HFY3-3720-STR-ITP-0001 - 1 Steel Structure Inspection and Test Plan-Code A
HFY3-3720-STR-ITP-0001 - 1 Steel Structure Inspection and Test Plan-Code A
Code A Approved.
Any comments made do not relieve the contractor/ vendor and/ or their
sub-<:ontractors of their responsibilities to meet the requirements of the
Contract.
PROVISION OF EPCC FOR
WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
CONTENTS
SYMBOL DEFINITION……………………………………………………….3
2
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK : STEEL STRUCTURE SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
“H” - HOLD: A point the subsequent activities of which can not proceed unless a formal prior notification by inspectorate
concerned has been received.
“W” - WITNESS: A point the subsequent activities of which can be proceed if no prior notification by inspectorate has been received.
"S" - SURVEILLANCE: A point the activities of which and related documents can be inspected randomly by CPECC and persons concerned
without prior notification.
“R” - REVIEW: The documents shall be submitted to persons concerned and only after these documents have been reviewed and
approved by CPECC or PMC, the relevant activities can proceed.
REMARKS:
3
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
1. Manufacturer
1.6 Ensure fire-proofing material is stored 1.Checklist 3-8-1
instruction W W
in good condition as per approved SP. 2.Checklist 3-8-1-2
2. Approved drawings
2 Approval of
WPS & PQR Check have approved WPS & PQR 1.HFY-GEN-CIV-SPC-0008 Approved WPS & PQR W W
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R-Review C-Certification
4
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R-Review C-Certification
5
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
6
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
7
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
8
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
9
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
10
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
11
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
12
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
13
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
14
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
15
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
10.5 Twist:
The twist between any two elevations
1.HFY-GEN-CIV-SPC-0014 1. Checklist 3-8-2
shall not exceed 0.5 degrees in 3 m. The W W
2.ASCE-10 2. FORM-SS-06
maximum twist over the structure height
shall not exceed 5 degrees.
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
16
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DISCIPLINE:
STEEL STRUCTURE DESCRIPTION OF WORK: STEEL STRUCTURAL SITE INSPECTION & TEST PLAN HFY3-3720-STR-ITP-0001
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review C-Certification
17
Inspection Check List
18
Crane girder & rail:
Crane girders assembled and erected as per specifications and □Yes □No □N/A
10 approved drawings.
For crane rail, recommendations of crane manufacturer shall be Comments:
followed:
Platforms, handrails & ladders: □Yes □No □N/A
11 Platforms, handrails and ladders assembled and erected as per
specifications and approved drawings. Comments:
Deviation in Plumbness & Alignment: □Yes □No
12 The deviation in column plumb, beams ends
Comments:
Sun shades: □Yes □No □N/A
13 Sun shade erected as specified in the approved drawings.
Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
19
Inspection Check List for Shop Prefabricaton
Element Acceptance
Document # : HFY-Checklist-3-8-1-1
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008, HFY-GEN-CP-SPC-0001
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure the material used by vender is as per the approved □Yes □No
1 material specification. Comments:
Check erection drawing and erection marking system of shop □Yes □No
4 prefabricated elements by vender, which are as per approved SP
and approved drawings. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
20
Inspection Check List for Material on Site
Document # : HFY-Checklist-3-8-1-2
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008, HFY-GEN-CP-SPC-0001
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure the material received on site is approved by PMC and □Yes □No
1 without any damage. Comments:
Ensure high strength bolts (HSB), nuts and washers are stored in
good condition and without any damage. The faster components □Yes □No
2 shall be protected from dirt and moisture in closed containers at Comments:
the site of installation.
□Yes □No
Check torque values of HSB received on site, which should
3 conform to approved SP.
Comments:
Ensure fire proofing material is stored good condition as per □Yes □No
4 approved SP. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
21
Inspection Check List for Prefabricated
Components on Site
Document # : HFY-Checklist-3-8-1-3
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008, HFY-GEN-CP-SPC-0001
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure material correction conforms to the requirements as per □Yes □No
1 approved SP and approved drawings. Comments:
Ensure marking-off conforms to the requirements as per approved □Yes □No □N/A
2 SP and approved drawings. Comments:
The thermal cutting of structural steel by hand-guided or □Yes □No
3 mechanically guided mean is permitted. Ensure cutting conforms
to the requirements as per approved SP and approved drawings. Comments:
Ensure holes conform to the requirements as per approved SP □Yes □No □N/A
4 and approved drawings. Comments:
Ensure tolerances of prefabricated components on site are as per
approved SP and approved drawings. For members that are
equal to or less than 9m, the variation of length should be less □Yes □No
5 than 2mm; For members that are more than 9m, the variation
should be less than 3mm. The variation in straightness shall be Comments:
equal to or less than 1/1000 of the axial length between point that
are to be laterally supported.
Ensure erection marking system of prefabricated components on □Yes □No □N/A
6 site is as per approved SP and approved drawings. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
22
Inspection Check List for Foundation Acceptance
Document # : HFY-Checklist-3-8-1-4
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure all civil QC records related to the structure foundation are signed off □Yes □No
1 by CONTRACTOR/PMC. Comments:
Perform a visual inspection to ensure the foundation without any □Yes □No
2 damage. Comments:
Ensure diameter of anchor bolts embedded conforms to the □Yes □No □N/A
3 requirement of approved drawings. Comments:
Ensure the cross center line and datum lines are marked on the □Yes □No □N/A
4 foundation. Comments:
Ensure tolerances of foundation center point from longitudinal and transverse
axial center line conforms to the requirement of approved drawings. The □Yes □No □N/A
5 variation in dimension from center of any anchor bolt group to column line Comments:
shall be equal to or less than 6mm.
Ensure center to center distance of anchor bolts embedded conforms to the □Yes □No □N/A
6 requirement of approved drawings. The variation in dimension between the
Comments:
center of anchor bolt shall be equal to or less than 3mm.
Ensure top elevation of foundation, not including second grouting layer, □Yes □No
7 conforms to the requirement of approved drawings. Comments:
Ensure elevation of top of anchor rods conforms to the requirement of □Yes □No □N/A
8 approved drawings. The variation in elevation of the top of anchor bolt shall
Comments:
be equal to or less than plus or minus 13mm.
Ensure elevation and level of bearing plates conform to the requirement of □Yes □No
9 approved drawings. Comments:
□Yes □No
10 Ensure surface of foundation is cleared out.
Comments:
□Yes □No
11 The foundation is released for steel work erection and assembly.
Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
23
Inspection Check List for Field Erection and
Assembly for Steel Structure
Document # : HFY-Checklist-3-8-1-5
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008, HFY-GEN-CP-SPC-0001
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure the elevation tolerances of column bases are as per approved SP □Yes □No
1 and approved drawings. The variation of elevation of column bases is equal
Comments:
to or less than plus 5mm and minus 8mm.
□Yes □No
Ensure tolerances of column base from center line conforms to the
2 requirement of approved SP. The maximum variation is 6mm.
Comments:
Ensure the angular variation of working line of column from a plumb line is □Yes □No
3 equal to or less than 1/500 between work point. Comments:
Ensure deviation of the beam ends elevation shall be equal to or less than □Yes □No
4 plus 5mm and minus 8mm. Comments:
Ensure all anchor bolts are tightened correctly after columns have been □Yes □No □N/A
5 positioned, plumbed and inspected. Comments:
Ensure horizontal and vertical bracing erected and assembled are as per □Yes □No □N/A
6 approved SP and approved drawings. Comments:
Ensure trusses erected and assembled are as per approved SP and □Yes □No □N/A
7 approved drawings. Comments:
Ensure crane girders erected and assembled are as per approved SP and □Yes □No □N/A
8 approved drawings. Comments:
Ensure platforms, stairways and ladders erected and assembled are as per □Yes □No □N/A
9 approved SP and approved drawings. Comments:
Ensure all temporary supports and bracing are removed after permanent □Yes □No
10 members and connections have been completed and inspected. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
24
Inspection Check List for Field Connecting of Steel
Structure
Document # : HFY-Checklist-3-8-1-6
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0008
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure field connections with high strength bolts or common bolts □Yes □No □N/A
1 are as per approved SP and approved drawings. Comments:
□Yes □No □N/A
2 Ensure the bolts tightened from the center outwards one by one.
Comments:
Ensure enlarging or cutting of blot holes for correcting fabricating □Yes □No □N/A
3 errors is as per approved SP. Comments:
Ensure the inertial coefficient of friction of high strength bolt (HSB) □Yes □No □N/A
4 is retested as per approved SP. Comments:
Ensure temporary bolts are used for temporary connection and □Yes □No □N/A
5 replaced to permanent bolts only after correction of deviation to
the steelwork has been made. Comments:
Ensure the torque value of torque wrench, which is adjusted □Yes □No □N/A
6 before daily work, conforms to approved SP. Comments:
Ensure final bolt tightening is made only after checking the □Yes □No □N/A
7 accuracy of the assembled frames. Comments:
Ensure final tightening torques of high strength bolts are □Yes □No □N/A
8 rechecked as per approved SP. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
25
Inspection Check List for Foundation Grouting
Document # : HFY-Checklist-3-8-1-7
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0014
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Ensure erection and assembly of columns and first story beams, □Yes □No
1 including horizontal and vertical bracing with them have been
completed and accepted. Comments:
Ensure foundation grouting area has been cleaned out as per □Yes □No
2 approved SP. Comments:
Check the structure steel column basement to ensure all □Yes □No
3 requirements are met as per the approved drawing and
specification. Comments:
Ensure grouting concrete grade conforms as approved civil
drawings. Dry pack mortar shall be used under column base, □Yes □No
machinery with base less than 0.25m2. No shrink, no ferrous, no-
4 chloride Portland cement, self-leveling grout shall be used under
vessels. Epoxy grouts shall be used when the grout is exposed to Comments:
chemical attack, high vibration.
The surface of concrete to receive cementitious grout shall be □Yes □No
5 wetted thoroughly. The surface of concrete to receive epoxy grout
shall be completely dry. Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
26
Inspection Check List for OHTL Steel Tower
Document # : HFY-Checklist-3-8-2
Report #: PRID #: Project Name: Contractor:
RFI #:
Inspection Date:
Dwg #: Location:
Spec References: HFY-GEN-CIV-SPC-0014
Inspector’s Checklist
Inspector’s Observation
Sr # Description of Activity
(Record the Data)
Check the imported material and pre-fabricated elements all as □Yes □No
1 per approved drawing, approved MR, meet the specifications and
without damages. Comments:
The horizontal distance between the vertical centerlines at any 2 □Yes □No
7 elevations shall not exceed 0.25% of the vertical distance between
the 2 elevations. Comments:
The twist between any two elevations shall not exceed 0.5 degrees in □Yes □No
8 3 m. The maximum twist over the structure height shall not exceed 5
degrees. Comments:
The slip splice length tolerance shall not exceed 10% of the design □Yes □No
9 slip splice length. Splices shall be pulled together to ensure firm
contact. Comments:
The straightness of the individual members shall be within tolerance □Yes □No
10 1 in 500 but not more than 1.6mm of the length between points that
are laterally supported. Comments:
27
Ensure that bolt holes shall be made by drilling/punching. □Yes □No
11 Holes by burning/flame cutting are not permitted.
Comments:
Any cut member shall be dressed and have smooth edge shall be re- □Yes □No □N/A
12 galvanized or re-painted.
Comments:
□Yes □No
13 Size and quantity of structural parts shall conform to design.
Comments:
□Yes □No □N/A
14 Ensure that anti-climbing device, bird-guards are installed.
Comments:
Note: Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer’s recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
28
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
±13 ±3 ±5 0 ~ -20 ±3 ≤2
±13 ±3 ±5 0 ~ -20 ±3 ≤2
±13 ±3 ±5 0 ~ -20 ±3 ≤2
±13 ±3 ±5 0 ~ -20 ±3 ≤2
±13 ±3 ±5 0 ~ -20 ±3 ≤2
±13 ±3 ±5 0 ~ -20 ±3 ≤2
SYMBOLS: T.O.F-----Top of anchor bolt; T.O.F-------Top of foundation, not including second grouting layer C.P.O.F-----Centre point of foundation
CONTRACTOR PMC
Name
Signature
Date
29
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
PROCEDURE: DATE:
DESCRIPTION:
Irregularity of C.B from C.L Column plumb
Elevation of B.O.C.B
Transverse Longitudinal Transverse (D) Longitudinal (D)
COLUMN NO. Height RESULT
Deviation Maximum Deviation Maximum Deviation Maximum Deviation Maximum Deviation Maximum
Tolerance Deviation Tolerance Deviation Tolerance Deviation (mm) Tolerance Deviation Tolerance Deviation
(mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm)
±2 ≤ 6 ≤ 6
±2 ≤ 6 ≤ 6
±2 ≤ 6 ≤ 6
±2 ≤ 6 ≤ 6
±2 ≤ 6 ≤ 6
SYMBOLS: B.O.C.B-----Bottom of column base; C.B-----Column base; C.L-----Center line
NOTE: 1. When H≤4m ,then D≤8mm; 2.When H>4m , then D≤H/500 and D≤50mm.
CONTRACTOR PMC
Name
Signature
Date
30
PROVISION OF EPCC FOR
WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
PROCEDURE: DATE:
DESCRIPTION:
Beam
Difference of height between two ends of the first story beam
NO. Deviation Tolerance Maximum Deviation
Height of beam (mm) RESULT
"B"(mm) "B"(mm)
+5
-8
+5
-8
+5
-8
+5
-8
+5
-8
+5
-8
+5
-8
+5
-8
+5
-8
Schematics
CONTRACTOR PMC
Name
Signature
Date
31
PROVISION OF EPCC FOR
WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
DESCRIPTION:
Qty of
Assemble Recheck of
Structure Bolt Quantity Bolt Dia. Enlarged
Torque Final Torque
Node No. Specification ( Pcs ) (mm) Holes
( N•m ) ( N•m )
( Pcs )
Note: (1) The assemble torque value: 0.32kN•m for M16, 0.63kN•m for M20, 1.098kN•m for M24.
(2) Spot-check 10 percent of structure nodes, no less than 10 nodes, and spot-check 10
percent bolts for one node, no less than 2 bolts.
CONTRACTOR PMC
Name
Signature
Date
32
PROVISION OF EPCC FOR
WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
PROCEDURE: DATE:
DESCRIPTION:
Contents:
1. Check the bearing plates (wedge and shim) are correctly placed within specified
tolerance.
2. Check the bearing plates (wedge and shim) are firmly fixed.
3. Ensure all the bearing plates are tack welded.
check contents and schematics
Schematics:
Inspection Result
Name
Signature
Date
33
PROVISION OF EPCC FOR WATER INJECTION BOOSTING STATION UPGRADE
STEEL STRUCTURE INSPECTION AND TEST PLAN
PROCEDURE: DATE:
DESCRIPTION:
Overall Height Plumb Twist Slip Splice Straightness
STEEL Over
Any Two
TOWER Maximum Deviation Maximum Maximum Structure Maximum Deviation Maximum Deviation Maximum RESULT
Elevations
Deviation Tolerance (m) Deviation Tolerance Deviation Deviation Height Deviation Tolerance Deviation Tolerance Deviation
NO. Tolerance
(m) (mm) (mm) (mm) Tolerance (mm) (mm) (mm) (mm) (mm)
(mm)
(mm)
SYMBOLS: H-----Overall height of an assembled structure; h-----vertical distance between two elevations; L-----length between points that are laterally supported; l-----
the design slip splice length.
CONTRACTOR PMC
Name
Signature
Date
34