod School,
Salem Saleh School, AI-
Waseti School, AI-
Faroq-Sebah School,
AI-Saeed School,
Mousa
Awadh School,
Motherhood & Child
Center -Qatabah and
AI-Salam Hospital.
Omar School.
Please find the
uploaded documents.
33 RCCB of Ac Coupling and MDB RCCB change and
installed in:
Haeel School,
Khawlah School_
Asma School,
AI-Khansa School,
Omar School,
AI-Dhahi Hospital.
34 MDB Neutral We fixed Only one
neutral wire connected
inside MDB:-
- Jarf Esbeel HC.
35 Paint in PV Modules the paint Removed
from PV modules in:-
-Wa'lan HC, Masaood
HC.
-AI-Maidan -
Health.Center.
-AI-Adel School.

36 Datalink between Inverter or BMV2 Datalink between


and - CCGX. Inverter or BMV2 and
CCGX is Working in:-
- Thee Ata'a Health
Center.
- Az-Zahr'a' School-
Yafe'e.

37 Main Circuit Breaker for MDB We changed main


circuit breaker for
MDB to 3poles in:
- AI-Hayfa Health
center.
- Dhebah HC.

38 PV module Fixing We fixed bolt and


Installed it for PV
module in:-
- Aisha School,
Zainab School &
Az-Zahra'a Schooi-
Yafe'e
39 Charge Controller We installed Smart
Solar Control Display
in:-
Al- zahra'a School-
Yafe'e,
Bait AI-Hojaini HC.
40 Ac Coupling We Installed MCCB in
AC coupling at - AI-
Wahdah School.