Professional Documents
Culture Documents
A Project Proposal
Presented to the Faculty of Mechanical Engineering Department
College of Engineering
Batangas State University – ALANGILAN
Alangilan, Batangas City
In Partial Fulfillment
of the Requirements for the Degree of
Bachelor of Science in Mechanical Engineering
by
May 2023
TABLE OF CONTENTS
Page
Title Page i
Table of Contents ii
List of Tables v
List of Figures viii
I. Design Background 1
Introduction 1
Rationale of the Study 3
Target Location of the Plant 5
Load Survey 13
Capitalization 28
Ownership 29
Organizational Structure 30
II. Technical Design 34
Theoretical Consideration 34
Design Objectives 41
Scope of the Design 42
Design Data 43
1. Brayton Cycle 44
2. Rankine Cycle 49
Design Options Calculations 53
1. Design Option 1 69
2. Design Option 2 84
3. Design Option 3 100
Description of the Process 122
1. Design Option 1 122
2. Design Option 2 124
3. Design Option 3 126
ii
Summary of Equipment Selection 128
1. Design Option 1 129
2. Design Option 2 131
3. Design Option 3 134
Plant Design and Specification Layout 136
III. Economic Analysis 141
Power Demand Analysis 141
Capital Expenditures 143
Operating Expenditures 165
Economic Evaluation 197
1. Net Present Value 205
2. Return on Investment 210
3. Payback Period 211
Sensitivity Analysis 212
IV. Environmental Management 220
Environmental Impact Assessment 220
Social Considerations 222
Political Considerations 224
Ethical Considerations 225
Health Requirements 225
Safety Requirements 227
DENR Standards 228
Waste Management 232
Pollutant Emissions 233
V. Project Construction Execution Plan 234
Construction Management and Strategy 234
Quality Control and Assurance 237
Work Scheduling 239
Overall Management and Commissioning of the Project 243
iii
VI. Project Design Trade-offs 245
Analysis of Technical Aspects 245
Analysis of Economic Conditions 246
Analysis of Environmental Conditions 250
Pareto Optimum Analysis for the Design Options 252
Best Design Option 254
VII. Summary of Findings, Conclusions, and Recommendations 256
Summary of Findings 256
Conclusions 258
Recommendations 259
References
iv
LIST OF TABLES
v
28 Summary of Calculations for Steam Cycle of Design Option 2 99
29 Summary of Calculations for Design Option 2 100
30 Summary of Calculations for Gas Cycle of Design Option 3 108
31 Summary of Calculations for Steam Cycle of Design Option 3 121
32 Summary of Calculations for Design Option 3 123
33 Summary of Equipment for Design Option 1 130
34 Summary of Equipment for Design Option 2 132
35 Summary of Equipment for Design Option 3 134
36 Projected Load Demand 141
37 Total Land Cost 145
38 Mechanical Equipment Costs for Design Option 1 145
39 Mechanical Equipment Costs for Design Option 2 146
40 Mechanical Equipment Costs for Design Option 3 147
41 Direct Building Cost for Design Option 1 154
42 Direct Building Cost for Design Option 2 155
43 Direct Building Cost for Design Option 3 156
44 Indirect Building Cost for Design Option 1 161
45 Indirect Building Cost for Design Option 2 161
46 Indirect Building Cost for Design Option 3 162
47 Total Capital Expenditure for Design Option 1 163
48 Total Capital Expenditure for Design Option 2 164
49 Total Capital Expenditure for Design Option 3 164
50 Total Labor Cost for Design Option 1 180
51 Total Labor Cost for Design Option 2 182
52 Total Labor Cost for Design Option 3 183
53 Total Miscellaneous Cost for Design Option 1 190
54 Total Miscellaneous Cost for Design Option 2 190
55 Total Miscellaneous Cost for Design Option 3 191
56 Total Fuel Cost for Design Option 1 193
57 Total Fuel Cost for Design Option 2 193
vi
58 Total Fuel Cost for Design Option 3 194
59 Total Operating Expenditure for Design Option 1 194
60 Total Operating Expenditure for Design Option 2 195
61 Total Operating Expenditure for Design Option 3 195
62 Total Project Cost for Design Option 1 196
63 Total Project Cost for Design Option 2 197
64 Total Project Cost for Design Option 3 197
65 Customer Sales 198
66 Sales Breakdown 200
67 Total Annual Revenue for Design Option 1 202
68 Summary of Design Option 1 212
69 Summary of Design Option 2 213
70 Summary of Design Option 3 214
71 Work Schedule of the Combined Cycle Power Plant 239
72 Cycle Efficiency Scale 244
73 Cycle Efficiency Analysis 245
74 Net Present Value Scale 246
75 Net Present Value Analysis 246
76 Payback Period Scale 247
77 Payback Period Analysis 248
78 Rate of Return Scale 248
79 Rate of Return Analysis 249
80 Mass of Fuel Scale 250
81 Mass of Fuel Analysis 250
82 Degree of Importance for Multiple Realistic Constraints 251
83 Pareto Optimum Analysis for Design Option 1 252
84 Pareto Optimum Analysis for Design Option 2 253
85 Pareto Optimum Analysis for Design Option 3 254
86 Summary of Results for Pareto Optimum Analysis 255
vii
viii
LIST OF FIGURES
viii
28 Open Feedwater Heater 40
29 Condenser 41
30 Control Volume at Compressor for Design Option 1 73
31 Control Volume at Combustion Chamber for Design Option 1 73
32 Control Volume at Gas Turbine for Design Option 1 74
33 Control Volume at Steam Turbine for Design Option 1 79
34 Control Volume at Pump for Design Option 1 80
35 Control Volume at HRSG for Design Option 1 80
36 Control Volume at Condenser for Design Option 1 81
37 Control Volume at Compressor for Design Option 2 87
38 Control Volume at Combustion Chamber for Design Option 2 87
39 Control Volume at Gas Turbine for Design Option 2 88
40 Control Volume at Steam High Pressure Turbine for Design Option 2 95
41 Control Volume at Steam Low Pressure Turbine for Design Option 2 96
42 Control Volume at Pump for Design Option 2 97
43 Control Volume at HRSG for Design Option 2 97
44 Control Volume at Condenser for Design Option 2 105
45 Control Volume at Compressor for Design Option 3 105
46 Control Volume at Combustion Chamber for Design Option 3 106
47 Control Volume at High Pressure Gas Turbine for Design Option 3 107
48 Control Volume at Reheater for Design Option 3 107
49 Control Volume at Low Pressure Gas Turbine for Design Option 3 117
50 Control Volume at Steam High Pressure Turbine for Design Option 3 118
51 Control Volume at Steam Low Pressure Turbine for Design Option 3 118
52 Control Volume at Pump I for Design Option 3 119
53 Control Volume at Pump II for Design Option 3 119
54 Control Volume at HRSG for Design Option 3 120
55 Control Volume at Condenser for Design Option 3 120
56 Cycle Diagram for Design Option 1 124
57 T-s Diagram for Design Option 1 124
ix
58 Cycle Diagram for Design Option 2 126
59 T-s Diagram for Design Option 2 126
60 Cycle Diagram for Design Option 3 128
61 T-s Diagram for Design Option 3 128
62 Combined Cycle Power Plant Layout in Isometric View 136
63 Combined Cycle Power Plant Layout in Top View 137
64 Cash Flow Diagram 205
65 Sensitivity Analysis for Design Option 1 216
66 Sensitivity Analysis for Design Option 2 217
67 Sensitivity Analysis for Design Option 3 218
68 Process Flow for Conventional Power Projects 229
69 Plant Layout of the Power Plant 236
x
CHAPTER I
DESIGN BACKGROUND
This chapter introduces the design background of the project, which involves the
type of power plant as well as the site selection considering the factors such as the target
customers and their load demands. Furthermore, it also determines the requirements for
the capitalization and ownership along with the organizational structure for the plant’s
operation. Lastly, an evaluation of the load survey in an hourly manner will be used to
establish the plant’s capacity together with its 15-year load demand projection.
Introduction
A power plant system is a facility that provides the energy required for daily
operations such as transportation, lighting, and the production of goods and services. It
consumption. From the past years until the present times, numerous places in the
Currently seen in news are the six power plants being reported for unforeseen power
grid (Crismundo, 2022). This was due to the load demand exceeding the forecasted one.
In line with this, the province of Quezon, belonging to the region of CALABARZON,
has listed numerous power plants fired with coal. These are the following: 1,200 MW
Atimonan power plant, 735 MW Pagbilao power plant, and 500 MW Mauban power
plant. However, some type of situation occurs when energy production is disrupted by
1
severe weather conditions such as heavy rain, strong winds, and overflowing rivers and
dams. Droughts and heat waves can also reduce the availability of water as a primary
source for hydroelectric power plants. Meanwhile, in some areas, the grid's power supply
is still insufficient. Hence, the idea of planning the construction of power plants emerges
in areas with sufficient resources to address inadequacy in power supply during daily or
peak demand.
On the other hand, resources can be classified into renewable and non-renewable,
wherein natural gas, as one of the non-renewable resources, serves as the most widely
used source of electricity in the country. The Philippines had 3.48 trillion cubic feet of
recognized gas reserves as of 2017, which is 31.4 times its annual consumption. Thus, at
the current rate of energy consumption, there are roughly 31 years of gas left which is
until the year 2048. However, as consumer demand grows, natural gas reserves may be
recommended.
In this proposed combined cycle power plant, natural gas will be combined with
water, it is possible for steam to be one of the most abundant renewable sources of
electricity. Particularly, the province of Quezon has these municipalities that have easy
access to the sea and supply of natural gas. Whereas, utilizing this steam power system
will not only reduce the use of non-renewable sources such as natural gas, but is also
good for the environment since it emits fewer or no greenhouse gases, which are harmful
to people's health.
2
As a result, combined natural gas and steam will be used to address the concerns
environmental pollution. Since the steam turbine will be able to generate more power by
utilizing the waste heat recovery generator from the gas turbine, this will result in a
Luzon island group. This place covers a land area of 8,706.60 square kilometers or
further subdivided into 1,209 barangays. According to the 2020 census, its population
was 1,950,459, accounting for 12.04% of the total population of the CALABARZON
Even though the province has the least population in the region, it has several
establishments and agricultural industries, mainly coconut plantations, which will be the
major beneficiary of the proposed combined cycle power plant. However, Quezon
industries that mainly use electricity. One example of this unfortunate circumstance
happened last November 2022, where Luzon grid power supply tumbles into a red alert
simultaneous outages of power plants. As such, this causes sporadic brownouts in the
area covered by the Manila Electric Company (MERALCO). Thus, in order to continue
the advancement of civilization and move towards modern technology in Quezon, enough
sources of electricity with no intermittent power outages must be provided. This will help
3
in sustaining and supporting the growing demand for electricity despite the growing
these problems that arise from the power outages experienced in the Luzon grid. These
line with this, a combined cycle power plant is efficient in generating power, dependable,
economical, and environmentally friendly. The focus of the project’s design is the process
of combined cycle power generation which recovers the temperature from the exhaust gas
To begin with, the first turbine is powered by combusted natural gas which is
connected to the generator whereas the energy produced from the combustion of natural
gas is used to convert water into steam. This will power the second turbine that is also
connected to a generator. In general, a combined cycle power plant can operate at full
capacity with high demand and its operation capacity can be reduced to 45% of partial
load. Through this, the power plant can only produce what power is required which
allows the plant to avoid oversupply. A waste heat recovery system is also present in this
infrastructure which may generate additional power. Moreover, numerous studies show
that combined cycle power plants produce around 50% additional electricity from the
same fuel consumption. Therefore, this type of power plant is considered as economical
4
Target Location of the Plant
facilities such as power plants to meet the rising demand for electricity.
municipalities. There are two power plants existing in the locality, the 735 MW Pagbilao
Coal-Fired Power Plant and 420 MW Mauban Coal-Fired Power Plant. Still, the
QUEZELCO II, and MERALCO, is not enough to sustain the demand of households and
establishments. In line with this, the target location for the proposed combined steam and
gas power plant system will be at Brgy. Bacong Ibaba, General Luna, Quezon, as shown
Source: www.googlemaps.com
Figure 1 illustrates the target project location site which should be located in a
large area with the lowest possible distribution costs. As such, the design of the plant will
be situated in a large open lot area of Brgy. Bacong Ibaba, General Luna, Quezon with a
5
total area of 65,054.50 m2 and the location's latitude and longitude of 13.663818 N and
122.196256 E, respectively.
Moreover, the salinity of soil has been evaluated in the province and found out
that the location of General Luna contains non-saline type of soil, as shown in Figure 2.
Source: www.bswm.da.gov.ph
the figure above, the municipality of General Luna contains a non-saline type of soil with
a range of 0-2. This can be a good choice for the construction of the power plant because
non-saline soil does not contain salt that reduces the corrosion resistance property of the
infrastructure.
Furthermore, in selecting the site for the plant’s location, the proponents
considered different factors. The generated power output will be transmitted to the
Quezon I Electric Cooperative (QUEZELCO I) which serves as the distribution utility for
third and fourth districts, since the municipality of General Luna belongs to 4th district.
6
Figure 3. Marketing Area
Source: www.inquirer.net
As seen in the figure above, the target customers will be the coverage area of
General Luna, Guinayangan, Gumaca, Lopez, Macalelon, Mulanay, Padre Burgos, Perez,
Pitogo, Plaridel, Quezon, San Andres, San Francisco, San Narciso, Tagkawayan, and
Unisan. In line with this, consumers of the aforementioned towns are classified as
residential such as in households, industrial like the Calauag Ice Plant and A’s Coco
On the other hand, the natural gas which is one of the raw materials for the
combined cycle power plant will be supplied by the Malampaya Onshore Gas Plant at
Batangas. This will be stored in Energy World International, Ltd. LNG Terminal located
at Pagbilao, Quezon. The said terminal is also the source of fuel for Pagbilao Power Plant
located in the same province. Since the capacity of fuel exceeds the capacity of the plant
7
Figure 4. Access of the Combined Cycle Power Plant to General Luna Port
Source: www.googlemaps.com
Illustrated in the figure above is the plant's chosen location close to the road and
the seaport of General Luna, to aid the problem of the transportation of essential supplies
and industrial equipment to the plant. Moreover, the availability of labor for the chosen
plant's location is in Quezon Province, with a total population of 1,950,459. This makes it
easier to find skilled craft workers, such as engineers, electricians, and welders, that will
be involved in plant maintenance to ensure the quality of the plant and its operation.
Meanwhile, the availability of energy is a major requirement for the plant. Shown
in the figure below is the Catanauan substation that is located nearly to the proposed
project site.
Figure 5. Access of the Combined Cycle Power Plant to Catanauan Power Station
8
The proposed combined steam and gas power plant aims to provide 200 MW of
I). The target location is 33 kilometers away from QUEZELCO I Catanauan Power
Substation. The power substation should be as close as possible to the location because it
saves on transmission costs. On the other hand, Figure 6 presents the access of the plant
As seen in the figure above, the plant also has access to the main facility of
the other hand, the availability of water is an important consideration in choosing the
project location because some processes depend on it. In line with this, the proposed site
is close to Tayabas Bay, which indicates that there is an abundant supply of water near the
area that can be used for the plant's operation, as shown in the figure below.
9
As illustrated in Figure 7, the location at Brgy. Bacong Ibaba, General Luna,
Quezon is near the Tayabas Bay, which will serve as the supplier for the water needed in
the steam cycle system of the combined cycle power plant. This will also be utilized
inside the condenser to condensate the steam coming from the turbine through the
condensate pump.
Meanwhile, the climate of Quezon province falls to the tropical type wherein
there is no extreme hotness or coldness. The average and maximum temperature as well
as the pressure and relative humidity for Brgy. Bacong Ibaba, General Luna, Quezon are
enumerated as follows: 25°C, 33°C, 101.325 kPa, and 83%. As stated by Petrakopoulou
et al. (2020), higher ambient temperatures can increase the pressure at the steam turbine
outlet which reduces the performance of the power plant. Thus, in the case of the
recirculating cooling system being utilized, the efficiency of power plants will be more
comprehensive land use of General Luna, Quezon, obtained from their main site. The
figure above shows the zoning map for the target location, with the lot sizes, type of soil,
and whether the space is for public or private usage. The map of General Luna and its
neighboring towns, including Catanauan in the South, Lopez in the Northeast, and
Macalelon in the Northwest, are shown in the figure below. It is reachable by Asian
5 (R-5) and Radial Road 6 (R-6), and is situated about 239 kilometers (km) from Metro
Manila.
10
Figure 8. Zoning Map of General Luna, Quezon
Whereas, Figure 9 illustrates the percentage of land share by Brgy. Bacong Ibaba
in the town.
It is seen in the figure above that the barangay has a total area of 650.07 hectares
with a percentage share of 6.43% for the total area of General Luna, Quezon. Meanwhile,
the next figure displays the elevation of General Luna and the category where it falls.
11
Figure 10. Elevation for Brgy. Bacong Ibaba
As noticed in the figure above, warm lowlands may be found on General Luna,
which has an elevation range of 0 to 300 meters above sea level (masl). The coastal
barangays in the western half of the municipality has 0–25 masl elevation zones., while
52.46%, or more than half, of the municipal lands are expected to be between 25 and 100
Furthermore, Figure 11 illustrates the slope, which is the degree of inclination for
12
From the figure above, the slope for Brgy. Bacong Ibaba was determined. The
majority of the total land area has 3-18% slope classification or gently sloping to
undulating at 3,342.28 hectare which conforms with the standard slope recommended by
the National Land Use Committee (NLUC). It is supported by the Bureau of Soils and
Water Management (BSWM) which affirms that the general slope characteristic of the
On the other hand, the next figure presents the administrative map of General
Luna, Quezon, with legends for municipal and barangay boundaries as well as the
Load Survey
The load survey is used to determine the load demand of the target consumers
under the Quezon I Electric Cooperative (QUEZELCO I). This includes the number of
consumers in the said vicinity as well as the amount of electricity they consume, which
will be essential for creating the 15-year load projection of the plant.
13
A. Target Consumers
The following figure and tables present the number of consumers for residential,
commercial, industrial, and the others. Figure 13 shows the percentage for each type of
Public Buildings, Street Lights, and BAPA, is shown in this pie graph. Due to the high
with 94.6%. The public buildings, street lights, and Barangay Power Association (BAPA)
have a percentage of 2.8 and 2.7 for the commercial enterprises, respectively. This will be
Whereas, Table 1 displays the number of consumers for the year 2016.
Table 1
Residential 119,016
Commercial 3,354
14
Table 1 (Continue)
Total 125,835
being obtained from load survey data. The consumers are divided into various categories,
such as residential, commercial, and public buildings, street lights, and BAPA with
119,016, 3,354, and 3,465 consumers, respectively. Hence, in 2016, QUEZELCO I had a
total of 125,835 consumers after adding the number of consumers in each category.
Meanwhile, the number of consumers for the year 2017 is presented below.
Table 2
Residential 128,520
Commercial 3,392
Total 135,418
This table shows the number of consumers for QUEZELCO I in 2017. Compared
to the consumers in the year 2016, there are 128,520 consumers in the residential
category, which is the highest number of consumers. Also, there were 3,392 consumers in
the commercial, and 3,506 in the last type. After summing the number of consumers in
15
On the other hand, the number of consumers for the year is illustrated in Table 3.
Table 3
Residential 133,155
Commercial 3,486
Total 140,286
This table describes the number of QUEZELCO I consumers in 2018. There are
133,155 consumers in the residential, 3,486 in the commercial category, and 3,645 for
public buildings and others. By adding the number of consumers in each category, this
Whereas, the table below illustrates the number of consumers for the year 2019.
Table 4
Residential 135,080
Commercial 3,624
Total 142,409
16
The number of QUEZELCO I consumers in 2019 is shown in this table. The
residential category has 135,080 consumers, followed by the other type with 3,705, and
the commercial with 3,624, which has the least number of consumers. There are 142,409
Meanwhile, the number of consumers for the year 2020 is tabulated as provided
below.
Table 5
Residential 137,857
Commercial 3,652
Total 145,314
comparison to the other categories, the residential category has the most consumers with
137,857, whereas there are 3,805 public buildings, street lights, and BAPA, and the
commercial category has 3,652 consumers. This results in a total of 145,314 consumers.
On the other hand, the total number of consumers from QUEZELCO I for the
Table 6
17
Table 6 (Continue)
Residential 145,021
Commercial 3,889
Total 152,824
145,021 consumers, the residential category has the most value when compared to the
rest. Meanwhile, The number of consumers for the other types are as follows: 3,889, and
3,914. In comparison to years 2016-2020, the number of consumers in 2021 is the highest
with 152,824.
For the previous year 2022, the number of consumers is presented below.
Table 7
Residential 151,002
Commercial 4,048
Total 159,399
This table shows the number of consumers for QUEZELCO I in 2022. The
residential category contains 151,002 consumers, the public buildings and street lights
with 4,349, and the commercial with 4,048 consumers. When the total customers for each
18
group are added together, there are 159,399 consumers. It is seen that the number of
B. Load Demand
The facility's overall power requirements are referred to as load demand. Upon
conducting a load survey to the target consumers under the QUEZELCO 1 distributor,
figures are presented below. These show the results from 2020 to 2021 on a daily and
yearly basis. Average load is defined as the average of the loads that occur in the power
plant system on an hourly basis from midnight to the next day. Presented in Table 8 are
the values for the average load ( in kW) for each year, namely: 2020, 2021, and 2022.
Table 8
19
Table 8
As seen in the table above, the values from years 2020-2022 were provided from
the hourly basis of the load survey gathered from QUEZELCO I. This shows that the load
varies every hour since none of the values are the same with one another. However, in the
year 2020, the peak load occurs during eight in the evening, similar for the years 2021
and 2022.
In line with this, Figure 14 shows the daily average load curve of QUEZELCO I
from 2020-2022. The x-axis shows the time in hours whereas the load in kilowatts is
20
Figure 14. Daily Average Load from 2020-2022
It is seen in the figure above that the difference in trend for the past three years,
namely 2020, 2021, and 2022, increased. This is due to the continuous growth of the
Peak load refers to the maximum consumption of electricity. In this case, the load
Table 9
21
Table 9
From the table above, it is observed that the peak or maximum load in each hour
increases and decreases due to its variation. Factors affecting these load variations are the
energy utilized by each consumer type in a particular time and the number of equipment
used by residential, commercial, as well as the public buildings and street lights.
As such, displayed in Figure 15 is the daily peak load curve for the past three
years.
22
Figure 15. Daily Peak Load from 2020-2022
Presented in the figure above is the daily peak load for years 2020, 2021, and
2022. It is observed that the loads vary with respect to time, where at some point, it
increases and consequently decreases. Still, the year 2020 has the lowest load while the
On the other hand, Figure 16 illustrates the annual peak load from 2020 to 2021.
Shown in the figure above are the trendlines for the peak load on a yearly basis. It
is noticed the values still vary from each other, however, the curve for the year 2022 is
the highest of all. Several factors affected it, such as population growth and increase in
energy utilization.
23
C. Load Demand Projection
demand and a limited supply of energy sources. Given the technological developments
we are currently experiencing, it is not impossible that communities, like General Luna in
Quezon, could eventually industrialize and have more establishments. Thus, a power
plant is necessary in the area to supply their electricity demands. Whereas, when building
a power plant, the capacity of the plant that will deliver during the following years must
be determined by taking into account the projected load of the demand. In view of this,
the forecasted values of the demand load, which are derived using the linear technique
and rise by 6.85% annually from the QUEZELCO I procurement plan, are tabulated
below.
Table 10
24
Table 10
Table 10 shows the projected load until the year 2038. From the actual load
demand of 40.01 MW during the year 2022, the load projection for the next 15 years is
expected to be at the highest value of 115.51 MW. These values will be utilized to get the
curve that will determine the accuracy of the said load demand projection.
Hence, based on the values tabulated above, a curve for the projected value below
25
The proposed power plant system's predicted demand load curve from 2020 to
2038 is depicted in the figure above. This demonstrates how the demand for power has
been rising over the duration of the year. The load consists of the total sales made by all
residential and commercial buildings, as well as by all buildings, street lighting, and the
Barangay Power Association (BAPA). Peak demand, with a peak value of 115.51 MW,
happens in 2038. The year 2020 saw the lowest peak demand, with a value of 37.17 MW.
A predicted load estimate of 115.51 MW is for the next fifteen years. According
to the QUEZELCO I procurement plan, the plant will have a 19% reserve capacity and
15% system losses. As such, the power plant's capacity will be determined as stated
below.
The formula for the plant capacity is the sum of the three factors, which are the
From the forecasted value of the load demand shown in Table 8, the year 2038 has
the highest value of 115.51 MW. Hence, this will be the load demand to be considered.
System losses are the amount of power output that is lost or dissipated due to heat
and other reasons. The cost of such a loss is compensated by the number of customer
connections impacted and supplied by a specific power plant. In order to get a low cost of
electricity bill, a smaller percentage of system loss, in this example 15% or 0.15, is
necessary.
26
System Losses = Peak Demand x %System Losses
In contrast, the electric grid uses reserve capacity as a backup energy source in the
recommended for power plant systems to have the required amount of reserve capacity in
order to supply for the future or in case of an emergency. Also, this might help to balance
Therefore, with a peak load of 115.51 MW and assumed factors of 15% and 19%
for system losses and reserve capacity, respectively, the required capacity for the
Capitalization
budget allocated for a plant is much higher than the ordinary establishments. The costs of
electricity in a combined steam and gas power plant highly vary depending on factors
27
gas consumption, and environmental regulations. Also, financing is said to be one of the
most important aspects of starting a business. As such, since all of the costs associated
with continuous operation require large sums of money, capital investment is required as
for purchasing supplies, hiring specialists, marketing, and testing. Given that the target
customers are residential, industrial, and commercial, capital is expected to come from
the government and bank loans, as well as the plant's operator/owner, or investors. In line
with this, a pie chart below shows the percentage share of the organizations that will fund
The figure above shows the various organizations' contributions to the proposed
power plant's funding. Seventy-eight percent of the finance will come from the plant's
owner, eleven percent from investors, eight percent from bank loans and the remaining
28
Ownership
Discussed in this section are the proponents' methods for authorizing the
construction and operation of the power plant. The concept for the proposed plan to build
the power plant came from a set of laws by the government known as the Republic Act
7718. This outlines the government's position on the financing, development, and
operation of the infrastructure project. In line with this, the capstone project will follow
the power plant facility for a specified time. As a result, the infrastructure will be given
to the government agency after the contract's expiration, which cannot exceed fifty years.
In line with this, the combined cycle power plant proposed in this study will be
owned by the public and private sectors. The project will transfer to the applicable
government organization after the investment as well as the operating and maintenance
costs was recovered. This high cost of capital for a power plant construction and
operation means that a public utility franchise is needed. Meanwhile, the Philippine
Energy Sector estimated that the country’s total power has increased by 3.2% from the
sustainability not just locally but also internationally. (DOE, 2016) However, as the
country aims to provide a solution for the increasing demand, funds are still not enough
country arise.
In line with this, the project's financier must be Filipino, or the corporation must
be legally registered with the Securities and Exchange Commission and have at least
sixty percent ownership by Filipinos in order for public utilities to support the project.
29
This project opens an invitation to potential investors to participate in the development of
the proposed project. Three subsidiary companies from the oldest and largest
conglomerates in the Philippines will be the major shareholder of the proposed power
plant. They are all known for their interests in power generation, power distribution,
assured that these three companies, which are power generation companies in the
Philippines, can support funding the proposed project. However, the investor will first
Procurement Reform Act in order to establish the necessary guidelines and rules for the
proponents will accept the investor that they consider will be most helpful to the
Organizational Structure
The proposed 155 MW combined steam and gas cycle power plant located at
Brgy. Bacong Ibaba, General Luna, Quezon will achieve its goal through the works of
employees. A good and clear description of the worker’s responsibilities and line of work
is the key for the success of the company. As such, shown in Figure 19 is the
30
Figure 19. Organizational Chart of Combined Steam and Gas Power Plant
31
The organizational chart presented above displays the company’s internal
structure of workers. To begin with, the company will be a corporation where the
quality of the board, nomination and remuneration committee is also included. This
committee is composed of the boards themselves which assesses each performance. The
plant manager is chosen by the board where the whole processes and happenings in the
company is within his/her sight. Meanwhile, the company secretary and the assistant
plant manager will help the plant manager to achieve the plant’s full potential.
The company secretary will be in charge of the administration of staff such as the
hiring of the employees that are needed in the plant. Also, the support and emergency
personnel are also under the supervision of the HR Department which is monitored by the
company secretary. This includes the canteen staff, fire fighters, security guards and the
cleaning staff. The target of this department under the company’s overall secretary is to
ensure the safety and comfortability of the workers. This department is included because
the proponents of this proposed power plant believe that the best outcome of work comes
from the best workers and one factor that can affect the performance of the workers is the
However, the assistant plant manager is responsible for the processes of the power
plant. Included in the radar of the assistant plant manager are four departments namely,
chief of operations, chief of technical officers and risk management committee. Under the
chief of operations are the workers that will check each component of the power plant.
Since the proposed power plant will run on a combined cycle of gas and steam, the gas
turbine engineer and the steam turbine engineer are included together with the gas turbine
32
mechanics and steam turbine mechanics that will help with the monitoring of the plant,
respectively. Also, the on-going projects would be under this department with the help of
the technicians and construction workers. To be more specific, the chief of operations
will handle four departments, line supervisor, operation manager, system operations and
the project supervisor. The chief technical officer will be in charge of the plant
management technician. Lastly is the risk management committee which includes the
environmental engineers, safety officers, environment officers and the pollution control
officers.
33
CHAPTER II
TECHNICAL DESIGN
This chapter discusses the technical design of the proposed combined steam and
gas power plant system, that covers the working principle and components of a combined
power plant, three system design options, and the detailed calculations for each that
support the technical specifications of the equipment used in the processes. It also
includes the plant layout, presenting the components and their connection as a whole
system.
Theoretical Consideration
In the field of energy engineering, one of the most crucial topics is the
development of power generation systems. The most effective use of energy and ways to
manage energy usage are crucial given the high cost of energy and the diminishing
supply of fossil fuels. Through continuous study, it is proven that combined cycle power
plants have higher efficiency compared to steam power plants and gas turbine cycle
In order to transfer the energy in a fuel into electric power, mechanical work must
first be created. This mechanical work is then converted into electric power by a
generator in a "simple cycle," which results in efficiency losses. The overall efficiency of
this conversion normally ranges between 30 and 40%, depending on the type of fuel and
thermodynamic process. This implies that a sizable portion of the fuel's latent energy is
lost as waste. The heated exhaust fumes from the combustion process contain thermal
34
However, the residual thermal energy in hot exhaust gases can be recovered and
used by a number of processes to boost the overall effectiveness of electric power plants.
This leads the way to combined cycle power plants. A combined cycle gas turbine
(CCGT) plant uses gas turbines and is the most popular form of combined cycle power
plant. The output of the steam turbine makes up around half of the output of the CCGT
plant since gas turbines are inefficient in simple cycle operation. CCGT power plants can
be set up in a variety of ways, but normally each GT has a separate HRSG, and several
turbine and a steam turbine to achieve higher efficiency than it can independently.
Combined Rankine Cycle and Brayton Cycle can generate up to 50% more energy from
the same fuel than a conventional simple cycle plant. To further discuss, the gas turbine
powers an electrical generator through the compression of air, mixing it with a highly
heated fuel in a combustion chamber at extremely high temperature, the hot air and fuel
mixture coming from the combustion chamber passing through the turbine blades making
them to rotate quickly, and the fast rotation of the turbine blades that powers the drive
In line with this, the exhaust gases from the gas turbine of the Brayton Cycle are
supplied to the heat recovery steam generator (HRSG), which recovers heat from the
exhaust gases of the gas turbine that feeds to the steam turbine of the Rankine Cycle,
which is also connected to a generator to produce more energy. (General Electric, 2022)
Therefore, a combined cycle power system is established. Due to multiple cycles present
35
in a combined cycle power plant, there is an increase in pressure levels and reheat circuits
giving a better cycle efficiency than a simple cycle plant. (Ipieca, 2022)
A combined cycle will never be set up without the components that are connected
with one another. In line with this, listed below are the components used in designing a
1. Gas Turbine
energy by using compressed gas to spin it. The pressurized gas in all contemporary gas
turbines is produced by burning a fuel such as natural gas. This fuel's heat causes the air
that is being used in the turbine to expand, producing useful energy. In line with this, a
A compressor draws in air from outside of the turbine and increases its pressure.
The axial kind of air compressor will be used in the proposed design since it offers a
larger flow rate and a higher pressure ratio, both of which lead to higher fuel efficiency.
36
Figure 21. Air Compressor
Source: gas-turbines.weebly.com
3. Combustion Chamber
The energy that powers the entire system is added in a gas turbine's combustion
chamber. The air-fuel mixture is compressed by the piston and ignited when it comes into
contact with the spark plug, pushing the mixture out of the combustion chamber as
energy.
thermal energy into mechanical work. Steam is used to power a steam turbine. The
majority of the energy contained in the hot, gaseous steam is released as it expands and
cools as it passes by the rotating blades of the turbine. The blades are constantly being
spun by this steam. Hence, the blades largely transform the potential energy of the steam
into kinetic energy. The generator is then powered by the turbine to create electricity.
37
Figure 23. Steam Turbine
Source: researchgate.net
An HRSG is a part of a power generation unit, it uses the heat from the turbine
exhaust gases to turn liquid water into steam so that it can be used in the same power
A generator uses the provided mechanical energy and forces the flow of present
electric charges inside the wire of its windings. A generator transforms the mechanical
energy from an external source into electrical energy, which is then sufficient to produce
38
Figure 25. Generator
Source: azom.com
7. Feed Water Pump
Feed water pumps (FWP) pump the feed water from the deaerator through the HP
heaters to the heat recovery steam generator. The major characteristic of the FWP is their
high differential head. In all sizes of gas-fired combined-cycle power plants, the FWP are
horizontal ring section type; occasionally, they could also be barrel or axially split type
(Sulzer, 2020).
A condensate pump is a centrifugal pump, which is named after the type of fluid
condensed steam as water condensate. In a closed circuit, the condensate pump pumps
39
the condensate directly into the boiler feed pump via a low-pressure feed heater. In an
open circuit, the condensate pump carries the condensate into a tank.
feedwater exiting the pump and steam produced from the turbine are combined. The
combination should ideally exit the heater at heater pressure as a saturated liquid.
10. Condenser
into water. Cooling water from the cooling tower circulates inside it while it carries out
this procedure. In order to increase efficiency, the pressure within a steam condenser is
40
kept below the atmospheric pressure. It is frequently utilized to reduce the backpressure
Design Objectives
but lower resource consumption, a combined cycle type of power plant system has been
used. In line with this, the design objectives and requirements for the proposed combined
steam and gas turbine power plant system are covered in this section.
The main objective of this project is to design a 155 MW combined steam and gas
and placed at Brgy. Bacong Ibaba, General Luna, Quezon. Specifically, this study aims
to:
1. Establish three design options for the proposed combined steam and gas cycle
1.2 Working principle of a combined steam and gas cycle power plant
41
1.3 Environmental and economical aspects of the plant design
2. Present the design calculations together with the schematic and process flow
diagram as well as the plant layout using AutoCAD and SketchUp software
applications.
3. Evaluate the performance of the three design options based on the plant capacity,
5. Perform an economic analysis for the three design options considering the
expenditure, net present value, payback period, and rate of return as well as the
sensitivity analysis.
6. Select the optimum design from the technical, environmental and economical
7. Present a detailed project execution plan of the selected design for the proposed
resources, the government and experts still find a way to sustain the needs without having
several studies have shown findings that combined cycle power plants, particularly the
steam and gas cycles, can produce a better efficiency compared to the simple plant
42
handbook for cogeneration and combined cycle power plants (2002), the thermal
efficiencies of combined cycle power plants can reach up to 60% whereas 30-40% for the
individual cycles.
resources, such as solar, biomass, and steam. Steam, one of the most well-liked and
efficient forms of energy, is mostly applied to produce electricity and serve as a heating
and lowering the consumption of traditional fuels like natural gas, which increases the
possibility of establishing a more efficient and cleaner power system. In line with this, a
combined steam and gas cycle power plant has been proposed, aiming to address the
aforementioned concerns. Furthermore, three design alternatives for the combined cycle
power plant have been proposed, each with their method of increasing efficiency. These
include the simple combined cycle, single-stage reheat for steam cycle, and single-stage
reheat for both steam and gas cycles. Cycle and T-s diagrams will be provided through
analysis for the gas cycle and the Steam Table for the steam cycle. The resulting
parameters will be essential in selecting the appropriate equipment from catalogs. Lastly,
a plant layout will be included, to be created using the Sketchup software application.
Design Data
This section presents the information and parameters required for the
computations, as obtained from the standards. These were employed in order to perform
the mass and energy balances in both Brayton and Rankine Cycles to establish a feasible
design.
43
A. Topping Cycle (Brayton Cycle)
The gas cycle (Brayton Cycle) was utilized as the topping cycle for this
proposed combined steam and gas power plant. Components in this cycle are as
follows: air compressor, combustion chamber, gas turbines, where high- and
low-pressure will be used for the last design alternative with single-stage reheat
gas turbines, a reheater, and a generator. Listed below are the data to be
considered for analyzing the topping cycle in all the three design options.
case, the natural gas. Tabulated below are the pressure and temperature of the
natural gas to be stored at Pagbilao Grande Island LNG Terminal. This will serve
Table 11
288.15 101.325
15°C, whereas the pressure accounts for the atmospheric conditions, with a value
natural gas supplied by Energy World Corporation Ltd. and stored in Pagbilao
44
Table 12
Nitrogen N2 4.52
Total 100
dioxide, nitrogen, and hydrogen sulfide, their molar ratios in percent are as
follows: 95.05, 0.13, 0.01, 0.25, 4.52, and 0.04. This sums to a total of 100
percent.
2. Climatic Conditions
which takes the first step in analyzing the cycle, as it will be the basis for the inlet
conditions of the compressor. The data were obtained from the site of
45
Table 13
Climatic Conditions
25 33 101.325 83
Source: Accuweather.com
as well as the pressure and relative humidity were given for Brgy. Bacong Ibaba,
General Luna, Quezon. The values are enumerated as follows: 25°C, 33°C,
The inlet temperature for the air compressor will be the average
temperature of the target location, which happens to be 25°C whereas the inlet
pressure will be based on the atmospheric condition with a value of 101.325 kPa.
Since an ideal setup will not be possible to attain in reality, an efficiency for air
efficiency ranges from 50% to 85%, hence, the maximum will be utilized in this
design.
Cogeneration and Combined Cycle Power Plants by Boyce (2002) that the
pressure ratio for gas cycles ranges from 8:1 to 30:1. In this case, the design
utilizes a compression ratio of 12 for the design option 1 and 15 for the second
and third design options. A summary of the parameters for the air compressor is
presented in Table 4.
46
Table 14
Efficiency ηc 85 %
Design Option 1
Compression Ratio rp 12 -
Compression Ratio rp 15 -
Shown in the table above are the parameters necessary for the air
ratio. This will be used in solving for the outlet temperature of the air compressor
Power Plants by Boyce (2002), the inlet temperature for large gas turbines can
reach up to 1644 K (1371°C). In this case, the gas turbines in design options 1 and
2 will utilize 1300 K (1027°C), while 1644 K (1371°C) on the last alternative. On
the other hand, due to some losses, the ideal setup of being a hundred percent
efficient will be hardly possible to happen. In this case, an efficiency for gas
industrial and utility-sized units, the gas turbine efficiency of capacities over 1000
47
kW or 1 MW is 80 to above 90%. However, for the reheat stage in the last design
option, the second gas turbine will still be using the same temperature as the first
turbine. To sum up, Table 5 presents the design data for gas turbines.
Table 15
Efficiency ηc 85 %
Efficiency ηc 85 %
As seen in the table above, the inlet temperatures and efficiencies for gas
turbines to be employed in the three design alternatives were provided. They have
the same values of 1300 K as inlet temperature and 85% as the gas turbine
efficiency.
mechanical into useful energy, the electricity. The ratio of electrical output to its
manufacturers that generators used have efficiencies that can reach up to 98.5%.
48
B. Bottoming Cycle (Rankine Cycle)
On the other hand, the steam (Rankine Cycle) was utilized as the
bottoming cycle of the proposed combined steam and gas power plant. The
condensate pump, open feedwater heater, feed pump, and a generator. Listed
below are the data to be considered for analyzing the topping cycle in all the three
design options, where the first design option is simple, single-stage reheat for the
The steam turbine in the first design option will use the inlet temperature
and pressure as obtained from the Siemens manufacturers, which are 400°C and 3
MPa, respectively. Whereas, for the reheating stage in design alternatives 2 and 3,
pressures and temperature are 16.5 MPa and 585°C. Hence, the aforementioned
Moreover, the reheating stages will employ the “perfect reheating method”
wherein the temperature of the high pressure turbine is what will also be used for
the low pressure steam turbine. Lastly, an ideal setup with a hundred percent
efficiency will not be possible in the real world, thus, an efficiency for the actual
work will be used. From the handbook entitled “Catalog of CHP Technologies”
49
steam turbine ranges from 65% for small units with 1000 kW to 90% for large
turbines. With this, a 90% efficiency will be utilized for the design. A summary of
Table 16
Design Option 1
Efficiency ηt 90 %
Efficiency ηt 90 %
Efficiency ηt 90 %
Shown in Table 6 are the specific data for steam turbines, which vary for
the three design options. It shows the inlet temperature which is 400°C and 585°C
for design options 1, 2, and 3, respectively. Whereas, the pressures for the three
design options are 3 MPa for simple turbine, 16.5 MPa for both high pressure
50
turbine and low pressure turbine. However, the efficiency of 90% remains the
2. Condenser Conditions
decrease the back pressure that increases the work output. Hence, the use of
condensers in a steam cycle increases the plant’s efficiency. From the Handbook
for Cogeneration and Combined Cycle Power Plants by Boyce (2002), the
kPa. In this case, the maximum value, which is 13 kPa, will be utilized in the
design.
Table 17
Design Option 1
Design Option 2
Design Option 3
From the table above, the inlet pressure of the condenser that will be used
in all the three design options will be 13 kPa, with different configurations, such
51
3. Condensate Pump Conditions
The condensate pump is used to pump water through the feedwater heater.
In this design, since the process is isobaric, the outlet pressure of the steam
turbine is the same with its inlet which is equal to the inlet of the condensate
pump too. Therefore, the inlet pressure of the condenser is 13 kPa. On the other
hand, from Evans (2012), the range of efficiencies for pumps in medium or large
sizes is between 75 and 93 percent, where the design will use the average
efficiency of 84%.
Table 18
Efficiency ηp 84 %
Shown in the table above are the initial parameters for the condensate
pump which are the inlet pressure and efficiency. In line with this, the values are
13 kPa and 84%, respectively, which will be applied to the three design options.
The feed pump is the bridge between the open feedwater heater and the
HRSG. The inlet pressure of a feed pump is the same with the inlet pressure at the
open feedwater heater, since they both lie on a single pressure line. Hence, the
value for the inlet pressure of a feed pump at the last design alternative will be
0.1301 MPa. On the other hand, similar to the condensate pump, the range of
52
efficiencies for pumps in medium or large sizes is between 75 and 93 percent,
where the design will use the average efficiency of 84%. (Evans, 2012)
Table 19
Efficiency ηp 84 %
Table 19 illustrates the data for the feed pump wherein the inlet pressure is
0,1301 MPa and has an 84% efficiency. This will be applied on design option 3
mechanical into useful energy, the electricity. The ratio of electrical output to its
manufacturers that generators used have efficiencies that can reach up to 98.5%.
This part presents the calculations performed for each of the design options for
the proposed 155 MW combined steam and gas power plant system. From the Handbook
for Cogeneration and Combined Cycle Power Plants by Boyce (2002), the usual division
of energy output generated is 40% for the steam turbine while the gas turbine generates
about 60%.
53
Combustion Stoichiometry of Natural Gas
The first step in computing for the gas cycle is the stoichiometric analysis of its
fuel, in this case, the natural gas. Stoichiometry takes into account a substance's chemical
The different molar fractions for each component of natural gas, primarily
methane, ethane, propane, carbon dioxide, nitrogen, and hydrogen sulfide, are displayed
in Table 2. Hence, the values are listed as follows: 95.05%, 0.13%, 0.01%, 0.25%, 4.52%,
Combustion Equation
Excess air is the portion of the total amount of air given that is higher than what is
natural gas, approximately 5–10% more air is needed. 7.5%, the midpoint of the range,
0.9505 CH4 + 0.0013 C2H6 + 0.0001 C3H8 + 0.0452 N2 + 0.0025 CO2 + 0.0004 H2S
S : 0.0004 = c ; c = 0.0004
54
N : 0.0452(2) + (1.075)(y)(2) = (1.075)(d)(2) ; d = 6.7108
0.9505 CH4 + 0.0013 C2H6 + 0.0001 C3H8 + 0.0452 N2 + 0.0025 CO2 + 0.0004
H2S + 1.075(1.7736 O2 + 6.6688 N2) → 0.9559 CO2 + 1.9057 H2O + 0.0004 SO2 +
(1.075) 6.7108 N2
0.9505 CH4 + 0.0013 C2H6 + 0.0001 C3H8 + 0.0452 N2 + 0.0025 CO2 + 0.0004
H2S + (1.90662 O2 + 7.16896 N2) → 0.9559 CO2 + 1.9057 H2O + 0.0004 SO2 +
7.2141 N2
The mass of fuel and the composition of the air can be calculated using the
simplified combustion equation for natural gas. Thus, an equation is provided below:
m=nxM
m = mass of component, kg
Gravimetric Analysis
number of moles in that substance. The masses of the natural gas's various chemical
A. Mass of air
mair = n x M
55
mair = (MO2)(nO2) + (MN2)(nN2)
𝑘𝑔𝑂2 𝑘𝑔𝑁2
mair = (2)(16 𝑚𝑜𝑙
)(1.90662 mol) + (2)(14 𝑚𝑜𝑙
)(7.16896 mol)
The value for the combustion process was 261.74272 kg, as determined by the
B. Mass of fuel
mCH4 = (MCH4)(nCH4)
𝑘𝑔 𝑘𝑔𝐻2
mCH4= [(1)(12 𝑚𝑜𝑙𝐶 ) + (4)(1 𝑚𝑜𝑙
)] [0.9505 mol]
mC2H6 = (MC2H6)(nC2H6)
𝑘𝑔 𝑘𝑔𝐻2
mC2H6= [(2)(12 𝑚𝑜𝑙𝐶 ) + (6)(1 𝑚𝑜𝑙
)] [0.0013 mol]
mC3H8 = (MC3H8)(nC3H8)
𝑘𝑔 𝑘𝑔𝐻2
mC3H8= [(3)(12 𝑚𝑜𝑙𝐶 ) + (8)(1 𝑚𝑜𝑙
)] [0.0001 mol]
mCO2 = (MCO2)(nCO2)
56
𝑘𝑔 𝑘𝑔𝑂2
mCO2= [(1)(12 𝑚𝑜𝑙𝐶 ) + (2)(16 𝑚𝑜𝑙
)] [0.0025 mol]
5. For Nitrogen, N2
mN2 = (MN2)(nN2)
𝑘𝑔
mN2= [(2)(14 𝑚𝑜𝑙𝐶 )] [0.0452 mol]
mH2S = (MH2S)(nH2S)
𝑘𝑔 𝑘𝑔𝐻2
mH2S= [(2)(1 𝑚𝑜𝑙𝐶 ) + (1)(32 𝑚𝑜𝑙
)] [0.0004 mol]
mf = 16.6406 kgf
Meanwhile, 16.6406 kg is the obtained value for the mass of fuel in accordance
maf = ma + mf
maf = 278.38332 kg
57
Upon adding together the mass of air and the mass of the fuel component for
Air-Fuel Ratio
The mass ratio of air to fuel is referred to as the air-fuel ratio. The formula for
calculating the air-fuel ratio is to divide the air mass by the fuel mass, as given below,
𝑚𝑎
AF = 𝑚𝑓
261.74272 𝑘𝑔𝑎
AF = 16.6406 𝑘𝑔𝑓
AF = 15.72916361 kga/kgf
Therefore, the corresponding value of the air-fuel ratio for the natural gas
The obtained mass of each natural gas component as well as the total masses of
air, fuel, and air-fuel mixture will be utilized to calculate the mass fraction of the
𝑚
𝑟𝑤 = 𝑚𝑡
58
𝑚
rw, CH4 = 𝑚𝑡
15.208 𝑘𝑔
rw, CH4 = 16.6406 𝑘𝑔
𝑚
rw, C2H6 = 𝑚𝑡
0.039 𝑘𝑔
rw, C2H6 = 16.6406 𝑘𝑔
𝑚
rw, C3H8 = 𝑚𝑡
0.0044 𝑘𝑔
rw, C3H8 = 16.6406 𝑘𝑔
𝑚
rw, CO2 = 𝑚𝑡
0.11 𝑘𝑔
rw, CO2 = 16.6406 𝑘𝑔
𝑚
rw, H2S = 𝑚𝑡
0.0136 𝑘𝑔
rw, H2S = 16.6406 𝑘𝑔
59
𝑚𝑓
rw, fuel= 𝑚𝑎𝑓
16.6406 𝑘𝑔
rw, fuel= 278.38332 𝑘𝑔
On the other hand, the mass fractions for the natural gas’ air composition are
displayed below:
a. For Oxygen, O2
𝑚
rw, O2 = 𝑚𝑡
61.01184 𝑘𝑔
rw, O2 = 278.38332 𝑘𝑔
rw, O2 = 0.2330985175
b. For Nitrogen, N2
𝑚
rw, N2 = 𝑚𝑡
200.73088 𝑘𝑔
rw, N2 = 278.38332 𝑘𝑔
rw, N2 = 0.7669014825
𝑚𝑎
rw, air= 𝑚𝑎𝑓
261.74272 𝑘𝑔
rw, air= 278.38332 𝑘𝑔
The following specific heat at constant pressure and volume parameters, along
with their corresponding values from Table 10, are required in order to compute the
60
equivalent specific heat of the fuel and air for the combustion process. The information
was taken from the 8th edition of Fundamentals of Thermodynamics by Borgnakke &
Sonntag (2012).
Table 20
As a result, the variables and numbers from Table 20 will be used to determine
each component's specific heat at constant pressure. The formula to apply in order to
61
Computing the specific heat at constant pressure of the natural gas’ fuel
composition:
Hence, the total specific heat at constant pressure of the fuel will be:
62
Cp,fuel = ∑(rw x Cp)
0.0008212011586kJ/kg-K
Computing for the specific heat at constant pressure of the natural gas’ air
composition:
a. For Oxygen, O2
b. For Nitrogen, N2
Therefore, the total specific heat at constant pressure in the air will be:
63
where: Cvm = specific heat in a constant volume of mixture
Solving for the specific heat in a constant volume of the natural gas’ fuel
composition:
64
Cv, H2S = (0.0008172782231)(0.7578 kJ/kg-K)
To sum up, the total specific heat in a constant volume of the fuel will be:
0.0006193334375 kJ/kg-K
Solving for the specific heat in a constant volume of the natural gas’ air
composition:
a. For Oxygen, O2
b. For Nitrogen, N2
Hence, the total specific heat in a constant volume of the air is:
65
After determining the values, Table 21 presents the summarized values of the
Table 21
Fuel
Composition
Cp, kJ/kg-K Cv, kJ/kg-K
Based on the table above, the total specific heat in constant pressure and constant
volume of the fuel composition were yielded to the values of 2.07092 kJ/kg-K and
1.59537 kJ/kg-K, respectively. It resulted from the partial values of the specific heat in
Whereas, shown in Table 22 are the summarized values of the specific heat in
constant pressure and volume of the air with the composition of air and nitrogen.
Table 22
Air
Composition
Cp, kJ/kg-K Cv, kJ/kg-K
66
Table 22 (Continue)
Presented in Table 22 is the summary of the calculated values for the air. Its total
specific heat in constant pressure and constant volume has corresponding values of
1.01403 kJ/kg-K and 0.72565 kJ/kg-K, respectively, which come from the summation of
In order to calculate the specific heat at constant pressure of the air-fuel mixture:
a. For fuel
b. For air
67
D. Specific Heat in Constant Volume of the Air-Fuel Mixture
Whereas, to solve for the specific heat in a constant volume of the air-fuel
mixture:
a. For fuel
b. For air
summary of the specific heats at constant pressure and volume as well as the mass
Table 23
rw 0.9402241485 0.05977585151 —
68
Table 23
The summary of the calculated values for the air-fuel mixture is shown in Table
23. The calculated total specific heat at constant pressure is 1.077204885 kJ/kg-K, while
the calculated total specific heat at constant volume is 0.7776408219 kJ/kg-K. The
obtained values will be used to calculate the heat added and the work of the turbine and
compressor.
The ratio of a gas's specific heat at constant volume to its specific heat at constant
𝐶𝑝
k= 𝐶𝑣
1.077204885 𝑘𝐽/𝑘𝑔−𝐾
k= 0.7776408219 𝑘𝐽/𝑘𝑔−𝐾
k= 1.385221628
Design Option 1
simple Brayton and Rankine Cycle. The calculation is classified into three parts: Gas
A. Gas Cycle
Process 1 to 2
69
𝑇2 𝑘−1
𝑇1 ( )
= 𝑟𝑝 𝑘
𝑘−1
𝑇2 = 𝑇1 𝑟𝑝 ( ) 𝑘
1.385221628−1
1.385221628
𝑇2 = 298 𝐾(12)
T2 = 594.7438247 K
Process 1 to 2’
𝑇2−𝑇1
η𝐶 = 𝑇2'−𝑇1
𝑇2−𝑇1
𝑇2' = η𝐶
+ 𝑇1
594.7438247 𝐾−298 𝐾
𝑇2' = 0.85
+ 298 𝐾
594.7438247 𝐾−298 𝐾
0. 85 = 𝑇2'−298 𝐾
T2’= 647.110382 K
Process 2 to 3
𝑘𝐽
𝑄𝑖𝑛 = (1. 014028178 𝑘𝑔−𝐾
)(1, 300 𝐾 − 647. 110382 𝐾)
Process 3 to 4
Computing for the inlet and outlet conditions in gas turbine in an ideal state:
𝑇3 𝑘−1
𝑇4 ( )
= 𝑟𝑝 𝑘
70
𝑇3
T4 = 𝑘−1
(𝑟𝑝) 𝑘
1300 𝐾
T4 = 1.385221628−1
1.385221628
(12)
T4 = 651.3728835 K
Process 3 to 4’
𝑇3−𝑇4'
η𝑇 = 𝑇3−𝑇4
T4’ = 748.666951 K
𝑘𝐽
𝑊𝑐' = (1. 014028178 𝑘𝑔−𝐾
)(647. 110382 𝐾 − 298 𝐾)
𝑘𝐽
𝑊𝑡' = (1. 077204885 𝑘𝑔−𝐾
)(1, 300 𝐾 − 748. 666951 𝐾)
In the topping cycle, the total work net calculated will be:
71
Wnet,gc = 239.8908894 kJ/kg
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
𝐸𝑃
BP = η𝑔
1000 𝑘𝑊 1 𝑘𝐽/𝑠
93 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 94416.24365 kJ/s
𝐵𝑟𝑎𝑘𝑒 𝑃𝑜𝑤𝑒𝑟
maf = 𝑊𝑛𝑒𝑡
94416.24365 𝑘𝐽/𝑠
maf = 239.8908894 𝑘𝐽/𝑘𝑔
Solving for the mass of air, ma using the air-fuel ratio of 15.72916361:
𝑚𝑎𝑓
ma = 𝐴𝐹
393.5799475 𝑘𝑔/𝑠
ma = 15.72916361
ma = 25.02230616 kg/s
mf = maf - ma
mf = 368.5576413 kg/s
At Compressor
72
Figure 30. Control Volume at Compressor for Design Option 1
Eout = Ein
𝑘𝐽 𝑘𝐽
Wc ' = (25.02230616 𝑠
)(1.014028178 𝑘𝑔−𝐾 )(647.110382 - 298) K
At Combustion Chamber
Eout = Ein
73
Qin = m3CpT3 - m2CpT2’ ; maf = m2 = m3
𝑘𝐽 𝑘𝐽
Qin = (393.5799475 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1300 - 647.110382) K
At Gas Turbine
𝑘𝐽 𝑘𝐽
Wt ' = (393.5799475 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1300 - 748.666951) K
𝑊𝑡' − 𝑊𝑐'
η𝑡ℎ = 𝑄𝑖𝑛
𝑥 100%
(233,746.601 −138,601.043) 𝑘𝑊
η𝑡ℎ = 276,803.1579 𝑘𝑊
𝑥 100%
74
ηth = 34.37300308%
which falls on the range of 30-40% as typical values of efficiencies for gas cycles.
(Boyce, 2002)
Table 24
Parameter Value
Table 14 presents the summary of calculation for design option 1, particularly the
gas or topping cycle. It is shown that the heat added, compressor work, turbine work, net
work output, and thermal efficiency has the values as follow: 276,803.1579 kW,
B. Steam Cycle
Statepoint 6
Pressure, P6 3 MPa
Temperature, T6 400 °C
75
Tsat @ 3 MPa = 233.9 °C
h6 = 3230.9 kJ/kg
s6 = 6.9212 kJ/kg -K
v6 = 0.09936 m3/kg
Statepoint 7
s7 = 6.9212 kJ/kg -K
P7 = 0.013 MPa
𝑠7 − 𝑠𝑓7
x= 𝑠𝑓𝑔7
7.133786815 𝑘𝐽/𝑘𝑔−𝐾 − 0.7172 𝑘𝐽/𝑘𝑔−𝐾
x= 7.3412 𝑘𝐽/𝑘𝑔−𝐾
x = 0.8450934452
h7 = hf7 + xhfg7
Statepoint 8
P8 = P7 = 0.013 MPa
Since the statepoint condition is in saturated liquid, the values of saturated liquid
h8 = h8 = 213.67 kJ/kg
v8 = v8 = 0.0010126 m3/kg
Statepoint 9
The work of the condensate pump should be solved first using the formula Wpump
1 𝑘𝐽
Wpump = 0.0010126 m3/kg (3,000 - 13) kPa ( 3 )
𝑘𝑃𝑎−𝑚
h9 = Wpump + h8
h9 = 216.6946362 kJ/kg
Statepoint 9’
𝑊𝑝𝑢𝑚𝑝
np = 𝑊𝑝𝑢𝑚𝑝'
where np = 0.84
77
3.0246362 𝑘𝐽/𝑘𝑔
Wpump’ = 0.84
h9’ = Wpump + h8
Wt = h6 - h7
Wt = 1005.738582 kJ/kg
𝑊𝑡'
nt = 𝑊𝑡
where nt = 0.9
Wt’ = nt x Wt
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
78
𝐸𝑃
BP = η𝑔
1000 𝑘𝑊 1 𝑘𝐽/𝑠
155 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 157360.4061 kJ/s
ms = 69.00769154 kg/s
At Turbine
Eout = Ein
Wt + msh7 = msh6
Wt = ms(h6 - h7)
Wt = 69403.69782 kW
79
Wt’ = 62463.32804 kW
At Pump
Eout = Ein
Wpump’ = 248.4799547 kW
At HRSG
Eout = Ein
80
Solving for Head Added, Qin
Qin = 207,963.5972 kW
At Condenser
Eout = Ein
Qout = 138808.3793 kW
Wnet = 62,214.84808 kW
81
𝑊𝑛𝑒𝑡
nth = 𝑄𝑖𝑛
x 100 %
62,214.84808 𝑘𝑊
nth = 207,963.5972
x 100 %
nth = 29.9162204 %
which falls on the range of 30-40% as typical values of efficiencies for steam cycles.
(Boyce, 2002)
Table 25
Parameter Value
Table 15 presents the summary of calculation for design option 1, particularly the
steam or bottoming cycle. It is shown that the heat added, pump work, turbine work, net
work output, and thermal efficiency has the values as follow: 207,963.5972 kW,
82
Combined Cycle
𝑊𝑛𝑒𝑡, 𝑡𝑜𝑡𝑎𝑙
nth1 = 𝑄𝑖𝑛, 𝑔𝑎𝑠
x 100 %
157,360.4061 𝑘𝑊
nth1 = 276,803.1579
x 100 %
nth1 = 56.84920911 %
Plants by Boyce (2002), thermal efficiencies can reach up to 60%. Hence, the calculated
Table 26
Parameter Value
cycle. It is shown that the total net work output and thermal efficiency has the values as
83
Design Option 2
A. Gas Cycle
Process 1 to 2
𝑇2 𝑘−1
𝑇1 ( )
= 𝑟𝑝 𝑘
𝑘−1
𝑇2 = 𝑇1 𝑟𝑝 ( ) 𝑘
1.385221628−1
1.385221628
𝑇2 = 298 𝐾(15)
T2 = 632.8197442 K
Process 1 to 2’
𝑇2−𝑇1
η𝐶 = 𝑇2'−𝑇1
𝑇2−𝑇1
𝑇2' = η𝐶
+ 𝑇1
632.8197442−298 𝐾
𝑇2' = 0.85
+ 298 𝐾
632.8197442 𝐾−298 𝐾
0. 85 = 𝑇2'−298 𝐾
T2’= 691.9055815 K
Process 2 to 3
84
𝑘𝐽
𝑄𝑖𝑛 = (1. 077204885 𝑘𝑔−𝐾
)(1, 300 𝐾 − 691. 9055815 𝐾)
Process 3 to 4
Computing for the inlet and outlet conditions in gas turbine in an ideal state:
𝑇3 𝑘−1
𝑇4 ( )
= 𝑟𝑝 𝑘
𝑇3
T4 = 𝑘−1
(𝑟𝑝) 𝑘
1300 𝐾
T4 = 1.385221628−1
1.385221628
(15)
T4 = 612.1806463 K
Process 3 to 4’
𝑇3−𝑇4'
η𝑇 = 𝑇3−𝑇4
T4’ = 715.3535493 K
𝑘𝐽
𝑊𝑐' = (1. 014028178 𝑘𝑔−𝐾
)(691. 9055815 𝐾 − 298 𝐾)
85
𝑘𝐽
𝑊𝑡' = (1. 077204885 𝑘𝑔−𝐾
)(1, 300 𝐾 − 715. 3535493 𝐾)
In the topping cycle, the total work net calculated will be:
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
𝐸𝑃
BP = η𝑔
1000 𝑘𝑊 1 𝑘𝐽/𝑠
93 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 94416.24365 kJ/s
𝐵𝑟𝑎𝑘𝑒 𝑃𝑜𝑤𝑒𝑟
maf = 𝑊𝑛𝑒𝑡
94416.24365 𝑘𝐽/𝑠
maf = 230.3526539 𝑘𝐽/𝑘𝑔
Solving for the mass of air, ma using the air-fuel ratio of 15.72916361:
𝑚𝑎𝑓
ma = 𝐴𝐹
409.876952 𝑘𝑔/𝑠
ma = 15.72916361
ma = 26.05840731 kg/s
86
Solving for the mass of air, mf:
mf = maf - ma
mf = 383.8185447 kg/s
At Compressor
Eout = Ein
𝑘𝐽 𝑘𝐽
Wc ' = ( 26.05840731 𝑠
)(1.014028178 𝑘𝑔−𝐾 )(691.9055815 - 298) K
At Combustion Chamber
87
Eout = Ein
𝑘𝐽 𝑘𝐽
Qin = (409.876952 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1300 - 691.9055815) K
At Gas Turbine
𝑘𝐽 𝑘𝐽
Wt ' = (409.876952 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1300 - 715.3535493) K
88
Therefore, the thermal efficiency, ηth will be:
𝑊𝑡' − 𝑊𝑐'
η𝑡ℎ = 𝑄𝑖𝑛
𝑥 100%
(258,133.9516 −162,860.7399) 𝑘𝑊
η𝑡ℎ = 268,486.7325 𝑘𝑊
𝑥 100%
ηth = 35.48525876%
which falls on the range of 30-40% as typical values of efficiencies for gas cycles.
(Boyce, 2002)
Table 27
Parameter Value
Table 27 presents the summary of calculation for design option 2, particularly the
gas or topping cycle with a simple cycle. It is shown that the heat added, compressor
work, turbine work, net work output, and thermal efficiency were computed from the
temperatures and pressures obtained in each statepoint. Hence, the total values are listed
89
as follows: 276,803.1579 kW, 138,601.043 kW, 233,746.601 kW, 95,145.55801 kW, and
34.37300308 %.
B. Steam Cycle
Statepoint 6
Pressure, P6 14 MPa
Temperature, T6 540 °C
h6 = 3432.4 kJ/kg
s6 = 6.5289 kJ/kg -K
Statepoint 7
s7 = 6.5289 kJ/kg -K
P7 = 4.5 MPa
At 4.5 MPa
P (MPa) sf (kJ/kg - K) sg (kJ/kg-K)
4.4 2.8485 6.0296
4.5 2.86085 6.01995
4.6 2.8732 6.0103
90
s7 > sg, the statepoint is in superheated vapor region
At 4.5 MPa
s (kJ/kg-K) h (kJ/kg) T (°C)
6.5131 3080.6 350
6.5289 3081.0029 354.029
6.5537 3106.1 360
T7 = 354.029°C
h7 = 3081.0029 kJ/kg
Statepoint 8
P8 = P7 = 4.5 MPa
T8 = 540 °C
Interpolation Method
P, MPa Tsat, °C
4.4 256.12
4.5 257.475
4.6 258.83
91
h8 = 3531.9 kJ/kg
s8 = 7.1467 kJ/kg -K
Statepoint 9
s9 = 7.1467 kJ/kg -K
P9 = 0.013 MPa
𝑠9 − 𝑠𝑓9
x= 𝑠𝑓𝑔9
x = 0.8758104942
h9 = hf9 + xhfg9
h9 = 2298.274138 kJ/kg
Statepoint 10
92
Since the statepoint condition is in saturated liquid, the values of saturated liquid
Statepoint 11
The work of the condenser pump should be solved first using the formula Wpump =
Statepoint 11’
𝑊𝑝𝑢𝑚𝑝
np = 𝑊𝑝𝑢𝑚𝑝'
where np = 0.84
14.1632362 𝑘𝐽/𝑘𝑔
Wpump’ = 0.84
93
h11’ = 16.86099548 kJ/kg + 213.67 kJ/kg
Wt = 1585.022962 kJ/kg
𝑊𝑡'
nt = 𝑊𝑡
where nt = 0.9
Wt’ = nt x Wt
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
𝐸𝑃
BP = η𝑔
1000 𝑘𝑊 1 𝑘𝐽/𝑠
155 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 157360.4061 kJ/s
94
Solving for the mass of steam, ms
ms = 44.04410202 kg/s
Figure 40. Control Volume at Steam High Pressure Turbine for Design Option 2
Eout = Ein
WHPT =15,476.96972 kW
Figure 41. Control Volume at Steam Low Pressure Turbine for Design Option 2
95
Eout = Ein
WLPT =54,333.94332 kW
Wt = WHPT + WLPT
Wt = 15,476.96972 kW +54,333.94332 kW
Wt = 69,810.91304 kW
Wt’ = 62,829.82172 kW
At Pump
Eout = Ein
96
Wpump’ = 44.04410202 kg/s (230.5309955 - 213.67 ) kJ/kg
Wpump’ = 742.627406 kW
At HRSG
Eout = Ein
Qin = 160,882.8029 kW
At Condenser
Eout = Ein
97
Solving for Head Rejected, Qout
Qout = 91814.51733 kW
Wnet = 62087.19432 kW
𝑊𝑛𝑒𝑡
nth = 𝑄𝑖𝑛
x 100 %
62087.19432 𝑘𝑊
nth = 160882.8029 𝑘𝑊
x 100 %
nth = 23.12486495 %
which falls on the range of 20-40% as typical values of efficiencies for steam cycles.
(Boyce, 2002)
Table 28
Parameter Value
98
Table 28
Table 28 presents the summary of calculation for design option 2, particularly the
steam or bottoming cycle. It is shown that the heat added, pump work, turbine work, net
work output, and thermal efficiency has the values as follow: 160,882.8029 kW,
Combined Cycle
𝑊𝑛𝑒𝑡, 𝑡𝑜𝑡𝑎𝑙
nth1 = 𝑄𝑖𝑛, 𝑔𝑎𝑠
x 100 %
157,360.4061 𝑘𝑊
nth1 = 268,486.7325𝑘𝑊
x 100 %
nth1 = 58.61012372 %
Plants by Boyce (2002), thermal efficiencies can reach up to 60%. Hence, the calculated
99
Table 29
Parameter Value
cycle. It is shown that the total net work output and thermal efficiency has the values as
Design Option 3:
A. Gas Cycle
Process 1 to 2
𝑇2 𝑘−1
𝑇1 ( )
= 𝑟𝑝 𝑘
𝑘−1
𝑇2 = 𝑇1 𝑟𝑝 ( ) 𝑘
1.385221628−1
1.385221628
𝑇2 = 298 𝐾(3. 5)
T2 = 420.9912823 K
Process 1 to 2’
𝑇2−𝑇1
η𝐶 = 𝑇2'−𝑇1
100
𝑇2−𝑇1
𝑇2' = η𝐶
+ 𝑇1
420.9912823 𝐾−298 𝐾
𝑇2' = 0.85
+ 298 𝐾
420.9912823 𝐾−298 𝐾
0. 85 = 𝑇2'−298 𝐾
T2’= 442.6956262 K
Process 2 to 3
𝑘𝐽
𝑄𝑖𝑛 = (1. 077204885 𝑘𝑔−𝐾
)(1073 𝐾 − 442. 6956262 𝐾)
Process 3 to 4
Computing for the inlet and outlet conditions in a gas turbine in an ideal state:
𝑇3 𝑘−1
𝑇4 ( )
= 𝑟𝑝 𝑘
𝑇3
T4 = 𝑘−1
(𝑟𝑝) 𝑘
1073 𝐾
T4 = 1.385221628−1
1.385221628
(3.5)
T4 = 759.5264165 K
Process 3 to 4’
𝑇3−𝑇4'
η𝑇 = 𝑇3−𝑇4
101
𝑇4' = 1073 𝐾 − 0. 85(1073 𝐾 − 759. 5264165 𝐾)
T4’ = 806.547454 K
Process 5 to 6
Computing for the inlet and outlet conditions in a gas turbine in an ideal state, when T3 =
T5.
𝑇5 𝑘−1
𝑇6 ( )
= 𝑟𝑝 𝑘
𝑇5
T6 = 𝑘−1
(𝑟𝑝) 𝑘
1073 𝐾
T6 = 1.385221628−1
1.385221628
(3.5)
T6 = 759.5264165 K
Process 5 to 6’
𝑇3−𝑇4'
η𝑇 = 𝑇3−𝑇4
T6’ = 806.547454 K
𝑘𝐽
𝑊𝑐' = (1. 014028178 𝑘𝑔−𝐾
)(442. 6956262 𝐾 − 298 𝐾)
102
𝑊𝑡1' = 𝐶𝑝𝑡(𝑇3 − 𝑇4')
𝑘𝐽
𝑊𝑡1' = (1. 077204885 𝑘𝑔−𝐾
)(1073 𝐾 − 806. 547454 𝐾)
𝑘𝐽
𝑊𝑡2' = (1. 077204885 𝑘𝑔−𝐾
)(1073 𝐾 − 806. 547454 𝐾)
𝑘𝐽 𝑘𝐽
𝑊𝑡' = (1. 077204885 𝑘𝑔−𝐾
)(1073 𝐾 − 806. 547454 𝐾) + (1. 077204885 𝑘𝑔−𝐾
)
In the topping cycle, the total work net calculated will be:
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
𝐸𝑃
BP = η𝑔
103
1000 𝑘𝑊 1 𝑘𝐽/𝑠
93 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 94416.24365 kJ/s
𝐵𝑟𝑎𝑘𝑒 𝑃𝑜𝑤𝑒𝑟
maf = 𝑊𝑛𝑒𝑡
94416.24365 𝑘𝐽/𝑠
maf = 427.3225263 𝑘𝐽/𝑘𝑔
Solving for the mass of fuel, mf using the air-fuel ratio of 15.72916361:
𝑚𝑎𝑓
mf = 𝐴𝐹
220.9484355 𝑘𝑔/𝑠
mf = 15.72916361
mf = 14.04705558 kg/s
ma = maf - mf
ma = 206.9013799 kg/s
At Compressor
Eout = Ein
104
Solving for the mass balance at the compressor:
𝑘𝑔 𝑘𝐽
Wc ' = (206.9013799 𝑠
)(1.014028178 𝑘𝑔−𝐾 )(442.6956262 - 298) K
At Combustion Chamber
𝑘𝐽 𝑘𝐽
Qin = (220.9484355 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1073- 442.6956262) K
Figure 47. Control Volume at High Pressure Gas Turbine for Design Option 3
105
Eout = Ein
Solving for the mass balance at the high pressure gas turbine:
𝑘𝐽 𝑘𝐽
Wt1 ' = (220.9484355 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1073-806.547454) K
At Reheater
Eout = Ein
𝑘𝐽 𝑘𝐽
Qreheat = (220.9484355 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1073 - 570.9171458) K
106
At Low Pressure Gas Turbine
Figure 49. Control Volume at Low Pressure Gas Turbine for Design Option 3
Eout = Ein
Solving for the mass balance at the low pressure gas turbine:
𝑘𝐽 𝑘𝐽
Wt2 ' = (220.9484355 𝑠
)(1.077204885 𝑘𝑔−𝐾 )(1073 - 806.547454) K
ηth = 35.79653183%
107
The calculated thermal efficiency of the Brayton cycle is approximately
Table 30
Parameter Value
Table 30 presents the summary of calculation for design option 3, particularly the
gas or topping cycle. It is shown that the heat added, compressor work, turbine work, net
work output, and thermal efficiency has the values as follow: 269,515.7859 kW,
B. Steam Cycle
Statepoint 8
Temperature, T8 585 °C
Interpolation Method
108
P, MPa Tsat, °C
16.4 349.44
16.5 349.935
16.6 350.43
At 16.5 MPa
T (°C) h (kJ/kg) s (kJ/kg-K)
580 3515 6.5592
585 3528.55 6.575
590 3542.1 6.5908
h8 = 3528.55 kJ/kg
s8 = 6.575 kJ/kg -K
Statepoint 9
s9 = 6.575 kJ/kg -K
P9 = 4.5 MPa
109
s9 > sg, the statepoint is in superheated vapor region
At 4.5 MPa
s (kJ/kg-K) h (kJ/kg) T (°C)
6.5537 3106.1 360
6.575 3119.703817 365.4198473
6.593 3131.2 370
T9 =365.4198473°C
h9 = 3119.703817 kJ/kg
Statepoint 10
T10 = 585 °C
Interpolation Method
P, MPa Tsat, °C
4.4 256.12
4.5 257.475
4.6 258.83
Tsat 4.5 MPa = 257.475 °C
At 4.5 MPa
T (°C) h (kJ/kg) s (kJ/kg-K)
580 3624.3 7.2575
110
585 3635.85 7.27095
590 3647.4 7.2844
h10 = 3635.85 kJ/kg
Statepoint 11
sg = 7.27095 kJ/kg -K
T11 = 107.1520238 °C
Statepoint 12
111
hf12 = 213.67 kJ/kg
𝑠12 − 𝑠𝑓12
x= 𝑠𝑓𝑔12
x = 0.8927355201
Statepoint 13
Since the statepoint condition is in saturated liquid, the values of saturated liquid
112
Statepoint 14
The work of the condenser pump should be solved first using the formula Wpump,1
Statepoint 14’
𝑊𝑝𝑢𝑚𝑝,1
np = 𝑊𝑝𝑢𝑚𝑝,1'
where np = 0.84
0.1185746563 𝑘𝐽/𝑘𝑔
Wpump,1’ = 0.84
Statepoint 15
113
Since the statepoint condition is in saturated liquid, the values of saturated liquid
At 1.484554712 MPa
P (MPa) hf (kJ/kg) sf (kJ/kg-K) vf (m3/kg)
0.13 449.15 1.3867 0.0010492
0.1300992063 449.2428571 1.386944048 0.001049217857
0.135 453.83 1.399 0.0010501
Statepoint 16
The work of the condenser pump should be solved first using the formula Wpump,2
Statepoint 16’
𝑊𝑝𝑢𝑚𝑝,2
np = 𝑊𝑝𝑢𝑚𝑝,2'
114
where np = 0.84
17.17559223 𝑘𝐽/𝑘𝑔
Wpump,2’ = 0.84
Solving for y
ℎ15 − ℎ14'
y= ℎ11 − ℎ14'
y = 0.09518843183
Wt = 1672.956824 kJ/kg
𝑊𝑡'
nt = 𝑊𝑡
where nt = 0.9
Wt’ = nt x Wt
115
Solving for the Net Work Output, Wnet
Solving for the brake power, BP for a generator efficiency of 98.5% or 0.985:
𝐸𝑃
ηg = 𝐵𝑃
𝐸𝑃
BP = η𝑔
1000 𝑘𝑊 1 𝑘𝐽/𝑠
155 𝑀𝑊 ( )( )
BP = 1 𝑀𝑊
0.985
1 𝑘𝑊
BP = 157360.4061 kJ/s
ms = 42.38456216 kg/s
Figure 50. Control Volume at Steam High Pressure Turbine for Design Option 3
116
Eout = Ein
WHPT =17,328.76646 kW
Figure 51. Control Volume at Steam Low Pressure Turbine for Design Option 3
Eout = Ein
WLPT = 53578.77605 kW
Wt = WHPT + WLPT
117
Wt = 17,328.76646 kW + 53578.77605 kW
Wt = 70,907.54251 kW
Wt’ = 63,816.78826 kW
At Pump I
Wpump,1’ = 5.983017729 kW
At Pump II
118
Eout = Ein
Wpump,2’ =866.6428054 kW
Thus,
Wpump’ =872.6258231 kW
At HRSG
kJ/kg
Qin = 151,525.0722 kW
119
At Condenser
Qout =81,489.58597kW
Wnet = 62944.16244 kW
𝑊𝑛𝑒𝑡
nth = 𝑄𝑖𝑛
x 100 %
62,944.16244 𝑘𝑊
nth = 151,525.0722 𝑘𝑊
x 100 %
nth = 41.54042729 %
which exceeds a little the range of 20-40% as typical values of efficiencies for steam
120
Table 31 displays the table on the summary of calculations performed to analyze
Table 31
Parameter Value
Table 31 presents the summary of calculation for design option 3, particularly the
steam or bottoming cycle. It is shown that the heat added, pump work, turbine work, net
work output, and thermal efficiency has the values as follow: 151,525.0722 kW,
Combined Cycle
𝑊𝑛𝑒𝑡, 𝑡𝑜𝑡𝑎𝑙
nth1 = 𝑄𝑖𝑛, 𝑔𝑎𝑠
x 100 %
157360.4061 𝑘𝑊
nth1 = 269,515.7859 𝑘𝑊
x 100 %
121
nth1 = 58.3863411 %
Plants by Boyce (2002), thermal efficiencies can reach up to 60%. Hence, the calculated
Table 32
Parameter Value
cycle. It is shown that the total net work output and thermal efficiency has the values as
For a clear understanding of the systems proposed, discussed below are the
detailed processes for each design option, in accordance with their cycle and
Temperature-entropy (T-s) diagrams. The three design options have the same working
Design Option 1
Shown in the following diagrams are the cycle and T-s diagrams for a simple
122
Figure 56. Cycle Diagram for Design Option 1
Figures 56 and 57 reflect the design option 1, which consists of a simple gas
turbine cycle and simple steam turbine cycle. There are nine state points included in this
cycle, wherein state points 1 to 5 are for the gas turbine cycle and 6 to 9 for the steam
123
turbine. The components for the gas cycle are compressor, combustion chamber and the
gas turbine. The process starts with the air being compressed isentropically in the air
compressor. This process occurs on the state point 1-2. Furthermore, the fuel is injected
and burned using the compressed air in the combustion chamber to raise the temperature.
This process on the state point 2-3 is isobaric combustion where pressure remains
constant. Then, the high temperature gas enables the turbine to rotate and generate
electricity which results in the isentropic expansion occurring on state point 3-4. State
In connection with the gas cycle, its extracted gas will be fed into the heat
recovery steam generator (HRSG) as shown on the state point 5. The simple steam cycle
consists of a pump, HRSG boiler, steam turbine and a condenser. State point 8-9 occurs
on the pump where the water is pumped on the boiler. Then the boiler will transform the
water into steam at state point 9-6 which is utilized to turn the turbine blades and generate
the electricity. This isentropic expansion of the steam occurs on state point 6-7. The
Design Option 2
Presented in the following diagrams are the cycle and T-s diagrams for a
combined cycle with simple gas cycle and single-stage reheat cycle, denoted as the
124
Figure 58. Cycle Diagram for Design Option 2
On the other hand, Figures 58 and 59 account for design option 2 that includes a
simple gas turbine cycle and a single-stage reheat steam turbine. The combined cycle
consists of 11 state points, with state points 1-5 for the simple gas turbine and 6 to 11 for
the single-stage reheat steam turbine. Compressor, combustion chamber, and gas turbine
125
make up the gas turbine cycle. Similar to the first design alternative, the process starts in
the air compressor where air is compressed isentropically. This procedure takes place in
states 1-2. Moreover, the compressed air in the combustion chamber is used to inject and
burn the fuel, increasing the temperature. Also known as isobaric combustion, this
process occurs at state points 2-3 and pressure is maintained throughout. On the other
hand, isentropic expansion then takes place on state points 3–4, which is caused by the
high temperature gas allowing the turbine to rotate and produce electricity. The heat
rejection phase of the gas cycle is described in state points 3–4, whereas the cycle will
extract the gas and use it to power the HRSG, which is seen in state point 5.
Meanwhile, the steam turbine consists of a pump, condenser, HRSG boiler as well
as high and low pressure turbines. The single-stage reheat steam turbine cycle starts when
the steam enters the high pressure turbine and then expands isentropically, state point 6-7,
for reheating, state point 7-8 then the steam will enter the low pressure turbine. After the
expansion the steam will be condensed in the condenser, state point 9-10 then the pump
will push the water in the boiler at state point 10-11 then the cycle continues.
Design Option 3
Presented in the following diagrams are the cycle and T-s diagrams for a
combined cycle with a single-stage reheat gas cycle and single-stage reheat-regenerative
126
Figure 60. Cycle Diagram for Design Option 3
For the last design option, it consists of a single-stage reheat gas turbine cycle and
single reheat and regenerative steam turbine cycle, as shown in Figures 60 and 61. The
combined cycle has 16 state points, with state points 1-7 for single reheat gas turbines
and 8-16 for the single reheat and regenerative steam turbine cycle. The single reheat gas
turbine cycle includes compressor, combustion chamber, gas turbines and reheater. The
gas turbine cycle starts at state point 1-2 where the air is isentropically compressed in the
127
compression. Right after, the compressed air is utilized to burn the fuel injected at the
combustion chamber at state point 2-3 where isobaric combustion occurs. For state point
3-4, isentropic expansion takes place then the gas is reheated, state point 4-5 then
expands isentropically, state point 5-6. The gas is then extracted into the HRSG boiler at
state point 7.
boiler (HRSG), Two stage turbine,the high and the low pressure turbine, condenser and
two pumps. The single reheat and single regenerative steam turbine cycle starts at state
point 8-9 where the steam enters the turbine and expands isentropically before reheating.
The steam enters the HRSG boiler for reheating at state point 9-10. Then the reheated
steam expands isentropically at state points 10-11 and 11-12. However at state point 11,
the steam is extracted by an open feedwater heater. The steam is condensed in the
condenser at state point 12-13. The feed pump I is at state point 13-14 and the feed pump
II which connects the open feedwater heater that the steam at state point 11 enters is at
state point 15-16 which pushes the liquid back in the HRSG boiler.
Upon performing all the calculations necessary for designing the combined steam
and gas cycle power plant, the resulting parameters have been the basis for selecting the
appropriate equipment from various catalogs and manufacturers. This section shows the
Table 33 presents the summary of equipment for design option 1. This includes
the equipment, manufacturer, selection parameters, and specifications for gas turbine, air
compressor, condenser, feed pump, HRSG, steam turbine, as well as gas and steam
128
generators. The equipment manufacturers for this design option are Siemens, GE Gas
Power, Sulzer, and Thermax. Whereas, the selection parameters are power output,
exhaust and inlet pressures and temperatures, capacity, efficiency, and discharge pressure.
Table 33
129
35,000 m2
Tube Length:
Up to 18m
130
10.5-20 kV
Table 33 presents the equipment selection for design option 2. This includes the
equipment, manufacturer, selection parameters, and specifications for gas turbine, air
compressor, condenser, feed pump, HRSG, steam turbine, gas generator and steam
generator. The equipment manufacturers for this design option are Siemens, GE Gas
Power, Sulzer, and Thermax, whereas various parameters were set as independent
Table 34
131
532°C
132
Turbine Output: Power Output:
25-75 MW 25-75 MW
Inlet Speed: Up to
Pressure: Up 13,200 rpm
to 14 MPa Inlet Pressure:
Up to 14 MPa
Inlet
Temperature:
Up to 540°C
Table 35 displays the summary of equipment for the last design option. This
includes the equipment, manufacturer, selection parameters, and specifications for gas
turbine, air compressor, condenser, feed pump, HRSG, steam turbine, as well as gas and
steam generators. Similar to the first two design alternatives, the equipment
133
manufacturers of every component are listed: Siemens, GE Gas Power, Sulzer, and
Thermax.
Table 35
134
Tube Length:
Up to 18m
135
Steam Siemens Apparent Model:
Generator Power: SGen-100A
25-180 Frequency: 50
MVA Hz
Efficiency: Apparent
Up to Power: 25-180
98.5% MVA
Efficiency: Up
to 98.5%
Terminal
Voltage:
6.3-15.75 kV
Upon performing the calculations and selecting the appropriate equipment from
catalogues, a plant layout was established for the proposed combined gas and steam
power plant. Along with the main plant layout are the ancillary buildings that play an
important role to the plant itself. Shown in Figure 62 is the plant layout in its isometric
view.
136
As seen in the figure above, the 3D visualization of the proposed power plant was
created with the software application SketchUp 2022. The planned project is situated on a
65,054.50 square meter site. It consists of many facilities such as the office, fire station,
As such, the plant layout in its top view is presented in Figure 63, with labels for
Illustrated in Figure 63 is the layout of the combined cycle power plant in its top
perspective. In line with this, listed below are the facilities included as well as their
137
1. Parking area
A facility where the transport vehicles of the employees and visitors can be
situated. Furthermore, it is located right after the entrance of the power plant which
makes it accessible. The parking area lies inside the vicinity, making the vehicles safe.
2. Guard House
The center of security of the proposed power plant is the guard house, which also
serves as the lounge for the guards after their duty. Also, there are security cameras
installed in this facility which are monitored daily. The area covered by the guard house
The safety and satisfaction of the employees are also considered in making the
proposed design of this power plant. This location of the facility is accessible for every
office and building in the proposed design of the power plant, with a measurement of 10
4. Office
The office or offices for general administration is also considered in the design of
the proposed power plant. This is where the executive offices,meeting place or office for
the investors and shareholders are located here, that has the dimensions of 8 meters long
5. Fire Station
Fire stations are also included in the proposed design of this power plant. This
facility will ensure the safety of the workers if an emergency happens on the power plant.
Moreover, the fire station is also responsible for the fire prevention program for the
138
power plant, where the risk of having a fire accident will be minimized. This facility, of
56 square meter area, is located near the power plant operation which makes it accessible
6. Warehouse
The warehouse is the facility where the storage of the raw materials happens. It is
responsible for accepting the materials that will be used in the powerplant and ensuring
its quality while storing before using those materials. In line with this, the area for the
7. Maintenance Department
fixing, and installing machinery, industrial equipment, and other assets that support
power plant operations. Every piece of equipment in a power plant plays an important
role in meeting performance objectives and supporting the plant's workflow. In addition,
consequences ranging from decreased plant output to full-fledged outages. As such, this
area covers 6.5 meters by 7.5 meters, with a total area of 48.75 square meters.
This facility, 8 meters long and 7.5 meters wide, monitors all plant activities to
distribution of electricity from power plants to businesses, homes, and factories. To sum
up, the control room is a room for troubleshooting if something is wrong within the
system. The thermal scanners and other measuring equipment are recorded with this
facility.
139
9. Generator
This part of the proposed design of the power plant is where the conversion of the
mechanical energy into electricity. This facility includes the generator which is a main
component of the power plant. Two generators are proposed in the design, which is one
The most significant part of the power plant is the combined cycle power plant.
This is the system that creates the mechanical energy that is passed by the generator.
Furthermore, several pieces of equipment are included in this cycle. This combined cycle
utilizes both gas turbine cycle and steam turbine cycle to increase the power plants
efficiency.
electricity on its designated substation or receives power from a nearby generating station
and uses a large power transformer to boost the power output for transport to different
areas.
140
CHAPTER III
ECONOMIC ANALYSIS
This chapter presents the economic analysis of the design taking into account the
computation of capital expenditures, operating expenditures, and the total project cost. In
relation to this, the power demand analysis will be shown as well as the sensitivity
analysis, considering the economic indicators such as the net present value, payback
period, and rate of return on investment. Hence, this chapter determines the economic
As discussed in the previous chapter, the load demand projection for 15 years has
been tabulated below. The load demand comes from the data gathered from QUEZELCO
I, with an increased percentage rate of 6.85% annually, for a straight line method.
Table 36
141
Table 36 (Continue)
Table 36 shows the projected load until the year 2038. The projected load for the
A predicted load estimate of 115.51 MW is for the next fifteen years, as of 2038.
From an average demand and peak demand of 84.78MW and 115.51 MW, respectively,
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐷𝑒𝑚𝑎𝑛𝑑
Load factor = 𝑃𝑒𝑎𝑘 𝐷𝑒𝑚𝑎𝑛𝑑
84.17880294 𝑀𝑊
Load factor = 115.51 𝑀𝑊
The load factor estimates up to 0.7288 or 72.88 percent. This denotes an average
value for a load factor which has a significant effect on the cost per unit generated by a
142
consumer. On the other hand, for an average demand of 84.78 MW and a plant capacity
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐷𝑒𝑚𝑎𝑛𝑑
Plant capacity factor = 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
84.17880294 𝑀𝑊
Plant capacity factor = 155 𝑀𝑊
The plant capacity factor obtained was 0.5431 or roughly 54.31%. This shows the
ratio of the average demand or the actual capacity generated for a particular period of
time to the maximum capacity the plant can deliver, in this case, is 155 MW. Thus, a
factor of more than half is a good thing especially that it is connected to the load factor
which causes a significant effect to the consumption cost paid by the customers. Overall,
the load and capacity factor were determined as they will be utilized for the economic
Capital Expenditures
First in line is the calculation of the capital expenditures, which refers to the
several expenses associated with building a combined steam and gas turbine power plant
system. It is the sum of money spent on the project's entire operation, including the cost
of the land, the cost of the equipment, the cost of the building, the cost of the
construction, the cost of the physical labor, and other fees. All the currencies are set in
US Dollars ($).
I. Land Cost
This part will discuss the land cost for a 155 MW combined cycle power plant
with a land area of 65,075 square meters, which will be constructed in Brgy. Bacon,
Ibaba, General Quezon. It is important to have an idea on how much land costs per square
143
meter in the said vicinity to determine whether the price is justifiable or not. In line with
this, all the design options will have the same measurement and price of land.
According to the Bureau of Internal Revenue (BIR), under the Revenue District
Office (RDO No. 61) for Department Order (DO 037-2022), the cost of land per square
meter for an area specified as CR or commercial is Php1,100 or $20.26. In this case, for a
land area of 65,075 m2, the total land area cost is $1,318,419.50.
B. Land Tax
Meanwhile, Seabury (2020) stated that property taxes, particularly land, can be
obtained by using the value of the property multiplied to its corresponding rate. In terms
of the rate of tax applied to the cost of land area, the typical value is 2% if the location is
in the vicinity of Metro Manila and 1% in provinces, according to the Property Tax
Reform of the Department of Finance (2013). Since the location lies outside Metro
With this, shown in Table 37 is the total land cost for design options 1,2, and 3.
144
Table 37
The land cost for the 155 MW combined cycle power plant at Brgy Bacong Ibaba,
General Luna, Quezon is presented in the table above. This includes the rate, price, and
total price for land area cost and land tax. Adding the total price for land area cost and
This section will discuss the estimated costs of each piece of equipment utilized in
the three design options for combined cycle power plant with a 155 MW capacity. The
model and quantity of each piece of equipment from manufacturer’s guide and online
markets were used to estimate its price. Shown in the table below is the summary of the
cost of each piece of equipment in terms of quantity and unit price for design option 1.
Table 38
145
Table 38 (Continue)
The mechanical equipment costs for design option 1 for the 155 MW combined
power plant at Brgy Bacong Ibaba, General Luna, Quezon is shown in Table 38. This
contains the equipment, quantity, price, and total price for each piece of equipment. The
Meanwhile, shown in Table 39 are the mechanical equipment costs for the second
design option.
Table 39
146
Table 39 (Continue)
The cost of the mechanical equipment for the 155 MW combined power plant at
Brgy. Bacong Ibaba, General Luna, Quezon for design option 2 is shown in the table. It
also contains the equipment, quantity, cost, and total cost of the equipment utilized in the
design option 2. Due to the different model equipment that is used, design option 2 is
On the other hand, the equipment costs for design option 3 is presented in the
table below.
Table 40
147
Table 40 (Continue)
The table summarizes the cost of the mechanical components of design option 3
for the 155 MW combined power plant at Brgy Bacong Ibaba,General Luna, Quezon.
Also, it shows the equipment utilized in design option 3 along with its quantity, pricing,
and overall cost. The design option 3 is the most expensive out of the design options in
terms of the overall cost of the equipment because of the different models of equipment
The direct building cost for the 155 MW combined power plant will be presented
in this section, which refers to the expenses faced by a company that are directly related
to the development of a good or the delivery of a service. This includes the cost of the
other miscellaneous costs. However, the basis for determining the building cost is the
total equipment cost, whereas the percentage for each part was based on the Kolmetz
A. Building Facility
The first aspect is cost for building the facility, where it is stated that the range of
percentage share is around 3-18%. In this case, the design utilizes the maximum of 18%.
148
The following presents the calculation of building facility costs for each design
alternative.
B. Piping Cost
Piping refers to the process of constructing pipes that transports fluids from one
location to another. It is a must to consider the interconnection of these pipes since it also
contributes to the cost of construction for the power plant. Costs associated with piping
include labor, valves, fittings, pipe supports, and other expenses for the construction of all
pipework are immediately utilized in the process. The price of piping also depends on the
method involved, estimates of the amounts could range from 16-66% of the purchasing
price for equipment. Hence, this design utilizes a 16% allotted budget for the piping cost.
149
For Design Option 1:
C. Electrical Cost
will not be operated without electricity. This creates an impact on the costs paid by the
consumers and also accounts for the total capital expenses, which is 10% of the total
equipment cost.
150
Electrical Cost = 0.1 x $147,322,500
D. Instrumentation Cost
instruments and any other necessary accessories for the whole system. These factors are
costs can be computed as similar percentages from the acquired equipment, in this case,
is 15%.
151
Instrumentation Cost = $30,803,625
typical plants, depending on the complexity of the equipment and the kind of plant in
which it is set, the cost of installing process equipment may be around 43%. Hence, this
design used 11% for material and labor of platforms and supports.
F. Miscellaneous Cost
This part involves any supplemental supplies needed to run the plant that are not
covered by the other aspects, such as the building permit. As a result, by specifying and
calculating the costs of all required goods, an exact estimate can be created. In this
152
For Design Option 1:
G. Yard Improvement
The yard improvement should also be taken into consideration when putting up a
power plant. From the handbook for these expenditures, the percentage allotted for the
yard improvement is 5% of the total equipment cost, which differs from all the design
options.
153
Yard Improvement = 0.05 x $147,322,500
H. Service Facility
Lastly for the direct building costs, the service facility is in-charge of the services
the plant provides. Therefore, this proposed project will have a 14% of service facility.
Upon calculating all the subtopics for the direct building costs, the tables are
provided. For Table 41, the detailed values are presented below.
154
Table 41
The direct building costs for combined cycle power plants considering design
option 1 are shown in the table. The table also includes the rate, total cost of the
equipment, and total cost for each criteria that must be calculated to determine the
building's total cost. Design Option 1 has a total building cost of $121,594,275.
Whereas, the direct building costs for the second design option is illustrated in
Table 42.
155
Table 42
The table summarizes the direct building costs for combined cycle power plants
for design option 2. The rate, total equipment, and total cost for each criteria are also
included in the table. Design option 2 has a higher total equipment cost, which is used to
determine building costs, than design option 1, resulting in a higher building cost of
$145,849,275.
Lastly, the design option 3 will have dissimilar cost as compared to the two
options, hence, the table that summarizes the costs was shown below.
156
Table 43
The direct building costs for combined cycle power plants for design option 3 are
shown in the table. The table also includes the rate, total equipment cost, and total price
for each category. Design option 3 has a higher building cost of $203,303,925 than the
This part presents the indirect building costs for the three design options for the
155 MW combined cycle power plant. This includes the engineering and supervision,
157
costs, the total equipment cost serves as the basis for calculating the indirect building
cost.
Building the whole plant will not be completed without the supervision of the
surveyors, inspectors, managers, and project engineers. The skills they possess will help
codes and standards. Shown below are the calculations for the engineering and
B. Contractor's Fee
The contractor’s fee refers to the payment allotted for the contractor who provides
the services to build the power plant. This includes the profit of the contractor and the
158
payment for overhead costs to control the design and development. In this project, the
C. Construction Expense
This type of expense is involved with the connection of the materials and
equipment to the design, installation, and construction of the combined cycle power
plant. Similar to the contractor’s fee, the expense for the construction is 9% of the total
equipment cost.
159
For Design Option 2:
D. Contingency
The contingency cost is the amount allotted for the payment of miscellaneous or
unforeseen costs during the construction of the plant. The percentage share to the
equipment cost is commonly 5-10%, wherein this design utilizes the maximum which is
10%.
Contingency = $12,282,250
Contingency = $14,732,250
160
Contingency = 0.1 x $205,357,500
Contingency = $20,535,750
Upon the completion of indirect building costs for the power plant, the following
tables display the summary of the calculations for each design option. Table 44 presents
Table 44
The table above demonstrates the indirect building costs for the combined cycle
power plant for design option 1. The rate, total equipment cost, and total cost for each set
of criteria that must be determined to establish the total indirect building cost are also
included in the table. Thus, the total indirect building cost for design option 1 is
$58,954,800.
Meanwhile, the table below shows the summary of indirect building cost for
design option 2.
161
Table 45
The indirect building costs for the second design option of the combined cycle
power plant are shown in the table. The table also shows the rate, total equipment cost,
and total cost for each criteria. Design option 2 has a higher indirect building cost of
$56,719,162.50 because it has a higher total equipment cost than design option 1.
Lastly, Table 46 tabulates the indirect building cost for the last design option.
Table 46
162
For design option 3, the table displays the direct building costs for combined
cycle power plants. The rate, total equipment cost, and total price for each category are
also included in the table. Due to its more costly total equipment cost, design option 3 has
The total capital expenditure costs for the 155 MW combined power plant at
Brgy. Bacong Ibaba, General Luna, Quezon are discussed in this section. This refers to
the total cost that contributes in determining the overall profitability of the power plant.
Included in this part are the total price of the equipment cost, land cost, direct building
Table 47 presents the total capital expenditures for the design option 1.
Table 47
The total capital expenditure cost for the first design option is shown in a table.
Considering the total costs for equipment, land, direct building, and indirect building
163
On the other hand, the table below displays the total capital expenditure for the
Table 48
Table 48 shows the total capital expenditure expenses for design option 2. When
the costs for equipment, land, direct building, and indirect direct building are combined
Table 49
164
The table above shows the total capital expenditure costs for design option 3.
Summarizing the costs for the equipment, land, direct building, and indirect building
Operating Expenditure
Operating expenditures refer to the costs incurred during the normal plant
operation of the combined steam and gas turbine power plant system. This includes the
labor cost with salaries for different positions, the miscellaneous cost classified as
insurance, as well as the fuel cost since LNG will be the raw material.
I. Labor Cost
The labor cost is the amount of money allocated to the manpower who operates
the plant, directly or indirectly involved in the processes. It is dependent on the number
of personnel as well as the salary on the daily basis and the number of hours they have in
the power plant. In this design, the power plant will operate for 355 continuous days
wherein ten days will be allocated annually for its maintenance. In line with this, the total
number of hours per day for employees is eight, and any hours exceeding this will be
referred to as the overtime work according to the Project Jurisprudence (2019). Hence,
workers will also be present for 355 days, with three shifts for 12:00 am - 8:00 am, 8:00
am to 4:00 pm, and 4:00 pm - 12 mn.Moreover, the salaries on a daily basis was obtained
A. Plant Manager
By ensuring that rules and regulations are adhered to, the plant manager will be
responsible for managing all daily operations at the facility, including production and
165
manufacturing. Their guidance will help to improve production, quality, safety, and
accountability. There will be three plant managers with a daily wage of $120.75 for all
design options.
The control for energy management systems are all managed by assistant plant
managers throughout the facilities. They do relevant work orders into the maintenance
management system under the guidance of the plant manager, then complete or delegate
the task. There will be three assistant plant managers with a daily wage of $57.48.
166
Total Cost = $61,216.20
The maintenance and repair of the equipment for the power plant is overseen by a
plant management technician. In this project, there will be four plant management
technicians for the first design option and six for design options 2 and 3, with a daily
wage of $28.47.
167
For Design Option 3:
D. Line Supervisor
The line supervisor is in charge of guiding, coordinating, and evaluating the work
of other line personnels as well as the engagement of line crews in electrical line
installation and maintenance. Hence, there will be four line supervisors for the first
design option and six for design options 2 and 3, with a daily wage of $45.84.
168
E. Operation Manager
They oversee quality assurance and train other members to guarantee that everyone
completes their job on time. There will be three operation managers with a daily wage of
$82.97.
F. System Operators
The whole operation of the system is monitored and managed by the system
operator. Also, in order to ensure that the system is in good condition and can operate
regularly, the operator initiates and terminates system tasks, and keeps an eye out for
uncommon conditions. This project will consist of 12 system operators for design options
1 and 2, and 15 for the third design option, with a daily wage of $17.86.
169
For Design Option 1:
G. Logistic Manager
The supply chain must be productive and efficient across the entire firm, which is
managed by the logistics manager. Also, to make sure that supplies are delivered to the
right locations, they organize, store, and oversee the distribution of resources. There will
170
Total Cost = 3 x 355 x $52.75
H. Project Supervisor
The project supervisors offer the supervision and guidance for a successful
project. They also assist problem-solving and project resourcing while upholding project
standards. Therefore, there will be four project supervisors for the first design option and
171
I. Project Engineer
under the supervision of project engineers. They plan projects, establish project criteria,
organize project reviews, and make sure project components are implemented correctly.
This design consists of nine project engineers for design option 1 and ten for design
J. Mechanical Engineer
Mechanical engineers who work in power plants ensure that the equipment, such
as turbines and boilers, are operating at their optimum condition in order for the power to
be continuously produced. In this project, there will be nine mechanical engineers for
design option 1 and ten for design options 2 and 3, with a daily wage of $55.93.
172
For Design Option 1:
K. Electrical Engineer
The aspects of electric motors, industrial controls, lights systems, generators, and
energy transmission networks are responsibilities of the electrical engineers to which they
design, develop, test, and oversee. In this project, there will be nine electrical engineers
for design option 1 and ten for design options 2 and 3, with a daily wage of $59.68.
173
Total Cost = 10 x 355 x $59.68
L. Maintenance Engineer
The maintenance engineers ensure that the machinery and equipment at the
facility are correctly maintained and functioning. They also oversee the maintenance
program for the building; locate and assess equipment or machinery faults; and
implement corrective measures. In this project, there will be nine maintenance engineers
for design option 1 and ten for design options 2 and 3, with a daily wage of $32.64.
174
M. Technician
facilities. Some processes involve assembling machinery, installing cables and wiring in
this position. In this project, there will be 12 plant technicians for design options 1 and 2,
N. Safety Engineer
occupational health and safety., and implementing rules and regulations are the
responsibilities of health and safety engineers. They describe how to put safety strategies
into place, deal with problems, and prevent accidents. In this project, there will be nine
175
safety engineers for design option 1 and ten for design options 2 and 3, with a daily wage
of $60.48.
O. Environmental Engineer
environmental engineers. They ensure that systems such as water treatment and air
pollution control conform with the standards to minimize the contribution of the power
engineers for design option 1 and ten for design options 2 and 3, with a daily wage of
$50.61.
176
Total Cost = 9 x 355 x $50.61
P. Safety Officer
The safety officers diagnose and fix issues aligned with electrical devices and
control systems, including fire alarms, dryers, freezers, overhead doors, motors, standby
generators, and other appliances. This project will consist of seven safety officers for
design option 1, eight for design option 2, and nine for design option 3, with a daily wage
of $25.76.
177
Total Cost = $73,158.40
Q. Environmental Officer
evaluation tasks, and giving technical assistance. This project will consist of seven
environmental officers for design option 1, eight for design option 2, and nine for design
178
R. Pollution Control Officer
The pollution control officers are in-charge in monitoring the operations of the
plant to make sure they adhere to specified environmental regulatory standards. Also,
they audit the facilities for pollution control. This project will consist of seven pollution
control officers for design option 1, eight for design option 2, and nine for design option
S. Administrator
general office management. In line with this, the project will consist of seven
179
administrators for design option 1 and eight for design options 2 and 3, with a daily wage
of $24.75.
Upon calculating the labor cost, the summary was tabulated for each of the design
options as seen below. In accordance with this, Table 50 presents the total labor cost for
design option 1.
Table 50
180
Table 50 (Continue)
181
As seen in the table above, for a total of 130 personnels in various positions
working in a span of 355 days, the total labor cost amounts to $2,017,891. Whereas,
Table 51 shows the total labor cost for the second design option.
Table 51
182
Table 51 (Continue)
As presented in the table above, for a total of 146 staff in various positions
working in a span of 355 days, the total labor cost amounts to $2,248,211.45. Lastly,
Table 52 displays the total labor cost for the third design option.
Table 52
183
Table 52 (Continue)
As seen in the table above, for a total of 155 staff in various positions working in
a span of 355 days, the total labor cost amounts to $2,334,643.30. Compared to the total
labor costs of the other design alternatives, this design option possesses the highest
amount, due to its more complicated process of the power plant system.
184
II. Miscellaneous Cost
This refers to the cost required for the unexpected costs as well as the
miscellaneous materials not covered by other major factors such as building and
construction expenses. Miscellaneous costs include the cost for maintenance and repair,
This cost will cover the materials and labor costs for plant maintenance and repair.
The percentage share for maintenance and repair cost is 9-10% of the total capital
expenditures.
185
B. Lubrication Cost
The gas turbine and other equipment uses a lubrication system to treat and purify
the circulating oil. Since the combined cycle power plant utilizes a gas plant, it is a must
to have an appropriate budget for the lubrication. In this case, the percentage share of
C. Supplies Cost
Supplies cost refers to the money allocated for the supplies necessary to operate
the power plant. In this case, the supplies cost is 6-7.5% of the total capital expenditures.
186
Total Cost = $22,852,738.40
D. Operating Taxes
This cost refers to the local taxes required to be paid by the power plant,
187
Total Cost = 0.02 x $490,082,453.70
E. Transportation Cost
have a small amount of transportation cost compared to the synthetic fibers and other
solids being distributed. In this case, the cost allocated for transportation is 4-7.5% of the
F. Insurance Cost
A power plant must also allocate money for insurance, as this provides assurance
for the power plant during construction and operation. The annual insurance paid is
188
For Design Option 1:
In accordance with the computations performed for the miscellaneous cost, tables
have been provided below to present the summary. As such, Table 53 shows the total
Table 53
189
Table 53
For a percentage share of 10, 5, 7.5, 2, 7.5, and 10 for the maintenance and repair,
Meanwhile, the table below illustrates the calculated results for design option 2.
Table 54
190
For a percentage share of 9.5, 5, 7.5, 2, 7.5, and 5 for the maintenance and repair,
Whereas, Table 55 presents the calculated results for the last design option.
Table 55
Insurance Cost
0.05 490,082,453.70 24,504,122.68
For a percentage share of 9.5, 4, 7.5, 2, 7, and 5 for the maintenance and repair,
option 3 has the lowest percentage share compared to the other options, it still has the
expenditures.
191
III. Fuel Cost
For the proposed combined steam and gas power plant, the raw material of the gas
power plant will be the liquefied natural gas (LNG) that is supplied by the Malampaya
Onshore Gas Plant. With this, the cost of fuel for an annual operation should also be
The price of LNG to be fed into the combustion chamber was obtained from the
site of Malampaya Onshore Gas Plant, which is $0.078/kWh (Yap & De Lara, 2017).
Whereas, the time is calculated as days multiplied by the number of seconds in a day. In
terms of the flow rate, it is varying based on each design option, denoted in kg/s. The
Total Cost = Flow rate (kg/s) x Time (hrs) x Price per kWh
Total Cost = Flow rate (kg/s) x Time (hrs) x Price per kWh
Total Cost = Flow rate (kg/s) x Time (hrs) x Price per kWh
192
As shown from the calculations performed above, the following tables will
provide the summary. For the first design option, Table 56 is presented.
Table 56
Fuel Flow rate Time (s) Price per Total Price ($)
(kg/s) kWh
With a flow rate of 25.02230616 kg/s in a span of 31536000 seconds and a price
of $0.078/kWh, the total annual fuel cost will be $61,550,068.87. Meanwhile, Table 57
Table 57
Fuel Flow rate Time (s) Price per Total Price ($)
(kg/s) kWh
For a flow rate of 26.05840731 kg/s in a span of 31536000 seconds and a price of
$0.078/kWh, the total annual fuel cost will be $64,098,678.77, higher than that of the first
design option. Lastly, Table 58 displays the total fuel cost for design option 3.
Table 58
193
Fuel Flow rate Time (s) Price per Total Price ($)
(kg/s) kWh
Considering the flow rate of 5.029691165 kg/s in a span of 31536000 seconds and
a price of $0.078/kWh, the total annual fuel cost will be $12,372,074.57, much lower
Upon calculating all the necessary aspects termed as the operating expenditures,
the results were tabulated in accordance to each design option. For Table 59, the total
Table 59
the fuel cost of $61,550,068.87, the total operating cost yielded to $191,543,294.92. On
the other hand, Table 60 shows the total operating expenditure for the second design
option.
194
Table 60
$126,440,114.83, and the fuel cost of $64,098,678.77, the total operating cost yielded to
$192,787,005.05, much higher than the first. Whereas, Table 61 displays the total
Table 61
$147,024,736.11, and the fuel cost of $34,553,059.69, the total operating cost yielded to
195
Total Project Cost
The total project cost covers the overall cost of the power plant system wherein
the calculation is simply the sum of the total capital and operating expenditures. Hence,
shown in the following tables are the total project costs for each design option. Table 62
displays the total cost of the project for the first design option.
Table 62
Meanwhile, the table below tabulates the result for the total project cost of the second
design option.
Table 63
196
Considering the total capital expenditure of $351,222,541.20 and a total operating
higher than the first design option. Lastly, the table below tabulates the result for the total
Table 64
In terms of the total capital and operating expenditures which have the value of
Economic Evaluation
This section presents the evaluation of the economic aspect for the 155 MW
combined steam and gas power plant. It includes the customer sales, sales breakdown for
each type of consumer, annual revenue, salvage value, and annual depreciation costs.
This will aid in analyzing the marketability of the power plant in terms of the economic
indicators such as the net present value, return on investment, and payback period.
I. Customer Sales
Included in the economic analysis of a power plant is the sales obtained from the
consumers they supply to. In this project, the customers are divided into five
197
classifications, namely: streetlights, residential, commercial, public building, and
barangay power association (BAPA). Shown in Table 65 are the customer sales in kWh
Table 65
Customer Sales
As seen above, the highest sales come from residential with 143,491.51 MWh,
followed by BAPA with 3,820.62 MWh, commercial with 2,901.02 MWh, and public
buildings with 2,533.46 MWh. The lowest comes from the streetlights with 589.23 MWh,
In line with the customer sales, the sales breakdown for each type will be
computed as the individual rate divided along the total customer sales, which is
153,583.42 MWh. Shown below are the individual calculations for the sales breakdown
198
A. Streetlights
𝑅𝑎𝑡𝑒𝑠 (𝑀𝑊ℎ)
Sales Percentage = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑆𝑎𝑙𝑒𝑠
589.23 𝑀𝑊ℎ
Sales Percentage = 153,583.42 𝑀𝑊ℎ
B. Residential
𝑅𝑎𝑡𝑒𝑠 (𝑀𝑊ℎ)
Sales Percentage = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑆𝑎𝑙𝑒𝑠
143,491.51 𝑀𝑊ℎ
Sales Percentage = 153,583.42 𝑀𝑊ℎ
C. Commercial
𝑅𝑎𝑡𝑒𝑠 (𝑀𝑊ℎ)
Sales Percentage = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑆𝑎𝑙𝑒𝑠
2,901.02 𝑀𝑊ℎ
Sales Percentage = 153,583.42 𝑀𝑊ℎ
D. Public Building
𝑅𝑎𝑡𝑒𝑠 (𝑀𝑊ℎ)
Sales Percentage = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑆𝑎𝑙𝑒𝑠
2,533.46 𝑀𝑊ℎ
Sales Percentage = 153,583.42 𝑀𝑊ℎ
E. BAPA
𝑅𝑎𝑡𝑒𝑠 (𝑀𝑊ℎ)
Sales Percentage = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑆𝑎𝑙𝑒𝑠
3820.624963 𝑀𝑊ℎ
Sales Percentage = 153,583.42 𝑀𝑊ℎ
199
Tabulated below is the summary for the sales breakdown of each type, with their
Table 66
Sales Breakdown
Shown in Table 66 are the percentage shares for each type of consumer. The
with 2.539999753, public buildings with 2.300679718, and the lowest is streetlights with
This section shows the annual revenue for the customers, referring to the product
of the generation rate, plant capacity, sales breakdown, and operating time of 24 hours a
day, 7 times a week. The generation rates, on the other hand, was obtained from the load
200
A. Streetlights
B. Residential
C. Commercial
D. Public Building
E. BAPA
201
Annual Revenue = $0.13 x 155000 x 0.044409903411 x 8760
Shown below is the tabulated form of the total annual revenue for a combined
cycle power plant with 155 MW capacity and operating time of 8760 hours.
Table 67
The annual revenues for streetlights, residential, commercial, public building, and
Salvage value is the estimated resale value of an asset at the end of its useful life.
The method that can be used in order to identify the salvage value is the declining
balance method. Furthermore, according to Sargent & Lundy (n.d.), the typical operating/
202
useful life of a combined cycle power plant is 25-30 years, in this case, the project
assumes that the useful life will be 30 years. Thus, the calculations for salvage value for
2 𝑢𝑠𝑒𝑓𝑢𝑙 𝑙𝑖𝑓𝑒
Salvage Value = (Total Capital Expenditure) x (1 - 𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
)
2 30
Salvage Value = $304,703,178.70 x (1 - 30
)
2 𝑢𝑠𝑒𝑓𝑢𝑙 𝑙𝑖𝑓𝑒
Salvage Value = (Total Capital Expenditure) x (1 - 𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
)
2 30
Salvage Value = $351,222,541.20 x (1 - 30
)
2 𝑢𝑠𝑒𝑓𝑢𝑙 𝑙𝑖𝑓𝑒
Salvage Value = (Total Capital Expenditure) x (1 - 𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
)
2 30
Salvage Value = $490,082,453.70 x (1 - 30
)
For the annual depreciation, this needs to consider the interest rate of 8% as well
as the useful life of a combined cycle power plant which is operated for 30 years (Sargent
& Lundy, nd). Therefore, the annual depreciation cost for each design option is presented
below.
0.08
kkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk( 30 )
(1+0.08) −1
𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒
kkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk ( 𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒 )
(1+𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒) −1
0.08
kkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk ( 30 )
(1+0.08) −1
𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒
kkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk ( 𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒 )
(1+𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒) −1
0.08
kkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk( 30 )
(1+0.08) −1
One of the economic indicators that will determine if the plant is justifiable or not
is the net present value. It is the difference between the amount of cash that flows in and
out. Generally, this design utilizes the operational life of a combined power plant for 30
years. Shown in Figure 64 is the cash flow diagram applicable for all the design options.
204
Figure 64. Cash Flow Diagram
The figure above presents the cash flow diagram for the proposed 155 MW
combined steam and gas power plant. For a useful life of 30 years as stated by Sargent &
Lundy (n.d.), the revenue (R) is denoted by arrows pointing upward from year 1 to year
30, whereas expenditures (E) are for arrows pointing downward. Meanwhile, the cash
outflow (Co) begins from the starting operation of the plant and salvage value (SV) at the
I. Cash Inflows
The cash inflow refers to the money that flows into the power plant system which
The revenue is referred to as the income generated through the project operations,
wherein the present value of the annual revenue considers the interest rate of 8% and the
205
For Design Option 1:
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
1−(1+𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
PV of Annual Revenue = Annual Revenue x ( 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒
)
−30
1−(1+0.08)
PV of Annual Revenue = $249,882,568.82 x ( 0.08
)
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
1−(1+𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
PV of Annual Revenue = Annual Revenue x ( 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒
)
−30
1−(1+0.08)
PV of Annual Revenue = $249,882,568.82 x ( 0.08
)
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
1−(1+𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
PV of Annual Revenue = Annual Revenue x ( 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒
)
−30
1−(1+0.08)
PV of Annual Revenue = $249,882,568.82 x ( 0.08
)
In terms of the present value, this also takes in consideration the interest rate and
useful life of 8% and 30 years, respectively, which is multiplied to the salvage value
obtained earlier. Even if the interest and useful years are constant for the three design
options, each still has its own present value of salvage value.
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
PV of Salvage Value = Salvage Value x (1 + 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
−30
PV of Salvage Value = $38,457,432.24 x (1 + 0. 08)
206
PV of Salvage Value = $3,821,797.03
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
PV of Salvage Value = Salvage Value x (1 + 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
−30
PV of Salvage Value =$44,328,769.85 x (1 + 0. 08)
−𝑈𝑠𝑒𝑓𝑢𝑙 𝐿𝑖𝑓𝑒
PV of Salvage Value = Salvage Value x (1 + 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑅𝑎𝑡𝑒)
−30
PV of Salvage Value = $61,854,664.06 x (1 + 0. 08)
Upon calculating the present values of annual revenue and salvage values, the
sum of it will be solved to determine the present value of cash inflows, as shown below.
207
PV of Cash Inflows = $2,819,270,772.48
Cash outflow refers to the money that flows out from the power plant, such as the
expenses that involve the total project cost and annual cost.
208
PV of Cash Outflows = $2,786,997,421.75
Hence, the net present value may be obtained by subtracting the cash outflows
from the cash inflows. In order to determine if the power plant is profitable, the net
The rate of return (ROI) is the gain or loss of an investment over a certain period
of time. This can be computed by the ratio of net annual revenue to the capital
expenditure, or simply the ratio of the difference in annual revenue and cost all over the
209
total project cost. Meanwhile, to determine if the project is justified in economic terms,
the ROI should be greater than the interest rate, which is 8%.
$249,882,568.82 − $193,893,561.51
Return on Investment = $496,246,473.62
x 100%
$249,882,568.82 − $195,496,089.37
Return on Investment = $544,009,546.24
x 100%
$249,882,568.82 − $187,692,591.39
Return on Investment = $673,994,892.80
x 100%
The last economic indicator is the payback period which refers to the number of
years the investment of the project can be recovered. This can be calculated by dividing
the total project cost to the difference between total revenue and annual cost. To
determine if the project is economically viable, the payback period of the combined cycle
210
power plant should be in the range of 8.5 to 15 years, as stated by Hittingers and
Williams (2021).
$496,246,473.62
Payback Period = $249,882,568.82 − $193,893,561.51
justified.
$544,009,546.24
Payback Period = $249,882,568.82 − $195,496,089.37
justified.
$673,994,892.80
Payback Period = $249,882,568.82 − $187,692,591.39
justified.
211
Sensitivity Analysis
The sensitivity analysis for the 155 MW combined cycle power plant will be
presented in this section. Sensitivity analysis will make it easier to determine the
important factors that affect the project cost for developing the power plant. It enables the
proponents to point out potential improvements for the power plant's profitability. The
following aspects are to be considered: sudden change in LNG fuel price, useful life of
the equipment, and the generation rate per kWh. They will be analyzed for each design
option, specifically on their effect with the present worth of the plant.
In line with this, the calculations for sensitivity analysis will cover all the results
from the performed computations on the capital and operating expenditures, as well as
the depreciation cost, salvage value, and annual revenue for a specific interest rate and
period of time. Hence, shown in Table 68 is the summary for design option 1.
Table 68
Description Value
212
Table 68 (Continue)
As seen in the table above, for a useful life of 30 years, interest rate of 8%, and
depreciation rate of 0.03333333333, the salvage value, annual depreciation cost, annual
revenue, annual cost, capital expenditure, labor cost, fuel cost, operating expenditure, and
total project cost were provided. This is applicable for a power plant system with simple
Meanwhile, presented in the table below is the summary for design option 2.
Table 69
Description Value
213
Table 69
Observed in Table 69 that for a useful life of 30 years, interest rate of 8%, and
depreciation rate of 0.03333333333, the salvage value, annual depreciation cost, annual
revenue, annual cost, capital expenditure, labor cost, fuel cost, operating expenditure, and
total project cost were listed. This applies for a power plant system with a simple cycle in
Lastly, the summary for the last design option is displayed in Table 70.
Table 70
Description Value
214
Table 70
Table 70 illustrates that for a useful life of 30 years, interest rate of 8%, and
depreciation rate of 0.03333333333, the salvage value, annual depreciation cost, annual
revenue, annual cost, capital expenditure, labor cost, fuel cost, operating expenditure, and
total project cost were calculated as given. Thus, this is applicable for a power plant
system with single-stage reheat for gas and a simple reheat-regenerative cycle for steam.
On the other hand, the effect in three aspects were analyzed for a power plant
system with the percent change prediction of -40% to 40% with a 10% interval. A spider
plot will be utilized to graphically present the result on present worth being dependent
with LNG fuel price, useful life of components, and generation per kWh.
215
Design Option 1
Figure 65 shows the graphical representation of the predictions for LNG fuel price
labeled by a blue line, useful life of the equipment for the orange line, and green line for
the generation rate per kWh. Similar to the first design option, it is clearly seen that all
the variables cause either increase and decrease with the present worth of the power
plant, however, the change for useful life has much lesser effect compared to the other
two. For a 40% increase or decrease, the trend of the line for the generation rate and
useful life is increasing, whereas for the LNG price is decreasing. In terms of the present
worth, the design may be considered not economically viable if its value is negative.
Therefore, the increase of approximately 20% on the price of the LNG fuel as well as
10% decrease on the generation rate will be considered unprofitable for the project. The
constant decrease of $15,089,348.18 has been recorded for the LNG price fuel and
constant increase of $56,262,476.42 for the present worth from the generation rate.
216
Furthermore, the most sensitive variable is the generation rate since it has the steepest
Design Option 2
A graphical review of the projections for the price of LNG fuel is depicted in the
image above with a blue line for LNG fuel, an orange line for equipment usable life, and
a green line for generation rate per kWh. It is apparent that each variable affects how
much the power plant is supposedly worth, either increasing or decreasing it. However,
the change in useful life has a considerably smaller impact than the other two. The trend
of the line is increasing for the generation rate and useful life while decreasing for the
price of LNG for a 40% rise or drop. Also, if the design has a negative present worth, it
might not be considered economically feasible. As a result, the project will be interpreted
as unprofitable if the price of LNG fuel increases by about 10% and the generation rate
decreases by 10%. For the price of LNG fuel, a continuous decrease of $15,714,154.34
217
has been noted, whereas a constant gain of $56,262,476.42 for the present value resulting
from the generation rate. Moreover, the generation rate is the most susceptible variable
because its slope is steeper than that of the price of LNG and usable life of equipment.
Design Option 3
The image above shows a graphical analysis of the price prediction for LNG fuel,
with a green line for generation rate per kWh, an orange line for equipment useful life,
and a blue line for LNG fuel. It is observed that every single factor has an impact on how
much the power plant is currently worth, either raising or lowering it. The difference in
useful life, however, has a far lower effect than the other two. The trendline is upward for
generation rate and useful life for a 40% increase or decrease, but downward for LNG
price. However, the design might not be regarded as economically feasible if it has a
negative present value. As a result, the project will be viewed as unprofitable if the price
of LNG fuel increases by about 10% and the generation rate decreases by 10%. For the
price of LNG fuel, a continuous drop of $3,033,084.19 has been seen, as well as the
218
constant gain of $56,262,476.42 for the present value resulting from the generation rate.
Moreover, similar to the first and second design options, the generation rate is the most
vulnerable variable because its slope is steeper than that of the price and usable life of
LNG.
219
CHAPTER IV
ENVIRONMENTAL MANAGEMENT
combined steam and gas power plant at Quezon province, particularly on land, water, air,
as well as the residents and ecology. The social, political, and ethical aspects will also be
taken into consideration during the construction until the plant operation. Standards such
as from the Department of Environment and Natural Resources (DENR) will also be
discussed in terms of the health and safety requirements, especially about the wastes and
pollutants that will be emitted at the facility. With this, mitigation strategies will be
It is important to assess and determine first the direct and indirect environmental
impacts of the proposed 155 MW combined gas and steam cycle power plant in the
environment and the welfare of the community (DENR, 2023). Hence, this method to
lessen negative effects and assist in customizing the project to the local environment may
A gas turbine and a steam turbine are used to generate power in a combined-cycle
technology. Natural gas and saltwater will be utilized in the planned project, which does
220
have a lesser environmental effect than other fossil fuels. By producing steam from the
exhaust heat of the gas turbine, power is produced twice as efficiently and with less
waste. Meanwhile, in the steam cycle, water from the turbine passes through the
condenser and goes to the cooling tower and feedwater heater before being reused in the
cycle. The gases emitted by the chimney, on the other hand, are filtered to guarantee that
Listed below are some of the environmental impact assessments procedures that
may be considered on the proposed combined gas and steam cycle power plant.
Land
The preparation for the construction requires excavations which can cause
geological changes and minor seismic activities. Therefore, the proponents need to
conduct a field survey and review reports about the target location with the help of
(PHIVOLCS). This involves the collection of soil samples in the project site and
conducting soil testing to determine the initial chemical and physical condition of the
soil. In line with this, the municipality of General Luna contains a non-saline type of soil
with a range of 0-2. This can be a good choice for the construction of the power plant
because non-saline soil does not contain salt that reduces the corrosion resistance
221
Water
Conducting field assessments on bodies of water around the project site will be
done to evaluate water quality and protect it from pollution caused by the power plant's
Ibaba, Quezon Province, and perform surveys of marine life in the project site. It is also
required to monitor the waste water output of the power plant as this may affect the
Air
monitoring near the project site to determine the components of the ambient air. Studying
the most recent PAGASA reports on the meteorology and climate of the target site will
also help to better understand the region and anticipate hazards from future natural
disasters. Lastly, since the plant system involves the combustion process, monitoring the
emissions from the proposed power plant from the construction to the start of operation
will help to take an action that will reduce adverse effects to the community and
environment.
perception surveys may be conducted to the residents in Brgy. Bacong Ibaba, General
Luna, Quezon to learn what they think about the proposed power plant. Whereas, to
reduce the impact of power plant construction on the ecology of the target area, the
proponents should perform terrestrial flora and fauna surveys. This will help them to
understand the species and behavior that live in the region and how the proposed project
222
would affect them. So, if there are potential risks, those affected plants and animals can
Social Considerations
During the construction period, local workforce from the nearby town and within
the Quezon province shall be employed for the construction works. This will contribute
too much needed monetary income in the region. The contractors shall discuss potential
barriers for employment with local labor / training organizations so that measures to
overcome these barriers can be developed and put in place. The company will assure that
there is no discrimination in hiring and salaries will not be based on gender, age, religion,
Moreover, there are no people living at the site and no land is used by the local
population in General Luna, Quezon. The area has already been acquired, fenced, and
foreseen for construction and entered a land purchase agreement with the seller. Thus, the
proposed project guarantees that the land is free of any form of occupancy or any other
possession by any third party and there are no current and, to the best of its knowledge,
threatened or pending actions, suits or other proceedings. The land is solely for energy,
In addition, there are no houses or private assets located inside the construction
site, so no physical relocation or acquisition of further land will be necessary for this
project. Some fields and farmlands are located near part of the construction site but
outside of the project area. These will not be impacted by the project. However, there are
some who live illegally near the construction site, which may be affected by noise and air
impacts, but no physical or economic displacement will occur due to the project.
223
Lastly, if there is any chance of a cultural and historical site, the construction has
there are no cultural or historic sites known within the construction site and the project
area.
Political Considerations
unitary and indivisible republic headed by the President. In line with this, the state is
organized according to the principle of separation and balance of the powers - the
The impacts of the proposed project are identified in order to calculate the
potential consequences of constructing the combined cycle power plant. The government
changes the standards for attaining acceptable levels based on the results. With large
capacity generation being developed to address increasing energy demand, NGCP is also
preparing to enable the grid integration of these power production units. One example is
with approximately 1500 MW of electricity entering the grid wherein once these plants
are operational, it is a must to have a new power gateway in Quezon province that can
In line with this, the NGCP just completed a series of public consultations with
the Quezon local government and the communities that will be affected by the project.
They organized these conversations to showcase the project, obtain community support,
224
and address any concerns the public may have, particularly about right-of-way
acquisition and the possible impact of the project on livelihoods. Therefore, it will help to
Southern Luzon with the collaboration of the LGU, other connected government
Ethical Considerations
combined cycle power plant. There are advantages and downsides to operating this type
of power plant. Natural gas is the primary fuel used and when compared to other fossil
fuels, it has the lowest environmental impact. Despite these low values, it is still
carbon dioxide, nitrogen oxide, and sulfur oxide helps to minimize the impacts of ozone
possible to minimize effects on the environment and the local population is significant.
Furthermore, the noise emissions from the numerous parts of the power plant, including
the condenser, steam turbine, and heat recovery steam generator (HRSG), should also be
taken into account. This emission will be reduced through appropriate noise reduction
With regards to the discharge of wastewater, this must also be appropriately taken
into account because nearby local communities depend on the aquatic resources. Several
225
water treatment processes are needed to be considered before disposing wastewater into
Health Requirements
electricity using processes, such as combustion of fuel and cycles of steam generation.
These procedures use dangerous materials and provide serious risks to both the
environment and the health and safety of the personnel. Power plants must adhere to
The Occupational Safety and Health Administration (OSHA) rules are one of the
main health and safety requirements for power plants. Power plants are required by
their personnel. OSHA regulations cover a wide range of dangers, including electrical,
chemical, and physical dangers, and they require the use of protective gear to reduce
exposure to these dangers. On the other hand, the norms and standards of the National
Fire Protection Association (NFPA) are another significant standard for power plants.
The storage and handling of flammable and combustible materials, electrical equipment,
and fuel systems are just a few of the hazards that these standards cover when it comes to
fire and explosion hazards in power plants. To reduce the risk of fire and explosion, the
NFPA also offers rules for the design, construction, and upkeep of power plants.
Power plants should also follow industry-specific standards, such as those set by
the Institute of Electrical and Electronics Engineers (IEEE), in addition to these legal
electrical safety, protective relaying, and generator protection. As they offer rules for the
226
design, construction, testing, and maintenance of power plant equipment, these standards
are essential for preserving the dependability and safety of power plants. In order to
maintain compliance with legal requirements and standards particular to the industry,
power plants also adopt a variety of safety management systems. These systems, which
include safety rules, procedures, and training courses, are intended to recognize and
reduce risks, avoid mishaps and injuries, and foster a safety culture inside the company.
To sum up, in order to guarantee the security of both employees and the
surrounding area, power plants must adhere to strict health and safety regulations.
Regulatory standards such as OSHA and NFPA codes and industry-specific standards like
IEEE provide guidelines for the design, construction, and maintenance of power plant
equipment. To ensure adherence to these requirements and foster a safety culture inside
the power plant, safety management systems, which include policies, procedures, and
training programs, are also essential. Power plants can continue to provide electricity in a
Safety Requirements
There are numerous professions where a certain level of risk is expected because
it is part of the job. In power plants, safety in material handling, such as natural gas
handling systems and other chemical handling systems, and also safety in boiler
Proper housekeeping for safety and good plant operation must be taken into
account in order to reduce risk for workers and provide a good flow of plant operation.
Power plants should also follow design standards for proper ventilation and fresh air
circulation. Moreover, workers must be trained before the actual work in plant operation
227
to avoid accidents. Proper clothing and personal protective equipment (PPE) should be
observed properly. The boiler operator needs to have knowledge of fitting boiler
displayed properly as well as the storage system. Equipment selection must also follow
codes and standards. Materials should be stored properly in a sealed tank. There should
be bond walls to prevent tank leakages. Skills development training must also be
provided for workers to avoid unnecessary activities that might lead to accidents. Rated
fire extinguishers must be provided in all areas where fire might start. Lastly, there should
be routine maintenance, calibration, and testing of the burner management system and
combustion control safety device and transmitter to avoid loose ends in boiler operation.
plant operation.
DENR Standards
natural resources are under the purview of the Department of Environment and Natural
Resources (DENR). It must guarantee the correct use of these resources as well as
the department’s purpose, the proposed power plant will fall under the energy projects
According to Republic Act No. 1936, also known as the Electric Power Industry
Reform Act (EPIRA) of 2001, the proposed power plant shall strengthen the market
growth, assure customer choice, stimulate competition, and punish market power abuse in
228
the restructured electrical sector. Furthermore, once the budget for this project is
obtained, the proponents or the investors must follow the process and complete the
Source: www.doe.gov.ph
The figure presents the main processes that the proposed power plant must follow.
For every procedure, there are requirements that must be fulfilled. The preliminary step
after the budget is obtained is for the power plant to be registered. The proponents for this
project shall present the overall plan for the powerplant to the Department of Energy to
obtain the certificate of endorsement which is one of the requirements needed. Moreover,
the other requirements includes the certificate of registration form securities and
identification number (TIN) from the bureau of internal revenues, the barangay clearance
from the barangay which the plan will be located, the business permit from the
municipality office and since the proposed power plant is located at the Brgy. Bacong
Ibaba, General Luna, Quezon, the proponents must contact the barangay as well, as well
requirements for the registration process, the employer and employees registration must
be fulfilled at the Social Security System office, the pag-ibig employer’s registration from
229
Home Development Mutual Fund or Pag-IBIG office, the employer’s registration on
PhilHealth and lastly the business registration from the Department of Labor and
Employment.
After the registration, the proposed power plant will start its construction but
before that, requirements must be complete and standards must be followed accordingly.
Numerous legal departments shall approve the proposed design and layout of the power
plant before proceeding to the actual construction. This is the reason behind the
Department of Energy and Natural Resources (DENR) standards must be signed by both
parties, the DENR and the proponents of the proposed power plant. This agreement
(FLAg), Foreshore Lease Agreement, etc. Furthermore, the proponents of the proposed
power plant must conduct a system impact study and facility study which will be
Meanwhile, the study with regards the impact of the proposed power plant to the
other electricity providers in the Philippines must be considered and presented to the
Department of Energy (DOE). Also, the power supply agreement must be fulfilled from
this department. The National Commision on Indigenous People (NCIP) will also take
part in constructing the proposed power plant by assuring that the people residing near
the proposed location of the power plant are protected. For this reason, free prior
this department. The department of Agrarian Reform (DAR) is responsible for the land
use conversion of the proposed power plant. On the other hand, the endorsement and
230
other resolutions regarding the proposed power plant is done by the Local Government
Unit (LGU) of the municipality of Quezon and the barangay of Bacong Ibaba. The
Philippine Board of Investments (BOI) is an agency that interferes with the importation
authority of the proposed power plant, as well as the project registration. The proposed
power plant must also get the water permit from the National Water Resources Board
(NWRB).
More importantly, the proposed power plant must follow the standards such as the
height limitation clearance, if the smokestack is within 2-km radius of a runway or air
strip provided by Civil Aviation Authority (CAAP). The permit to supply natural gas,
pipeline permit and permit for construction, maintenance as well as the ER 1-94
Memorandum of Agreement and the certificate of endorsement for other agencies are
given by the Department of Energy (DOE) once the power plant achieves the
The development and construction of the proposed power plant also needs
Before proceeding with the actual construction, the proponents and the investors shall
obtain permit and clearance from the Local Government Unit of Barangay Bacong Ibaba,
Quezon City. The Department of Labor and Employment will also require the proposed
power plant to have occupational safety and health (OSH) officers before proceeding
with the construction. The Bureau of Customs will issue an importation clearance if the
standards under this clearance are approved. The National Grid Power Corporation is
231
Regulatory Commission will issue the certificate of compliance and lastly the certificate
After the plant is built and ready to function, monitoring its process and the plant
itself is a must. Various departments are required to observe and keep track of the
condition of the power plant. The LGU, NGCP, ERC, TRANSCO, BOI and DOE are
some of the departments that will continue its connection with the power plant. In this
way, the standards set by this department is followed by the power plant. To sum up,
these requirements and standards are used to make the proposed power plant sustainable,
functional and safe that can benefit both the investors or proponents and the people that
Waste Management
the government for environmental compliance and preservation. Waste that is not
disposed of properly might harm the environment. Power plant trash must be disposed of
appropriately since the facility produces several end products that call for particular
disposal techniques. Each organization has a different approach to waste utilization since
the power plant produces a variety of waste products. Several of these include recycling
the parts that can still be usefully utilized. While handling waste from power plants,
factors such as human health, aesthetics, and environmental protection are taken into
account.
Power plant waste can be created by the system or the employees and it comes in
all types. Furthermore, the Republic Act No. 9003 also known as the Ecological Solid
Waste Management Act of 2000 is recognized by the proponents of the proposed power
232
plant. This law is composed of the proper disposal of waste, as well as its segregation. In
addition, this regulation highlights the importance of a clean environment and expresses
grave concern for the health of the people living in a defined area. The aforementioned
republic legislation specifies the proper procedure of dealing with garbage, from
output and live a more environmentally friendly lifestyle. Companies that produce
energy, such power plants, are closely monitored and inspected for compliance with the
republic act since these facilities produce significant amounts of trash that might pose a
serious threat to the environment and human health. The legislation includes clear
directions for appropriate disposal along with the consequences and punishments for
Pollutant Emissions
Natural gas, a fuel with a lesser environmental effect than other fossil fuels, is
used to produce electricity using combined-cycle power plants (CCPP), which employs
both a gas turbine and a steam turbine. By producing steam from the gas turbine's exhaust
heat, energy is produced twice as much efficiently and with less waste.
A combined cycle power plant produces mostly Nitrogen Oxide (NOx) and
Carbon Monoxide (CO), whereas Sulfur Dioxide (SOx) and Promethium (PM) are
irrelevant since natural gas contains no sulfur and burning of a gaseous fuel produces no
PM. The emission rate of the former two pollutants, however, is strongly dependent on
the gas turbine operating conditions: NOx formation is favored by high combustion
233
due to an incomplete combustion process at low temperatures, so it is most emitted
during partial-load operation or start-ups. CO and NOx are produced during startup due
to the uneven flow distribution. Gonzales-Salazar et al. estimate that the emissions from a
CCGT start-up will fall between 0.02-0.9 kg/MW for NOx and 0.1-1.8 kg/MW for CO.
However, the following pollutant emissions will not affect the environment because the
proposed power plant layout and design is based on different standards and
234
CHAPTER V
This chapter summarizes the execution plan for the construction of the proposed
155 MW combined steam and gas power plant at Brgy. Bacong Ibaba, General Luna,
Quezon. It includes the construction management and strategy, quality control and
assurance, work scheduling, as well as the overall management and commissioning of the
project.
The construction of the proposed 155 MW combined cycle power plant requires
equipment. For the proposed project, there are fundamental phases that were followed to
Project planning, this is the stage in which the different parameters for the
viability of the project are measured. Design options are developed for technical and
economic analysis. It also includes the right location selection technique, in which all of
the essential requirements must be fulfilled for an area to be set up by a combined cycle
power plant. Also, the proximity to water is an essential requirement for such criteria to
be satisfied, the same with the accessibility for fuel transportation. Moreover, factors such
as the effects on the surrounding environment will be considered towards the conclusion
of the planning process. Emissions to the environment are also taken into account.
Because of the actual project construction, the execution phase tends to take the longest.
During this phase, an engineering and construction team collaborate to build the different
services of the power plant. This stage typically begins with foundation excavation,
235
sewage, and electrical work, followed by the rise of the many structures that will house
the various activities of the plant. In this phase, the fundamental parts of a combined
cycle power plant such as the steam turbine, gas turbine, and HRSG, are also installed.
After the construction phase ends, the monitoring and control phase begins. At
this point, real performance testing is carried out to ensure that all of the measured
parameters have been met. Regular meetings are held to supervise the implementation of
the project and to create an expedient reaction to any concerns that arise. With any
change to the plan, management is accountable for providing a timely update and
disseminating it to all employees. Last is the commissioning phase, which includes final
component testing. Fuel transportation processes are also checked to ensure that there are
no delays. Furthermore, all auxiliary components, such as waste water treatment, are
examined to ensure the greatest performance. A critical step in this phase is to do final
With this, the proposed 155 MW combined steam and gas cycle power plant to be
constructed for four years will operate at Brgy. Bacong Ibaba, General Luna, Quezon.
The plant layout inserted on the target location is shown in the figure below.
236
As seen in Figure 69, the proposed layout of the combined cycle power plant is
situated on the land of Brgy. Bacong Ibaba, General Luna, Quezon which is suitable for
properly. As a result, quality control and assurance are crucial for ensuring that power
plants run effectively, safely, and with as few adverse environmental effects as possible.
Quality control is the process of ensuring that the products or services are
produced to meet or exceed specified requirements. In the context of the power plant,
quality control involves verifying that the power plant's components, processes, and
procedures meet the necessary standards for safety, efficiency, and environmental impact.
This includes testing the materials used in the construction of the power plant, assessing
the performance of the equipment, and monitoring the emissions produced by the plant.
Quality assurance, on the other hand, is the process of ensuring that quality control
measures are effectively implemented and maintained throughout the life cycle of the
power plant. It involves establishing and documenting procedures for quality control,
Hence, to ensure that a power plant operates efficiently and safely, quality control
and assurance must be implemented at every stage of the power plant's life cycle, from
initial planning and design to decommissioning. In the planning and design stage, quality
control measures can ensure that the power plant is designed to meet or exceed the
necessary safety, efficiency, and environmental standards. This includes testing the
237
materials used in the construction of the power plant, assessing the performance of the
During the construction and installation phase, quality control measures can
ensure that the power plant is built to the necessary specifications and standards, and that
the equipment is installed and tested correctly. This includes ensuring that all workers
involved in the construction and installation process have the necessary training and
qualifications to perform their tasks safely and effectively. Once the power plant is
ensure that the plant operates efficiently and safely. This includes monitoring the
performance of the equipment, testing the emissions produced by the plant, and
In addition to ensuring that a power plant operates efficiently and safely, quality
control and assurance measures can also help to minimize the negative impact of the
power plant on the environment. This includes implementing procedures for monitoring
and reducing emissions, implementing procedures for managing waste products, and
implementing procedures for minimizing the use of natural resources. With that, the
proposed combined cycle power plant should follow the following quality control and
assurance procedures:
1. Providing a manual for the quality control and assurance of the project.
238
6. Documentation of the results of testing as well as the construction of the power plant.
Work Scheduling
The proposed 155 combined cycle power plant at Brgy. Bacong Ibaba, General
Luna, Quezon has a detailed work schedule that outlines the necessary tasks and events
to be completed during the construction phase. The Gantt chart, as shown in the table
below, depicts the timeline for the period of construction, highlighting the essential
activities that need to be completed along with their expected durations for completion..
It also illustrates the quarterly timeline for the construction of the power plant from 2024
to 2027. Thus, the schedule was planned with the expectation that the construction would
239
Table 71
Awarding of Contracts
Budgeting
Site Selection
Site Excavation
Electrical System
Installation
240
Initially, before starting the project, a feasibility study is carried out to determine
plant. This study helps to identify potential risks and challenges and provides a basis for
decision-making regarding the project. Then, the awarding of a contract for building a
power plant typically involves selecting the most qualified and capable contractor,
clarifying contractual terms and conditions, and establishing a mutually agreeable price
and payment schedule. The completion date for these two tasks is set to be before the end
Budgeting for the construction of the combined power plant requires careful
planning and monitoring to ensure that the project is completed on time and within
budget. The budget should include all expenses related to the project, including materials,
equipment, labor, permits, and other expenses. After completing the first three tasks, the
appropriate location for the power plant is selected, considering factors such as access to
fuel sources, proximity to transmission lines, and environmental considerations. The next
task involves obtaining permits and approvals, as local and state authorities require
approvals. The completion of the third, fourth, and fifth tasks is planned for the second
quarter of 2024.
For the power plant design, detailed engineering plans and designs for the power
plant are developed, including the selection of equipment, materials, and construction
techniques. After designing a plant layout, site excavation will be done since site
excavation is an essential part of building a power plant as it involves the removal of soil,
rock, and other materials to prepare the ground for the construction of the power plant's
241
foundation and other structures. These tasks will be performed before the third quarter of
Once the tasks mentioned above are finished, the process of procuring the
necessary equipment, materials, and services required for the power plant construction
will commence. This task will be completed before the end of the first quarter of 2025.
The next task in constructing the combined power plant is the actual building process,
which typically starts with site preparation, including clearing the site of any obstructions
and leveling the ground. The next step is the construction of building foundations and
equipment and systems. The completion of these tasks is anticipated to take place before
The task of installing an electrical system, which includes creating a secure and
effective network of electrical components to distribute power from the power plant to
the grid, will be completed before the second quarter of 2027 is over. For the testing and
procedures to ensure that the power plant is constructed and operating safely and
efficiently. This will be accomplished at the end of the third quarter of 2027. Lastly, once
the power plant is constructed and commissioned, it is essential to ensure that it continues
to operate safely and efficiently over its lifespan. The operation phase involves managing
the day-to-day operations of the power plant, which includes starting and stopping the
equipment, monitoring performance, and controlling the power output. The power plant
is planned to undergo operation and maintenance until the end of the fourth quarter of
242
2027, and it will be ready to provide its services to the intended consumers after that
time.
The construction and operation of the proposed power plant should be safe and
efficient at the same time. This will be done by regularly checking the equipment that are
utilized in building and operating the power plant. Also, workers should follow the safety
standards to lessen the risk of having accidents to achieve the desirable working
checking and assessing the facility to be ready for the service. The following
1. Administrative Manual
manual. Moreover, each documentation of the system for the plant has
instructions for these tasks. While commissioning the power plant, competent
startup staff are required to deliver satisfactory performance with their abilities to
structures are monitored and checked, and different reports, general control
2. Monitoring Assessment
international level which means that these regulations must be followed and
243
achieved. Furthermore, separate elements are examined and evaluated as part of
monitoring evaluation until the complete plant is operated and tested, starting with
the compressor, gas turbine, HRSG, steam turbine, condenser, and pump. Often,
3. Technical Manual
manual. Given the fact that power plants are composed of numerous equipment or
4. Inspection Manual
inspecting each component is significant. This manual will help the personnel or
staff responsible for this task as this manual holds different data and information
244
CHAPTER VI
In this chapter, the three design options of the proposed combined steam and gas
cycle power plant are evaluated, considering multiple realistic constraints such as the
aspects for technical, economic, and environmental. Scales and calculated values are
utilized, which are analyzed through the Pareto Optimum analysis in order to establish
Evaluating the technical aspects of the proposed three design options includes the
cycle efficiency, which is the efficiency of the power plant to generate electricity. As
indicated in the Handbook for Cogeneration and Combined Cycle Power Plants by Boyce
(2002), thermal efficiencies can reach up to 60%. Hence, shown in the table below is the
Table 72
60 10
55 8
50 6
45 4
40 2
For the cycle efficiency, the maximum and minimum values are 60% and 40%,
with the interval of 5%. Alongside with is the scale corresponding to the values. The
245
highest is 10 and the lowest is 2, which is directly proportional to the cycle efficiency
since the higher the cycle efficiency, the greater it is to be the design of the power plant.
In line with this, the analysis for the three design options is shown in the table
below.
Table 73
The second design option is observed as the highest with the efficiency of
58.3863411% and 9.354536439. Whereas the first design option has the lowest with
The economic aspect is also taken into account when designing a power plant,
including the profitability and its importance to the marker. This involves the net present
Shown in Table 4 is the scale to be utilized for analyzing the net present value.
Table 74
246
Table 74
202,500,000.00 10
67,500,000.00 8
22,500,000.00 6
7,500,000.00 4
2,500,000.00 2
The maximum and minimum values for the net present value are $202,500,000.00
and $2,500,000.00, respectively with a scale of 10 as the highest and 2 as the lowest. The
relation is direct wherein the higher the net present value, the better is the design.
Therefore, the table below presents the analysis of the net present value.
Table 75
The first design option is observed as the highest with the net present value of
$72,666,931.04 and 8.076547127. Whereas the third design option has the lowest with
247
Meanwhile, the payback period should also be a factor in evaluating the design of
the power plant. It is stated from the article that in order to determine if the project is
economically viable, the payback period of the combined cycle power plant should be in
the range of 8.5 to 15 years (Hittingers and Williams, 2021). Tabulated below is the scale
Table 76
3 10
6 8
9 6
12 4
15 2
The scale to be used is the same with the former ones, with 10 as the highest and
2 as the lowest. However, it is advised that the lesser the payback period, the better the
design of the power plant As such, the scale has an inverse relationship with the payback
In line with this, shown in Table 77 is the analysis for the payback period of three
design options.
Table 77
248
Table 77 (Continue)
The first design option is observed as the highest with the payback period of
with 10.00266154 years and 5.331558973. Whereas the third design option has the
On the other hand, the rate of return should be greater than the interest rate
wherein the project utilized 8%. However, it is supported by Speights (2023) that a good
ROI has the value of 10% or more when dealing with long-term investments. As such,
Table 78
15 10
12 8
9 6
6 4
3 2
249
The higher the rate of return, the more profitable a design is. Hence, the scale of
10 as highest and 2 as lowest is directly proportional to the rate of return with 15% as the
In line with this, Table 79 shows the analysis for rate of return.
Table 79
The first design option is observed as the highest with the rate of return of
9.997339168% and 6.664892779. Whereas the third design option has the lowest with
Last to be taken into account is the environmental condition that refers to the
effect of the proposed design to the surroundings. This includes the factor of fuel to
which the plant utilizes liquefied natural gas (LNG) with mass flow rates that vary among
design options.
Table 80
250
Mass of Fuel (kg/s) Scale
2 10
4 8
8 6
16 4
32 2
The scale of 10 as the highest and 2 as the lowest is inversely proportional to the
mass of fuel since the lower the mass, the better it is to use the proposed design of the
power plant. Whereas, the minimum mass flow rate of fuel is 2 kg/s and 32 kg/s is the
highest.
Table 81
The third design option is observed as the highest with the mass of fuel of
14.04705558 kg/s and numerical value of 4.488236105, followed by design option 1 with
25.02230616 kg/s and 2.87221173. Whereas the second design option has the lowest with
251
Pareto Optimum Analysis for the Design Options
The Pareto optimum analysis is the method used for selecting the best design
option of the proposed 155 MW combined steam and gas cycle power plant. This shows
As such, shown in the table below are the degrees of importance for each
constraint.
Table 82
Payback Period 2
Rate of Return 1
As seen in the table above, the technical, economical, and environmental factors
are evaluated through the degree of importance set. There is a value of 5 for the cycle
efficiency, 1 for the net present value, mass of fuel, and rate of return, and a value of 2 for
In line with this, Table 83 presents the Pareto Optimum analysis for the first
design option.
Table 83
252
Multiple Realistic Constraints Value
TOTAL 75.31736129
The total value for design option 1 is 75.31736129% with 43.69841822% for
cycle efficiency, 9.042776848% for net present value, 12.18228798% for payback period,
7.52166652% for the rate of return, and 2.87221173% for the mass of fuel.
Moreover, shown in Table 84 is the pareto optimum analysis for the second design
option.
Table 84
TOTAL 75.36750438
253
The total value for design option 2 is 75.36750438% with 47.22024744% for
cycle efficiency, 8.076547127% for net present value, 10.66311795% for payback period,
6.664892779% for the rate of return, and 2.742699086% for the mass of fuel.
Lastly, the pareto optimum analysis for design option 3 is presented below.
Table 85
TOTAL 73.39643303
The total value for design option 3 is 73.39643303% with 46.7726822% for cycle
efficiency, 6.434371144% for net present value, 9.549763893% for payback period,
6.151379691% for the rate of return, and 4.488236105% for the mass of fuel.
Upon performing the Pareto Optimum analysis, Table 16 shows the summary of
254
Table 86
1 75.31736129 2
2 75.36750438 1
3 73.39643303 3
The summary of results for Pareto optimum analysis is presented above. Design
option 1 has the value of 75.31736129% and design option 3 with 73.39643303%, lower
than the first design option. However, with a value of 7275.36750438%, design option 2
consisting of a single gas cycle and a single-stage reheat steam cycle is the highest among
the three. Hence, the optimum design for the proposed 155 MW combined steam and gas
255
CHAPTER VII
In this section, the summary of the findings are presented, as well as the
conclusion drawn for the proposed 155 MW combined steam and gas cycle power plant.
Summary of Findings
Based on a thorough evaluation and examination of the obtained results and data
in the proposed design of a 155 MW combined cycle power plant. The design summary
1. The proposed design of the 155 MW combined cycle power plant is situated in
Brgy. Bacong Ibaba, General Luna, Quezon Province, which will provide
covered by it.
MW for the year 2038, added by a 15% system loss and 19% reserve capacity,
resulting in 155 MW capacity of the power plant. It was used to calculate the load
3. The following design options are presented in the design project, such as the
design option 1 that consists of a simple Brayton and Rankine Cycle, design
option 2 which presents a simple gas turbine cycle and a single-stage reheat steam
turbine, and design option 3 with a single-stage reheat gas cycle and single-stage
256
4. The obtained overall plant efficiencies for design options 1,2, and 3 are
5. A net present value for the first design option is $137,887,437.23 which is
economic risk, and rate of return of 11.28249978 %. For design option 2, the net
payback period that shows a low-level economic risk, and a rate of return of
9.997339168 %. Lastly, the net present value for the third design option is
$3,796,833.87, the payback period is 11 years and 3 months, and the rate of return
6. The establishment of a 155 MW combined cycle power plant will consider the
environmental impact assessment (EIA) for the social, political, and ethical
bodies of water around the project site will be done to evaluate water quality and
protect it from pollution caused by the power plant's construction. Risk mitigation
measurements for air include performing an air quality monitoring near the
the best alternative design option 2 which is the combined cycle power plant
operating with simple gas turbine cycle and a single-stage reheat steam turbine.
257
Conclusions
Upon taking into account all the data and principles observed and calculated from
the whole study and through an in-depth analysis of the results, the proponents have
1. Based on the principles of choosing the location of the power plant and the
present zoning ordinance, the proposed location of Brgy. Bacong Ibaba, General
2. The equipment chosen for each design option varies upon the requirement of each
generator, pumps, open feed water heaters, and a heat recovery steam generator.
3. All design options passed the environmental considerations for a combined cycle
power plant, given that all are economical as the plant releases less emissions as
4. Considering the economical aspects of the design options, the design option 1 has
the highest value since it utilizes less equipment. Whereas based on the technical
aspects, the design option 2 has the best technical aspect. On the other hand,
design option 3 has the best environmental consideration since it uses less mass of
fuel.
5. Comparing the results found from the three aspects using the method of Pareto
Optimum analysis based on the overall cycle thermal efficiency, mass of fuel,
payback period, net present value, and rate of return, the best design option is
258
Recommendations
After completing the capstone project for the proposed 155 MW combined cycle
power plant and evaluating the selected design option, it was discovered that there are
still opportunities for improvement to boost the efficiency and ensure optimal
performance of the power plant. As a result, the proponents suggest the following
recommendations:
providing more detailed and current data on the electrical consumption from the
target location.
2. In order to create a detailed and reliable plant layout, the proponents should
data from the current Quezelco I procurement plan regarding the percentage of
conducting further research into the equipment costs and the factors utilized in
acquire the insights of a mechanical engineer who can provide an expert opinion
for the detailed data of the technical aspects involved in the project.
259
References
https://www.worldometers.info/gas/philippines-natural-gas/
https://www.doe.gov.ph/sites/default/files/pdf/e_ipo/investment_opportunities_phi
l_energy_sector.pdf
https://www.google.com/url-Salinity-2020-Technical-Report-Quezon.pdf
change on fossil fuel power-plant efficiency and water use. Journal of Cleaner
Velasco, M. (2022, November 28). Luzon grid power supply tumbles into ‘red alert.
Manila Bulletin.
https://mb.com.ph/2022/11/28/luzon-grid-power-supply-tumbles-into-red-alert/