DESIGN & PROTECTION FOR CHANGE IN CIRCUIT CABLE SIZE

TX
P.B P.B P.B P.B Last
100A P.B
Note:
For all the circuits in the Reticulation from the second to last P.B we have
Decreased the cable size from185 Sq.mm to 95 Sq.mm.
We have placed a 100 A service Fuse in the pillar box to protect this cable
Typical Single Phase P.B Wiring Diagram as the protection fuse in the TX exceeds 95 Sq.mm Cable rating.
Typical 1C LV
Reticulation Cable
(A)
63A
To Consumer -1 All MV/LV Cable Terminations inside the pillar box shall be done as per EFL Regulatory
(185 Sq.mm Al) 63A
To Consumer -2 Team Requirements.
35 Sq.mm 1C CU 100A Service To Subsequent Pillar Box
PVC Cable Rated Fuse
at 112A Connected to 35 Sq.mm 1C CU
185 Sq.mm AL XLPE Cable PVC Cable Rated
via Bi Metallic Lug at 112A Connected to
95 Sq.mm AL XLPE Cable
via Bi Metallic Lug
ENGINEERING CONTRACTOR DESIGNED DESIGN CHK SCALE
CLIENT: PROJECT: DRAWING TITLE:
HS HS NTS
ENGINEERING & POWER SOLUTIONS
GENERAL ELECTRICAL ENGINEERING, CIVIL, MECHANICAL & INSTALLATION SERVICES CHALLENGE ENGINEERING LTD. Challenge Residential Subdivision DESIGN AND PROTECTION CHANGE DRAFTED DRAFTING CHK ISSUE DATE
Commercial, Industrial, Hotel/ Resorts, Infrastructure & Developments DS DS 22-04-2021
Electrical Reticulation CIRCUIT
49 Vitogo Parade P O Box D110 Email : epowersolutionsltka@gmail.com - DRAWING NO. REVISION
Lautoka City Lautoka Phone : (+679 836 3334/ 836 5288
REV DESCRIPTION BY DATE CEL-007 R2 R2