52535-PRE-HAT-380-300-0001-work Methodology For Seawater Intake Station
52535-PRE-HAT-380-300-0001-work Methodology For Seawater Intake Station
Mechan
Discipline Process Civil Piping I&C Electrical
ical
Work Methodology
01 29/01/2018 for Sea water intake station
1|Page
Shuaibah III Expansion II Desalination Plant
1. Between any previous and subsequent concrete joints. Hatco shall install water
stop as per approved drawing and project specifications.
b) Earthling System
1. Hatco shall install Earthling system as per approved drawing, & Method
Statement, ITP and project specifications.
c) Drainage system
1. Drainage pipes will also be laid at locations shown in the approved shop
drawings, Method Statement, ITP and project specifications. Should the
steel bars obstruct the plant of drainage; the drainage will be shifted with
the approval of (ABEIMA& FISIA)
2. All MEP services falling within the structure shall be installed and
inspected prior to placing the top reinforcement bars.
d) Plain Concrete
1. Depending on the readiness of worked areas Hatco will decide the numbers of
casting for -13.40 & -12.40 substructure levels and -1.20 at grade level.
2. Hatco shall pour plain concrete as per approved drawings, Method Statement, &
ITP and project specification.
2|Page
Shuaibah III Expansion II Desalination Plant
e) Reinforced Concrete
1. First cast for reinforced concrete from level - 13.40 m to level -12.10 (Figure 1
Red color).
2. First cast for Reinforced concrete from level - 12.40 m to level -11.10 (Figure 1
Green color).
3. Second cast for reinforced concrete from level - 13.40 m to level -12.40 (Figure 1
Blue color).
4. Third cast for reinforced concrete from level - 13.40 m to level -12.40 (Figure 1
Yellow color).
5. The vertical wall between level (- 12.10 m , -1.20 m) shall be poured after finalize
clause (1,2,3,4)
6. for the walls (internal and retaining walls) sequence will be:
Pouring the raft at finish level (-12.10 m & -11.10 m)
First Cast (First lift): Pouring the vertical walls Highlighted Green (Doka
drawing No.: 356-000062-1300_01) progressively as project specification.
Second Cast (First lift): Pouring the vertical walls Highlighted dark blue
(Doka drawing No.: 356-000062-1300_01) progressively as project
specification.
3|Page
Shuaibah III Expansion II Desalination Plant
Third Cast (First lift): Pouring the vertical walls Highlighted Orange
(Doka drawing No.: 356-000062-1300_01) progressively as project
specification.
First Cast (Second lift): Pouring the vertical walls Highlighted light blue
(Doka drawing No.: 356-000062-1300_01) progressively as project
specification.
Second Cast (Second lift): Pouring the vertical walls Highlighted dark
blue (Doka drawing No.: 356-000062-1300_01) progressively as project
specification.
Third Cast (Second lift): Pouring the vertical walls Highlighted Orange
(Doka drawing No.: 356-000062-1300_01) progressively as project
specification.
After pouring the inclined Walls and Second lift (Doka drawing No.: 356-
000062-1300_01) Hatco shall pour the top slab on +0.30 levels.
f) Applying Formwork:
4|Page