Professional Documents
Culture Documents
1. API 653 is more relaxed in peaking, banding, out of plumpness except for
Radiographic requirements
2. OFF SET for new vertical joint = 5 t ( where T is thickness of the thicker
course) (API 650 & API 653)
3. LOW Hydrogen electrode should be used for all Manual metal Arc
welding , annular ring and Shell course ( Same for API 650 & 653)
a. For Gr 1 –III more than 0.5 inch
b. For Group IV to VII all thickness
6. Foundation Tolerance :
When concrete wall is present it is 3mm in 30 feet or 6 mm overall
When concrete wall is not present it is 3mm in 10 feet or 12.5 mm overall
7. Radiography
Here API 653 is more stricter by taking one additional shot
For Thickness below 10 mm one shot in the first 10 feet and one
additional shot in every further 100 feet. And 25 % of all T joints
For thickness 10 mm – 25 mm : Additional one spot,
For thickness above 25 mm: 100 % RT
Besides Two spots in every vertical join for the Lowest course
For API 653 you have to take one extra spot in each vertical joint joining
new weld with existing weld
9. Measurement Points
Minimum 5 readings are needed to determine the minimum thickness over
the corroded area to find Length L.
L = 3.7 SQ root of ( D t2) or 40 inch which ever is less. Here actual
corroded length may be more than calculated L
10. Pressure:
Internal Pressure of AST or atmospheric pressure = 2.5 psi , Code is API
650 Appendix F
External pressure minimum – 1 inch water
External pressure maximum 1psi For external pressure code API 620
Leak Testing 14.5 Psi
Vacuum Box testing 3-5 psi
14. Bottom plate Projection area thickness is 0.1 inch and outside projection is
3/8 inch
But by API 653, Bottom plate projection beyond the corner weld is 1inch
Annular plate projection beyond the shell is 2 inch
UT is needed to check lap joint hot tap, for butt weld if there is no
radiography
RT : All butt weld, Insert weld, Annular plate weld, repair weld, all T joints
Vac box test : Shell to bottom weld when diesel test is not done
Bottom weld when tracer gas test is not done
Roof plate weld for gas tight tanks
Tracer gas test : Only for bottom weld when vac box testing is not done
20. Shell ring may be dismantled by cutting 6 inch away from existing weld
When dismantling shell tank roof or bottom plate shall e cut 2 inch away
from the weld
When reusing the entire bottom in the intact condition , Shell should be cut
12 inch above the top of the bottom plate
Edge of any permanent attachment should be 3 inch away from horizontal
weld & 6 inch away from the vertical weld
21. Vacuum Box testing
Size of the Vacuum Box 30 inch by 6 inch
Vacuum needed 8psi to 10 psi. But if required by the customer to detect
small leaks 3.5 psi can be used
Minimum overlap = 2 inches,
Temp is 4 Degree Centigrade to 52 Degree Centigrade Light needed
1000 Lux, Vacuum should be maintained minimum for 5 sec or the time
needed to view the area under the test
So UI table 1 REINFORCEMENT
RT DEFECTS
UI 10 mm 3mm ( Defect Size)
More than 10 mm - UI 57 mm t/3
More than 57 mm 19 mm
23. UG
Below 2 inch Ug is .02 inch
From 2 inch – UI 3 inch .03
Over 3 and UI 4 inch 04
Over 4 inch 07 in
24. LESS THAN Cases Mixed
27. For more than 38 mm, multi pas is needed. For more than 19 mm one
pass. And plus 200 deg F pre heat is required
28. Shell to fillet weld Leak testing Leak testing 15 PSI is best.
1. API 653 is code used for inspection, repair, and alteration for the
aboveground storage tanks which are placed in Service. API 650 is
the basic construction code for making New Tanks.
2. API 650 and API 653 are used for aboveground storage tanks at
atmospheric pressure (maximum 2.5 psi above atmospheric) and
temperatures not exceeding 90ºC.
4. Where necessary, as per Fig. 2-1 (API 650), the tank materials shall be
checked against brittle failure by conducting impact testing. Acceptance
criteria shall be as per Table 2-4.
t = 4 . 9 D ( H−0
d Sd
.3 ) G
+ CA and t =
4 . 9 D(H −0 . 3)
Stt
(Metric)
t d =
2. 6 D( H−1) G
Sd
+ C . A . and t = 2 .6 D(StH −1)
t
(US units)
Where:
7. Shell thickness calculated above (point no. 6) shall not be less than
that required by Diameter – Thickness table in API 650. (3.6.1.1)
8. Values of Sd and St are taken from Table 3-2 of API 650. For unlisted
material:
Sd = Lower of 2/3 (Y.S) or 2/5 (T.S.) and
St = Lower of ¾ (Y.S) or 3/7 (T.S.)
10. All nozzles, manholes and other openings shall have dimensions
thickness, reinforcement plates and weld sizes as per tables 3-6 and 3-
7 of API 650.
11. Radiography inspection is required for all shell butt welds and annular
plate butt welds and inserts plates for manhole and nozzles.
12. For shell plates the number of radiographs required depend on whether
the plate thickness is up to 10 mm (3/8), or above 10 mm to 25 mm
(3/8” – 1”) or above 25 mm (1”). (Fig. 6-1 of API 650).
a. An owner operator
b. Subcontractor to owner operator
c. Inspection organization of jurisdiction
d. Inspection organization of insurance company
a. Owner-user
b. Subcontractor to owner-user
c. Subcontractor authorized or approved by
jurisdiction
7. Tank roof plates which are so corroded that there are through
holes or the average thickness is less than 0.09 inch in any 100
sq. inch area, then plates must be repaired or replaced, i.e., tank
cannot be permitted to continue operation.
12. Min. thickness in “critical zone” is smaller of:(but not less than
0.1”)
a. Half of original bottom thickness in critical zone,
and
b. Half of tmin for first shell course.
13. Tanks designed prior to API 650 (7th edition, 1980) may be
assessed for brittle failure as per Fig. 5.2.
14. Tanks are not likely to fail in brittle failure if thickness is not more than
½” or shell temperature is not less than 60º F or stress level is less than
7,000 psi.
DAILY POINTS TO RECALL (DAY 3)
11. All shell plate defects like the cracks, gauges, tears, widely scattered
.pits and corroded areas shall be evaluated case by case as per
chapter 4 of API 653.
13. Repairs within critical zone of the bottom require additional precautions
like “Tombstone” type patch and additional PT or MPI testing after
visual examination of patch welds, and weld shall be made by minimum
2 passes.
14. If impact test was not done on original tank material, the hot taps shall
be limited to NPS 4 (max).
15. Toe-to-toe minimum spacing between hot tap and adjacent nozzle shall
be = √ RT where R= tank shell radius in inches T is shell plate
thickness in inches.
DAILY POINTS TO RECALL (DAY 4)
1. For tank relocation, the bottom, shell or roof may be cut in any size
from existing tank so that the pieces are suitable for transportation.
2. For dismantling the tank the bottom may be cut 12” away from shell to
bottom weld, if entire bottom plates are to be used.
3. Alternatively cut the bottom and shell at 1/2” from toe of shell to bottom
weld and discard the weld portion.
PT / MT: For all fillet welds and fill-up (weld-build up) during repair or
alteration
8. Radiography:
a. New welds during repair or alteration between the
plates such as:
11. Out of plumbness for reconstructed tank is 1/100 of the tank height
subject to maximum 5 inches.
B = 0.37 R
Where B = Max. height of bulge or depth of settlement (inches)
And R = Radius of largest inscribing circle (feet)
14. Based on Fig. B-10, and B-11 maximum allowable edge settlement is
worked out depending on settled area being approximately parallel or
perpendicular to shell.
3. Bend test crack shall not exceed 1/8” in any direction for face bend,
root bend or side bend.
Impressed current:
14. The principal advantages for thin-film lining are lower cost and
ease of application compared to thick-film lining systems.
16. Temperature during blast cleaning and applying the linings shall be 3°C
(5°F) above the dew-point temperature and relative humidity not to
exceed 80%.
DAILY POINTS TO RECALL (DAY 6)
GENERAL:
FOR RT:
b. Backscatter:
Light image of B on dark background - Unacceptable
c. Density Limitations:
u) Hole pani should be placed parallel to the weld whiled the wire
should be placed perpendicular ie across the weld
v) If 2 IQI are used one should be in the lightest area and the other
should be in the darkest area
x) Shims are place if the peni canot be placed on the part directly
The tem should not exceed 200 Deg F.. For higher temp Prodeure has to be
qualified accordinly. In the same way high temp couplany & High tem
probe gas to be used. For Every 100 Deg F excess temp , 1 % is the
correction facter
UT can be used for all the material where UT waves travels t constant
velocity
T = vt/2, T = Thk, V = velocity, t = Transit time
Three kinds of display 1) A scan display, 2)Flaw detecters with A scan
display & direct Thk Read out, 3) Direct hk Readout
For thin section Highly damped High Freq probe is used
Dual probes are used for thk above 3 mm
Dual probes are used for rough surface
Std calibration block should have same acoustic velocity
Maximum accuracy will be got from materials with parallel or concentric
surface
For thin section direct Readout units without A can display gives errors
For Rough pitted or corroded surface A scan units are prefgerrable
Scope – Selecting and developing UT procedure for part, components,
materials and all thickness determinations
Written Procedure: contain minimum requirement listed in cable 7.522
essential and non-essential variables procedure to be qualified when
specified.
Equipment: Plus Echo type UT instrument shall be used, frequency over
range of the atleast 1 Mhz to 5 Mhz, gain control – 2.0 dB or less
Couplant: nickel base alloy sulphur not more than 250psi SS or Titanium
halide (chloride + Flourid) not > 250psi
Calibration Block: P1, P3, P4, P5 are equivalent
C.B should be same material Specific product from, heat treatment as the
material being examined
Penetrant Developer
Dwell Time in
time in Minutes
Minutes
Casting & 5 7
Common Weld
Material Wrought, 10 7
Plate
All other All forms 5 7
materials
Water washable penetrant water pressure should not exceed 50 psi and
temperature should not exceed 43ºC
Post emulsification penetrant Lipophilic & hydrophilic emulsification
Lipophilic no pre-rinsing with water before emulsification, after
emulsification rinsing with water
Hydrophilic Prior to emulsification pre-rinsing with water time shall not
exceed 1 minute, after emulsification rinse with water
Solvent removable solvents first remove with cloth or absorbent paper by
wiping then cloth or paper moistured with solvent likely wipe the
surface flushing the surface with solvent is prohibited
Developer Colour contrast penetrant only wet developer
Dry developer shall be applied powder gun, soft brush, hand powder bulb
Wet developer
Minimum light intensity shall be 50 FC (500 lux) for color contrast penetrant
Prod Technique:
For 19 mm thickness greater 100 amp/in – 125 amp/in
o > 19 90 - 110 amp/in
o Prod spacing shall not exceed 18 inch
o Less than 3 inch spacing is not permitted
o Current is > 25 V – lead, steel or aluminum (rather than copper)
tipped prods are recommended
Yoke Technique:
4. The terms “Sketch plates” and “annular plates” refer to Plates in:
a. Tank roof
b. Tank bottom
c. Tank shell
d. None of above
11. When the tank is empty, the floating roof of open-top tank is
a. At its top-most position
b. Resting on the bottom
c. Resting on the legs
d. May be at any location
12. Since the tank is neither a pressure vessel, nor the piping, the
welding procedures and welders for API 650 tanks are qualified as
per:
a. AWS D 1.1
b. API 1104
c. Still use ASME IX
d. Any of above is OK
13. Which of the following is/are mandatory appurtenances for Storage
tanks?
a. Tank level gauge
b. Tank vents
c. Pressure gauge
d. Temperature gauge / thermometer
----------------------END------------------------
QB 1: BENCH MARK QUIZ
ANSWE KEY
Q. No. Answer
1 C
2 D
3 A
4 B
5 A
6 B
7 B
8 C
9 D
10 A
11 C
12 C
13 B
14 B
15 A
QB 2: API 653-2009
OPEN BOOK QUESTIONS FOR API 653
Note: try these questions after read API 653 once; these questions are
prepared to understand each and every section of the API 653
7. What will be the allowable hydrostatic test stress (1bf/ sq .in) for
A537 Class-2 material of 2nd course shall in tank?
a. 41,500
b. 37,800
c. 34,300
d. 30,000
10. When calculating minimum thickness, the weld joint efficiency for
butt welled tank constructed according to API 650 10 th edition.
a. 1.0
b. 0.85
c. 0.7
d. None of the above.
11. The following are some historical causes of the tank bottom leakage
or failure. But not one of this is
a. Lack of an annular plate ring when required.
b. Inadequately supported sumps.
c. Weld joint cracking.
d. Thinner the bottom plate more the corrosion.
12. For bottom plate thickness measurement we are using MFL & UT.
The quality of data obtained for these techniques is dependent on
personnel, equipment and _________
a. Location where the measurement was taken.
b. Procedure
c. Inspector
d. All of the above.
13. The 1st shell thickness of the tank is 1inch and its stress is
27000 lbf/ sq.in. what will be the annular plate thickness. (note:
product specific gravity is 0.9)
a. 0.22 inch.
b. 0.50 inch.
c. 0.31 inch.
d. 0.10 inch.
e. Not enough information given to calculate annular plate thickness.
14. The 1st shell thickness of the tank is 1 inch and material is A537 Gr-2,
what will be the annular plate thickness (note: product specific
gravity is 1.1)
a. 3/8 inch.
b. 1/4 inch.
c. 5/8 inch.
d. 7/16 inch.
e. Not enough information given to calculate annular plate thickness.
15. Hairline cracks of uniform width do not seriously affect the strength
of the concrete foundation. However these cracks can be potential
access points for moisture or water seepage that could eventually
result in corrosion of the ____________.
a. Bottom plate.
b. Annular plate.
c. Reinforcing steel.
d. Shell plate.
18. Industry experience and laboratory test have shown that a membrane
stress in tank shell plate of ______________ 7 ksi is required to
cause failure due to brittle fracture.
a. Equal to.
b. At least.
c. More than.
d. Less than.
24. For reconstruction tanks, the maximum design liquid level for
product shall be determined by calculating the maximum design
liquid level for the each shell course based on the specific gravity of
the product. For this calculation allowable stress for the material
shall be determined using API std 650, table 3-2, for material not
listed in table 3-2 an allowable stress value of ___________.
a. Lesser of 3/4 yield strength or 3/7 tensile strength shall be used.
b. Higher of 3/4 yield strength or 3/7 tensile strength shall be used.
c. Lesser of 2/3 yield strength or 2/5 tensile strength shall be used.
d. Higher of 2/3 yield strength or 2/5 tensile strength shall be used.
25. The thickness of the replacement shell plate shall not be less than
the greatest nominal thickness of any plate in the same course
adjoining the replacement plate except where the adjoining plate is a
__________________ plate.
a. Thinner insert.
b. Thickened insert.
c. Thickened patch.
d. Thinner patch.
26. In tank replacement, for existing shell plate ½ inch thick and less, the
outer edge of the butt weld attaching the replacement shell plate
shall be at least _________ from the outer edge of vertical joints or
_____________ form the outer edge of horizontal.
a. 8t; 10 inch.
b. 6 inch; 6 inch.
c. 6 inch; 3 inch.
d. 12 inch; 12 inch.
28. In a tank shell plate some area severely corroded and it has to
replace with same shell plate material, thickness of shell plate is ¾
inch. What will be the corner radius of the new insert replacement
shell plate?
a. 6 inch.
b. 3 inch.
c. 4.5 inch.
d. 12 inch.
29. 1-inch shell corroded area is planned to repair with lap welded 1-inch
patch plate, this patch planning to weld from outside of tank. What
fillet weld size on the patch plate near shell to bottom welds?
(existing corner weld size is one inch)
a. 3/16 inch.
b. Lesser of repair plate thickness or bottom plate thickness.
c. ¼ inch.
d. ½ inch.
e. ¾ inch.
30. The maximum vertical and horizontal dimension of the repair plate
for lapped patch shell repair is ___________.
a. 36 inch and 72 inch respectively.
b. 48 inch and 72 inch respectively.
c. 24 inch and 64 inch respectively.
d. 56 inch and 80 inch respectively.
31. The minimum lapped patch shell repair plate dimension shall be 4
inch with a minimum and maximum overlap of ___________.
a. 2t : 6t
b. 1 inch: 8t.
c. 4t : 6t
d. 6 inch: 24 inch.
32. Lapped patch repair method shall not be used if exposure of the fillet
welds to the product will produce ______________.
a. Product corrosion.
b. H2S corrosion.
c. Stress corrosion cracking.
d. Crevice corrosion.
33. When reinforcing plates are used over insert plate, the minimum
diameter of the insert plate shall equal to the diameter of the
__________.
a. Penetration diameter + 12 inch.
b. Reinforcing diameter + 12 inch.
c. Penetration diameter + 24 inch.
d. None of the above.
39. A tank in service, this tank diameter is 200 feet and first shell
thickness is ¾ inch, the tank design engineer analyzed and allowed
to weld one 14 inch nozzle in service. This new nozzle location going
to be near to existing nozzle. As an API 653 inspector what distance
you will suggest to install new nozzle weld from existing one?
a. 9inch.
b. 12inch.
c. 30inch.
d. 43inch.
e. At least 14inch.
40. During dismantling of tank, how much minimum distance has to cut
from the shell to bottom weld toe, when the entire bottom is to be
reused?
a. 1/2inch.
b. 2inch.
c. 12inch.
d. 6t (t is bottom plate thickness)
41. While dismantling of tank shell plate, any shell ring may be
dismantled by cutting out existing weld seems and the heat affected
zone of the weld, for the purpose of this method, the minimum HAZ
to be removed will be_______________.
a. 1/2 of the weld metal width or 1/4inch, which ever is less, in any
side of the weld seam.
b. 1/2 of the weld metal width or 1/4inch, which ever is less on both
sides of the weld seam.
c. Cutting through the weld may use for dismantle any shell ring
1/2inch thick or thicker without removing HAZ?
d. All of the above.
46. Allowable peaking & banding for reconstructed tank in any 36inch of
welding will be _______.
a. ½ inch maximum peaking: 1inch maximum banding.
b. 1inch maximum peaking: ½ inch maximum banding.
c. ½ inch peaking and banding maximum.
d. None of the above.
48. A tank new shell plates replaced and welded over an existing shell
plates, for this condition, what will be the additional RT requirement?
a. New replacement shell plates to existing shell plates, one additional
RT shall be taken in each vertical joints.
b. New replacement shell to existing shell plates, one additional RT for
each 50 feet of repaired horizontal weld.
c. New replacement shell plates to existing shell plates, each
intersection shall be radio graphed.
d. All of the above.
ANSWERS- OK-653-2009
Q. NO ANS REF
1. E 4.3.2.1.e API653
2. C 4.3.2.1(b) API653
3. B 3.14 API653
4. B 4.3.2.2 API653
5. E 4.3.3.1 API653
6. B Table 4.1 API653
7. B Table 4.1 API653
8. D Table 4.1 API653
9. D Table 4.1 note 6 API653
10. A Table4.2 API653
11. D 4.4.2 API653
12. B 4.4.1 API653
13. C Table 4.5 API653
14. D 4.4.8.3, Table 4.5 API653
15. C 4.5.1.2e API653
16. E 5.2.3 API653
17. C 5.3.5 API653
18. B 5.3.7 API653
19. B Table 4.4 API653
20. B 6.8.1 API653
21. B 7.3.1.1 API653
22. A 7.3.1.2 API653
23. D 7.3.2 API653
24. C 8.4.2 API653
25. B 9.2.1 API653
26. C 9.2.3.3 API653
27. D 9.2.3.4 API653
28. A Fig.9.1,DIMENSION R API653
29. A Fig.9.2, DIMENSION B API653
30. B 9.3.1.7 API653
31. B 9.3.2.3 API653
32. D 9.3.4.4 API653
33. B 9.8.6.b API653
34. A 9.10.1.1b API653
35. D 9.10.1.2b API653
36. A 9.10..2.7 D API653
37. A 9.14.1.1 API653
38. B Table9.1 API653
39. C 9.14.3.1 API653
40. C Fig.10.1 API653
41. B 10.3.3.1a API653
42. A 10.4.2.1 API653
43. C 10.4.2.9&10.4.2.10 API653
44. B Table10.1 API653
45. A 10.5.3 API653
46. A 10.5.4&10.5.5 API653
47. C 12.1.4.1 API653
48. D 12.2.1.2 & 12.2.1.3 API653
49. C 12.2.1.6.1 & 12.2.1.6.2 API653
50. D 3.18 API653
51. D 12.3.1 API653
QB 3: API 653-2009
Note: try these questions after reading API 653 once; some of following
questions will be as open book. These questions are prepared to under stand
each and every section of the API 653
3. API 653 scope is limited to the following but not one of this?
a. tank foundation.
b. First threaded joint
c. Roof
d. Attached appurtenances.
e. None of the above.
14. The portion of the tank bottom or annular plate with in 3” of the
inside edge of the shell, measured radially inward is……………
a. Critical area.
b. Special attention area.
c. Alarm area.
d. Critical Zone.
15. The following are example of repair in tank and not this one?
a. Removal of reinforcing plate.
b. Repair of tears or gouges by grinding.
c. Re-leveling and/or jacking of tank.
d. None of the above.
28. When determining actual thickness; the actual corroded area may
________ to the maximum vertical length (L).
a. Lesser
b. Exceed
c. Same
d. Average
35. For bottom plate thickness measurements MFL and UT are used
but……….......
a. UT is often used to confirm and further quantify data obtained by
MFL.
b. UT will be always preferred for bottom plate.
c. After UT measurements taken inspector should confirm with
MFL method.
d. None of the above.
36. Unless stress analysis is performed, the minimum bottom plate
thickness is the critical zone of the tank bottom shall be the
smaller of ½ of the original bottom plate thickness or 50% of ‘t’
min. of the lower shell course but not less than________________
a. 1in.
b. 0.5in.
c. 0.25in.
d. 0.1in.
38. The projection of the bottom plate beyond the outside toe of the
shell-to-bottom weld shell shall be at least______________.
a. ¼ in.
b. ½ in.
c. 3/8 in.
d. 5/8 in.
43. The following all are tank failure due to brittle fracture but not this
one_____.
a. Tank continuously served in low temperature service.
b. After erection during hydrostatic testing.
c. First filling in cold weather.
d. After a change to lower temperature service.
e. None of the above.
44. A tank has demonstrated the ability to with stand the combined
effects of maximum liquid level and lower operating temperature
without failing. For the above tank, whether the risk of failure due
to brittle fracture with continued service in minimal?
a. No, brittle fracture will depend on low temperature of product.
b. No, brittle fracture is not dangerous in tank by experience.
c. Yes it is minimal.
d. None of the above.
47. To avoid brittle fracture some tanks have heaters this heaters will
increase the metal temperature by heating the _________.
a. Shell plate.
b. Bottom plate.
c. Tank contents.
d. Fire water line.
50. In some cases _______ also control the frequency and interval of
the inspection.
a. National board regulations.
b. Jurisdictional regulations.
c. Owner/operator regulations.
d. Authorized inspector.
53. Routine in-service inspection shall include the following and not
this one?
a. Thickness check.
b. Visual inspection.
c. Evidence of leak.
d. Shell distortions.
e. Corrosion.
54. External inspection for all tanks shall be given a visual external
inspection by authorized inspector. For this inspection maximum
interval will be ____.
a. 5 years.
b. 5 years or RCA/2N years, which ever is less.
c. 5 years or RCA/4N years, which ever is less.
d. 5 years if corrosion allowance known, 15 years if corrosion
allowance not known.
55. External inspection for all tanks shall be done by Al. And during
this inspection that tank ________________________.
a. Shall be in operation during this inspection.
b. May be in operation during this inspection.
c. Should be in operation during this inspection.
d. None of the above.
56. You are the inspector for tank to do external inspection. And tank
was insulated by 150mm outside insulation and covered by
aluminum sheets. What will be your action?
a. Remove small area for inspection and cover it properly after
inspection.
b. Removal of insulation is not at all required for external
inspection.
c. Insulation removal only for necessary area to check the external
wall.
d. It is always authorized inspector’s option to open insulation.
57. The extent of ultrasonic thickness measurement inspection shall
be determined by …………………
a. Authorized inspector.
b. UT operator.
c. Owner/operator.
d. Tank design engineer.
58. When the corrosion rate is known what will be the maximum
interval of ultrasonic thickness inspection?
a. 5 years.
b. 15 years.
c. RCA/4N.
d. Both ‘a’ and ‘c’ which ever is smaller.
e. None of the above.
61. What is the maximum routine in-service inspection interval for the
tank ABC 650?
a. 3 years.
b. 11/2 year.
c. 1 month.
d. 5 years.
62. External inspection interval for tank ABC 650 is?
a. 6 years.
b. 1½ year.
c. 3 years.
d. 5 years.
e. 15 years.
70. When corrosion rates are not known and similar service
experience is not available to estimate bottom plate minimum
thickness at the next inspection, the inspection interval shall not
exceed____________.
a. 10 years.
b. 20 years.
c. 5 years.
d. Owner/operator should decide.
e. Authorized inspector should decide.
71. If external inspection can access to all the area of tank, then the
internal inspection can be eliminated.
a. Yes.
b. No, internal inspection never eliminated by external inspection.
c. Depends on owner-operator requirements.
d. None of the above.
72. All new material used for repair, alteration, or reconstruction shall
confirm to ___
a. Current applicable tank standards.
b. Applicable tank standard.
c. Construction code.
d. API 653
e. API 650
75. When material not identified shall be tested, for this test specimen
selection by ____________.
a. One per heat.
b. One per lot
c. One per tank
d. Each plate.
77. For tank all new shell joints shall be _____ with complete
penetration and complete fusion.
a. Lap weld.
b. Full weld.
c. Butt weld.
d. Groove weld.
81. The Authorized inspector may give prior general authorization for
limited or routine repair as long as authorized inspector is
______________.
a. After consulting with an engineer experienced in storage tank
design.
b. Sure that repair will not require hydrostatic testing or don’t
require an engineering evaluation.
c. If the repair as per API 650.
d. ‘a’ and ‘b’.
87. Lapped patch shell repair shall not be used on any shell course
thickness that exceeds ________ or to replace door sheets or
shell plates.
a. ¼
b. ½
c. ¾
d. 1
90. Weld reinforcement in excess are with in the limit to API 650 for a
exiting weld of a tank. If change of service this weld
reinforcement…………………
a. It is acceptable to API 650, so nothing to do.
b. Smooth grinding required.
c. For a floating roof with flexible seals service it may required to
grinding.
d. Floating roof with flexible seals has to design according to the
existing weld reinforcements.
91. If the shell plate greater than ½ inch. All penetration shall be
installed with the use of an insert plate if the penetration diameter
____________________.
a. 2 inch and above.
b. Above 2 inch.
c. Less than 2 inch.
d. Insert plate is not required for nozzles.
93. The minimum dimension for a weld on patch that over laps a
bottom seam or existing patch is _________. When the thickness
of existing plate is ½ inch.
a. 12 inch.
b. 6 inch.
c. 3 inch.
d. 24 inch.
94. Welded-on patch plate over the areas of the tank bottom that have
global dishing, local dishing, settlement or over distortion are
______________.
a. Shall be profiled to that shape.
b. Shall not be used.
c. Split patches can be used.
d. None of the above.
103. At hot tapping required reinforcement plate this plate has two
half, after reinforcement plate has been welded to the shell and
NDT carried out, the pad shall be pneumatically tested. For this
pneumatic test how many telltale hole required.
a. One
b. Each half one.
c. Any where to convenient to NDT person.
d. None of the above.
104. Who shall approve all reconstruction work at the designated hold
points and after reconstruction has been completed in
accordance with the requirement of API653.
a. Authorized inspector.
b. An engineer experienced in storage tank design.
c. ‘a’ or ‘b’.
d. Any one designated by owner/operator.
105. A tank has decided to dismantle and reconstruct in new site,
during dismantling roof, shell, bottom plates are to be cut by
reconstruction organization. They are cutting in to pieces, the size
of cutting for their convenient to _____________.
a. Erect properly.
b. Transportable.
c. Drawing size.
d. They have to follow drawing for cutting.
111. What NDT shall be done for completed welds attaching nozzle
neck to shell and reinforcing plate to shell and to nozzle neck?
a. MT or PT.
b. Visual.
c. FMT and/or UT.
d. ‘a’ or ‘c’.
113. New welds attaching existing shell plate to existing or new shell
plate shall be examined by _______________.
a. UT
b. RT
c. MT
d. PT
114. New welding on the shell to bottom joint first weld pass shall be
inspected by applying ______________ to the side opposite the
first weld pass made. The oil shall be allowed to stand at least 4
hours and then the weld inspected for wicking action.
a. Light diesel oil.
b. Vegetable oil.
c. Inspection oil.
d. Light viscosity oil.
e. Any of the above.
115. After completion of shell to bottom inside and outside fillet or
partial penetration welds, the welds shall be tested by
pressurizing the volume between the inside and outside welds
with air pressure to _______ and applying a solution film to both
welds.
a. 25 psig.
b. 15 psig.
c. 50 psig.
d. 65 psig.
QB 3: CLOSED BOOK QB- ANSWERS-653-2009 OK
1. C 1.1.1 API653
2. A 1.1.1 API653
3. E 1.1.1. API653
4. B 1.1.2 API653
5. D 1.2 API653
6. D 1.3 API653
7. A 1.4 API653
8. B 3.1 API653
9. D 3.2 API653
10. C 3.3 API653
11. E 3.3 API653
12. A 3.5 API653
13. A 3.9 APl653
14. D 3.10 API653
15. A 3.24 API653
16. D 3.25 API653
17. D 4.2.1.2 API653
18. C 4.2.1.1 API653
19. B 4.2.2.1 API653
20. C 4.2.3.3 API653
21. B 4.2.3.4 API653
22. B 4.2.4.2 API653
23. D 4.2.4.1 API653
24. C 4.2.4.3 API653
25. A Table 4.3 API653
26. A 4.3.2.1b API653
27. B 4.3.2.1 b API653
28. B 4.3.2.lb API653
29. B 4.3.2.1b API653
30. B 4.3.2.1 c API653
31. A 4.3.2.la API653
32. C 4.3.2.2 API653
33. C 4.3.3.1 last API653
34. B 4.4.4 API653
35. A 4.4.4 API653
36. D 4.4.5.4 API653
37. D 4.4.5.7 API653
38. C 4.4.5.7 API653
39. B 4.4.7.4 & 4.4.6.1 API653
40. C 4.4.6.1 API653
41. A 4.5.1.2b API653
42. D 4.5.1.2e API653
43. A 5.2.2 API653
44. C 5.2.2 API653
45. A 5.3.5 API653
46. B 5.3.6 API653
47. C 5.3.6 API653
48. C 5.3.8 API653
49. A 6.2.2 API653
50. B 6.2.3 API653
51. D 6.3.1.1 API653
52. C 6.3.1.2 API653
53. A 6.3.1.3 API653
54. C 6.3.2 API653
55. B 6.3.2.1 API653
56. C 6.3.2.2 API653
57. C 6.3.3.1 API653
58. B 6.3.3.2b API653
59. A 6.3.3.2 API653
60. C 6.3.3.2 API653
61. C 6.3.1.2 API653
62. C 6.3.2.1 API653
63. A 6.3.3.2 API653
64. D 6.3.3.2 API653
65. D 6.3.3.3 API653
66. C 6.4.2. 2 API653
67. B 6.4.2. 2 API653
68. A 6.4.2.4 API653
69. A 6.4.1 1 a API653
70. A 6.4.2.1 API653
71. A 6.5 API653
72. A 7.2 API653
73. C 7.3.1. I API653
74. C 7.3.1.2 API653
75 . D 7.3.1.2 APl653
76. C 7.3.1.2 API653
77. C 8.2.2 API653
78. A 8.4.1 API653
79. B 8.4.4. API653
80. C 9.1.3 API653
81. B 9.1.3 API653
82. D 9.2.2.1 API653
83. D 9.2.2.1 API653
84. C 9.2.2.2 API653
85. B 9.2.2.2 API653
86. A FIG9. I note 1 API653
87. B 9.3.1.2 API653
88. C 9.3.1.4 API653
89. B 9.3.1.8 API653
90. C 9.6.2 API653
91. B 9.8.6 API653
92. C 9.8.6 a API653
93. A 9.10.1.1a API653
94. B 9.10.1.1c API653
95. B 9.10.1.1c APl653
96. C FIG 9.5 APl653
97. B 9.10.1.2.3 API653
98. C 9.11.2.1 API653
99. B 9.12.3 API653
100. B 9.13.1 APl653
101. A 9.14.1.2 API653
102. B 9.14.3.2 API653
FIG 9.10-Page no
103. B API653
9-20
104. C 10.1.4 API653
105. B 10.3.1 API653
106. B 10.4.2.3 API653
107. C 10.4.2.5 API653
108. D 10.4.2.7 API653
109. B 10.5.2 API653
110. C 11. 1.2 API653
111. C 12.1.2.3 APl653
112. B 12.1.2.4 API653
113. B 12.1.5.1 API653
114. A 12.1.6.1 API653
115. B 12.1.6.2 API653
QB : 4 API 653-2009
4. What is the joint efficiency of a lap riveted joint with one (1) row of
rivets?
a. 45%
b. 60%
c. 75%
d. 80%
5. All prior reported brittle fracture tank failures have occurred under
which of the following conditions/situations?
a. Atmospheric temperature of 20° F or lower.
b. During a hydro test where the test water was 50° F or colder.
c. Shortly after erection, following a repair / alteration, first cold
weather filling or change to lower temperature service.
d. Where a testing medium other than water was used.
6. When external UT “t” measurements are used to determine a rate
of general, uniform corrosion (relevant to shell integrity) which of the
following values cannot be exceeded?
a. 10 years maximum
b. 15 years maximum
c. 5 years (after commissioning), or at 15 year intervals (where
corrosion rate is not known).
d. Five years or RCA / 4N, whichever is more.
16. Calculate the minimum thickness for the first course based on
product alone.
a. 7/8”
b. 3/4”
c. 5/8”
d. 1/2”
17. Calculate the “L” length for an area of general corrosion found ten
feet from the bottom on the north side of the shell, t 2 = 0.125 inches.
a. 3.7”
b. 10”
c. 13.84’
d. 40”
18. There are four pits lined vertically on the south side of the tank in the
first course. The pits measure 1”, 1.250”, 1.” and .500” in length
along a vertical line 8” long. The pit depth is approximately 0.255”
each.
a. A repair is required.
b. Because of the vertical pits, no repair is required.
c. If the pit depth is only .130 inches the pits may be ignored.
d. Scattered pits may be ignored.
19. A bulge is found on the tank floor, the diameter of the bulge is 30
inches, what is the maximum permissible height for the bulge?
a. 11.1”
b. .463”
c. .962”
d. 1.11”
20. An area of edge settlement in the tank bottom 6 feet from the tank
shell has sloped down and settled. The settlement measures 2 inches
at the deepest point. The edge settlement area has bottom lap welds
approximately parallel to the shell.
a. A more rigorous stress analysis must be performed.
b. The area must be repaired.
c. Sloped edge settlement is usually no problem.
d. The area should be documented and checked during the next
inspection.
QB : 4 API 653-2009
ANSWERS
t min = 11,356.8
23,600
12 = 1.25 feet.
B = .37R
B = .37 (1.25) B = .463 inches
20. D The area should be documented and checked during the next
inspection. Figure B-11
Using figure B-11 the area is acceptable, it should be documented.
QB 5: API 653-2009
5. According to API 653, a full hydrostatic test, held for 24 hours, shall
be performed on:
a. A new tank
b. An in-service tank
c. A reconstructed tank
d. An out-of-service tank
8. The minimum thickness of new roof plates shall be … inch, plus any
corrosion allowances, as specified in the repair specification.
a. ½
7
b. 8
3
c. 16
d. ⅜
9. Which type of tank settlement will rotate the tank in a tilted plane?
a. Uniform settlement
b. Rigid body
c. Out-of-plane settlement
d. Differential settlement
11. … settlement occurs when the tank shell settles sharply around the
periphery, resulting in deformation of the bottom plate.
a. Uniform
b. Edge
c. Out-of-Plane
d. Rigid Body Tilting
12. The corrosion rate for an AST is External 5 mils per year. Based on
API 653 requirements when should the next inspection be
scheduled?
Note: Remaining Corrosion Allowance is 0.17 inches.
a. 17 years
b. 15 years
c. 20 years
d. 5 years
13. The design thickness of a reconstructed tank is based on …
a. Original shell thickness
b. Measurements taken within 180 days prior to relocation
c. Measurements taken when the tank was removed from service
d. New product loads
19. Minimum thickness for tank bottom plate, when there is no means
of leak detection and containment, is ... inch.
a. 0.10
b. 0.075
c. 0.15
d. 0.05
QB 5: API 653-2009
ANSWERS
OPEN BOOK
3. Calculate the “L” length for an area of general corrosion found 10’
from the bottom on the south side of the shell, T2=0.125”.
a. 40”
b. 12.68”
c. 6.80”
d. 11.75”
4. There are three pits aligned vertically on the north side of the tank,
in the first course. The diameters of the pits are 1.250”, 1”, and
0.500” in length along a vertical line 8” long.
Note: Assume pit depth of slightly less one-half of the minimum
acceptable tank shell thickness, exclusive of the corrosion
allowance.
a. Because the pits are aligned vertically no repair is required
b. Scattered pits may be ignored
c. If the pit is round, it may be ignored
d. A repair is required
5. Three circumferentially scattered pits are located on the west side
of the tank 18” from the bottom. The pits measured 0.500 “, 0.477”
and 0.732” in diameter.
Note: Assume pit depth of slightly less one-half of the minimum
acceptable tank shell thickness, exclusive of the corrosion
allowance.
a. Because the pits are scattered circumferentially, no repair is
required
b. All pits may be ignored
c. If the pit is round, it may be ignored
d. A repair is required
6. A bulge is found on the tank floor, the diameter of the bulge is 30”.
What is the maximum permissible height for the bulge?
a. 11.1”
b. 0.4625”
c. 0.962”
d. 1.11”
7. An area of the tank bottom 6’ from the shell has sloped down and
settled. The settlement measures 2” at the deepest point.
a. A more rigorous stress analysis must be performed
b. The area should be repaired
c. Sloped edge settlement is usually no problem
d. The area should be documented and checked during the next
inspection
CLOSED BOOK
11. Per API 653, tanks shall have a formal visual inspection once every
… years or at the quarter corrosion-rate life of the shell, whichever
is less.
a. Three
b. Four
c. Five
d. Seven
13. In accordance with API Standard 653, Repairs and Alteration have
been defined as distinct activities. State which of the following
activities does not constitute an Alteration?
a. The addition of man-ways and nozzles greater than NPS 12
b. Increase and decrease in tank shell height
c. Replacement of damaged flange on nozzle by flange of same
size and material
d. All of the above
14. In accordance with API Standard 653, Repairs and Alteration have
been defined as distinct activities. Activity, which entails any work
necessary to maintain or restore a tank to a condition suitable for
safe operation. State which of the following activities does not
constitute repair?
a. Re-leveling and/or jacking of a tank shell, bottom or roof
b. Addition of reinforcing plate/s to existing shell penetration/s
c. Changing the content with higher specific gravity
d. Repair of flaws, such as tears or gouges, by grinding followed by
welding
15. In accordance with API Standard 653, Critical Zone for repairs to a
tank bottom is that portion which is:
a. Measured vertically upwards along shell, within 6” of tank
bottom
b. Measured radially inward, within 3” of the inside edge of shell
c. Measured radially outward within 1 ½” of outside edge of shell
d. A circular area measurable radially within 12” from center of tank
bottom
16. Normally the corrosion rates of the tank bottom control the
inspection interval, which are based on the actual or anticipated
rates of corrosion. In the case of a tank, where corrosion rates are
not known, and where similar service experience is not available,
the actual thickness of the bottom is to be determined by due
inspections within by RBI
a. 20 years
b. 5 years
c. 10 years
d. 25 years
18. As per API Standard 653, a routine, in service, close visual external
inspection of an aboveground storage tank (AST) shall be done, at
an interval not exceeding:
a. One year
b. Five years
c. One month
d. d. Ten years
19. As AST has a measured shell thickness of 0.75”; and its minimum
required thickness is 0.5”. The known rate of corrosion of shell is 5
mils per year. As per API Standard 653, when should the external
visual inspection by an Authorized Inspector be carried out at an
interval not exceeding?
a. One year
b. Five years
c. Twelve and half years
d. Ten years
20. An AST has a measured shell thickness of 0.75; and its minimum
required thickness is 0.5”. The rate of corrosion of shell is not
known. As per API Standard 653, the external ultrasonic thickness
measurement shall be carried out an interval not exceeding:
a. One year
b. Five years
c. Six & half years
d. Ten years
21. An AST has a measured shell thickness of 0.75”; and its minimum
required thickness is 0.5”. The known rate of corrosion of shell is 5
mils per year. As per API Standard 653, the external ultrasonic
thickness measurement shall be carried out at an interval not
exceeding:
a. One year
b. Twenty-five years
c. Fifteen years
d. Ten years
26. For all repairs and alterations under API 653, the ultimate
responsibility rests with:
a. Owner-operator
b. API Committee
c. API 653 Inspector
d. Jurisdiction Authority
Answers
Q.NO. ANS REF
1 b 4.3.3.1
2 d 4.3.3.1
3 b 4.3.2.1 (b)
4 a 4.3.2.2
5 a 4.3.2.2
6 b B 3.3
7 d B 3.3
8 c 4.3.3.1
9 a B 3.3
10 b 4.3.3.1
11 b 6.3.21
12 b 6.3.1.1
13 C API 653, 3.1 & 3.24
14 C API 653, 3.1 & 3.24
15 B API 653, 3.10
16 D API 653, 6.4.2.2
17 B API 653, Fig. 5-2 & 5.3.5& 5.3.6
18 C API 653, 6.3.1.2
19 B API 653, 6.3.2.1
20 B API 653, 6.3.3.2 (a)
21 C API 653, 6.3.3.2 (b)
22 D API 653, 4.4.3.3 & 4.4.4 GK
23 A API 653, 4.3.6
24 D API 650, 573.4
25 D API 653, 3.3
26 A API 653, 1.2
27 D API 653, GK, 6.4.2.1
28 B API 653, 3.18
29 A API 653, 3.24
30 A API 653, 6.5
The total length of arrow line drawn is 8 inches. The length of the line
in each of the corroded areas A, B and C are 1.5”, 0.3” and 0.2”
respectively. Comment on the acceptability of the corroded
condition.
a. Acceptable
b. Not acceptable
c. Conduct a patch plate repair
d. The pitting can be ignored as a case of widely scattered pitting
2. A tank is constructed as per API 650. Its original thickness is 0.500
inch. Its diameter is 25 feet and height is 15 feet. After 10 years, the
tank is inspected and the following readings are recorded on the
shell. Figure 2 exhibits a corroded portion of the developed shell of
the tank from the inside. The designed corrosion allowance is 0.125”.
Minimum thickness (t2) is among the following readings.
6. Find the value of the allowable stress in the first shell course of the
conditions of the tank considered in above question if material is not
known.
a. 4680 psi
b. 23600 psi
c. 2550 psi
d. 30000 psi
13. The Liquid Height in tank is 50 feet. . If the Liquid height is decreased
by 10 feet, How much % change in the Minimum acceptable thk for the
given portion of the shell will occur ( 40/50= 80 % ie -20%)
a) 50 %
b) -20%
c) 25%
d) – 25 %
a) + 50%
b) + 80 %
c) + 67 %
d) – 40 %
QB 7: API 653-2009
In the example,
ANSWER: A
Q3. L = 3 .7√ Dt
2 = 3.7 √ 25 x 0.275 = 9.7
ANSWER: A
Q10. ANSWER: B
Q11. ANSWER: B
Q12. ANSWER: B
Q 13 ) C
Q14) D
QB 7: (API 653-2009