Professional Documents
Culture Documents
52535-PRE-HAT-380-200-0002-methodology of Work For Gravity Filter
52535-PRE-HAT-380-200-0002-methodology of Work For Gravity Filter
ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017
Mechan
Discipline Process Civil Piping I&C Electrical
ical
1|Page
Shuaibah III Expansion II Desalination Plant
ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017
b) Water Proofing
c) Water Stop
1. Between any previous and subsequent concrete joints. Hatco shall install water
stop as per approved drawing and project specifications.
d) Earthling System
1. Hatco shall install Earthling system as per approved drawing, Method Statement,
ITP and project specifications.
e) Drainage system
1. Drainage pipes will also be laid at locations shown in the approved shop
drawings, Method Statement, ITP and project specifications. Should the
steel bars obstruct the plant of drainage; the drainage will be shifted with
the approval of (ABEIMA& FISIA)
2. All MEP services falling within the structure shall be installed and
inspected prior to placing the top reinforcement bars.
2|Page
Shuaibah III Expansion II Desalination Plant
ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017
f) Plain Concrete
1. Depending on the readiness of worked areas hatco will decide the numbers of
casting for GF building.
2. Hatco shall pouring plain concrete as per approved drawing, Method Statement,
ITP and project specification.
g) Reinforced Concrete
1. Reinforced concrete at finish level (- 2.3 m) between the longitude of Axis (2, 3)
– (4, 5) – (6, 7) shall be poured first.
2. Reinforced concrete at finish level (+.25 m) between the longitude of Axis (1, 2) –
(3, 4) – (5, 6) – (7, 8) shall be poured first.
3. The vertical wall between level (- 2.3 m , +.25 m) shall be poured after finalize
clause (1,2)
4. for the walls at water distribution channel the sequence will be
pouring the raft at finish level (+0.25 m)
for Axis ( 1,2) pouring the vertical walls at levels (+1.25, +1.8)
progressively
for Axis (3,4) will be identical to Axis (1,2)
after pouring the inclined slab hatco shall pour the remain height of the
walls
5. small pillars shall be poured till level (+0.95) after finalize clause 2
6. for wall type( A) the sequence shall be
7. for vertical walls longitude between axis (2,3) the sequence shall be
8. For vertical walls longitude between axis (6, 7) the sequence shall be identical to
clause 7.
3|Page