MONTHLY PROGRESS REPORT November
MONTHLY PROGRESS REPORT November
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
TGEM
JSC “TAJIKHYDROELECTROMONTAZH”
Financed by:
November - 2022
Monthly Progress Report (November -2022)
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
Content
s 1
1. Introduction...........................................................................................................................................................4
2. Purpose of the report............................................................................................................................................4
3. Types of work performed by the contractor during the reporting period......................................................5
4. Monitoring Results...............................................................................................................................................5
5. Conclusion and Recommendations.....................................................................................................................7
Monthly Progress Report (November -2022)
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
ABBREVIATIONS
Abbreviations Description
ADB Asian Development Bank
CEP Committee for Environmental Protection
SSEMP Special Environmental Management Plan
EMP Environmental Management Plan
GoT Government of Tajikistan
PEE Initial environmental review
MT Ministry of transportation
PIU Project Implementation Center
SEE State environmental "expertise"
PMO Waste management plan
SPS ADB Safeguards Policy Statement
CAREC Investment Program for the Development of Corridors of the
Central Asian Regional Economic Cooperation
GOST technical standard
KRZHP Consumer Complaint Management Committee
POPs Health Officer
Occupational health Health and Safety Officer
and safety
KNS Construction Supervision Consultant
PIU RR Project Implementation Unit for Road Rehabilitation
Monthly Progress Report (November -2022)
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
1. Introduction
Since 1998, the Government of the Republic of Tajikistan, through the Ministry of
Transport, has been successfully implementing projects for the construction, rehabilitation
and overhaul of roads and railways of the republic with the assistance of international
financial institutions.
This report is a quarterly review of the monitoring of the environment in the area of
influence of the Dushanbe-Tursunzade and Ayni-Penjikent Road Safety Improvement
Project "Black Spots" program for the period from April to June, 2022. This project is
financed by the Asian Development Bank (ADB).
Customer project Improving road safety Dushanbe-Tursunzade and Ayni-Penjikent "Black
spots" programis the Ministry of Transport (MT) of the Republic of Tajikistan. The
Executing Agency (EA) is the Center for the Implementation of Road Rehabilitation
Projects (PIU RR) of the MoT RT.
The project implementation contractor is JSC "TAJIKHYDROELECTROMONTAZH"
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
Construction works are progressing mainly in the "Black point" projects according to the
plan. The level and quality of the work meets the requirements of the employer, and the
representatives of the Center monitor the implementation of the projects almost every day.
All those objects used for construction are examined in the laboratory. A total of 27,427 m2
of paving work has been completed in the Dushanbe-Tursunzoda project. A total of 55
workers are currently working on the Dushanbe-Tursunzoda project. Good working
conditions and special clothes are provided for workers. In this project, more than 10 small
and large equipment are working.
In the Aini-Panjakent project, 129 m3 of concrete was taken in the retaining walls until the
calculation period. The waterproofing of the retaining walls is 410 m2, Backfill is
organizing 250 m3, Slope layout is 184 m2, weaving reinforcement 96 m2. 17 workers and
5 work equipment are working on the project.
All completed works are collected in the form of photos before and after construction.
During the construction, our employees try to comply with all environmental requirements
so that nothing and no one is harmed.
Environmental protection specialist Sh. Rofiev and safety engineer of the company
Ismatullo S. conducted explanatory activities in the community and explained the nature of
the implemented project to the local residents. Photos are shown below:
Monthly Progress Report (November -2022)
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
2. Damage to property √
(buildings, walls, plantings,
etc.)
3. Improper waste √
management
5. Improper stockpiling √
8. Flooding, erosion, √
siltation disruption of the
existing irrigation network
as a result of project
activities
Monthly Progress Report (November -2022)
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
11. Archaeological or √
historical finds.
b) Land acquisitions √
c) Air pollution √
d) Noise √
e) Smell √
g) Vibrations √
g) Damage to property √
Taking into account the requirements of the legislation of the Republic of Tajikistan and the
Environmental Protection Committee of the Government of the Republic of Tajikistan,
relevant permits have been obtained for the construction of the facility. They also received
relevant conclusions about the quality and reliability of construction materials from state
and non-state laboratories. All construction materials are tested in the laboratory before use.
If the materials are of poor quality, it is not allowed to use them
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
All the defects that are revealed during the construction will be eliminated in time. In order
to further eliminate the shortcomings in the future, specialists will be involved who will not
interfere with the progress of the construction work, and the work will be completed on
time and with high quality.
A permit (positive conclusion) was obtained from the state expert and submitted to the
environmental protection office of the region, city and district. Other permits were obtained
for felling of trees, storage of construction debris, excess soil and solid waste generated
during the construction of the facility. sewer collector.
At the request of the consultant, a complaint book was created, during the reporting period
there were no complaints from citizens or other persons related to the project. All
employees of the contractor, starting from the management to the ordinary worker, carry
out anti-epidemiological and safety measures.
The construction project must include a specific health and safety plan in case of COVID-
19.
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots
GRANT 0569 Additional funding for the project: "Improvement of traffic safety in Dushanbe-Tursunzade and Ayni-Penjikent Program Black spots