Sl.no Kind of application Timeline Remarks Total days for Plan
approval 1. Uploading drawings 15 days through online 2. AAI and Fire & Rescue 30 days Parallel activity department NOC 3. DTCP/LPA & District 45 days Collector NOC 15 days + 45 days + 30 4. Forward and obtain 30 days days + 15 days = 90 days approval from Chennai DTCP 5. Getting final approval 15 days Final statutory approval from Coimbatore DTCP payment to be made and on return from approval copy will be issued. Chennai DTCP 6. Constant to 45 days After Getting DTCP approval establishment (CTE) 7. Approval from 45 days After getting an order from 90 days + 45 days = 135 Coimbatore LPA. DTCP approved days Corporation drawing once again to be uploaded through smart DCR. Grace Period 15 days Total number of Days for plan approval 150 days