You are on page 1of 3

Column Inspection Check List

PROJECT : G+P+6+R RESIDENTIAL BUILDING AT MOTOR CITY


MAIN CONTRACTOR : ATCON CONSTRUCTION DATE

COSNULTANT : CHAWALLA ENGINEERING CONSULTANT COL NAME GRID SIZE REINF TIES

COLUMN NAME/GRIDAND SIZE AND STEEL


ATCON
SUB CONTRACTOR FOREMAN IN SENIOR
IN CHARGE CHARGE SITE ENGINEER ENGINEER COMMENTS
General & reinforcement

1 Plotting of gridline for center of column above plinth / floor slab.

2 Locating & marking the centers of columns.


Binding & placing column reinforcement above upper floor slab as per
3 required height, considering lap length of the bar.

4 Column reinforcement & its arrangement as per drawing.

5 Ring spacing & their arrangement as per R.C.C. drawings.

6 Proper binding of reinforcement with binding wire.

7 Fixing of concrete or P.V.C. cover blocks to reinforcement.


Checking of shuttering for columns

1 The quality of shuttering before placing.

2 Applying deshuttering oil to plywood shuttering.

3 Fixing M.S.clamps (shinkanjas) at every 0.6 m (2’0″) internal.

4 Stiffness of side supports to have formwork in plumb.


Checking of column before concreting

1 Size as per drawing.

2 Diagonals as required.

3 Oiling of shuttering.

4 Plumb on both sides.

5 Line of columns as desired.

6 Sufficient Marking level up to which concreting to be done.

7 Supports.

8 Reinforcement cover provided.

9 Spacing of reinforcement above concrete level, maintained as required.

10 Proper filling of gaps from outside by soil paste.

forman/General Forman Site engineer Senior Engineer


Column Inspection Check List
PROJECT : G+P+6+R RESIDENTIAL BUILDING AT MOTOR CITY

MAIN CONTRACTOR : ATCON CONSTRUCTION

COSNULTANT : CHAWALLA ENGINEERING CONSULTANT


Checking of column while concreting.

1 Quality of materials of concrete.

2 The proportion & mixing of material.

3 Six cube mould are kept ready to cast cubes from different batches.

4 Controlled water cement ratio.

5 Availability of vibrator or labour for tamping.

6 Proper cover after concreting on top level.

7 Casting of concrete cubes as required.

8 Proper numbering on cubes.

9 Fill joints if slurry flows from anywhere.

10 Maintain required concrete level.

11 Cleaning of mixing platform.


Checking of columns after concreting.

1 Deshuttering of columns after 24 hrs-48 hrs.

2 Submission of the deshuttering report to higher authority.

3 Finishing of honey combing, if any, with proper care.

4 Date of casting written on column.

5 Hacking of columns.
Cubes removed next day & kept for curing, with code numbers, cast
6 code, site name on cubes.
Curing of columns done for minimum 15 days. Wet nesian cloth wrapped
7 around it.

8 Testing of cubes on due dates i.e. after seventh & twenty eighth day.

forman/General Forman Site engineer Senior Engineer


BEAMS Inspection Check List
PROJECT : G+P+6+R RESIDENTIAL BUILDING AT MOTOR CITY
MAIN CONTRACTOR : ATCON CONSTRUCTION DATE
COSNULTANT : CHAWALLA ENGINEERING
CONSULTANT BEAM NAME GRID SIZE REINF TIES
BEAM NAME/GRID AND SIZE

ATCON
SUB CONTRACTOR FOREMAN IN SITE SENIOR
IN CHARGE CHARGE ENGINEER ENGINEER COMMENTS

Approved shop drawings and Authorities drawings


1
2 Beam dimensions
3 Bottom reinforcement
4 Top reinforcement
5 Additional top reinforcement
6 Additional bottom reinforcement
Top of concrete in columns / core walls / retaining
7 walls
8 Shear links
9 Columns / walls / core walls starter bars
Reinforcement overlap locations to be in
10 compression zones only
11 MEP Clearances
12 Construction joints at 1/3rd or ½ of the span
13 Pour strip at 1/3rd of the span
14 Pre-camber requirements
15 Concrete spacers / cover blocks
16 Safety
17 Cleaning
18 Openings additional reinforcement
19 Tightening of bars
20 Planted walls / columns
Terminated columns / walls / core walls / retaining
21 walls

Forman/General Forman Site Engineer Construction Manager

You might also like