Shuaibah III Expansion II Desalination Plant

ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017

Shuaibah-3 Second Water


Expansion Project
Work Methodology
for Gravity Filter
Building

Mechan
Discipline Process Civil Piping I&C Electrical
ical

Name Issue for Information

Description of the revision and Elaborate Revised Approved


Revision Date
changes d by by by

1|Page
Shuaibah III Expansion II Desalination Plant

ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017

Methodology of work for Gravity Filter Building


a) Earth Work
1. There is two level
 Above ground water table.
 Below ground water level.
2. Dewatering system shall be installed as per approved drawing and sequence.
3. According to approved drawing no (52535-DRA-EPC-000-300-7260) there’s two
bed levels for excavation (-3.0 m,-0.4 m).
4. All earth work shall be executed as per approved drawing , Method Statement
5. ), ITP and project specification.

b) Water Proofing

1. Water proofing type, installation, intervals , overlaps , screed , accessories ,


protection boards shall be installed as per approved drawing , Method Statement,
ITP and project specifications.

c) Water Stop

1. Between any previous and subsequent concrete joints. Hatco shall install water
stop as per approved drawing and project specifications.

d) Earthling System

1. Hatco shall install Earthling system as per approved drawing, Method Statement,
ITP and project specifications.

e) Drainage system

1. Drainage pipes will also be laid at locations shown in the approved shop
drawings, Method Statement, ITP and project specifications. Should the
steel bars obstruct the plant of drainage; the drainage will be shifted with
the approval of (ABEIMA& FISIA)
2. All MEP services falling within the structure shall be installed and
inspected prior to placing the top reinforcement bars.

2|Page
Shuaibah III Expansion II Desalination Plant

ABEIMA Title
Code
Methodology of work for gravity filter
'52535-PRE-HAT-380-200-0002
STPC
Rev: 01 Pages Date 20/12/2017

f) Plain Concrete

1. Depending on the readiness of worked areas hatco will decide the numbers of
casting for GF building.
2. Hatco shall pouring plain concrete as per approved drawing, Method Statement,
ITP and project specification.

g) Reinforced Concrete

The sequence for executing the reinforced concrete is:

1. Reinforced concrete at finish level (- 2.3 m) between the longitude of Axis (2, 3)
– (4, 5) – (6, 7) shall be poured first.
2. Reinforced concrete at finish level (+.25 m) between the longitude of Axis (1, 2) –
(3, 4) – (5, 6) – (7, 8) shall be poured first.
3. The vertical wall between level (- 2.3 m , +.25 m) shall be poured after finalize
clause (1,2)
4. for the walls at water distribution channel the sequence will be
 pouring the raft at finish level (+0.25 m)
 for Axis ( 1,2) pouring the vertical walls at levels (+1.25, +1.8)
progressively
 for Axis (3,4) will be identical to Axis (1,2)
 after pouring the inclined slab hatco shall pour the remain height of the
walls
5. small pillars shall be poured till level (+0.95) after finalize clause 2
6. for wall type( A) the sequence shall be

 Finalize the clause 2 first


 pour the vertical walls till level (+0.95)
 continue pouring concrete walls till the end level

7. for vertical walls longitude between axis (2,3) the sequence shall be

 Finalize the clauses (1,2,3) first


 pouring vertical walls till level (+1.45)
 pouring vertical walls till bottom slab level (+6.275)
 After pouring the slab. The walls shall be continuing to the end level.

8. For vertical walls longitude between axis (6, 7) the sequence shall be identical to
clause 7.

3|Page