Timeline for getting Plan Approval

Sl.no Kind of application Timeline Remarks Total days for Plan


approval
1. Uploading drawings 15 days
through online
2. AAI and Fire & Rescue 30 days Parallel activity
department NOC
3. DTCP/LPA & District 45 days
Collector NOC
15 days + 45 days + 30
4. Forward and obtain 30 days
days + 15 days = 90 days
approval from Chennai
DTCP
5. Getting final approval 15 days Final statutory approval
from Coimbatore DTCP payment to be made and
on return from approval copy will be issued.
Chennai DTCP
6. Constant to 45 days After Getting DTCP approval
establishment (CTE)
7. Approval from 45 days After getting an order from
90 days + 45 days = 135
Coimbatore LPA. DTCP approved
days
Corporation drawing once again to be
uploaded through smart
DCR.
Grace Period 15 days
Total number of Days for plan approval 150 days