You are on page 1of 2

No. Form : FRM.PRJ.

04
REPORT PROGRESS Revisi : 0
Tanggal : 17 Maret 2023

Unit
No Pekerjaan Keterangan
1 2 3 4 5 6 7
1 Las bodi atas, luar, dalam,bordes 100% 100% 100% 100% 100% 100% 100%
2 Pemasangan rockwool dan glass cloth 100% 100% 100% 100% 100% 100% 100%
3 Pemasangan Plat lubang 100% 100% 100% 100% 100% 100% 100%
4 Pemasangan Lis Aluminium 100% 100% 100% 100% 100% 100% 100%
5 Pengecatan luar Enclosure
Barrier 80 100% 100% 100% 100% 100% 100% 100%
penguard 100% 100% 100% 100% 100% 100% 100%
Hardtop XP 85% 85% 60% 40% 0% 0% 0% Final Cat
Pengecatan dalam Enclosure
Barrier 80 100% 100% 100% 100% 100% 100% 100%
penguard 100% 100% 100% 100% 100% 100% 100%
Hardtop XP 100% 100% 100% 100% 100% 100% 100%
6 Fabrikasi Attenuator Intake 100% 100% 100% 100% 100% 100% 100%
Cat 100% 100% 100% 100% 100% 100% 100%
Pembuatan support 100% 100% 100% 100% 100% 100% 100%
Pasang 100% 100% 100% 100% 100% 100% 100%
7 Fabrikasi Attenuator discharge 100% 100% 100% 100% 100% 100% 100%
Pengecatan 100% 100% 100% 100% 100% 100% 100%
Pembuatan support 100% 100% 100% 100% 100% 100% 100%
Pasang 100% 100% 100% 100% 100% 100% 100%
8 Fabrikasi Damper 100% 100% 100% 100% 100% 100% 80%
stoper 100% 100% 100% 100% 100% 100% 0%
solenoid 100% 100% 100% 100% 50% 50% 50%
motor 100% 100% 100% 100% 100% 100% 100%
Pengecatan 100% 100% 100% 100% 60% 60% 0%
Pasang cover samping 100% 100% 70% 70% 50% 50% 50%
Pasang damper 100% 100% 100% 100% 0% 0% 0%
9 Fabrikasi grille intake 100% 100% 100% 100% 100% 100% 100%
Cat Barrier 80 100% 100% 100% 100% 100% 100% 100%
penguard 100% 100% 100% 100% 100% 100% 100%
Hardtop XP 80% 80% 80% 80% 80% 80% 80% Final Cat
Pasang 100% 100% 100% 100% 100% 100% 100%
10 Fabrikasi grille discharge 100% 100% 100% 100% 100% 100% 100%
Cat Barrier 80 100% 100% 100% 100% 100% 100% 100%
penguard 100% 100% 100% 100% 100% 100% 100%
Hardtop XP 100% 100% 100% 100% 100% 100% 100%
Pasang 100% 100% 100% 100% 100% 100% 100%
11 Fabrikasi daily tank 100% 100% 100% 100% 100% 100% 100%
Cat Barrier 80 100% 100% 100% 100% 100% 100% 100%
penguard 100% 100% 100% 100% 100% 100% 100%
Hardtop XP 100% 100% 100% 100% 100% 100% 100%
setting 100% 100% 100% 100% 100% 100% 100%
12 Instalasi pipa daily Tank 100% 100% 70% 75% 40% 40% 20% (-) watermur dan valve gate
Intalasi pipa polishing 100% 100% 100% 100% 100% 100% 100%
Instalasi pipa genset(supply&return) 95% 95% 70% 70% 0% 40% 40% sedang finishing
Instalasi pipa dari storage to daily 90% 90% 50% 50% 0% 40% 40% sedang finishing
13 Elektrikal
Panel Transfer Pump 100% 100% 100% 100% 100% 100% 100%
Panel MCFA (HEAT DETECTOR) 100% 100% 100% 100% 50% 50% 50% instalasi sedang berjalan
Panel Damper 100% 100% 100% 100% 100% 100% 100%
Panel EDG AUX Power 100% 100% 100% 100% 100% 100% 100%
Panel Batere Charger 100% 100% 100% 100% 100% 100% 100%
Panel Leak Detektor 60% 60% 0% 0% 0% 0% 0% sedang instalasi by vendor
Panel JB POWER control dan Instrument 100% 100% 100% 100% 100% 100% 100%
Panel EDG Main terminal box 100% 100% 100% 100% 100% 100% 100%
Interkoneksi MOD Bus 50% 50% 0% 0% 0% 0% 0% sedang proses interkoneksi
Interkoneksi kontrol 50% 50% 0% 0% 0% 0% 0% sedang proses interkoneksi
Interkoneksi power 70% 70% 0% 0% 0% 0% 0% sedang proses interkoneksi
Interkoneksi instrumen 75% 75% 0% 0% 0% 0% 0% sedang proses interkoneksi
Panel Enclosure Terpasang 93% 93% 90% 90% 79% 79% 79% sedang proses interkoneksi
Install line Power and Lighting 100% 100% 60% 60% 0% 0% 0% sedang proses interkoneksi
Terminasi kabel TR 75% 75% 0% 0% 0% 0% 0% sedang proses terminasi
Terminasi kabel TM 75% 75% 0% 0% 0% 0% 0% sedang proses terminasi
14 Fabrikasi tangga 100% 100% 100% 100% 100% 100% 100%
cat ( kuning 1018) 100% 100% 100% 100% 80% 80% 80%
pasang 100% 100% 100% 100% 0% 0% 0%
15 Fabrikasi pagar 100% 100% 100% 100% 100% 100% 100%
cat ( kuning 1018 ) 100% 100% 100% 100% 0% 0% 0%
pasang 100% 100% 100% 100% 0% 0% 0%
16 Fabrikasi wiremesh (frame) intake 100% 100% 100% 100% 100% 100% 100%
struktur/rangka 100% 100% 100% 100% 100% 100% 100%
cat 100% 100% 100% 100% 100% 100% 100%
pasang 100% 100% 100% 100% 100% 100% 100%
17 Fabrikasi grating 100% 100% 100% 100% 0% 0% 0%
pasang 100% 100% 100% 100% 0% 0% 0%
18 Fabrikasi support SCR Muffler
support horizontal 100% 100% 100% 100% 100% 100% 100%
Cat 100% 100% 100% 100% 100% 100% 100%
pasang 100% 100% 100% 100% 100% 100% 100%
support vertical muffler 100% 100% 100% 100% 100% 100% 100%
Cat 60% 60% 30% 30% 30% 30% 30%
pasang 75% 75% 0% 0% 0% 0% 0% sedang pasang tower unit 1,2
19 Fabrikasi Elbow Muffler 100% 100% 100% 100% 100% 100% 100%
Setting instalasi muffler 100% 100% 0% 30% 0% 0% 0%
20 Cat bordes (hitam 9004) 50% 50% 30% 0% 0% 0% 0%
21 Instalasi SCR : Pemasangan main part 80% 80% 80% 80% 80% 80% 80%
Pemasangan Instrumen / Sensor 0% 0% 0% 0% 0% 0% 0% blm terpasang karena safety alat
22 Setting polishing 100% 100% 100% 100% 100% 100% 100%
23 Setting Urea tank 100% 100% 100% 100% 80% 80% 80%
24 Heat detector 100% 100% 100% 100% 0% 0% 0%
25 Leakage detector 50% 50% 10% 10% 0% 0% 0% sedang instalasi panel
26 Fabrikasi Pintu 100% 100% 100% 100% 100% 100% 100%
Cat 50% 50% 50% 50% 30% 30% 30%
Pasang 100% 100% 100% 100% 80% 80% 80%
27 Setting Engine ( Install spring mounting ) 95% 95% 95% 80% 50% 95% 80%
28 Ducting radiator
Kanvas 100% 100% 0% 0% 0% 0% 0%
Siku 100% 100% 30% 30% 20% 20% 20%
Plate 2 mm 100% 100% 30% 30% 20% 20% 20%
29 Fusible Link 100% 100% 40% 40% 0% 0% 0%

TOTAL PROGRESS PER UNIT >>>09 Maret 2023 88% 89% 81% 82% 71% 73% 72%
TOTAL PROGRESS PER UNIT >>> 17 Maret 2023 95% 96% 85% 85% 73% 76% 74%