You are on page 1of 16

PAPERS Identifying Success Factors in

Construction Projects: A Case Study


Terry Williams, Hull University Business School, University of Hull, Hull, UK

ABSTRACT INTRODUCTION ■

T
Defining “project success” has been of inter- his study considers “success” within projects. There has been research
est for many years, and recent developments into the factors that contribute to success (e.g., Belassi & Tukel, 1996).
combine multiple measurable and psychoso- The nature of success has been of interest for many years; indeed,
cial factors that add to this definition. There the Project Management Institute held a whole conference dedicated
has also been research into success factors, to the topic (see, e.g., the paper by de Wit, 1986), looking at the multi-
but little research into the causal chains faceted nature of the idea of “success,” particularly where success is defined
through which success emerges. Following beyond the simple acceptance of a product. There has been little research,
the multi-dimensionality of “success,” this however, into the causal chains by which success in terms of these different
article shows how success factors combine facets emerges. This study therefore looks at these chains and their inter-
in complex interactions; it describes factors connectedness leading to success. By looking at the inter-connectedness, the
contributing to project performance by a study outlines how to identify the root causes of success factors, particularly
company working on two major construc- where those root causes enable multiple success criteria simultaneously. In
tion programs and shows how to map and order to look in-depth at the complex structures of effects, a single detailed
analyze paths from root causes to success case study was used, using a causal mapping method for analysis. This
criteria. The study also identifies some spe- article expands on the extension of the ideas of systemicity into the current
cific factors—some generic, some context- predominately linear dominant discourse of project management (Cooke-
dependent—none of these is uncommon Davies, 2011; Edkins, Kurul, Maytorena-Sanchez, & Rintala, 2007; Williams,
but here they come together synergistically. 2005), by looking at a particular case of projects as practice (Blomquist,
Hallgren, Nilsson, & Soderholm, 2010).
KEYWORDS: systems thinking; project An appropriate case study for this research arose in late 2013, when a UK
management; complexity; project success company was coming to the end of its involvement in two major construction
programs. The company had a reputation for considerable success with these
programs; and since the project teams would likely be disbanded with the end
of these programs, it seemed important to reflect on this success. Was it real?
What does “success” mean? And, where did this success come from? This
article reports the results, mainly drawing lessons about the nature of success
and the inter-relatedness and complexity of success factors, and also identify-
ing a number of key reasons for company success—some generic, and some
context-dependent—but potentially useful for other projects.
Both research and practice have been moving away from a simplistic defi-
nition of project “success” as meeting cost, schedule, and performance targets,
to a more multi-dimensional definition, involving both objective and more
subjective criteria. However, the inter-relationships between these criteria are
less well researched. Similarly, success factors are often theorized, but there
is little research into the causality; in other words, “how” these factors lead to
project success. This study therefore looks at the drivers for the various success
factors, to see where they inter-connect, and what the key root causes of proj-
ect success are. This is interesting from an academic perspective, but is par-
ticularly important to help the practitioner understand how improving these
root causes will lead to increased performance in multiple project criteria.
Project Management Journal, Vol. 47, No. 1, 97–112 The article considers the method and then the case; it looks at the literature
© 2015 by the Project Management Institute around the definition of project success and how this case compares; it looks
Published online in Wiley Online Library at the literature behind success factors; then at the analysis of this case to see
(wileyonlinelibrary.com). DOI: 10.1002/pmj.21558 the interacting nature of the factors and the tracing of success outcomes back

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 97


Identifying Success Factors
PAPERS

to root causes. Conclusions are drawn chaining back in causality by asking in “lessons learned” exercises (Williams,
about the content of the factors but par- “Why?” or “What caused this?” Again, 2004). This study of a project program
ticularly about the underlying systemic- “grounded” in the sense that no external was more akin to the latter; workshops
ity. Although there is some discussion “best-practice” or literature-initiated were fairly small, in this case approxi-
about the success of the projects, the input was given to the workshop. Views mately 8 to 10 participants, carefully
aim of this article is to consider root in which possible root causes were sug- chosen with an appropriate mix of skills
causes and systemicity within the causal gested were subjected to chaining for- to ensure coverage of the main knowl-
chains rather than audit the programs. ward by asking: “So what?” or “What edge areas, and provide the opportunity
would the implications of this be?” to for participants to “piggy back” off each
Method develop the richness of the diagram. other ’s knowledge and memories, chal-
In order to capture the view of inter- Similar considerations were given to lenge views, and together develop a
connectedness and systemicity of the intermediary concepts. In order to help comprehensive overview (Ackermann &
factors, this study used “causal maps” ground the discussions in actual cases, Eden, 2001). The workshops attempted
(Eden & Ackermann, 1998) to plot out four cases were chosen as typical for to complete loops where they were
what caused what, and how these causal this study (see as follows). The maps found and chained up and down to the
chains and combinations led to project noted where particular cases were good end of causal chains; however, time
success—a type of analysis becoming examples of the concepts identified constraints meant that large saturated
used more in project management, as and where particular evidence could maps were not developed as in the for-
analysts try to understand the complex- be obtained later to back up the claims mer type of study.
ity of projects (Edkins et al., 2007). Maps made. The cases provided a useful check The second part of the study con-
produced using Decision Explorer soft- to looking at the causal chain developed sidered the maps, looking for evidence
ware (Banxia, 2013) can be seen in the and see whether the team recognized (statistical or cases) to support or refute
figures throughout this article, where the effect from the case study (see as the statements; although this was not
arrows represent causality; the concepts follows). These evidential and exemplar an “audit,” it served to ensure the study
are numbered, but this is only for con- links have not been reproduced in this was not misled by company myths. The
venience and has no meaning other article but were essential to grounding evidence came from a wide variety of
than for identification. the overall study in reality. sources, including site statistics, defect
The first and main part of the study The maps resulting from the work- data, safety statistics, externally exe-
consisted of two workshops in which shops, having been built visually in cuted employee engagement surveys,
teams of managers drew up causal maps front of the team, were reasonably easy subcontractor payment statistics, cus-
of effects in an attempt to uncover the to read. After the workshop, the author tomer satisfaction data, evidence of
chains of causality. The first workshop divided the diagrams into six areas, in community engagement; “considerate
entailed staff with an overview of the roughly temporal order, simply to make constructor” actions taken to increase
construction process, including direc- the diagrams readable, without chang- community satisfaction, such as behav-
tors, project, site, and commercial man- ing the logic. The language in the dia- ior codes near a school; employee post-
agers and planners; it was not clear grams was left as the informal language ers displayed around sites; architect
that there was sufficient knowledge of captured in the workshops. The use of selection scoring sheets, the supplier
the later stages of a project, so the sec- the workshops was a very efficient use database, supplier inquiry documen-
ond workshop also included Facilities of the time of the teams, which was very tation, and selected meeting minutes.
Management (FM). The maps were pro- limited; a study that sought to be fully The final report contained references
jected on a screen by the author, so all auditable would have spent a subse- to much of these data; however, the
workshop participants could see the quent phase revising and checking the main aim of the study (and this article)
causal structure being generated and logic of these diagrams; as they stand, was to uncover causality, root causes,
contribute explanations (all discussions however, they represent the views of and the systemicity within the causal
were led by the author rather than using the teams. The respondents felt they chains; the case study showed why the
the multi-computer “Group Explorer” “owned” the maps as a group, but the programs were successful, rather than
system, whereby all participants directly sources of individual inputs are deliber- quantifying the success, but this lack of
contribute to the model; Ackermann, ately not recorded, as is normal in such quantification should be recognized as
Andersen, Eden, & Richardson, 2010). studies (Eden & Ackermann, 1998). a limitation of this article.
The first part of each workshop Such workshops on single projects
sought to define “project success,” start- are not unknown, either in forensic The Case
ing from a “blank sheet of paper.” Fol- (e.g., Delay and Disruption) claims work The 140-year-old Sewell Group (Sewell,
lowing this, the diagram was built by (Williams, Ackermann, & Eden, 2003) or 2013), based in Hull, United Kingdom,

98 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


has an annual turnover over UK£100 unique or high risk undertaking which of the project?); and (5) sustainability
million (over US$150 million). Its main have to be completed by a certain date, (Will the positive impacts of the project
business is in estates, covering a range for a certain amount of money, within continue longer term?). Thus, a proj-
of activity. The Group has carried out some expected level of performance” ect such as the Sydney Opera House
construction projects in and around (p. 16). This threefold criterion of suc- or the Scottish Parliament, famously
Hull since the turn of the century under cess—meeting cost, schedule, and per- over budget and late, but producing
two major UK Government Public Pri- formance targets—has in the decades iconic buildings, might be considered
vate Partnership (PPP) programs involv- since become widely used as a standard unsuccessful in efficiency but effective;
ing complex partnership schemes. The success criterion often called the “iron Samset ’s ( 2009 ) Norwegian off-shore
first, Building Schools for the Future triangle.” Barnes ( 1988 ), sometimes torpedo battery (on time and on bud-
(BSF) (National Audit Office [NAO], credited with inventing the “iron tri- get but closed down by Parliament a
2009) aimed to refurbish or rebuild angle,” states (with particular reference week after opening) could be described
every secondary school in England over to construction projects) that “the cli- as successful in efficiency terms, but
15 years; the second, the Local Improve- ent’s objectives are always a combina- unsuccessful in impact, relevance, and
ment Finance Trust (LIFT) programs tion of the objectives for performance sustainability. Similarly, a project such
(National Audit Office [NAO], 2005), of the completed scheme, for achieving as the Three Gorges Dam appears suc-
involved building health facilities. From this performance within a named cost cessful in terms of efficiency, effective-
investing, through design and construc- or budgetary limit and for getting the ness, and relevance, but has been the
tion, to facilities management (FM), project into use by a target date” (p. 69). subject of considerable debate in terms
Sewell attempted to deal with a proj- By the late 1980s a wider definition of impact.
ect from inception to operation with a was being sought, which captured both Shenhar and Dvir (2007) have a not
seamless approach to try to maximize the success of the management of the dissimilar set of five measures, but bro-
value for money, buildability, and cus- project, and the success of the project ken down hierarchically (Fig. 2.1, p. 27);
tomer satisfaction. (While opportunities output. This was when the Project Man- one of their five measures though is
exist in the BSF program for FM, this is agement Institute held the conference an internal “impact on team,” a simi-
not part of the core offering from Sewell, noted earlier. Pinto and Slevin (1988) lar concept to that in Chipulu et al.
but all of the 12 completed LIFT build- brought in both the internal (project) (2014), discussed as follows. They also
ings incorporate FM involvement). With and the external (client) views. Mor- show conceptually how these measures
these two programs coming to an end, ris and Hough (1987) discussed project change in relative importance over
with the expectation that teams would success in terms of project functional- time (p. 31). A longer-term view is thus
start to be dismantled, this seemed to ity (did the project perform?), project required: How the success of a project is
be a good opportunity to try to capture management (the “iron triangle”), con- viewed will often depend on the phase
where the teams’ success came from, tractors’ commercial performance, and it is in, or how long it has been since the
if indeed they had been successful. It project cancellation (where relevant). project was completed. Some projects
became clear that there weren’t one or Perhaps the most influential framework seen as successful or unsuccessful are
two individual “magic bullets,” rather seeking thus to widen the definition seen quite differently in the longer term
a number of factors came together to was developed through work with the (e.g., Orlikowski & Yates, 2006).
produce success, strengthening the U.S. Agency for International Devel- Different stakeholders will often
approach taken. The workshops looked opment, then the United Nations and have quite different definitions of suc-
at the programs overall, but grounded OECD (Samset, 2010, Chapter 2). This cess and perceptions of what consti-
discussions in four cases—two schools characterizes a project’s success in five tutes project success. A comprehensive
and two health units—one of each being ways: (1) efficiency (Could the outputs literature survey in Davis (2014) shows
a notably larger contract than the other. have been produced in a better way? the evolution of the idea of project
Was the project well managed?); (2) success over successive decades and
Project Success effectiveness (Were the goals achieved? shows little commonality between the
It is clear that without an adequate Did the output meet the goals?); (3) definitions of senior management,
definition of project success, the per- relevance (How useful was the proj- project teams, and project recipient
formance of a company over a program ect to the organization in context? stakeholders. Research showing that
of projects cannot be assessed (Müller, Was the goal aligned with the needs project success is clearly related to an
Martinsuo, & Blomquist, 2008 ). But of the organization?); (4) impact (was agreed on and common view of suc-
what is project success? Steiner ’s (1969) the goal appropriate to the purpose of cess criteria between the stakeholders
definition of a project included: “Proj- the organization? What was the sum (Turner, 2004) becomes (while a valu-
ects generally involve large, expensive, of the anticipated/unintended effects able statement) almost a truism. The

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 99


Identifying Success Factors
PAPERS

necessity of engaging stakeholders and the long-term relationship between the from this literature is not the content of
their view of project success become supplier and buyer (Nixon, Harrington, the criteria, but the multiplicity of the
even more important in cases in which & Parker, 2011). factors and their overlapping nature.
project execution requires developmen- A single definition of “success” is We need to consider all the factors and
tal input from both the purchaser and clearly not possible; indeed, Nixon et al. their inter-relationships to capture the
supplier or from many stakeholders, (2011) describe a definition of project concept of “success.”
such as the value co-creation in major failure as “unattainable” (p. 212). Mül-
defense projects (Chang, Chih, Chew, & ler, Geraldi, and Turner (2012) use the Project Success and the
Pisarki, 2013). Some criteria are clearly “iron triangle plus nine other success Company
measurable but others are subjective or criteria” (p. 78), although in using these The company would not necessarily
psycho-social (Bryde, 2005). empirically they ignore one criterion have known all this academic literature;
This case is largely involved in the and use the mean of others, hence los- indeed the concept of the “iron triangle”
construction phase of PPP projects. But ing richness of the 10 different potential is so embedded in the project manage-
the advent of PPP is a key type of a dimensions in their definition. “Some ment culture generally that there is a
general move in construction manage- conceptualize [‘project success’] as a line of argument that the prevailing cul-
ment toward “servitized” construction, uni-dimensional construct concerned ture limits project managers from think-
in which the contractor takes increasing with meeting budget, time and quality… ing outside of this subconcept of project
responsibility for the post-construction whereas others consider project success success (see the Foucauldian argument
performance of the building, as dis- a complex, multi-dimensional concept of Hodgson, 2004). So what happened
cussed in Caldwell, Roehrich, and encompassing many more attributes” when the Sewell teams discussed how
Davies (2009). This turns the procure- (Mir & Pinnington, 2014, p. 203). Some they viewed project success? This was
ment activity to “procuring complex look to categorize sets of criteria: Shen- a discussion with no input of content
performance” (Lewis & Roehrich, 2009) har ’s empirical work (Shenhar, Tishler, from the facilitator so should reflect
rather than procuring a complex build- Dvir, Lipovetsky, & Lechler, 2002) used on the mindsets of the managers. After
ing, even if the client is not always fully 13 criteria divided into “meeting design considerable discussion, their defini-
aware of this. Caldwell et al. (2009) goals,” “benefits to customers,” and tion covered four related areas, which
therefore discuss how complex perfor- “commercial success and future poten- can be broken down into 17 subsec-
mance can be procured in the design tial.” Factor analysis can be used more tions, as shown in Table 1.
and construction phases of major con- formally to combine criteria, such as Table 1 shows a considerable appre-
struction buildings. They emphasize the Chipulu et al. (2014), who empirically ciation for the broader concepts of proj-
need for informal control and the key find two factors: one involving hard ect success. The “iron triangle” is there,
area of “trust and mutual commitment” goals and project control; the other although not highlighted as the first
within such construction—in a comple- project team management and intra- item (on-time and on-budget only com-
mentary role to the formal and con- organizational goals. (This is not to be ing into the second section)—and even
tractual structures (particularly within confused with the Success Factor work the efficiency definition is richer and
PPP; Zheng, Roehrich, & Lewis, 2008). discussed as follows, looking at the fac- more subtle, including changes, dis-
The need is even greater if we consider tors that create success.) The key finding putes, contracts, and health and safety.

Was the final product good? Did the project meet its delivery objectives?
1. Zero defects on building handover 1. On time
2. Low defects in use 2. On budget
3. Better FM service and resultant increased life cycle performance of the facility 3. Production of a legacy, not just a building
Were the stakeholders satisfied with the project? Was project management successful?
1. Happy customers 1. Good health and safety record
2. Happy users 2. Projects set up better and better contract
3. Happy subcontractors 3. Fewer changes
4. Happy Sewell team (which would of course lead to better project performance) 4. Fewer disputes
5. Good community relationships 5. Smooth/clean/tidy site
6. Predictability and control of cost, time, quality, and risk
Table 1: Success criteria.

100 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


The need to take all stakeholders into concludes that these issues “strongly be seen to have often identified and
account is clearly uppermost in the suggest that the approach has not been sometimes theorized success factors;
minds of these managers, including not successful,” p. 290). These criticisms however, there is little discussion about
only those with power in the project also apply to construction projects. the “how”—looking at the causality of
(customer, users, subcontractors, and There are essential lessons to be producing project success. To take one
the project team) but also the wider drawn from this literature—perhaps example, Nixon et al. (2011) claim that
community. Of particular note is the the needs for collaboration and com- “leadership performance is significantly
long-term perspective—the desire to munication being the most consistent important in determining project out-
leave “a legacy, not just a building.” It (e.g., El-Sheikh & Pryke, 2010). Increas- come,” but without seeing the relation-
could be argued that not all of these ingly, however, the success of projects ships, “further research [is] necessary to
are ultimate “success” criteria; we will has come to be seen to be context- better understand....” (p. 3). Some look
return to this point in the following dependent, with there being no one at moderating factors—looking at the
discussion. “right” answer. Shenhar and Dvir (2007) same variables, Müller et al. (2012), for
in particular (building upon Shenhar example find that project complexity
Success Factors: The Literature et al., 2002, as discussed earlier), show has a moderating effect between lead-
What are the factors that can lead to how determining success factors in all ership and success. For this article, the
project “success”? There has been much projects is context-dependent, and build earlier discussion about the multiple-
literature attempting to identify these up a structure of contexts involving the interacting criteria within the definition
factors; some of this work is popular extent of the project’s Novelty, Technol- of project success, would suggest that
with those looking for a “magic bullet” ogy, Complexity, and Pace (the well- there are likely to be multiple-interacting
or simple generalizations. Belassi and known four-dimensional “diamond” causal chains of factors producing proj-
Tukel (1996) summarize and classify model). Williams (2005) arrives sepa- ect success in this richer definition. This
what had been found by the mid-1990s rately at a not dissimilar structure of the will guide the case study.
and provide some general categories. extent to which a project is (structurally)
Much of the early work was through complex, uncertain, and time-limited. Case Findings
practitioner surveys: Pinto and Slevin PPP projects exhibit particular To show how the various factors come
(1987) and Pinto and Mantel (1990) attributes due to the long relationships together, the workshop maps show dia-
found 10 critical success factors (one of involved. Liu, Love, Smith, Regan, and grams of factors, the arrows showing
which is discussed below), which they Davis (2014) analyzed the normative causality. The workshop “success” defi-
found to be generalizable to a wide vari- literature on PPP success factors to nition (see above) is shown in these dia-
ety of applications. Cooke-Davies (2002) derive a set of factors within the differ- grams as highlighted shadowed boxes.
looks to answer not only “what factors ent lifetime phases of PPP infrastructure The maps, shown in Figures 1 through 6,
lead to project success?” but also “what projects, with different success factors consisted of six areas, roughly in causal
factors lead to a successful project?” within the initiation/planning phase, order. Company culture was seen above
and “what factors lead to consistently the procurement phase, and the part- to be a key factor and is the subject of
successful projects?” The last factor is nership phase. The case discussed in the first diagram; the second concen-
reflected in the findings that follow. this article was largely concerned with trates on a smaller area, the “Single
There are also a number of detailed the first of these two phases. Team”; the third map covers the project
case studies, which can provide some Beyond these attempts at making setup, which was also seen above as
insights, particularly through cross- a taxonomy of contexts, however, the important; then two smaller areas have
case comparisons, most notably in the literature now often draws conclusions been put into separate maps for ease of
seminal work of Morris and Hough about the success or failure of projects reading: customer satisfaction and sub-
(1987), which gave a framework, includ- within their specific contexts and histo- contractors and the construction site;
ing 84 factors grouped under 10 head- ries, which is how we will look at these the final map covers post-handover.
ings. In more complex and ill-defined projects in the following section. This
projects, such as IT systems projects, also aligns with the increasing concern Company Culture
the factors-based approach has been to research “projects as practice” look- The start of the causality lies within the
considerably criticized, because of the ing at the praxis, the practitioners, and company culture, as shown in Figure 1.
difficulty in definition; lack of empiri- the practices within the situated context Sewell has a family business ethos
cal validation; clarity between “factors” (Blomquist et al., 2010; Cicmil, Wil- rather than that associated with big
and “concerns”; prescriptiveness; and, liams, Thomas, & Hodgson, 2006). corporations. With a flat structure and
of course, the difficulty in defining suc- Looking at the situated context is lean form, the company considers that
cess (see specifically Sauer [1999], who also important, because research can it exhibits a bias for action, openness,

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 101


Identifying Success Factors
PAPERS

and expedient decision making, and The team of project managers appeared causality and that might not appear in
publicly declares a “no blame” environ- to exhibit higher leadership skills (as the general literature. One is the local-
ment. The company culture starts with distinct from project management skills), ity of the company: it is based in (and
leadership from the managing direc- known to be an important factor in proj- well-known in) the city; Hull is an east-
tor, exhibiting similar characteristics ect success (Nixon et al., 2011). How- coast city, somewhat geographically
and similar causal outcomes as those ever, there are other external factors at isolated within the United Kingdom,
described in Pillai and Meindl (1998). work, which can be seen to be roots of meaning that there is a strong sense of

127 “look local 91 s/c respect:


71 THE SINGLE TEAM
first” procurement Sewell delivering on
strategy their promises; pay 96 client sees that
15 relationship on time Sewell deliver on
between builders and promises and are
FM 21 behaviors doing their most
(Professional, 92 the Sewell
Positive, Team company culture
119 happy Sewell
Player, Customer 104 better
team
Focused, communication
Do the Right
Thing)
40 more interest by
105 delivery on
board in execution 52 Sewell site promises internally
culture (enforced) 31 trust— 20 concern for
empowerment of 54 higher leadership company brand
management 103 enables everyone
skills in project
to have a view
managers
55 leadership from across the Sewell
Paul Sewell Group
30 stability of
management—not
41 no blame culture
transient

22 open attitude to
defects 44 more flexible

18 locality
33 less layered
company—multi-role
management 32 size of company
118 manage risk (implies “intimacy”)
better
39 personal
28 focus on delivery
performance
29 attitude of the rather than systems
management
38 engagement with project manager— and processes
customer throughout individual brand
project
113 more individual
concern for the
company reputation

Figure 1: Company culture.

67 helping the
73 early workshops
client choose their
with everyone with 69 architect architect
plans—and culturally aligned (personality as well 12 early engagement
communicating with Sewell (and as company) with client
results to everyone with end-user)

15 relationship 82 partnership with


between builders and s/c
FM

71 THE SINGLE TEAM 76 s/c and designers


119 happy Sewell stay from
team pre-project through
project

92 the Sewell
4 team has already
company culture 26 development of done LIFT
100 no separate “Learning Teams”
estimating
department

Figure 2: The “single team.”

102 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


identification with the city and a close- • Externally, clients appear to see the in Figure 2. LIFT and BSF allowed the
knit community; the effect of being a company delivering on promises and company to follow the ethos of the influ-
local company in Hull is greater than doing its utmost in projects. The com- ential Latham Report (Latham, 1994),
that in a less isolated city. A second pany engenders respect from sub- which called for partnering (which
effect is the size of the company: big contractors as they are seen to be “includes the concepts of teamwork
enough to take on these projects, yet delivering and averaging payment between supplier and client, and of total
small enough that members of the man- times markedly lower than tender continuous improvement. It requires
agement team all know each other and expectations, resulting in the company openness between the parties, ready
the workforce has a sense of intimacy. being able to demand performance acceptance of new ideas, trust and per-
From these factors follow many from subcontractors and their best ceived mutual benefit” (p. 62), and the
ramifications (see Figure 1): (even requesting named) operatives. later Egan Report (Egan, 1998), which
• The concept of the “Single Team” is an also emphasized integrated process and
• One implication of the locality, as a important part of the culture as we will teams. The single team approach cov-
fairly isolated city, is that the manage- see as follows. ers subcontractors and designers stay-
ment of the company has been stable • The size and nature of the company ing from pre-project throughout the
rather than transient. Combined with enable management to have a view project; it includes early engagement
the size and the culture of the company across the Group, leading to better with the client and a close relationship
and its top-level leadership, this has communication. All staff members are between construction teams and those
important ramifications. The company encouraged to participate in top-level carrying out FM. It includes helping the
is less layered than usual, with teams business planning, including a regu- client choose their architect (personal-
reporting directly to the Board, mean- lar balanced scorecard. Weekly “hud- ity as well as company) and helping
ing that more trust is placed in the dles” are held across business units to to get an architect culturally aligned
empowered site based project manag- review issues encouraging feedback, with the company and end-user. It obvi-
ers and managers can work flexibly, with cross fertilization from members ates the need for a separate estimating
sometimes doing work that properly attending other huddles. department that prepares bids and then
lies in each other’s territories. • A “no blame” culture leads to an open “hands the project over” to the team
• Arising from these factors is a focus attitude to detection and discussion of (a well-known issue; e.g., Verner, Over-
on delivery rather than systems and defects and a better ability to manage myer, & McCain, 1999). Through this
processes. Although the company has risk. However, mediocre performance greater collaboration and consistency,
embraced Quality Systems (BS5750, is not accepted; Personal Improvement “learning teams” were formed, which
ISO 9001, Six Sigma), each employee Plans are used, and if performance is naturally gel together and improve
has Performance Agreements that go not improved, employees are required the product, from which, when rolled
beyond his or her role profile. There is to exit the company. At a site level, from scheme to scheme based on per-
more individual concern for the com- the use of warnings or even indefinite formance, bring continuous improve-
pany reputation within employees (as expulsions enables identification of ment to a program of work such as
indicated by company questionnaires), operatives not performing to the site that in LIFT or BSF (avoiding learning
and individual managers feel a per- induction’s expected levels. loss when teams are disbanded post-
sonal investment in the projects, lead- • Finally, company culture leads to a project; Williams, 2008). Innovation in
ing to more customer engagement. The site culture, including “skip level” small, project-based construction firms
company has established “behaviors” management where each employee is is known to come from “learning on the
upon which the company hires/fires encouraged to meet with the Managing job” (Barrett & Sexton, 2006).
and rewards: “Professional, Positive, Director, without his or her line man-
Team Player, Customer Focused, Do agement. This is supported by each Project Setup
the Right Thing”; all staff are required director participating in advertised The culture enables a range of effects
to buy into these fully. The locality of “back to the floor” days and attend- in project setup—often considered
the company means there is a strong ing sites across the company estate to the stage crucially determining suc-
concern for the company brand among work actively within the business at the cess (Williams & Samset, 2012). Figure
management. site level. 3 shows some of these effects. In this
• There is a noticeably high interest figure, two key concepts—numbers 92
within the Company Board in project The “Single Team” (“the Sewell culture”) and 71 (“the single
execution, known to be a success factor The idea of the “single team” is an team”)—are removed to make the dia-
in projects (Thomas, Delisle, & Jugdev, important part of the company culture; gram readable; however, the ramifica-
2002). this covers a range of issues as shown tions of these two concepts can be seen

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 103


PAPERS

104
(a) 113 more individual
79 get the right 95 work in finding concern for the
people around the out who are the company reputation
table stakeholders and who
are the actual 58 high-user 10 community
decision makers engagement engagement
18 locality

69 architect

February/March 2016
culturally aligned 12 early engagement 11 good community
67 helping the 61 significant
with Sewell (and with client relationship
64 pointing them to client choose their pre-planning
schemes you’ve done architect with end-user)
before so they can (personality as well
visualise as company) 23 on time
117 different
procurement
possibilities
60 long-standing
programme experience
(e.g., LIFT)
62 projects set up
68 managing better with a better 37 happy customer
63 engagement of all expectation 104 better
contract
other groups communication
Identifying Success Factors

31 trust—
119 happy Sewell empowerment of
97 uncertainties and team management
66 identifying all risks either ironed
the stakeholders out or
early well-allocated
24 on budget

96 client sees that


Sewell delivers on
promises and are
50 few disputes doing their utmost

80 Sewell provides
project leadership 28 focus on delivery
as well as project rather than systems 100 no separate

■ Project Management Journal ■ DOI: 10.1002/pmj


management and processes estimating
department

(b) 28 focus on delivery (c)


99 time and rather than systems 41 no blame culture
commitment given to and processes 58 high-user 79 get the right
71 THE SINGLE TEAM
risk workshops— engagement people around the 80 Sewell provides
rather than doing table project leadership
paper exercise
as well as project
115 better product management
118 manage risk
better
73 early workshops
126 risks identified with everyone with
early, properly plans—and
23 on time 77 understanding
allocated and communicating final result before
managed 62 projects set up results to everyone
128 predictability it comes
better with a better
contract and control of cost,
time, quality, and 30 stability of
risk management—not
74 everyone buys transient
76 s/c and designers into process and
stay from timescale
24 on budget pre-project through
project
96 client sees that
50 few disputes 75 fewer changes
Sewell delivers on
promises and are
doing their most

Figure 3: Project setup.


throughout the diagram. There are also process and timescale; users and clients are identified early, properly allocated
two other inputs to this diagram, specific understand the final result in advance; by the “single team,” allocated on the
policies pursued by the company as part there are fewer changes (see Figure 3c) basis of who is the most appropriate
of stakeholder management: identify- as the project proceeds; many issues to accept or manage that risk, assigned
ing all the stakeholders early, and work are avoided rather than retrospectively the proper action (management, mitiga-
in finding out who the actual decision addressed (thus, blame is avoided); and tion, or removal) and costed with the
makers and stakeholders are (see, e.g., people are encouraged to help resolve benefit of that action remaining with the
Sutterfield, Friday-Stroud, & Shivers- arising issues. One of Pinto and Mantel’s owner of the risk. This leads to a good
Blackwell, 2006, for the dangers of not (1990) 10 critical success factors was project setup with a better contract and
doing this). Figure 3 has been divided “Communication, consultation, and fewer disputes. Predictability and con-
into three parts to help readability: Fig- active listening to all impacted parties.” trol of cost, time, quality, and risk help
ure 3(a) contains most of the material The engagement of all groups helps to lead to delivery on bid and commu-
but interlinked with these are specific to manage expectations, which leads nity promises.
parts separated into Figure 3(b,c). There to better project setup and contracts. Long-standing program experience
are many “causal chains” here, which Consistency of personnel—across the enables the company to point users
feed into the various project success company, supply chain, and client to previous schemes to help visualize
criteria, outlined as follows. teams, for the duration of the project, the product, which enhances engage-
The focus on delivery rather than with minimal changes, all buying into ment and helps the client choose the
systems and processes (and project lead- the design, program, financial position, architect. High early user engagement
ership as well as project management) risks, and construction method—helps shows the client the different procure-
leads to a number of initial meetings lead to greater collaboration. Fewer ment possibilities. Early engagement
(initial representation of organiza- disputes, significant pre-planning, bet- with the client and visible efforts to
tions’ board of directors establishing ter project setup and contract, better achieve delivery on promises keeps
the right attendees); early workshops communication, and better manage- the client satisfied and results in fewer
with all stakeholders with plans (and ment of risk all help to create confi- disputes.
the results communicated to every- dence in the “iron triangle.” The locality and the individual con-
one); and time and commitment given Figure 3(b) shows the treatment of cern for the company reputation lead
to risk workshops. Pre-planning means risk (a critical success factor in Liu et al., to close community engagement, which
that risks are either resolved or well- 2014). As is good practice (Association combined with the high level of pre-
allocated; stakeholders “buy into” the of Project Management, 2004 ), risks planning leads to good community

19 continual
involvement in
following 12 months
(rather than
snagging team)
109 handover between
16 low defects in 7 zero defects on
construction and
use building handover
operations “soft
landing”
37 happy customer
115 better product
119 happy Sewell
team

96 client sees that


Sewell deliver on 12 early engagement
promises and are with client
50 few disputes
doing their utmost

56 faster response 6 consistent


times construction partner
for LIFT (market
tested)

108 round-table 38 engagement with


meeting 6 months customer throughout
before completion project

Figure 4: Customer satisfaction.

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 105


Identifying Success Factors
PAPERS

114 transmitting
Sewell culture 35 using same
127 “look local
supply-chain on 47 well-defined
18 locality first” procurement 93 commitment from multiple projects robust s/c database
strategy s/c (LIFT)—
relationships built
23 on time 7 zero defects on
building handover
53 effort by Sewell
in relationship with 48 shared goals with
94 better s/c s/c s/c
40 more interest by
board in execution performance

31 trust— 9 good H&S record


empowerment of 24 on budget
management
45 happy s/c
83 use of s/c in
many schemes
119 happy Sewell
team 82 partnership with
s/c
76 s/c and designers
stay from
46 smooth/clean/ pre-project through
52 Sewell site 91 s/c respect: project
tidy site
culture (enforced) Sewell delivering on
their promises; pay
on time
87 enquiries:
document presented
81 s/c involvement to s/c at enquiry
in the bidding—“if meeting
you win it, we win 89 post-tender
it” meeting—s/c
88 setting s/c commercial guys
expectations
98 excellent site
facilities 90 pre-commencement
meeting—with s/c
85 the “10 minute delivery; also
rule” induction meeting

Figure 5: Subcontractors and the construction site.

relations. This is increasingly recognized and Khadaroo ( 2010 ) that “satisfac- ect team (rather than a snagging team)
as an important success factor: Smit tion levels in school PFI projects relate in the 12 months after handover, lead-
(2001) in describing his Eden project to the extent of involvement with the ing to very low numbers of defects on
says “[a] mountain of paperwork, a scheme” (p. 18); although again, this is handover and in use.
design team from heaven and some up- partially context dependent since the
country big cheeses count for nothing in authors continue: “bigger PPP schemes Subcontractors and the
Cornwall without local support” (p. 103). may militate against this because com- Construction Site
Key site statistics are clearly displayed promises are more likely to be made in The way the company procures and
on the site board giving openness on the bigger schemes” (p. 18) (“bigger” treats subcontractors and the way it
key performance indicators (KPIs) (e.g., here means those above £20 million keeps construction sites, flow from
accident rates, recycling, program posi- [US$30 million]—approximately half of many of the ideas above (see Figure 5).
tion, apprentice numbers, local labor, the projects studied in the current study Again, the “company culture” has been
and local spend. Investment in better- fall into this category). Second, the long left off this diagram to aid readability,
than-expected site facilities creates an exclusive relationship with LIFT over but the consequences of the culture can
experience and sets the tone of what is a number of projects enables an early be seen throughout the diagram. The
expected from those entering the site. engagement with the client and a better company puts much effort into sub-
product. Few disputes on the project contractor relationships; it has a good
Customer Satisfaction help customer satisfaction, as does the subcontractor database and has been
In terms of the theory of Treacy and client seeing the company deliver on using the same supply-chain on mul-
Wiersema (1993), the company has pro- promises and doing its utmost (mirror- tiple projects in each program, build-
gressed through exceling at “customer ing the importance of trust in the work ing good relationships, and enabling
intimacy” while being above standard of Roehrich, Lewis, Caldwell et al., dis- the realization of efficiencies. With
in operational excellence and prod- cussed above). A final factor is a prod- the locality of the company, there is a
uct leadership. Customer satisfaction uct that functions better, for various “look local first” procurement strategy.
comes from a combination of factors reasons; there is a round-table meet- This helps to build close partnerships,
(Figure 4). First is engagement with ing six months before completion and with subcontractors staying from pre-
the customer throughout the project a handover between construction and project through the end of the proj-
and subsequent response times. This operations to provide a “soft landing” ect. The subcontractor is involved in
agrees with the findings in Demirag and continual involvement by the proj- the bidding, helping to build shared

106 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


106 involvement of
final permanent FM 32 size of company
107 better FM presence and (implies “intimacy”)
60 long-standing service
83 use of s/c in program experience 14 experience of help-desk people
many schemes (e.g., LIFT) other LIFT defects during execution

108 round-table
meeting 6 months 69 architect
84 FM s/c same on 109 handover between
7 zero defects on before completion
earlier schemes construction and culturally aligned
building handover
operations “soft with Sewell (and
landing” with end-user)

12 relationship
37 happy customer 38 engagement with
between builders and
customer throughout
FM
project
23 on time

50 few disputes
29 attitude of the 120 an engaged
project manager— community prepared
individual brand 19 continual for its asset and
involvement in prepared to look 46 smooth/ clean/ 24 on budget 116 buildability
following 12 months after it tidy site
(rather than
snagging team)
11 good community
10 community
relationships
engagement
22 open attitude to 123 apprenticeships 124 engagement with
18 locality
defects throughout the schools
127 “look local
supply chain 125 formation of a
first” procurement
Skill Academy by
strategy
121 legacy, not just Sewell
20 concern for
company brand building
122 wealth captured
locally

Figure 6: Post handover.

goals. At the inquiry stage a docu- than the industry average (from gov- customer throughout the project and
ment is presented to the subcontrac- ernment statistics [Health and Safety the emphasis on customer satisfaction,
tor to help establish expectations, and Executive, 2012]) and fewer defects. help minimize disputes during and after
there is a post-tender meeting with construction, aided in part by enhanced
the subcontractor commercial team. Post Handover client training during the soft landing
For the subcontractor delivery team, The after building handover is shown in period, and the “no blame” philosophy.
there is a pre-commencement meet- Figure 6. Concentration on the capital The locality of the company and man-
ing and site-specific induction meet- delivery with insufficient attention to agement’s concern for company brand
ings, all helping build the “single team,” later operation has been identified as the means there is continual involvement
with the company culture transmitted reason for poor quality in, for example, in the project during the 12 months fol-
throughout. This partnership leads to the Millenium Dome (National Audit lowing handover, rather than sending in
commitment and respect from subcon- Office [NAO], 2000). A long-term main- a “snagging team” (a separate team that
tractors, helping performance; along tenance responsibility beyond comple- rectifies minor faults). The open atti-
with the company ethos, this results in tion could be expected to encourage tude toward defects and the personal
the subcontractor being well placed to design and build quality. In light of investment by the project manager in
continue working throughout the pro- this, the company tries to “feel” like the project make this process open and
gram. Company sites are notably clean the end-user through FM; this team is efficient in ensuring minimum disrup-
and tidy (a rule enforced is that the last part of the single team throughout the tion caused by defects post-handover.
10 minutes of the day are spent tidying process, giving the client confidence. Success in the longer term, as dis-
the site), which helps promote pride Liu et al. (2014) discusses the often cussed above, includes a measure of
and commitment to the project and under-recognized importance of this as how the client and end-user feel after
makes work more efficient and mutually a success factor. one year in the new building; the low
reinforcing. Better subcontractor per- With the long-standing program levels of contractual penalties incurred
formance and the smooth, clean, tidy experience of typical defects, plus the by the company perhaps show how that
site, combined with the interest by the relationship between the construc- manifests itself in reality. In the case
board in execution and the empowered tion and FM teams (either from the of the LIFT buildings, landlord carries
project management, all lead to better company group, or known from earlier out regular customer feedback surveys
“iron triangle” performance and also a schemes), there are minimal defects and these are used to further improve
much better health and safety record during handover. Engagement with the facilities management (FM). Using an

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 107


Identifying Success Factors
PAPERS

architect culturally aligned with the been high,” the majority of the increase company “behaviors”; and the higher
company and end-user helps produce a in estimated total costs from the origi- leadership skills possessed by the proj-
buildable design and enhances engage- nal estimates was “because the Depart- ect managers. Four others identify the
ment with the customer during the ment has increased the scope of the key principles in how projects are car-
project. The meeting six months before program,” and “the total capital cost ried out: identifying all stakeholders
completion establishes issues, and the of each BSF school…is similar to most early; work in finding out who the stake-
tidy site helps the “soft landing.” This other schools”; furthermore, “early evi- holders and actual decision makers are;
combined with the involvement of the dence shows that having a [Local Edu- “engagement with schools” and a well-
final permanent FM presence and “help cation Partnership] can lead to time defined robust subcontractor database.
desk” staff during execution of the proj- and cost savings on repeat procure- Finally, there is a strategic decision of a
ect (the smaller company helps pre- ments” (“key findings” in NAO, 2009, carefully planned expansion with BSF/
serve these relationships rather than a pp. 6–7). In this case, we didn’t have LIFT.
distant unknown “help desk”) all lead to access to financial data, but in terms Similarly, the seven “heads” (the
better FM service. of the multiple inter-linked criteria of ends of the causal chains) can be ana-
We have already seen the impor- Table 1, evidence of good success was lyzed. These might be expected to be
tance placed on good community seen in much of what was mentioned the (shaded) “success criteria,” but
relationships: an important effect of above. This include low defects both these are inter-linked and thus not all
this post-handover is that it leaves an on building handover and in use; good “heads.” It could thus be argued that
engaged community prepared for its FM service; stakeholder satisfaction not all of these are ultimate “success”
asset and prepared to look after it. It across the spectrum of stakeholders criteria. For example, “projects set up
is important for the community that (customer, user, subcontractor, project better with a better contract” or “pre-
what is left is a legacy, not just a build- team, and considerable support from dictability and control of cost, time,
ing. In the case of these projects, this the local community); good buildings quality, and risk” lead to many other
includes the company’s “look local first” provided; good health and safety record good outcomes, so could be argued to
procurement strategy, wealth captured and smoothly run projects, as well as be important determinants of success,
locally, apprenticeships throughout the the standard “iron triangle” of on time/ but not actual success criteria. Even
supply chain, and engagement with cost/budget. Furthermore, the empha- a “smooth/clean/tidy site” ultimately
schools leading to the formation of a sis on consistent teams that learned on does not matter—but having such a
skills academy. long-run programs would support the site during the project produces a good
last of the National Audit Office findings health and safety record, happier sub-
Success above. This study shows why this com- contractors, and a more efficient proj-
The aim of this article is to show the pany might have performed better and ect. Using this multi-criteria definition
systemicity within the causal chains has identified some “root causes” and of success facilitated the identification
leading to success, rather than an audit their combination, as discussed in the of this causality. Interestingly, there is
of whether these were actually “suc- Conclusion below. one “head” that is not a success crite-
cessful” projects; however, the second rion: “an engaged community prepared
part of the study looked for evidence Analysis of the Map for its asset and prepared to look after
(statistical or cases) to support or refute A formal analysis of this complex map of it,” which is an explanation of reasons
the statements. BSF as a program was causality provides some useful results. for wanting one of the success criteria
significantly criticized by the incom- The analysis and clustering methods (“good community relations”).
ing government as being “characterized within Decision Explorer (Eden & Ack- “Centrality” analysis indicates the
by massive overspends, tragic delays, ermann, 1998) are used here to carry influence of concepts within the causal
botched construction projects, and this out. structure. This is not a definitive mea-
needless bureaucracy” (BBC, 2010) and First, the 12 “tails” (roots of causal- sure of concept importance, but gives
unstarted projects in the program were ity) of the map can be seen exogenously an indication and is useful for initiating
stopped. A more independent study by initiating chains of causality. We have a discussion. The most central con-
the National Audit Office the following identified three of these as important cept in this map was the “Single Team.”
year, however, concluded that, while facilitators to success: the company This might be a function of the way
the program was “overly optimistic in locality; the company size; and the long- the workshops were facilitated, but
their assumptions of how quickly the standing program experience. Four deal probably does indicate the importance
first schools could be delivered” and with the type of company that has devel- placed upon this concept by the team.
that “the costs of establishing the first oped: the company culture; the leader- The next most central concepts, inter-
[Local Education Partnerships] have ship from the managing director; the estingly, were trust/empowerment of

108 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


management, and a happy company practically as we try to measure the per- to be inhibited (for unwanted “vicious
team followed by the company culture. formance of project teams. circles”).
This shows the importance of the com- Second, the case showed that in The article did not explore these
pany culture and its management for the same way that success is defined by concepts quantitatively, and thus must
developing success. The next two most multiple interacting criteria, success is be considered a limitation. Further
central concepts were a “happy cus- achieved by multiple interacting factors. research could go further in the mod-
tomer” and early engagement with the Previous research has often identified eling “cascade” of Howick, Eden, Ack-
client, showing the importance of cus- and sometimes theorized success fac- ermann, and Williams (2008) to try to
tomer engagement to the company per- tors, but rarely looked at the interacting model these interactions. Nor did the
formance of projects. Following these in causal chains. This article has demon- study fully audit all of the statements
the list of centrality were many concepts strated some factors, but more impor- and causal links in the case, as it was
together, not surprisingly in the context tantly shown how they interact, and seeking explanations and indications
of a highly inter-related map. how to map out, analyze, and under- rather than a forensic audit.
Finally, a standard analysis of such stand these causal paths. Searching for The study did show, however, impor-
maps is to look for feedback. Partly due success factors that do not recognize tant aspects that resulted in project
to the fairly loose, informal, data col- this complexity; risks arriving at over- performance success for this particular
lection, there are thousands of loops in simplistic conclusions, which might not company and why these root causes are
the data. But even an informal analysis lead to success in this wider definition important. Some of these are generic
of Figure 5 shows examples of rein- and might indeed inhibit some of the lessons applicable to other organiza-
forcing loops of behaviors: keeping the success criteria. tions, whereas some are context depen-
same subcontractors from pre-project Learning lessons from individual dent for the company in its current
through execution; increasing sub- projects is increasingly recognized as an situation.
contractor satisfaction and partner- important element in improving proj-
ing, leading to better performance and ect-management practice (Williams, • Organizational culture. Performance
more frequent use on the same program 2008), but the root causes of project suc- was reasonable on the “hardware” of
(which leads to the “learning teams”); cess/failure can be difficult to discern systems, process, structure, and so
mutual respect between contractor and even in individual projects. This article forth, but was particularly strong on
subcontractor, and so on. has taken methods that can be used in the “software” or leadership aspects
An analysis of such maps can thus individual projects (Williams, 2004) and of culture, communication, and stake-
show the root causes of project suc- has used them to encompass the project holder engagement. It may be difficult
cess, and how these feed through causal management practice within an organi- to replicate this by initiative or policy;
chains to produce that success—often zation overall, in a program of projects. this may be easier in a family type of
ideas and linkages difficult to see con- This moves the discourse from learning company or where a longer-term view
ceptually. Analysis can indicate the from one project to the next, onto con- may prevail over the need for shorter-
most important factors and why these sidering the organization as a learning term results.
factors are important. And where posi- organization and considering the orga- • The company’s sense of locality and
tive “virtuous circle” feedback can be nizational, cultural, and environmental size. The Sewell company is large and
observed, this provides useful areas for factors that can lead to success or failure sophisticated enough to pre-qualify
management to concentrate upon. in a program of projects. This analy- and be appointed to these national
sis can complement the more focused programs, but small and local enough
Conclusions and Discussion analysis on an individual project. to care about the community served
This study set out first to explore the The analysis described here can that it would call its own; this produces
multi-faceted nature of success. The provide management with useful and an acute sense of brand reputation
study illustrates the increasingly rec- sometimes unexpected insight. Analysis and hence a motivation to keep prom-
ognized nature of project success as can show the important concepts driv- ises and leave a legacy beyond the
being multi-dimensional, with different ing the causal structure and explain how buildings. The sense of “place” and
criteria, only some clearly measurable. (for example) “management empower- consequent ownership appear to be
However, the causal approach (as in ment” actually leads to more success important and give a more holistic,
Eden & Ackermann, 1998; Edkins et al., in projects. Identification of positive long-term approach.
2007) showed in this case how the cri- feedback loops illustrate areas where • The adoption of Latham’s “single team”
teria are not independent but come promoting concepts will be particu- approach, from project inception to
together in complex causal interactions. larly beneficial (for desirable “virtuous building operation. This expanded
This is important conceptually, but also circles”) or where these concepts need the definition of “project” to a wider

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 109


Identifying Success Factors
PAPERS

and longer concept. The supply chain Banxia. (2013). Decision explorer. management: Researching the actuality
was procured on more than purely a Retrieved from http://www.banxia.com/ of projects. International Journal of
commercial basis, producing mutual dexplore/ downloaded February 2013. Project Management, 24(8), 675–686.
respect and a sharing of long-term Barnes, M. (1988). Construction project Cooke-Davies, T. (2002). The “real”
aims and values. Facilities Manage- management. International Journal of success factors on projects. International
ment was part of the single team and Project Management, 6(2), 69–79. Journal of Project Management, 20(3),
ensured stakeholders’ views were rep- Barrett, P., & Sexton, B. (2006). 185–190.
resented, helping to guarantee design Innovation in small, project-based Cooke-Davies, T. (2011). Aspects of
and build quality. The frequent frag- construction firms. British Journal of complexity. Newtown Square, PA: Project
mentation of design, build, and FM, Management, 17(4), 331–346. Management Institute.
which produces friction at the inter-
BBC. (2010). School building Davis, K. (2014). Different stakeholder
faces, was absent, allowing risks to be
scheme scrapped. BBC News website, groups and their perceptions of project
better managed.
Retrieved from http://www.bbc.co.uk/ success. International Journal of Project
• The study also brought out (a little less
news/10514113 Management, 32(2), 189–201.
strongly) the main aspects of Latham
(1994) and Egan (1998) in having the Belassi, W., & Tukel, O. L. (1996). de Wit, A. (1986, September). Measuring
luxury of a pipeline program of proj- A new framework for determining project success: An illusion. Measuring
ects to encourage “learning teams” critical success/failure factors in success, proceedings of the 18th annual
to pursue demonstrable continual projects. International Journal of Project seminar/symposium of the Project
improvement and be kept together and Management, 14(3), 141–151. Management Institute, Montreal, Canada
appointed for the following project. Blomquist, T., Hallgren, M., Nilsson, (pp. 13–21). Newtown Square, PA:
A., & Soderholm, A. (2010). Project- Project Management Institute.
None of these is uncommon in the as-practice: In search of project Demirag, I., & Khadaroo, I. (2010).
literature or practical rhetoric. In these management research that matters. Costs, outputs and outcomes in school
projects, however, (Sewell’s Building Project Management Journal, 41(1), 5–16. PFI contracts and the significance
Schools for the Future and NHS SIFT Bryde, D. J. (2005). Methods for of project size. Public Money &
Programs, 2008–2013), multiple good managing different perspectives of Management, 30(1), 13–18.
practices and principles, and context, project success. British Journal of Eden, C., & Ackermann, F. (1998). The
appear to have come together in a Management, 16(2), 119–131. journey of strategic change. Chichester,
combination in which the total effect England: Sage.
Caldwell, N. D., Roehrich, J. K., &
is much greater than the sum of the Edkins, A. J., Kurul, E., Maytorena-
Davies, A. C. (2009). Procuring complex
parts—a “perfect storm” perhaps of Sanchez, E., & Rintala, K. (2007).
performance in construction: London
good fortune and good practice, to the The application of cognitive mapping
Heathrow terminal 5 and a private
benefit of clients, end-users, and the methodologies in project management
finance initiative hospital. Journal of
community served. research. International Journal of Project
Purchasing and Supply Management,
15(3), 178–186. Management, 25(8), 762–772.
References Chang, A., Chih, Y.-Y., Chew, E., & Egan, J. (1998). Rethinking construction:
Ackermann, F., Andersen, D. F., Eden, Pisarki, A. (2013). Reconceptualising Report of the construction task force.
C., & Richardson, G. P. (2010). Using a mega project success in Australian London, England: HMSO.
group decision support system to add defense: Recognizing the importance of El-Sheikh, A., & Pryke, S. D. (2010).
value to group model building. System value co-creation. International Journal Network gaps and project success.
Dynamics Review, 26(4), 335–346. of Project Management, 31(8), 1139–1153. Construction Management and
Ackermann, F., & Eden, C. (2001). Chipulu, M., Ojiako, U., Gardiner, P., Economics, 28(12), 1205–1217.
Contrasting single user and networked Williams, T., Mota, C., Maguire, S., Health and Safety Executive. (2012).
group decision support systems. … Marshall, A. (2014). Exploring the Annual statistics report 2011/2012.
Group Decision and Negotiation, 10(1), impact of cultural values on project Retrieved from http://www.hse.gov.uk/
47–66. performance. International Journal of statistics/overall/hssh1112
Association of Project Management Operations and Production Management, Hodgson, D. E. (2004). Project work:
(2004). Project risk analysis and 34(3), 364–389. The legacy of bureaucratic control in
management guide (2nd ed.). High Cicmil, S., Williams, T., Thomas, J., & the post-bureaucratic organization.
Wycombe, England: APM. Hodgson, D. (2006). Rethinking project Organization, 11(1), 81–100.

110 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj


Howick, S., Eden, C., Ackermann, 28 session 2005–2006. London, England: Rethinking management information
F., & Williams, T. (2008). Building The Stationery Office. systems: An interdisciplinary perspective
confidence in models for multiple National Audit Office. (2009, (pp. 279–309). Oxford, England: Oxford
audiences: The modelling cascade. February 12). The building schools for University Press.
European Journal of Operational the future programme: Renewing the Sewell. (2013). Sewell….powered by you.
Research, 186(3), 1068–1083. secondary school estate. Report by the Retrieved from http://www.sewell-group
Latham, M. (1994). Constructing the comptroller and auditor general, HC 135 .co.uk/
team. London, England: HMSO. session 2008–2009. London, England: Shenhar, A. J., & Dvir, D. (2007).
Lewis, M. A., & Roehrich, J. K. (2009). The Stationery Office. Reinventing project management: The
Contracts, relationships and integration: Nixon, P., Harrington, M., & Parker, diamond approach to successful growth
Towards a model of the procurement D. (2011). Leadership performance and innovation. Boston, MA: Harvard
of complex performance. International is significant to project success or Business School Press.
Journal of Procurement Management, failure: A critical analysis. International Shenhar, A. J., Tishler, A., Dvir, D.,
2(2), 125–142. Journal of Productivity and Performance Lipovetsky, S., & Lechler, T. (2002).
Liu, J., Love, P. E. D., Smith, J., Regan, Management, 61(2), 204–216. Refining the search for project success
M., & Davis, P. R. (2014). Life cycle Orlikowski, W., & Yates, J. (2006). factors: A multivariate, typological
critical success factors for public-private ICT and organizational change: A approach. R&D Management, 32(2),
partnership infrastructure projects. commentary. Journal of Applied 111–126.
Journal of Management in Engineering. Behavioral Science, 42(1), 127–134.
Smit, T. (2001). Eden. London, England:
doi:10.1061/(ASCE)ME.1943- Pillai, R., & Meindl, J. R. (1998). Corgi Books.
5479.0000307 Context and charisma: A “meso” level
Steiner, G. A. (1969). Top management
Mir, F. A., & Pinnington, A. H. examination of the relationship of
planning. New York, NY: MacMillan.
(2014). Exploring the value of organic structure, collectivism, and crisis
project management: Linking project to charismatic leadership. Journal of Sutterfield, S., Friday-Stroud, S. S.,
management performance and project Management, 24(5), 643–671. & Shivers-Blackwell, S. L. (2006). A
success. International Journal of Project case study of project and stakeholder
Pinto, J. K., & Mantel, S. J. (1990).
Management, 32(2), 202–217. management failures: Lessons learned.
The causes of project failure.
Project Management Journal, 37(5),
Morris, P. W. G., & Hough, G. H. (1987). IEEE Transactions on Engineering
26–35.
The anatomy of major projects: A study Management, 37(4), 269–276.
of the reality of project management. Pinto, J. K., & Slevin, D. P. (1987). Thomas, J., Delisle, C. L., & Jugdev, K.
London, England: Wiley. Critical factors in successful project (2002). Selling project management to
implementation. IEEE Transactions on senior executives: Framing the moves that
Müller, R., Geraldi, J., & Turner,
Engineering Management, 34(1), 22–27. matter. Newtown Square, PA: Project
J. R. (2012). Relationships between
Management Institute.
leadership and success in different Pinto, J. K., & Slevin, D. P. (1988). Project
types of project complexities. success: Definitions and measurement Treacy, M., & Wiersema, F. (1993).
IEEE Transactions on Engineering techniques. Project Management Journal, Customer intimacy and other value
Management, 59(1), 77–90. XIXX(1), 67–72. disciplines. Harvard Business Review, 71,
Müller, R., Martinsuo, M., & Blomquist, Samset, K. (2009). Projects, their quality 84–93.
T. (2008). Project portfolio control and at entry and challenges in the front-end Turner, J. R. (2004). Five conditions for
portfolio management performance in phase. In T. M. Williams, K. Samset, & project success. International Journal of
different contexts. Project Management K. Sunnevåg (Eds.), Making essential Project Management, 22(5), 349–350.
Journal, 39(3), 28–42. choices with scant information: Front- Verner, J. M., Overmyer, S. P., & McCain,
National Audit Office. (2000). The end decision-making in major projects, K. W. (1999). In the 25 years since The
millennium dome. Report by the Chapter 2. Basingstoke, England: Mythical Man-Month what have we
comptroller and auditor general. HC 936 Palgrave Macmillan. learned about project management?
session 1999–2000. London, England: Samset, K. (2010). Early project Information and Software Technology,
The Stationery Office. appraisal. Basingstoke, England: Palgrave 41(14), 1021–1026.
National Audit Office. (2005, Macmillan. Williams, T. M. (2004). Identifying
May 19). Innovation in the NHS: Local Sauer, C. (1999). Deciding the future the hard lessons from projects—
improvement finance trusts. Report by for IS failures: Not the choice you might easily. International Journal of Project
the comptroller and auditor general, HC think. In W. L. Currie & R. Galliers (Eds.), Management, 22(4), 273–279.

February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj 111


Identifying Success Factors
PAPERS

Williams, T. M. (2005). Assessing and Zheng, J., Roehrich, J. K., & Lewis, M. projects—both pre- and post-project—and was with
moving on from the dominant project A. (2008). The dynamics of contractual a team supporting over US$1.5 billion post-project
management discourse in the light of and relational governance: Evidence Delay and Disruption claims. In 2005, Terry joined
project overruns. IEEE Transactions from long-term public-private Southampton University, a center for PRM research,
on Engineering Management, 52(4), procurement arrangements. Journal of where he later became director of the School of
497–508. Purchasing and Supply Management, Management, and then joined Hull University
Williams, T. M. (2008). How do 14(1), 43–54. Business School as Dean in 2011. He has continued
organisations learn lessons from his work in consulting and research. Terry speaks
projects—and do they? IEEE Transactions and writes on project modeling, which includes
on Engineering Management, 55(2), Terry Williams has degrees in Mathematics, approximately 70 project management/OR journal
248–266. Operational Research (OR), and Engineering Production articles, and a number of books on modeling projects,
Williams, T. M., Ackermann, F. R., & from Oxford University and Birmingham University learning from projects, project governance, front-end
Eden, C. L. (2003). Structuring a delay in England. Terry worked in OR for nine years at analysis, as well as professional OR. He is a Project
and disruption claim. European Journal Engineering Consultants YARD, developing Project Management Professional (PMP)® certification holder
of Operational Research, 148(1), 192–204. Risk Management (PRM) and acting as a risk manager and has edited a leading academic journal; he was
for major defense projects. He joined Strathclyde on the United Kingdom’s “REF” panel and the PMI
Williams, T. M., & Samset, K. (Eds.).
University in 1992, where he became Professor of Academic Members Advisory Group, and is a
(2012). Project governance: Getting
OR and Department Head and continued research/ Fellow of various institutes. He can be contacted
investments right. Basingstoke, England:
consultancy, modeling the behavior of major at terry.williams@hull.ac.uk
Palgrave Macmillan.

112 February/March 2016 ■ Project Management Journal ■ DOI: 10.1002/pmj

You might also like