Sector chosen for study: Manufacturing Process: - Milk processing procedure.
Flow Process Chart
Task: Milk Processing Procedure.
Beginning: Raw milk receiving.
Ending: Distribution of processed milk.
Time Distance
Step no. ( min) ( m) Symbol Step Description
3000
1 45 Raw milk Receiving
2 10 Filter
4 1 5 Milk transportation
5 20 Separator
7 20 Pasteurization
8 5 Vitamin addition
9 15 Homogenization
10 5 Pasteurized storage
11 5 Filter
12 3 10 Milk Transportation
13 5 Packaging material
14 2 Cold storage
15 15 5000 Distribution
SUMMARY
Symbol
Time (min) 64 70 15 5 5
Operation
Transportation
Inspection
Delay
Storage