EWT SPOOLS TRACKER @ JAD YARD

INSTALLATION TORQUING INTEGRATION COMMENTS


S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 4'' Water export line 50% 30% 80% Awaiting welding
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 50% 0% 50%
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
Modification
45 1'' discharge from line heater 50% 30% 80% required
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
Modification
52 6'' connection from FLKO & FLKO 2 to flare stack 10% 10% 20% required
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 15% 0% 15%
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems 0% 0% 0%
60 Blasting and Painting
61 Fabrication of structural support for fan/ blower
62 Fabrication of Air wall
81%
Note: The Percentage for spools as @ 11-08-2022 (6:10pm)
updated design to quick connect
air wall design
ata site visit dimension for fabrication
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 4'' Water export line 50% 30% 80% Awaiting welding
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 50% 0% 50%
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
Modification
52 6'' connection from FLKO & FLKO 2 to flare stack 15% 10% 25% required
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 15% 0% 15%
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems 0% 0% 0%
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 40% 10% 50%
62 Fabrication of Air wall 0% 0% 0%

84%
Note: The Percentage for spools as @ 12-08-2022 (7:00pm)
updated design to quick connect
air wall design
ata site visit dimension for fabrication
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 4'' Water export line 50% 30% 80% Awaiting welding
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 50% 0% 50%
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
Modification
52 6'' connection from FLKO & FLKO 2 to flare stack 40% 20% 60% required
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 55% 30% 85%
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems 0% 0% 0%
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 50% 20% 70%
62 Fabrication of Air wall 0% 0% 0%

86%
Note: The Percentage for spools as @ 13-08-2022 (7:25pm)
updated design to quick connect
air wall design
ata site visit dimension for fabrication
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
Modification
20 4'' Water export line 50% 30% 80% required
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
Modification
33 Fire Hydrant water spools 55% 30% 85% required
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
Modification
52 6'' connection from FLKO & FLKO 2 to flare stack 55% 35% 90% required
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 58% 30% 88% awaiting welding
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems 10% 10% 20%
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 55% 30% 85%
62 Fabrication of Air wall 0% 0% 0%

88%
Note: The Percentage for spools as @ 14-08-2022 (6:20pm)
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
Modification
20 4'' Water export line 50% 30% 80% required
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 60% 40% 100% Awaiting welding
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
52 6'' connection from FLKO & FLKO 2 to flare stack 60% 40% 100% Awaiting welding
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 60% 40% 100% awaiting welding
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems (oil) 10% 10% 20%
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 60% 40% 100%
62 Fabrication of Air wall 15% 0% 15%

89%
Note: The Percentage for spools as @ 15-08-2022 (6:00pm)
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 6'' Water export line 60% 40% 100%
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 60% 40% 100% Awaiting welding
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
52 6'' connection from FLKO & FLKO 2 to flare stack 60% 40% 100%
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 0% 0% 0%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 60% 40% 100%
57 NDT 0% 0% 0%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems (oil) 60% 40% 100% Awaiting welding
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 60% 40% 100%
62 Fabrication of Air wall 40% 15% 55%

91%
Note: The Percentage for spools as @ 17-08-2022 (6:00pm)
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 6'' Water export line 60% 40% 100%
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 60% 40% 100%
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
52 6'' connection from FLKO & FLKO 2 to flare stack 60% 40% 100%
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 60% 40% 100%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 60% 40% 100% Awaiting welding
57 NDT 10% 10% 20%
58 Hydrotest / Leak test 0% 0% 0%
59 Connections to the quick connect systems (oil) 60% 40% 100%
60 Blasting and Painting 0% 0% 0%
61 Fabrication of structural support for fan/ blower 60% 40% 100%
62 Fabrication of Air wall 40% 15% 55%

93%
Note: The Percentage for spools as @ 18-08-2022 (6:00pm)
EWT SPOOLS TRACKER @ JAD YARD
INSTALLATION TORQUING INTEGRATION COMMENTS
S/N SPOOLS IDENTIFICATION (60%) (40%) COMPLETION (100%)
1 2'' close drain vessel pump spool to buffer tank 60% 40% 100%
2 14'' Dehydration vessel gas outlet 60% 40% 100%
3 6''*4'' close drain manifold 60% 40% 100%
4 6'' Surge vessel to dehydration vessel 60% 40% 100%
5 16'' EPF Gas header 60% 40% 100%
6 6'' Surge vessel relief 60% 40% 100%
7 8'' buffer tank oil outlet to motorized oil pumps (1) 60% 40% 100%
8 4'' buffer tank briddle 60% 40% 100%
9 6'' dehydration vessel water outlet to water pump (spool 1) 60% 40% 100%
10 4'' recirculation pump line 60% 40% 100%
11 8'' buffer tank oil outlet to motorized oil pumps (2) 60% 40% 100%
12 6'' dehydration vessel gas outlet to LP FLK (Spool 2) 60% 40% 100%
13 6'' buffer tank gas outlet to FLK 60% 40% 100%
14 6''*4'' Water pumps to Polisher 60% 40% 100%
15 4'' dehydration vessel drain outlet to close drain vessel (spool 1) 60% 40% 100%
16 4'' dehydration vessel drain outlet to close drain vessel (spool 2) 60% 40% 100%
17 6'' dehydration vessel to buffer tank (spool 2) 60% 40% 100%
18 6'' water export line from water polisher 60% 40% 100%
19 4'' Oil export line (spool 1) 60% 40% 100%
20 6'' Water export line 60% 40% 100%
21 6'' Surge vessel oil outlet to dehydration vessel (2) 60% 40% 100%
22 8'' EPF gas header to HP FLK (spool 1) 60% 40% 100%
23 6'' dehydration vessel gas outlet to LP FLK vessel (spool 1) 60% 40% 100%
24 6'' Dehydration vessel oil outlet to buffer tank 60% 40% 100%
25 3'' oil discharge from buffer tank to pneumatic oil pumps 60% 40% 100%
26 4'' Close drain vessel briddle 60% 40% 100%
27 6'' Surge vessel oil outlet to dehydration vessel (Spool 3) 60% 40% 100%
28 6'' dehydration vessel oil outet to oil pump 60% 40% 100%
29 6'' Water polisher to water metering skid ( spool 2) 60% 40% 100%
30 6'' Water polisher to water metering skid ( spool 1) 60% 40% 100%
31 8'' EPF gas header to HP FLK (spool 2) 60% 40% 100%
32 Dehydration vessel handrail (1 & 2) 60% 40% 100%
33 Fire Hydrant water spools 60% 40% 100%
34 Water rentention PSV 60% 40% 100%
35 FLK 1 & 2 PSV 60% 40% 100%
36 HP PSV 60% 40% 100%
37 Water Polisher A&B 60% 40% 100%
38 Surge Vessel 60% 40% 100%
39 6'' surge vessel gas outlet to gas header 60% 40% 100%
40 6'' LP gas outlet to gas header 60% 40% 100%
41 6'' surge vessel oil inlet from Lp Separator 60% 40% 100%
42 2'' recirculation line from dehydration vessel 60% 40% 100%
43 2'' bypass water line from dehydration 60% 40% 100%
44 1'' Supply to line hearter 60% 40% 100%
45 1'' discharge from line heater 60% 40% 100%
46 2'' supply to line heater 60% 40% 100%
47 2'' discharge from line heater 60% 40% 100%
48 4'' supply line from the inlet manifold to test separator 60% 40% 100%
49 6''*4'' suppy line from inlet manifold to Hp separator 60% 40% 100%
50 6''*4'' supply line from inlet manifold to LP separator 60% 40% 100%
51 Test Separator PSV 60% 40% 100%
52 6'' connection from FLKO & FLKO 2 to flare stack 60% 40% 100%
53 Dehydration vessel 60% 40% 100%
54 Connection to chemical injection skid 60% 40% 100%
55 Connection to flow bridge 0% 0% 0%
56 Instrument air compressor connection 60% 40% 100%
57 NDT 75% 75%

#3 of PSV needs to be replaced: PSV 401 (LP


Separator), PSV 501 (Surge Vessel ), PSV 601 ( Water
Rentention) , PI (801) LP FLKO and PI (901) HP FLKO
needs to be replaced, Leaks on threaded tie-in to the
58 Hydrotest / Leak test 80% 80% pneumatic pumps needs to be checked and torqued
59 Connections to the quick connect systems (oil) 60% 40% 100%
60 Blasting and Painting 70% 70%
61 Fabrication of structural support for fan/ blower 60% 40% 100%
62 Fabrication of Air wall 100% 100%

97%
Note: The Percentage for spools as @ 23-08-2022 (1:20am)