Professional Documents
Culture Documents
Lecture 8 Scheduling
Lecture 8 Scheduling
Chapter 8 – part 4
Outline
▪ PERT
8-2
PERT
■ Project Evaluation and Review Technique (PERT)
■ Task time durations are treated as uncertain
■ A - optimistic time estimate
■ minimum time in which the task could be completed
■ everything has to go right
■ M - most likely task duration
■ task duration under “normal” working conditions
■ most frequent task duration based on past experience
■ B - pessimistic time estimate
■ time required under particularly “bad” circumstances
■ most difficult to estimate, includes unexpected delays
■ should be exceeded no more than 1% of the time
Discussion
times
Time A
Assume a Beta-distribution
Time M
Time B
Beta - distribution
Expected Time & Variance
▪ Early Finish (EF) and Late Finish (LF) computed as for CPM with TE
Example: Solving the Network
8-9
The AON Network from the previous table
8-10
Calculating Activity Times
8-11
The Results
8-12
Critical Path and Time
8-13
Critical Path and Time Continued
8-14
Slack
8-15
Slack Values
8-16
Precedence Diagramming Restrictions
▪ Finish to start: FS
▪ Start to start: SS
▪ Finish to finish: FF
▪ Start to finish: SF
8-17
Precedence Diagramming Conventions
8-18
Microsoft Project
8-19
Gantt Chart
8-20
Activity on Node (AON) Network
8-21
Microsoft Project Calendar
8-22