Professional Documents
Culture Documents
1/07)
Certified by :
NOTES : * If the thesis is CONFIDENTAL or RESTRICTED, please attach with the letter from
the organization with period and reasons for confidentiality or restriction.
“I hereby declare that I have read this report and in my opinion this report has fulfils
the scope and quality for the award of degree of Bachelor of Engineering
(Electrical)”.
Signature : _______________________________
Name of Supervisor : ALIAS B. MOHD YUSOF
Date :
DISTRIBUTED GENERATION IMPACTS ON THE COORDINATION OF
OVERCURRENT RELAY IN DISTRIBUTED NETWORK
JULY 2012
ii
DECLARATION
Signature : ....................................................
Name : BONG ENG YUEH
Date : 01 JULY 2012
iii
ACKNOWLEDGEMENT
Apart from that, I would also like to thank to the lab technicians and staffs
who had been very supportive and helpful throughout this project. Their guidance
and help had made the experiment conducted smoothly and thus made this thesis
possible.
My appreciation also goes to my family and friends who has been very
supportive to me. Their unconditional encouragement and support is very essential to
me throughout this project.
And also, it is a pleasure for me to thank all those whom were involved
directly or indirectly that had made this thesis possible.
ABSTRACT
ABSTRAK
TABLE OF CONTENTS
1 INTRODUCTION 1
1.1 Background 1
1.2 Statement of problem 2
1.3 Objectives 3
1.4 Scope of study 3
1.5 Thesis Outline 4
2 LITERATURE REVIEW 5
2.1 Introduction 5
2.2 Distributed Generation 5
viii
3 METHODOLOGY 15
3.1 Introduction 15
3.2 POWER WORLD Simulator 16
3.2.1 POWER WORLD Simulator 17
Components
3.2.1.1 Generator and Distributed 17
Generation
3.2.1.2 Busbaar 18
ix
LIST OF TABLES
LIST OF FIGURES
3.1 Generator 17
3.2 Generator Information 18
3.3 Busbar 18
3.4 Buabar Information 19
3.5 Circuit Breaker 19
3.6 Circuit Breaker Information 20
3.7 Transmission Line 20
3.8 Transmission Line Information 21
3.9 Load 21
3.10 Load Information 22
3.11 Circuit Without Installation of Distributed Generation 23
3.12 Circuit With Installation of Distributed Generation 23
3.13 Current Transformer 25
3.14 Settings of Current Transformer 26
3.15 Overcurrent Relay 26
3.16 Settings of Overcurrent Relay 27
3.17 Circuit Without Installation of Distributed Generation 28
3.18 Circuit With Installation of 50MVADistributed 28
Generation
xiv
LIST OF ABBREVIATIONS
LIST OF APPENDICES
CHAPTER 1
INTRODUCTION
In the new era of today, rapidly developing of new technologies arouse the
interest of engineers to develop distributed generation. At the same time, the oil
crisis always a hot topic among engineers and it finally enhance the interest of
electrical power engineers to develop distributed generation (DG) from renewable
source which is having high efficiency [1]. There are several advantages of using
distributed generation at the power system especially from renewable source, one of
it will be pollution free to the environment.
Protection system is the system which is used in power system to protect any
faults that occur in power system. Removal of fault as quick as possible is very
important in order to prevent any insulator damage, conductor melting, explosion.
Installation of DG has created a situation where fault current was flow in unexpected
direction. At the same time, additional fault current supplied by DG can cause relays
to under-reach or over-reach and might cause the protection system no longer
compliant with the requirements of the protection policy.
1.3 Objective
To make sure this project aims are achieved, the following are the objectives
of the project
1. To learn the basic concept of Distributed Generation and Overcurrent relay.
2. To identify the application of overcurrent protection and the impact of the
distributed generation into the system.
3. To determine the coordination of overcurrent relay after the installation of
DG. Verified the results with the manual calculation.
4. To do the analysis to the results obtained.
5. To observe if the existence overcurrent relay still reliable.
There are five chapters in this thesis. In the first chapter, background of the
study, problem statement, objective and scope of study for this project will be
discussed. For the second chapter, it will discuss more on the details about the
theory and the literature review that have been done for this project. Next, in chapter
3, methodology which is covers the software implementation for the simulation and
the manual calculation will be discussed. While in chapter 4, results, verifications,
analysis and discussions will be focused. Last but not least, the last chapter provides
the conclusion and also the recommendation for future analysis.
5
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
In this report, the main part of the project that will be focused are the general
overview of the Distributed Generation (DG) and overcurrent protection system as
the main scheme of protection that will be used in the project. Basically, this chapter
will discuss about the DG technology and the theory of protection system of Inverse
Definite Minimum Time (IDMT) overcurrent relay, relay coordination and
determination of IDMT relay settings.
2.3.2 Microturbines
A new and emerging technology, microturbines are currently only
available from a few manufacturers. This engine range is from 30 to 200 kW.
Microturbines develop low emission levels, but expensive [1]. Most of the
installations are for the purpose of technology testing.
2.3.5 Photovoltaics
Basically known as solar energy. It ranges from less than 5 kW [1].
The most preferable is it produces no emissions, and requires minimal
maintenance. However, it is quite costly. Photovoltaics are used as primarily
in remote locations without grid connections and also to generate green
power.
2.6 Advantages of DG
The speed of rotation of the disc is on the current setting (torque), the speed
of rotation of the disc increased when the load current increases, hence decreased the
12
operating time [5]. Thus the time current characteristics of the relay observe inverse-
Square law. The definite minimum time characteristics of the relay are obtained by
the use of a saturated upper magnet. This ensures that there is no further increase in
f1ux when the current has reached a certain value and any further increase of current
will not affect the relay operation. This results in a flattened current time
characteristic and the relay obtains its name as Inverse definite minimum time
(I.D.M.T.) relay.
PS >
Five basic equations which were used for calculation of relay settings [5]:
1.
2.
3.
4.
5.
where:
CT = current transformer primary rating in amperes
PS = relay plug setting
TSM = time setting multiplier
14
CHAPTER 3
METHODOLOGY
3.1 Introduction
This project was begun with the literature review focus on both the
distributed generation (DG) and IDMT overcurrent relay. In the literature review
most of the information found were came from power reference books and journals
download from internet.
After the literature review have been done, will get to understand the basic
concept of DG and IDMT overcurrent relay. The problems were investigated to the
fault current with and without the installation of DG.
The analysis of this project will executed by using Power World Software to
obtain the fault current at each busbars of the circuit designed. The analysis for this
project will involve the circuit design with and without installation of DG. After that,
fault currents were obtained and the IDMT relay settings at radial system were
determined by using manual calculation with the formula as stated in literature
16
review were used. In the end, the values of real operating time (ROT) for each busbar
were obtained.
This project also used ETAP software to obtain the fault current at each
busbars. New circuit that with relay was designed in Etap software and using the
PSM and TSM calculated to obtain it ROT through the special feature of Etap
software; Star View Relay Curve. After that, verification was done by comparing
both ROT values obtained from manual calculation and Star View Relay Curve.
Finally, the comparisons between analyse circuits design with and without
installing distributed generation were analysed to study their impact at the radial
system in distribution network.
POWER WORLD simulator is one of the common power system software that
been used among engineers. This simulator consists of a number of integrated product
and very useful for the analysis the system with more buses. Besides that, this simulator
allows the user to visualize the system through the use of animated online diagrams
where it is also came out with interactive graphical that can be used to explain power
system operation to non-technical users. This simulator consist of more features and
tools such as tools to perform integrated economic dispatch, area transaction, short
circuit analysis and fault current analysis, it is easily to conduct with a consistent and
colourful visual interface [15]. This simulator will only be used to perform the fault
current analysis for this project.
17
There are several components from the simulator will be used in order to
develop the circuit design, so it is very important to know the component well with
its function so that the analysis and simulation will be perform correctly. The list
below is components will be used:
i. Generator (voltage source)
ii. Distributed Generation (synchronous machine)
iii. Busbar
iv. Circuit breaker
v. Transmission line
vi. Load
The circuit breaker is original build in with the generator. Besides, the
generator field is place near the generator to indicate the generators outputs in MW,
MVA or KV. In this project, the generator field is set to 100MVA/11kV. The
generator information is shown in the Figure 3.2.
18
3.2.1.2 Busbar
Busbar in power system are referring to the point where the other components
of the electrical device like generator, transmission line and load are connected
together. In the simulation component, busbar are represented as a thick horizontal or
vertical line and the number at the busbar indicates that the number of the busbar
itself as shown in the Figure 3.3.
In this project, there is only 4 busbars have been used to develop the circuit
design. The value of the voltage at each busbar is 11kV as shown in the busbar
information in the Figure 3.4.
19
The roles of circuit breaker in the circuit is actually open or close the
transmission line and also the transformer where in order to protect other equipment
in case of abnormal condition occurs, it will isolate the faulty part. When an
abnormal condition occur, a protective relay will detect the faulty signal and straight
away send the tripping signal to the circuit breaker in order to isolate the faulty part.
The symbol of circuit breaker is shown in Figure 3.5.
The circuit breaker information was shown in Figure 3.5. The circuit breaker
itself consists of two contacts which are fixed contact and a moving contact. These
two contacts will remain closed position under normal conditions and will move
away or opened when an abnormal condition occurs in order to isolate the faulty part.
20
3.2.1.5 Load
Load component is represented by an arrow with the real power value with it
as shown in Figure 3.8. Each load in the one-line diagram is equipped with a circuit
breaker originally.
The circuit breaker will appear as a filled of red square if it is in closed circuit
conditions and it will appear as a green square if it is in opened circuit conditions.
Load field objects are used to indicate various quantities associated with load
devices. Load fields are located at nearer the load on the online diagram to indicate
their MW or Mvar value. The load information is shown as Figure 3.9.
22
The circuit design for this project involves only seven different circuits which
are, the circuit without installation of distributed generation and the circuit with
installation of 50MVA and 60MVA distributed generation at busbar2, busbar3 and
busbar4.
The only power supply in this circuit design is the main power supply. There
is no distributed generation at any of the busbar as shown in Figure 3.10.
23
The distributed generation with the capacity of 50MVA and 60MVA were
installed at the busbar4 respectively. There will be other power supply for this
circuit design as shown in Figure 3.11.
This project also make sure both, 50MVA and 60MVA distributed generation
were installed at busbar3 and busbar2 afterward by moving the distributed generation
24
from busbar4 to busbar3 and then busbar2. Fault currents were obtained for every
installation of distributed generation at each busbars.
There are several components from the simulator will be used in order to
develop the circuit design, so it is very important to know the component well with
its function so that the analysis and simulation will be perform correctly. The list
below is components will be used:
i. Power Grid (voltage source)
ii. Distributed Generation (replaced by using power grid)
iii. Busbar
iv. Circuit Breaker
v. Cable
vi. Current Transformer
vii. Overcurrent Relay
viii. Load
25
3.3.1.1Current Transformer
The settings of current transformer are shown in Figure 3.13. The current
transformer ratio will set in overcurrent relay automatically when both of this
component are connected.
26
There are three connections of overcurrent relay but in this project, it just
used up the current input pin only that connected to current transformer. The
component of overcurrent relay is shown in Figure 3.14.
The settings of overcurrent relay are as shown in Figure 3.15. The plug
multiplier setting is defined as pick up setting and time multiplier setting is defined
as time dial in ETAP simulator.
27
Figure 3.16, Figure 3.17 and Figure 3.18 are the circuit that will be used in
order to perform the Star View Relay Curve to obtain it real operating time (ROT)
and to do the verification with the manual calculation of ROT.
Figure 3.19 shows the flow chart of the overall of the project from the
beginning to the end of the project.
LITERATURE REVIEW
VERIFICATION
NO
SATISFY TROUBLESHOOT
YES
DATA COLLECTION
ANALYZE DATA
RESULT
Figure 3.20 shows the flow chart of the IDMT relay setting determination.
START
END
CHAPTER 4
4.1 Introduction
In this chapter, the result and data will be presented and analyzed, based on
the objective that need to be achieved as stated in Chapter 1. The circuit design using
POWER WORLD simulator and ETAP simulator will be presented first with the
validation of fault current. Next, the manual calculations were shown and the ROT
obtained will be verified with the ROT obtained from Star View Relay Curve
(SVRC). After that, the data obtained will be analyzed according to their fault
currents and ROT.
project, circuit designed will only involve 4 busbars and two rating of distributed
generation that are 50MVA and 60MVA.
Figure 4.1 is the example of simulation to obtain the fault current for each
busbar. Data of fault current will be obtained for without installation of distributed
generation and with installation of distributed generation; rating 50MVA and
60MVA.
Table 4.1 shows the result of fault current with and without installation of
distributed generation at each busbar.
34
Figure 4.2 below show the example of fault currents obtained in ETAP. Data
of fault current will be obtained for without installation of distributed generation and
with installation of distributed generation; rating 50MVA and 60MVA.
Table 4.2 shows the result of fault current with and without installation of
distributed generation at each busbar.
For manual calculation, the values of fault current are obtained from POWER
WORLD simulator. First, calculate the relay plug setting (PS) using formulae [5]:
The plug setting for IDMT relay are usually in the range from 50% to 200%
in 25% intervals of the rated relay current [6]. Therefore the value of plug setting
can be adjusted to get the suitable current setting.
36
As mentioned early, this project was involved only three phase balanced fault
current. Current transformer ratio (CT ratio) for each relay were chosen based on the
value of maximum load current at each busbar and CT ratio value is based on
American Standard which is 5A at secondary side. Maximum load current formulae
In this section, it will show the star view relay curve that obtained from
ETAP simulator. Star view relay curve is the special feature of ETAP where the
result of ROT of the circuit design can be obtained directly. The figure below is the
example of star view relay curve. X-axis is fault current and Y-axis is ROT.
Table 4.17 is the results of ROT for each busbar obtained from star view
relay curve which are with and without installation of DG.
4.5 Verification
From the results of comparison above, the average of difference of the values
of ROT are +/- less than 0.05 second. Hence, according to the results of
verification I can conclude by saying that the values of ROT from manual calculation
are acceptable and correct.
Basically the data analysis in this section is divided into four cases which are
Fault Current Analysis, Position of Installation of DG, ROT Analysis and Reliability
of Existence Overcurrent Relay. Data analysis is a very significant section, this is
because it will show that if the objects of this project achieve.
47
The bar chart below was developed according to the data obtained in Table
4.3, 4.4, 4.7. It shows the fault current at each busbar when there are DG installed at
busbar and without DG installed.
7000 Without DG
Fault Current (Ampere)
6000
With
5000 DG(50MVA)
4000 With
DG(60MVA)
3000
2000
1000
0
1 2 3 4
Busbar
√
Where, = fault current
= line voltage
= total impedance
The equation shows that fault current is inversely proportional to the total
impedance. That means if total impedance decreases, the fault current value will be
increased. The circuit designs with the existence of distributed generation produce
the higher fault current compare to the circuit design without the distributed
48
Besides, fault current level only contributed from the source impedance,
feeder impedance and distributed generation impedance [4]. Impedance for the load
does not contribute the fault current level. Hence, the value of load impedance can
be ignored in order to determine the fault current. Meanwhile the value of voltage at
busbar is remained constant.
In this section, analysis is done by focus on the fault current at Busbar1 when
DG was installed at Busbar4, 3 and 2. Figure 4.5 show the fault current at Busbar1
when 50MVA DG was installed at each busbar.
As shown in Figure 4.5, when DG was installed closer to the Busbar1, fault
current at Busbar1 is increased regularly. In the whole radial system, the most
important and most expensive part will be the main power supply or substation. It is
always be the first consideration for electrical engineers to enhance the protection
system in these parts. Hence, according to analysis from Figure 4.5, I would like to
make a conclusion that installation of DG should or must be as far as possible from
the main power supply and substation so that the fault current at the busbar near to it
are as small as possible. At the same time, the backup protection systems are
increased when number of busbar between the installation of DG and power supply
increase.
Real operating time is the minimum clearing time for the overcurrent relay to
clear the faulty part when fault occur. Normally, ROT is adjusted less than 1 second
so that the fault area is isolated fast enough or immediately after the fault occur.
Table 4.25 shows the ROT at Busbar3 with 4 conditions which are without
DG, with 60MVA DG installed at Busbar4, 3, and 2.
maximum load current is high enough to enable overcurrent protection relay operated
successfully. The high value of ratio between the minimum fault current and
maximum load current is needed in order to prevent the possibility of mis-operation
under normal operating conditions.
Form the result obtained in Table 4.25, it can be analyzed that when fault is
occurred at the busbar with installation of DG, that particular busbar will having a
faster fault clearing time compare with the other busbar and this is due to the increase
of fault current when there is installation of DG.
The overcurrent relay installed in radial system must have it limit and the
overcurrent relay that I had used in this project is IDMT with the PSM range, 0.01-
20.00 and TSM range, 0.01-10.00 [12]. This analysis is very important because it
can show that the maximum of the rating of the DG so that the existence relay still
reliable.
PSM 7.93
RCOT 3.31
Busbar 1
TSM 0.25
ROT 0.83
Table above is the same data of Table 4.14: Relay Settings Calculation with
DG(60MVA) at Busbar4. As shown in table above, the PSM value of Relay 4 is
more than 20.00 which is over the range of PSM of the existence IDMT overcurrent
relay. Hence, in this case it shows that if DG with rating more than 50MVA is used
then the existence IDMT overcurrent relay no longer reliable and have to be
changed, install a wider range of PSM. Another solution, DG installed with rating
not more than 50MVA so that the existence IDMT overcurrent relay still reliable.
Mostly the second solution as mentioned above will be taken. This is because
changing of overcurrent relay is very costly.
Figure 4.6 shows that the ROT of the relay cannot be obtained due to the
limit of range of the relay PSM.
CHAPTER 5
5.1 Conclusion
Overall, it can be concluded that this project has been achieved its objectives.
The fault current is increasing as expected after the installation of DG.
From the data analysis, I would like to make a severe conclusion on the
impact of installation of DG. First, fault current was obviously increased a lot after
DG installed. Second, the position of installation of DG should be as far as possible
from main power supply. Next, Relay with installation of DG will operate faster
53
which mean ROT decreased. Lastly, in this project the rating of DG should not be
more than 50MVA so that the existing relay still reliable.
Finally, I would like to conclude by saying that proper study of impact on the
protection system before and after installation of DG is compulsory in order to
determine any upgrade of the protection system is required.
5.2 Recommendation
Even though this project is quite successfully done, but there are still several
recommendations that might be useful in improving the this project in future analysis.
Firstly, in this project there is only 4 busbars involved in the circuit design.
Hence, more busbars or more to real case one-line diagram can be designed to obtain
the difference kind of possible impacts on radial system when DG is installed. Apart
from that, this project is only involved one DG installed at one time. Therefore, it is
recommended that there can be more than 1 DG install at one time to see the changes
of ROT and fault current.
Besides that, other than overcurrent relay, protect system such as fuse and
recloser also can be involve in this project. Analysis on more than one type of
protection system can be done.
REFERENCES
Appendix A
Gant Chart for FYP1
57
Appendix B
Gant Chart for FYP2
58
Appendix C
Star View Relay Curve from ETAP Simulator
a) Without installation of DG