Professional Documents
Culture Documents
PERT All
PERT All
PERT
1
• Recall that AON diagrams were based
on deterministic activity durations
2
• Since construction companies engage
in work that they have done in the past,
this results in multiple occurrences of
the same activity and a historical record
of durations or productivities
4
Frequency
8 9 10 11 12 13 14 15 16
Duration (days)
3
• No matter of the actual distribution, there are
three measures of central tendency: mean,
mode, and median
4
Frequency
8 9 10 11 12 13 14 15 16
Duration (days)
4
Frequency
8 9 10 11 12 13 14 15 16
Duration (days)
• Mean = 11.48
• Mode = 10 (most frequent occurrence)
• Median = 11 (equal number of observations above it
and equal number of observations below it)
• Note also that the range of observations = 16 – 8 = 8
4
• If all activities have been performed
multiple times in the past enough times
to generate a frequency histogram, a
sample can be taken from each
distribution that will give a duration for
each activity
4
Frequency
8 9 10 11 12 13 14 15 16
Duration (days)
5
Histogram of Duration (days), with Normal
Curve for a construction activity
4
Frequency
8 9 10 11 12 13 14 15 16
Duration (days)
to + 4tm + tp
te =
6
6
to + 4tm + tp
te =
6
te = mean or expected activity duration
to :optimistic activity duration
tm : most likely activity duration
tp : pessimistic activity duration
Network calculations
7
Example
8
• We can use S to describe the extent to which the
duration is expected to vary from the derived
mean
Standard deviation (S) = Range of activity durations
6
tp − to
S=
6
• Note that 6 in the equation refers to ±3 standard
deviations from the mean of a normal distribution, which
contains 99.73% of all population values
The variance
tp − to 2
Variance(V ) = S = ( 2
)
6
S= V
• Note that S Pr oject = SCP = V CP
9
Example
Slack
10
Calculating the probability of meeting
deadline dates
• Based on the normal distribution, we can
calculate the probability of project completion
within certain duration
11
Te = 24 days Ts = 27 days
Te = 24 days Ts = 27 days
12
T s − Te
Z=
SCP
Ts = 27 days
27 − 24
Te = 24 days
Z= = 1.43
2.095
PERT
13
PERT
• The Program Evaluation and Review Technique, commonly
abbreviated PERT, is a statistical tool, used in project
management, that is designed to analyze and represent the tasks
involved in completing a given project.
• Example
– For the following project determine the
following !
– The Critical Path ( C.P)
– What is The probability of finishing the project before or on day number 21?
– What is the finish time for the project with a probability of 95 % ?
14
Activity Pre. Duration
To Tm Tp
A - 2 3 5
B A 4 6 7
C A 1 2 3
D A 3 4 5
B
E 2 3 5
C
C
F 2 3 4
D
E
G 1 2 4
F
B
H 2 4 5
F
D
I 1 2 4
F
G
N H 2 3 4
I
To Tm Tp
Activity
Te
15
4 6 7 2 4 5
B H
5.83 3
3.83
2 5
E
3.17 2
2 3 5 1 2 3 1 4 2 3 4
A C G N
3.17 2 3
2.17 3
2 4
4
3 2
3 5 1 4
D I
4 2.17
13.34 Days
13.51 Days
C.P
16
Critical Path Activities Are :
2) What is The probability of finishing the project before or on day number 21?
Z = (Ts – Te ) / Scp
Standard Deviation For The Project (Scp) = ∑ √S² , where S : standard deviation for each Critical activity
17
So, :
18