You are on page 1of 8

Renewable Energy 147 (2020) 1231e1238

Contents lists available at ScienceDirect

Renewable Energy
journal homepage: www.elsevier.com/locate/renene

Real-time inspection and determination methods of faults on


photovoltaic power systems by thermal imaging in Turkey
M. Cubukcu*, A. Akanalci
Solar Energy Institute, Ege University, 35100, Bornova, Izmir, Turkey

a r t i c l e i n f o a b s t r a c t

Article history: In recent five years, the capacity of photovoltaic power systems (PVPS) based on solar energy had a
Received 2 February 2019 significant improvement in Turkey. Approximately 1.8 GWp PVPS was installed in 2017 and reached to
Received in revised form 5.062 GWp cumulative capacity at the end of the year 2018. In this development phase, it is critical to
10 August 2019
ensure a long-term high quality of PV power generation. To achieve a sustainable development, the
Accepted 15 September 2019
quality inspections has to be in place. It assures that expected commercial gains are caught and PV plants
Available online 18 September 2019
achieve a long service life. On-site testing of PVPS is very helpful to evaluate the real performance of the
plant and diagnose the failures. When compared to other inspection methods, the most time-efficient
Keywords:
Photovoltaic power systems
one is infrared thermal imaging (IRT) of the PV modules and also the electrical components. In this
Fault detection study, the results of IRT inspection for 19 different PVPSs in Turkey (115.36 MWp in total) is presented.
Thermal imaging The diagnosed defects were classified according to the failure type and the number of them were
Quality check normalized per MWp to evaluate the most frequently observed issues during the field tests. The
experimentation, both in terms of accuracy and processing time, confirms the effectiveness and the
efficiency of the thermal imaging approach. The results also showed that the sampling rate of testing is
very critical to get a right comparison and failure types are mainly caused due to active bypass diodes and
hotspots on PV modules, non-operative modules and strings, abnormally heated cables/fuses/breakers
and interconnection points.
© 2019 Published by Elsevier Ltd.

1. Introduction been an attractive investment for any investors with small or large
scale budgets in Turkey. Approximately 1.8 GWp PVPS was installed
Despite the fossil fuels still constitute a large share of total final in 2017 and a growth which was greater than in any European
energy consumption throughout the world, countries are heading country has been experienced in the solar energy industry during
towards renewable energy sources by defining the strategy plans the year. The cumulative PVPS has reached to 5.062 GWp at the end
and putting the supportive legal regulations into operation. In this of 2018 according to the statistical data provided by Turkish Elec-
context, solar energy has high potential of expansion due to its tricity Transmission Corporation [2]. In consideration that the
potential, ease of use, cleanliness, renewability, and its environ- installed cumulative PVPS power was 6 MWp at the end of 2013
ment-friendliness. and 300 MWp at the end of 2015, it may be observed that there is
Solar Energy is also the most important alternative clean energy remarkable increase [3].
resource which is still untapped in Turkey. The yearly average solar However, the elements driving such rapid expansion also in-
radiation is 1311 kW h/m2 per year and 3.6 kW h/m2 per day. The crease the risk of solar financial assets meeting long term fiscal and
total yearly insulation period is approximately 2460 h per year and performance goals. In order to achieve bankability and differenti-
7.2 h per day [1]. The energy yield potential for a PV plant reaches to ation, a premium level of quality assurance is required. Technical
1500e1800 kW h/kWp. Upon the identification of legal regulations, risks may arise from the power plant components as well as from
photovoltaic power systems (PVPS) based on solar energy have operational processes during and after installation. In this context,
both technical component quality and the financial return of the
installed systems have gained great importance.
* Corresponding author. Thanks to modern technologies and inexpensive production
E-mail addresses: mete.cubukcu@ege.edu.tr, metecubukcu04@gmail.com costs, photovoltaic power plants with capacities of Giga Watt may
(M. Cubukcu).

https://doi.org/10.1016/j.renene.2019.09.075
0960-1481/© 2019 Published by Elsevier Ltd.
1232 M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238

be installed. And this roughly means the provision of quality may not be considered so practical for large scale PV plants [7,9].
assurance of a complete system possessing millions of modules, IRT technique utilizes the concept of localized heat generation
kilometres of construction, kilometres of cables, hundreds of in- because of joule heating effect due to the poor contacts, shunted
verters and thousands of acres. In order to be able to obtain a high cells, short circuits. This happens because the cells which are
performance excellent system, power plant units with standard- generating less current as compared to the other cells connected in
ized quality and perfect systems that have passed inspections in the series become reverse biased and start behaving like resistors
terms of both components and system design. and dissipate heat. This dissipated heat results into a temperature
After PVPSs are getting in operation, the efficiency and reliability gradient which during thermal imaging appear as bright spots [6].
of the systems are getting key components. Therefore, the fault In the case of MWp ranged PV applications, IRT measurements
diagnosis on the field and maintenance strategy should be carefully are more practical. These tests may be realized under a clear-sky
defined. A classical PVPS inspection method covers detailed visual without interrupting PVPS's operation.
inspection of the installation and the complete system by an In the scope of this work, the results of infrared thermal imaging
experienced team. This kind of process is generally done before and inspections realized with different methods for 19 different PVPSs
after module installation to assess electrical, mechanical, and in Turkey (115.36 MWp in total) are analysed. The diagnosed fail-
environmental stresses on the PV modules. However, the visual ures were classified and the number of them were normalized per
inspection for large-scale PV systems is not feasible in real time MWp to evaluate the most frequently viewed issues during the on-
conditions due to high error rate and long process time [4]. Per- site testing. The first part of this article reviews the basic charac-
formance assessment based on I-V measurements has been adop- teristics and advantages of different inspection methods for PV
ted to analyse the power generation efficiency. The most common plants. Then, the second part gives a thorough review of the most
measurements of PV modules include open-circuit voltage, short- common fault types and the measurement methods by IRT imag-
circuit current, fill factor, and maximum power point. I-V curve ing. The third part shares the real-time measurement experiments
measurement provides adequate operational performance infor- and results for 19 different projects. On the basis of these previous
mation of PV modules. Unfortunately, to get the data such as open- explanations, the fourth and fifth parts summarize the results and
circuit voltage, short circuit current and maximum power mea- discuss their contributions to the quality approach of PV plants.
surements requires very good weather conditions and the PV Main objective of this article is to guide the investors and
modules has to be taken out from the PV system, this will lead commissioning companies to realize better and quick analysis
direct interruption of the PV system operation and reduces the considering thermal analysis on photovoltaic power plants. With
power generation [5]. the information provided in this paper, field workers can be able to
When compared to the visual inspection and I-V measurements, determine faults and their causes in a more clear way. The article
the most time-efficient method to diagnose the failures of a PVPS is covers the experience on PVPSs installed in Turkey, but situated
thermal imaging method of the PV plant and also the electrical problems are very likely represent the faults encountered world-
components. The PV modules may be tested by using an infrared wide. Developing countries such as Turkey, needs more energy as
camera during the operation of the system. With this process, the years passes by. Every bit of clean, renewable energy source has to
temperature profiles inside individual modules and in larger be operated properly in order to get better yields. So this paper may
module arrays may be visible. Additionally, other electrical com- lead to better performance outputs from photovoltaic power plants
ponents such as DC combiner boxes, cables, connectors, fuses, etc., by using thermal imaging.
may be checked for thermal defects.
The reliability of PV systems can be strongly affected by the
transportation and the installation of the components and also by
real (field) operation conditions. The failures on these stages may 2. Type of faults inspected by thermal imaging
result with excessive thermal and mechanical stresses on the
modules and also the other electrical components [4,6]. The quality check of PV plants under certain operating condi-
Electroluminescence (EL) and infrared thermal (IRT) imaging tions by employing infrared imaging has acquired significance
comprise effective and powerful tools for qualitative characteriza- during the last years [4,11,12]. High-resolution IR images made by
tion of PV modules; not only to witness the presence of faults various institutes, result in better understanding of the observed
within a PV plant, but also to detect their exact location, with high detects. Further investigations by thermal imaging were realized
accuracy [4]. for the modules and arrays installed on-site. After visual inspection,
A combination of EL and IRT techniques may be used in order to this method most effortless and easy to perform in real time con-
identify as many defects as possible [7]. These tests are non- ditions [13]. However, this method also needs adequate irradiance
destructive measurement techniques. These types of optical mea- for optimal results. Some examples showing temperature differ-
surements provide fast, real-time and high resolution images with ences for the same hotspot failure under various irradiation levels
a two-dimensional distribution of the characteristic features of PV may be seen in Fig. 1.
modules [8,9]. The following three methods are commonly used for thermal
While EL is superior for lifetime mapping, bulk defect imaging, imaging worldwide and also in Turkey (Fig. 2).
series resistance imaging and exact junction breakdown site im-
aging, IR-based techniques are superior for all tasks requiring  By walking,
quantitative current measurements [10].  By crane or lift,
EL is a good method to detect micro cracks, interrupted contacts  By drone
or a number of process failures (e.g. shunts or defects in the anti-
reflection layer), but it was not possible to determine the impact of The information and pictures (Figs. 1e9) shared on this article
these defects on the module power output. However, EL imaging were taken directly from the onsite inspection of 19 different PVPSs
method is more complex than infrared imaging and the consuming in Turkey. These images were selected to explain the different type
energy and time is much. These tests may be realized during night of faults and all of them are real-time field experiences.
time or after interrupting the PV plant's operation. It also often For thermal imaging inspection method, the most important
needs to inspect the modules one by one. Therefore, EL imaging factors are as the following:
M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238 1233

Fig. 1. Thermal inspection images at different irradiation levels results in different temperature values.

Fig. 2. Thermal inspection realized in PVPSs (a) by walking, (b) by crane, (c) by drone/UAV.

 The quality of the camera: It is very important because it will Crane/lift method takes shorter time to investigate thermally
determine the monitoring distance and accuracy of the tem- visible faults compared to walking. This method is also significantly
perature values thus the judgement. Usage of radiometric less affected by module angle and field topology. On the other hand,
thermal cameras is recommended. With that thermographic if the ground is wet, the vehicle will be in danger of sink to ground.
image, the controller may measure the temperature of every Additionally, some investors are not willing to let a crane to travel
single point (pixel) of the photogram with the support of related on PVPS site. Although this method enables to get good quality
programs/tools. thermal images, some faults needs close up footage to investigate.
 Module angle: In order to acquire best results, the thermal Another option is usage of drones with job specific made, special
camera lens angle has to be adjusted perpendicular to tilted small thermal cams and a handheld cam. The weight is the key
module surface. So it is highly recommended that, with walking factor for that operation. One of major advantage of the drone is,
method module inclination should not less than 15 if there are examination will not be depend on the module angle, topology or
more than two modules installed top of each other. ground conditions but the thermal camera operator still needs to
 The field topology: For the fields that has wavy topological get permission to entry by drone from the investor. This method is
structure, it is very hard to understand and view the standard the fastest method between all. But the image quality reduced due
temperature distribution on the PV modules. Additionally it to vibration and weight allocation of the drone. The comparison of
makes walking method very frustrating for the thermal camera all images from different methods can be seen in Fig. 3.
operator thus the process takes longer to evaluate. The most common defects found by IRT imaging on PV plants

Fig. 3. Thermal inspection image qualities by different methods, quality differences as can be seen from the pictures (a) by walking, (b) by crane, (c) by drone/UAV.
1234 M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238

Fig. 4. Images of active diodes and back side of the PV module (a) Active bypass diode from front,

 Hotspots on the photovoltaic modules: Hotspots could be occurred by various reasons. Such as different cell characteristics, broken cells, high resistance or cold solder
points due to manufacturing [16]. Additionally such problem may occur by soiling/dust accumulation or partial shading [17e20], faulty isolation on the module frame,
different degradation rates of the cells (Fig. 5).
(b) Active bypass diode from back side, (c) Junction box with active bypass diode.

Fig. 5. Hotspot faults are very common type of failures of the PV modules (a) internal cell soldering problem, (b) shading caused by plant.

 Module strings or single modules that are not operative: In some plants, especially if the plant's commissioning has just finished, it is a big probability that some strings or
tables will not be connected to the inverters. Even in some cases, modules and strings are connected with wrong polarity. In the plants that are in operation for long time
period, this kind of faults can be seen because of the fuses, damaged cables over time. With the thermal inspection, operators are able to find these faults easily as seen in
Fig. 6.

Fig. 6. Offline strings and tables (a) offline strings, (b) offline table.

 Abnormally heated cables, fuses, breakers, interconnection points: As seen in Fig. 7, the PV cables inside of the PV connection point, wrongly calculated. As a result,
temperature of the wires are too high and losing its isolation integrity. Faults caused by loose screws on the interconnection points and faulty breakers are seen in Fig. 8.
Also as seen in Fig. 9, some connections are heated due to stress resulted in loose connection, caused by workers.

are listed below: these components is reverse voltage/reverse current protection.


These components are come into role when PV module or array
 Active bypass diodes on the photovoltaic modules: Bypass di- shaded partially [14,15] and if the current is more than rated
odes are very significant components in PV modules, these are current, these diodes blow out to protect PV modules. It is very
placed to maintain performance of the module. Main role of important to select diode with the proper characteristics. As can
M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238 1235

Fig. 7. Heated cables due to faulty calculation of diameter and/or usage of damaged cables.

be seen in Fig. 4, active diode faults can easily be seen by infrared operative at maximum four weeks. Table 1 shows all the PV plants
camera. chosen for this research. These plants have total installed power of
115.36 MWp and total number of modules are 389486 pcs. In
Simulated performance of PV systems indicated that the per- Table 1, operation time refers to test time after plant is feeding
formance of the PV systems can be improved by 13% or more in energy to the grid.
comparison with actually measured performance identified by field The percentages of the fault types derived from all plants are
test [6]. seen in Fig. 10. The most detected faults are heated connection
points.
Distribution of faults in each plant are given in Fig. 11.
3. Fault diagnosis of 115.36 MWp PVPS IN Turkey
Number of faults are scaled for 1 MWp are seen in Fig. 12. As
seen, the number of faults are significantly higher in PVPS 3 and
In the scope of this work, the results of thermal imaging in-
PVPS 16, compared to other plants. When those systems are care-
spections generated from various sized PVPSs in Turkey are
fully inspected, it has been seen that those faults are mainly related
inspected. All these plants were investigated according to
to workmanship errors.
commissioning tests. Therefore, the inspected systems were

Fig. 8. Heated connection points due to not properly tightened joints and fuse/breaker faults (a) breaker heated up too much due to loose screw, (b) cable terminal heated up too
much due to loose screw,
(c) faulty breaker, (d) breaker heated up too much due to loose screw.
1236 M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238

Fig. 9. Heated connection points caused by workers stress/stretched, on the junction box and one of the PV string input side of inverter.

Table 1
All the locations and their properties that are evaluated with the thermal camera.

Plant Numbers Location Installed Power (MWp) PV Module Technology Unit PV Module Power (Wp) Number of Modules Operation Time (Week)

PVPS 1 Erzurum 2.22 c-Si 270 8228 4


PVPS 2 Erzurum 11.04 c-Si 270 40920 4
PVPS 3 Erzurum 1.14 c-Si 270 4224 4
PVPS 4 Erzurum 12.68 c-Si 270 46992 4
PVPS 5 Konya 3.54 c-Si 265 13376 2
PVPS 6 Konya 1.84 c-Si 265e280 3542 þ 3234 2
PVPS 7 Afyon 3.2 c-Si 265 12096 2
PVPS 8 Afyon 13.89 c-Si 265 52416 2
PVPS 9 Afyon 5.34 c-Si 265 20160 2
PVPS 10 Ankara 4.05 c-Si 270e275 11950 þ 3440 2
PVPS 11 Ankara 2.05 c-Si 265 7740 2
PVPS 12 Uşak 7.02 c-Si 325 21600 2
PVPS 13 Afyon 1.11 c-Si 320 3496 3
PVPS 14 Çanakkale 3.1 c-Si 265 11704 2
PVPS 15 Nigde 1.82 c-Si 260 7000 1
PVPS 16 Antalya 2.16 c-Si 270 8000 4
PVPS 17 Denizli 10.7 c-Si 320 33450 2
PVPS 18 €
Odemiş 11.7 c-Si 325 36000 1
PVPS 19 Mersin 16.76 c-Si 270 62084 1

4. Results and discussion modules, non-operative modules and strings, abnormally heated
cables/fuses/breakers and interconnection points. The results also
PV market presented an impressive growth in Turkey by pre- revealed that the sampling rate of testing is very critical to get a
senting a nearly exponential rate during the recent five years. For right inspection. It is strongly suggested to inspect all PV modules
the operating PVPSs surpassed 5 GWp, the maintenance and fault and the combiner boxes on-site.
diagnosis became the key requirements for the reliability of highly Total number of detected faults are 241 during IRT inspection of
competitive plants. 19 different projects. The classification of defected failures are as
Performance ratio (PR) and levelised cost of energy (LCOE) are the following (Fig. 10):
the key figures to evaluate the quality of large scale PV power
plants. Recently developed approaches allow for an independent  Heated connections (cables/fuses/breakers): 28%
assessment both of component and of design quality in order to  Hot-spots on PV modules: 25%
maintain best figures of PR and LCOE over the system's life time.  Active by-pass diodes: 19%
Such an approach leads to lower technical risk and increases trust  Non-operative string tables: 13%
and confidence for a PV system as a secure investment.  Heated junction boxes: 10%
There are many small sized component connections that make  Broken modules: 5%
PVPS an operative electric plant. In that matter, fuses, breakers,
every cable connection point is a potential fault source. This fault The inspected failure types are also classified as the following
can be caused by both of the manufacturer and/or workmanship. (Fig. 11):
Generally, workers are the main responsible in these kind of faults,
it is rarely related to the manufacturers.  7 of 19 inspected PVPSs consisted the active bypass diodes. One
It is extremely important in terms of PVPS reliability and quality of them (PVPS 8) was covering these failures extremely
to work with an experienced team and with a third party inde- (approximately 80% of total failure type). This failure was more
pendent organisation in the designing-installation-commissioning related to the manufacturer and also remarkable for PVPS 13,
and operation phases. PVPS 17 and PVPS 19.
The experimentation on IRT inspection for 19 different PVPSs in  11 of 19 inspected PVPSs consisted hotspots on PV modules. For
Turkey (115.36 MWp in total) showed that the following failure several cases these hotspots were caused due to the manufac-
types are common ones: active bypass diodes and hotspots on PV turer failures like broken cells, high resistance or cold solder
M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238 1237

points, faulty isolation on the module frame, different degra-


dation rates of the cells. For some cases, these hotspots occurred
due to partial shading and soiling/dust accumulations. This
failure was extremely for PVPS 5 and PVPS 6 (100% of total
failure type).
 Non-operative string tables were detected for 7 of 19 inspected
PVPSs. These failures were mainly observed during the initial
operation phase of systems. In some cases, the strings are
formed with wrong polarities. During the operation phase, the
damaged cables and fuses may also cause these failures. One of
19 projects (PVPS 3) was having remarkable non-operative
string tables which is more related to workmanship errors.
 15 of 19 inspected PVPSs consisted abnormally heated cables/
fuses/breakers and interconnection points. These failures may
be caused due to wrong calculation of cable dimensions, loose
screws on the interconnection points and faulty breakers.
 8 of 19 inspected PVPSs consisted broken modules. These fail-
ures are mainly caused due to transportation and installation of
PV modules. Rarely, surrounding factors lead to these issues
(such as free falling bullets, bird droppings)

IRT inspection may be easily conducted for the ground mounted


and also the rooftop PV systems.
It is also concluded that the most effective IRT method may be
realized by crane/lift in Turkey. This method is also less affected by
Fig. 10. Percentage distribution of faults for observed 115.36 MWp PVPS in Turkey. module angle and field topology compared to the IRT imaging by
walking. Additionally, the walking method needs much time for
MW ranged PV systems. Besides, the image quality is reduced due
to vibration and weight allocation on IRT method by drone.
Additionally on the financial side of the IRT imaging methods,
due to workmanship costs, walking method is the cheapest one for
Turkey. Best picture quality acquired by this method. But it takes
longer time to realize the service. Also working in tough conditions
such as extreme heat, human errors are expected to be more occur
on the results with this method. Crane method is the medium cost.
Picture quality is acceptable by the investors. Service time is also
average. However this method needs stable field conditions such as
rigid ground. Besides, some investors do not take risks of operating
of crane in the field. Drone method is the most expensive method of
all methods due to available technology market prices for each
component. But drone method is the fastest method. Image quality
is below average. The pictures or videos that taken with drones are
usually not serviceable to investors. After the inspection of the
footages, some more photos has to be taken by field expert.
Fig. 11. Percentage distribution of faults in each PVPS.

Fig. 12. Number of faults when each system is scaled for 1 MWp
1238 M. Cubukcu, A. Akanalci / Renewable Energy 147 (2020) 1231e1238

5. Conclusions files/2019-01/kurulu_guc_aralik_2018.pdf. (Accessed 7 August 2019).


[3] TEDAS. Turkish Electricity Distribution Corporation. www.tedas.gov.tr, 2018.
(Accessed 15 November 2018).
This paper represents a comprehensive effort to review, classify [4] J. Tsanakas, L. Ha, C. Buerhop, Faults and infrared thermographic diagnosis in
and highlight the inspected failures by thermal imaging under the operating c-Si photovoltaic modules: a review of research and future chal-
real-time operation of 19 different PVPS in Turkey. Various sized lenges, Renew. Sustain. Energy Rev. 62 (2016) 695e709.
[5] F. Gasparin, A. Bühler, G. Alexandre, et al., Statistical analysis of IeV curve
PVPSs in Turkey were inspected for this study. The power capacities parameters from photovoltaic modules, Sol. Energy 131 (2016) 30e38.
of them are ranged between 1 to 17 MWp. When the number of [6] V. Sharma, S.S. Chandel, Performance and degradation analysis for long term
faults are scaled for 1 MWp, the most detected ones were observed reliability of solar photovoltaic systems: a review, Renew. Sustain. Energy Rev.
27 (2013) 753e767.
as heated connections and junction boxes. The next significant [7] R. Ebner, S. Zamini, G. Újva ri, Defect analysis in different photovoltaic modules
defected failures were hot-spots on PV modules which are most using Electroluminescence (EL) and Infrared (IR)-thermography, in: Proc. 25th
related to the partial shading and soiling/dust accumulations. EUPVSEC, 2010, pp. 333e336.
[8] R. Ebner, B. Kubicek, G. Újv ari, S. Novalin, M. Rennhofer, M. Halwachs, Optical
Investments on photovoltaic systems are safe, but experience at characterization of different thin film module technologies, Int. J. Photoenergy
the stage of practice has clearly shown us the following items: in- (2015) 1e12, 2015.
spection of the engineering processes and component choices as [9] U. Jahn, M. Herz, M. Ko €ntges, et al., Review on Infrared and Electrolumines-
cence Imaging for PV Field Applications, IEA PVPS Task 13, 2018, ISBN 978-3-
well as the installation process in compliance with standards by 906042-53-4. Subtask 3.3 Report IEA-PVPS T13-10:2018, March.
third party independent organisations; final acceptance testing [10] O. Breitenstein, et al., Luminescence imaging versus thermography on solar
prior to commissioning and proper performance monitoring during cells and wafers, in: 26th EUPVSEC, 2011, pp. 1031e1038.
[11] Cl Buerhop, D. Schlegel, M. Niess, et al., Reliability of IR-imaging of PV-plants
the operation bear critical importance.
under operating conditions, Sol. Energy Mater. Sol. Cells 107 (2012) 154e164.
Generally, the main responsible of the failures was observed as [12] J. Tsanakas, L. Ha, F. Al Shakarchi, Advanced inspection of photovoltaic in-
the workmanship. Manufacturer caused problems were rarely stallations by aerial triangulation and terrestrial georeferencing of thermal/
inspected. Therefore, PVPS's performance may be improved visual imagery, Renew. Energy 102 (2017) 224e233.
[13] M. Simon, E. Meyer, Detection and analysis of hot-spot formation in solar cells,
significantly with a right quality check strategy. Sol. Energy Mater. Sol. Cells 94 (2010) 106e113.
Consequently, IRT imaging is one of the fastest method to [14] C.J. Winter, R.L. Sizmann, L.L. Vant-Hull, Solar Power Plants: Fundamentals,
inspect the failures on the operating phases of PVPSs. Technology, Systems, Economics, Springer Science & Business Media, 2012.
[15] W. Rezgui, N.K. Mouss, L.H. Mouss, M.D. Mouss, Y. Amirat, M. Benbouzid,
Faults modeling of the impedance and reversed polarity types within the PV
Acknowledgments generator operation, in: Proceedings of the 3rd International Symposium on
Environmental Friendly Energies and Applications, EFEA, 2014, pp. 1e6.
[16] A.M. Pavan, A. Mellit, D. De Pieri, V. Lughi, A study on the mismatch effect due
The authors of this paper thank to the SolarMENA Energy and to the use of different photovoltaic modules classes in large-scale solar parks,
_
Environment Tech. which is located in Izmir/Turkey. As being the Prog. Photovolt. Res. Appl. 22 (2014) 332e345.
company partner and/or employee, the authors realized the quality [17] A.M. Pavan, A. Mellit, D. De Pieri, The effect of soiling on energy production for
large-scale photovoltaic plants, Sol. Energy 85 (2011) 1128e1136.
assurance inspection of 19 different PVPS projects under the [18] E. Lorenzo, R. Moreto n, I. Luque, Dust effects on PV array performance: in-field
cooperation and assistance of this company. observations with non-uniform patterns, Prog. Photovolt. Res. Appl. 22 (2014)
666e670.
[19] S.A. Kalogirou, R. Agathokleous, G. Panayiotou, On-site PV characterization
References
and the effect of soiling on their performance, Energy 51 (2013) 439e446.
[20] M.J. Adinoyi, S.A. Said, Effect of dust accumulation on the power outputs of
[1] F. Dinçer, Overview of the photovoltaic technology status and perspective in solar photovoltaic modules, Renew. Energy 60 (2013) 633e636.
Turkey, Renew. Sustain. Energy Rev. 15 (2011) 3768e3779.
[2] Turkish electricity transmission corporation. www.teias.gov.tr/sites/default/

You might also like