Installation of pole and isolator to connect to the proposed transformers

EFL Cable Jointer Team = 1 Day ( 1xCable Termination at Isolator on Pole at Duavata Temple Junction) $649.92
EFL Line Construction Team= 1 Day( 1 pole + 1 Stay at Duavata Temple Junction) $914.78
EFL O&M Overhead Team= 1 Day( String 3 Phase LV & 3 Phase HV (1 Span) $741.50

Testing by EFL Technicians:

Transformer IR testing,Ratio testing,Continuity test & HV +LV


earth grid tests 2days
HV Cable IR & Continuity Test 1 day
LV Cable IR & Continuity Test= 45Pillar Boxes/10Pillar Boxes per day = 5days
Distribution Technician Senior Rate= $18.39
$18.39x8daysx5peoplex8hrs=$5884.80x 1.1((10% Con gency to work on Saturday Sundays)=$6473.28

Inspection of Cable Trench & backfilling (will be done by EFL cable team) (4hrs/day)

Engineering Power Solution work program


HV Cable=396m/99m per day= 4 days; states that installation of LV & HV cable will
take 18 days(4days HV cabling & 14days LV
LV Cable= Route Length =1900m x 4(1C)= 7600m; 7600m/550m per day= 14days cabling)

Cable Joint Verification will be done by EFL cable team (4hrs/day)

Engineering Power Solution work program


states that cable jointing will take 14 Note: Verify with work program of how you will plan for the
14days*4hrs/day=7days days(Cable Jointing) work. Your number of days may reduce or increase

Total= 4days + 14days= 18days *4hrs/day= 9days(Cable trench & backfilling)+7days(Cable Joint Verification)=16days

Cable Jointer team Rate= $649.92 Rate= $649.92*16days=$10398.72x


1.1(10% Contigency to work on Saturdays&Sundays)=$11438.59

EFL Inspection team

45 pillar boxes/10pillar boxes per day=5 days *$276.89=$1384.45


EFL inspection charges will be discussed with insp