Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

MONTHLY PROGRESS REPORT


FOR
NOVEMBER- 2022

TGEM
JSC “TAJIKHYDROELECTROMONTAZH”

Project:"Improving road safety Dushanbe-Tursunzade and Ayni-Penjikent


"Program Black spots"

Ministry of Transport of the Republic of Tajikistan

Financed by:

Asian Development Bank

November - 2022
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Content

s 1
1. Introduction...........................................................................................................................................................4
2. Purpose of the report............................................................................................................................................4
3. Types of work performed by the contractor during the reporting period......................................................5
4. Monitoring Results...............................................................................................................................................5
5. Conclusion and Recommendations.....................................................................................................................7
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

ABBREVIATIONS
Abbreviations Description
ADB Asian Development Bank
CEP Committee for Environmental Protection
SSEMP Special Environmental Management Plan
EMP Environmental Management Plan
GoT Government of Tajikistan
PEE Initial environmental review
MT Ministry of transportation
PIU Project Implementation Center
SEE State environmental "expertise"
PMO Waste management plan
SPS ADB Safeguards Policy Statement
CAREC Investment Program for the Development of Corridors of the
Central Asian Regional Economic Cooperation
GOST technical standard
KRZHP Consumer Complaint Management Committee
POPs Health Officer
Occupational health Health and Safety Officer
and safety
KNS Construction Supervision Consultant
PIU RR Project Implementation Unit for Road Rehabilitation
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

1. Introduction
Since 1998, the Government of the Republic of Tajikistan, through the Ministry of
Transport, has been successfully implementing projects for the construction, rehabilitation
and overhaul of roads and railways of the republic with the assistance of international
financial institutions.
This report is a quarterly review of the monitoring of the environment in the area of
influence of the Dushanbe-Tursunzade and Ayni-Penjikent Road Safety Improvement
Project "Black Spots" program for the period from April to June, 2022. This project is
financed by the Asian Development Bank (ADB).
Customer project Improving road safety Dushanbe-Tursunzade and Ayni-Penjikent "Black
spots" programis the Ministry of Transport (MT) of the Republic of Tajikistan. The
Executing Agency (EA) is the Center for the Implementation of Road Rehabilitation
Projects (PIU RR) of the MoT RT.
The project implementation contractor is JSC "TAJIKHYDROELECTROMONTAZH"

2. Purpose of the report


The purpose of the report is to include, first of all, the results of the work completed
until the reporting period, that is, until November 2022. During the preparation of the
report, all the works completed so far will be presented. One of the main goals of the report
is the effective process of work in the project. Traffic safety on the Dushanbe-Tursunzoda
and Ayni-Panjakent roads, which is indicated by the name of "Black Spots" in the planned
program of the Government of the country and ADB, is primarily the provision of road
safety in all seasons of the year.
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

3. Types of work performed by the contractor during the reporting period


During the calculation period, the contractor completed a lot of work on the Ayni-Panjakent
and Dushanbe-Tursunzoda projects, regardless of rain and snow.
- At km 53+700 paving works (Dushanbe-Tursunzade)
- At km 45+00 paving works, (Dushanbe-Tursunzade)
- At km 47+250 paving works (Dushanbe-Tursunzade)
- At km 55+900 paving works (Dushanbe-Tursunzade)
- At km 19+800 concrete pouring of retaining wall (Ayni-Panjakent)

- Excavation of a pit (Ayni-Panjakent)

- At km 53+00 digging a trench (Ayni-Panjakent)

Construction works are progressing mainly in the "Black point" projects according to the
plan. The level and quality of the work meets the requirements of the employer, and the
representatives of the Center monitor the implementation of the projects almost every day.
All those objects used for construction are examined in the laboratory. A total of 27,427 m2
of paving work has been completed in the Dushanbe-Tursunzoda project. A total of 55
workers are currently working on the Dushanbe-Tursunzoda project. Good working
conditions and special clothes are provided for workers. In this project, more than 10 small
and large equipment are working.
In the Aini-Panjakent project, 129 m3 of concrete was taken in the retaining walls until the
calculation period. The waterproofing of the retaining walls is 410 m2, Backfill is
organizing 250 m3, Slope layout is 184 m2, weaving reinforcement 96 m2. 17 workers and
5 work equipment are working on the project.
All completed works are collected in the form of photos before and after construction.
During the construction, our employees try to comply with all environmental requirements
so that nothing and no one is harmed.
Environmental protection specialist Sh. Rofiev and safety engineer of the company
Ismatullo S. conducted explanatory activities in the community and explained the nature of
the implemented project to the local residents. Photos are shown below:
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

4.Environmental Monitoring Results in the Aini-Panjakent and Dushanbe-


Turusunzoda projects
The monitoring results for the Dushanbe-Tursunzoda and Ayni-Penjikent sections during
the performance of work during the reporting period did not cause serious damage to the
environment and citizens, the results of which are presented to you in the table below.

Type of impact Ye Not Location Description Corrective action


s

1. Soil pollution √ Temporary Oil stains on the Leaks have been


camp at km 20 ground resulting eliminated.
from a leak from Contaminated soil
the mechanism collected and
discovered during handed over to
the Engineer's local waste
department for
inspection on May
safe disposal
22

2. Damage to property √
(buildings, walls, plantings,
etc.)

3. Improper waste √
management

4. Garbage scattered around √


the camp or work site

5. Improper stockpiling √

6. Dust associated with √ Dust generation A water carrier was


project activities due to excavation mobilized with
km19+500) instructions to
by an excavator to
widen the road in regularly water the
dry and windy road
weather

7. Excessive air pollution √


from exhaust gases of
working mechanisms
(visually)

8. Flooding, erosion, √
siltation disruption of the
existing irrigation network
as a result of project
activities
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

9. Cutting down trees or tall √


shrubs.

10. Species of fauna or √


flora listed in the Red Book
found within or near the
object

11. Archaeological or √
historical finds.

12. Violation of cemeteries √


and other places of cultural
or religious significance

13. Other impacts seen √

Public complaints about:


a) Water Quality √
Deteriorations

b) Land acquisitions √

c) Air pollution √

d) Noise √

e) Smell √

g) Vibrations √

g) Damage to property √

Taking into account the requirements of the legislation of the Republic of Tajikistan and the
Environmental Protection Committee of the Government of the Republic of Tajikistan,
relevant permits have been obtained for the construction of the facility. They also received
relevant conclusions about the quality and reliability of construction materials from state
and non-state laboratories. All construction materials are tested in the laboratory before use.
If the materials are of poor quality, it is not allowed to use them

5. Conclusion and Recommendations


Until this time, all the completed works were monitored by the consultant during the
questionnaire period, as a result of which sometimes comments and sometimes suggestions
were presented.
Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

All the defects that are revealed during the construction will be eliminated in time. In order
to further eliminate the shortcomings in the future, specialists will be involved who will not
interfere with the progress of the construction work, and the work will be completed on
time and with high quality.
A permit (positive conclusion) was obtained from the state expert and submitted to the
environmental protection office of the region, city and district. Other permits were obtained
for felling of trees, storage of construction debris, excess soil and solid waste generated
during the construction of the facility. sewer collector.
At the request of the consultant, a complaint book was created, during the reporting period
there were no complaints from citizens or other persons related to the project. All
employees of the contractor, starting from the management to the ordinary worker, carry
out anti-epidemiological and safety measures.
The construction project must include a specific health and safety plan in case of COVID-
19.

Picture 1 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 2 Ayni-Panjakent Retaininig wall

Picture 3 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 4 Ayni-Panjakent Retaininig wall

Picture 5 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 6 Ayni-Panjakent Retaininig wall

Picture 7 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 8 Ayni-Panjakent Retaininig wall

Picture 9 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 10 Ayni-Panjakent Retaininig wall

Picture 11 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 12 Ayni-Panjakent Retaininig wall

Picture 13 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 14 Ayni-Panjakent Retaininig wall

Picture 15 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 16 Ayni-Panjakent Retaininig wall

Picture 17 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 18 Ayni-Panjakent Retaininig wall

Picture 19 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 20 Ayni-Panjakent Retaininig wall

Picture 21 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 22 Ayni-Panjakent Retaininig wall

Picture 23 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 24 Ayni-Panjakent Retaininig wall

Picture 25 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 26 Ayni-Panjakent Retaininig wall

Picture 27 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 28 Ayni-Panjakent Retaininig wall

Picture 29 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 30 Ayni-Panjakent Retaininig wall

Picture 31 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 32 Ayni-Panjakent Retaininig wall

Picture 33 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 34 Ayni-Panjakent Retaininig wall

Picture 35 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 36 Ayni-Panjakent Retaininig wall

Picture 37 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 38 Ayni-Panjakent Retaininig wall

Picture 39 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 40 Ayni-Panjakent Retaininig wall

Picture 41 Ayni-Panjakent Retaininig wall


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 42 Ayni-Panjakent Retaininig wall

Picture 43 Conditions of work of paving stone of Dushanbe-Tursunzoda


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 44 small paving factory

Picture 44 small paving factory


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 45 small paving factory

Picture 46 The way to prepare paving stones


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 47How to store paving stones in a warehouse

Picture 48 Work progress in the Dushanbe-Tursunzoda project


Monthly Progress Report (November -2022)

GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots

Picture 49 Work progress in the Dushanbe-Tursunzoda project

Picture 50 Work progress in the Dushanbe-Tursunzoda project