Professional Documents
Culture Documents
A. SATATUTORY ACTIVITIES
SL No DESCRIPTION TIMELINE REMARKS
10 Apply for labour license & BOCW permission (After receipt of FORM-III) 02 days
2 Intimation by mail by TGS to all vendors for procurement of material 03 days After Seggregation
3 Rates to be taken from Vendors 04 days After Enquiry
After finalisation of rates
4 PO to be placed by subcontractor 7 days & vendors
Incase PO is not placed by subcontractor TGS would place the PO with After finalisation of rates
5 intimation to Sub contractor 10 Days & vendors
Material QAP/Data sheet to be obtained from competent vendor and After finalisation of rates
6 to be submitted to Client by TGS 7 days & vendors
After QAP approval, advance to be released by sub-contractor to
7 supplier 7 days After QAP Approval
A Machinery
1 Hydra (8 – 10 MT) Nos 2 10 days from date of FOA
2 D.G. Sets : (inclusive of generators) 62.5 KVA to 200 KVA Nos 1 10 days from date of FOA
3 Air Compressor (300CFM) Nos 1 10 days from date of FOA
4 Excavator Nos 1 10 days from date of FOA
5 HDD Rig with All Equipments & Accessories (Cap. 32 T TO 150 T) Nos 1 As per site requirement
6 Pressurization Pump – Motorized 150 kg/cm2 Nos 1 As per site requirement
7 Pressurization Pump – Manual 100 Kg/Cm2 Nos 1 As per site requirement
8 Filling Pumps (400 TO 1000 M3/HR) Nos 1 10 days from date of FOA
9 Tractor with trolley Nos 1 10 days from date of FOA
10 Dewatering Pump Nos 1
B Welding Tools
1 Vehicle For Staff & Worker Nos 3 10 days from date of FOA
2 Tripod with 5 Tons Chain Pulley Block Nos 2 10 days from date of FOA
3 Choker Belt 5 mtr x10 ton Nos 3 10 days from date of FOA
4 Choker Belt 2 mtr x 5 ton Nos 3 10 days from date of FOA
5 Wire Rope(cilling) 16 MM Mtr 6.5 10 days from date of FOA
6 U Clamp Nos 5 10 days from date of FOA
7 D Cycle 3, 5 & 10 TON Nos Each 3 10 days from date of FOA
8 External Clamp As Per Pipe DIA Nos 1 10 days from date of FOA
9 Hydrolic Jack 5 Ton & 10 Ton Nos Each 1 10 days from date of FOA
10 Welding Machines 400 AMPS Nos 1 10 days from date of FOA
11 Grinding machine AG-5 Nos 1 10 days from date of FOA
12 Grinding machine AG-7 Nos 1 10 days from date of FOA
13 Grinding Wheel AG-7 Nos 100 10 days from date of FOA
14 Grinding Wheel AG-5 Nos 20 10 days from date of FOA
15 Cutting Wheel AG-7 Nos 50 10 days from date of FOA
16 Cutting Wheel AG-5 Nos 20 10 days from date of FOA
17 Grinding machine Cable Mtr 100 10 days from date of FOA
18 Welding Helmet Nos 1 10 days from date of FOA
19 Welding White Glass Nos 300 10 days from date of FOA
20 Welding Black Glass Nos 50 10 days from date of FOA
21 Grinding Helmet Nos 5 10 days from date of FOA
22 Leather Hand Gloves Pair 10 10 days from date of FOA
23 Hand Sleeve Pair 10 10 days from date of FOA
24 Welding Holder 1000 AMP Nos 5 10 days from date of FOA
25 Short Cable Mtr 30 10 days from date of FOA
26 Welding Cable Mtr 50 10 days from date of FOA
27 Cable Lock Nos 20 10 days from date of FOA
28 Halogen Lamp Set 500W Nos 2 10 days from date of FOA
29 Halogen Tube 500W Nos 10 10 days from date of FOA
30 Lamp 100W Nos 2 10 days from date of FOA
31 Safety Helmet Nos 20 10 days from date of FOA
32 Safety Shoes Nos 20 10 days from date of FOA
33 Safety Leg Guards Nos 20 10 days from date of FOA
34 Safety Apron Nos 20 10 days from date of FOA
35 Tool Box Nos 1 10 days from date of FOA
36 Measuring Tape 5MTR, 50MTR, 100MTR Nos EACH 1 10 days from date of FOA
37 Adjustable Wrinch 50MM Nos 1 10 days from date of FOA
38 Cutting Player Nos 1 10 days from date of FOA
39 Screw Driver Nos 1 10 days from date of FOA
40 Parmanent Marker Pkt 1 10 days from date of FOA
41 Yellow Cholk Pkt 2 10 days from date of FOA
42 Garden Umbrella Nos 1 10 days from date of FOA
43 Spanner Set Box 1 10 days from date of FOA
44 Allen Key Set Box 1 10 days from date of FOA
45 PVC Tape Nos 10 10 days from date of FOA
46 Teflon Tape Nos 20 10 days from date of FOA
47 MS Hammer 1kg & 2 Kg Nos Each 1 10 days from date of FOA
48 Wire Brush Nos 5 10 days from date of FOA
49 PVC Rope 12MM Roll 1 10 days from date of FOA
50 Welding Hood Nos 2 10 days from date of FOA
51 Wooden Set 1.5 mtr x 6inch Nos 50 10 days from date of FOA
52 Lifting Hook Nos 5 10 days from date of FOA
53 Electrical Tools Box 1 10 days from date of FOA
54 Industrial LPG Cylinder Nos 3 10 days from date of FOA
55 LPG Regulator Nos 3 10 days from date of FOA
56 L PG Torch Nos 2 10 days from date of FOA
57 LPG Hose Pipe Mtr 50 10 days from date of FOA
58 Sand Blasting Nosel Nos 2 10 days from date of FOA
59 Mobile Sand blasting equipment Nos 1 10 days from date of FOA
60 Hopper for Sand blasting Nos 1 10 days from date of FOA
61 Ring Clamp 2 inch Nos 10 10 days from date of FOA
62 Hose Pipe 2 inch Mtr 30 10 days from date of FOA
63 Nose Mask Nos 50 10 days from date of FOA
64 White Goggles Nos 20 10 days from date of FOA
65 Black Goggles Nos 20 10 days from date of FOA
66 Brass Hammer 1 Kg Nos 1 10 days from date of FOA
67 Wranning Tape 100 MTR Nos 10 10 days from date of FOA
68 Canvas Tarpaulin 18"X36" Nos 2 10 days from date of FOA
69 Right Angle Nos 1 10 days from date of FOA
70 Speed Level Tool Nos 1 10 days from date of FOA
71 File Nos 1 10 days from date of FOA
72 Blasting Helmet Nos 2 10 days from date of FOA
C Instruments
1 Holiday Detector Unit Nos 1 10 days from date of FOA
2 Portable Peel Gauge testers Nos 1 10 days from date of FOA
3 Coating Thickness Gauge Nos 1 10 days from date of FOA
4 Peel Test Kit Set 1 10 days from date of FOA
5 Wet Film Thickness Gauge Nos 1 10 days from date of FOA
6 Press-o-Film Box 5 10 days from date of FOA
7 Coat Meter Nos 1 10 days from date of FOA
8 Temparature Gun Nos 1 10 days from date of FOA
9 Weld Gauge Nos 1 10 days from date of FOA
10 Micro Meter Nos 1 10 days from date of FOA
11 Magnifying Glass Nos 1 10 days from date of FOA
12 Multi Meter Nos 1 10 days from date of FOA
13 Filler Gauge Nos 1 10 days from date of FOA
14 Clamp Meter Nos 1 10 days from date of FOA
15 Pressure Gauge 0-100 Kg/Cm2 Nos 4 10 days from date of FOA
D Consumable Materials
1 Perp-60 Roll 1 15 days from date of FOA
2 Perp-80 Roll 1 15 days from date of FOA
3 Applicator Pads Nos 200 15 days from date of FOA
4 Epoxy Hand Pump Nos 2 15 days from date of FOA
5 Mixing sticks, cups etc Nos 200 15 days from date of FOA
6 Rubber Hand Gloves Pair 2 15 days from date of FOA
7 Silicon Hand Roller (curved) Nos 2 15 days from date of FOA
8 Silicon Hand Roller (Straight) Nos 2 15 days from date of FOA
9 Copper Slag/Sand Ton 10 15 days from date of FOA
10 Normal Coating Sleeve As Per Requirement Nos 200 15 days from date of FOA
11 Dirax Coating Sleeve As Per Requirement Nos 100 15 days from date of FOA
12 Epoxy Part-A Drum 1 15 days from date of FOA
13 Epoxy Part-B Drum 1 15 days from date of FOA
14 LR Bends As Per Contract - As per SOR 25 days from date of FOA
15 Fittings & Flanges As Per Contract - As per SOR 25 days from date of FOA
16 HDPE Duct As Per Contract - As per SOR 25 days from date of FOA
17 OFC As Per Contract - As per SOR 25 days from date of FOA
18 Electrode As Per Contract - As per SOR 25 days from date of FOA
19 Casing & Conduit As Per Contract - As per SOR 25 days from date of FOA
20 Valves As Per Contract - As per SOR 25 days from date of FOA
21 Warnning Mat As Per Contract - As per SOR 25 days from date of FOA
Annexure-II (for pipeline)
MINIMUM NUMBER OF MANPOWER LIST FOR 4''/6''/8'' X 5KM STEEL PIPELINE ( 1 SECTION)
SL NO. DESCRIPTION QUALIFICATION & EXPERIENCE UOM QTY Timeline REMARKS
1 Construction Manager / Section In-charge B. Tech (Mech) & 7-10 Yr Nos 1 10 days from date of FOA
2 Planning engineer B. Tech (Mech) & 2-3 Yr Nos 1 10 days from date of FOA
3 QA/ QC engineer B. Tech (Mech), ASNT L-II & 3-5 Yr Nos 1 10 days from date of FOA
4 Safety officer Diploma in HSE & 2-3 Yr Nos 1 10 days from date of FOA
5 Account Officer B.Com Nos 1 10 days from date of FOA
6 Qualified Surveyor Diploma in Civil Nos 1 10 days from date of FOA
7 Welding/ NDT engineer Diploma in Mech, ASNT L-II & 2-3 Yr Nos 1 20 days from date of FOA
8 Discipline Engineer's (Civil/ Mech/ Elec) B.Tech in Civil/ Mech/ Elec Nos 1 10 days from date of FOA
9 Foreman / Supervisor Diploma in Mech & 2-3 Yr Nos 1 10 days from date of FOA
10 Civil surveyor / liaison team Diploma in Civil Nos 1 10 days from date of FOA
11 Document controller Nos 1 10 days from date of FOA
12 Store keeper / store in-charge Nos 1 10 days from date of FOA
13 Electrician / Machine mechanic Diploma/ITI Nos 1 10 days from date of FOA
14 ARC Welder (1G , 5G & 6G) As Per API 1104 Nos 1 10 days from date of FOA
15 Pipeline Fitter Nos 1 10 days from date of FOA
16 Grinder Nos 1 10 days from date of FOA
17 Welder Helper Nos 2 10 days from date of FOA
18 Rigger Nos 2 10 days from date of FOA
19 Sand Blaster Nos 1 10 days from date of FOA
20 Insulator Nos 2 10 days from date of FOA
21 Coating Helper Nos 2 10 days from date of FOA
22 OFC jointing crew Team 1 30 days from date of FOA
23 Hydrotesting crew Team 1 As per site requirement
24 HDD crew Team 1 As per site requirement
25 TCP crew Team 1 30 days from date of FOA
26 X-ray / Gamma Ray crew ASNT LEVEL-II Team 1 30 days from date of FOA
27 Unskilled workers Nos 10 10 days from date of FOA
28 Heavy duty driver Nos 1 10 days from date of FOA
Annexure-III
SL. NO DESCRIPTION OF PROCEDURES TIMELINE REMARK
A. MAINLINE
PROPOSED WELDING PROCEDURE SPECIFICATION – 01
1 7 Days from date of FOA
(MAIN LINE WELDING)
PROPOSED WELDING PROCEDURE
2 7 Days from date of FOA
SPECIFICATION – 02 (TIE-IN WELDING)
PROPOSED WELDING PROCEDURE SPECIFICATION – 03 (PARTIAL
3 7 Days from date of FOA
REPAIR)
PROPOSED WELDING PROCEDURE SPECIFICATION – 04
4 (THROUGH THICKNESS REPAIR) 7 Days from date of FOA
5 PROPOSED PROCEDURE FOR ELECTRODE QUALIFICATION TEST 7 Days from date of FOA
6 PIPE HANDLING, HAULING & STORAGE OF LINE PIPE 10 Days from date of FOA
7 SURVEY, CLEARING & GRADING OF ROW 10 Days from date of FOA
8 Incoming Material Inspection 10 Days from date of FOA
HEALTH, SAFEY AND ENVIRONMENT
9 10 Days from date of FOA
MANAGEMENT PLAN
10 Line pipe Stringing 10 Days from date of FOA
11 MAIN LINE WELDING PROCEDURE 10 Days from date of FOA
12 TIE- IN WELDING PROCEDURE 10 Days from date of FOA
13 Weld Joint Repair 10 Days from date of FOA
14 JOINT NUMBERING 10 Days from date of FOA
15 NDT Procedures (X-Ray) 10 Days from date of FOA
16 NDT Procedures (Gamma-Ray) 10 Days from date of FOA
17 Manual Ultrasonic Test 10 Days from date of FOA
18 Liquid Penetrant Test 10 Days from date of FOA
19 Field Joint Coating & Repair 10 Days from date of FOA
20 Cased Crossing by Boring, Open Cut and Minor Crossing 10 Days from date of FOA
21 HDD Crossing 10 Days from date of FOA
22 Pre-HydroTesting of Pipeline 10 Days from date of FOA
23 Trenching 10 Days from date of FOA
24 Lowering 10 Days from date of FOA
25 HDPE LAYING 10 Days from date of FOA
26 Backfilling 10 Days from date of FOA
27 Pipe Book 10 Days from date of FOA
28 OFC Drum testing 10 Days from date of FOA
29 Restoration 10 Days from date of FOA
30 Pipeline Marker Fabrication & Installation 10 Days from date of FOA
31 PENUMETIC TESTING 10 Days from date of FOA
32 WELDER QUALIFICATION TEST 10 Days from date of FOA
33 COLD FIELD BENDING 10 Days from date of FOA
34 ARC STRIKE REPAIR 10 Days from date of FOA
35 CONCRETE WEIGHT COATING 10 Days from date of FOA
36 MAJOR WATER CROSSINGS 10 Days from date of FOA
37 Mainline HydroTesting of Pipeline 10 Days from date of FOA
38 POST HYDRO TEST (FOR HDD CROSSING) 10 Days from date of FOA
FIELD JOINT COATING OF HDD SECTION
39 10 Days from date of FOA
(DIRAX SLEEVE)
40 DE-WATERING AND SWABBING 10 Days from date of FOA
41 HDD with Cassing 10 Days from date of FOA
42 MDPE PIPE LAYING 10 Days from date of FOA
43 Pre- Commisining & Commisining 10 Days from date of FOA
10 Days from date of FOA
B. STATION PIPING
1 EQT OF STATION PIPING 20 Days from date of FOA
7 Station piping Fabrication, welding & erection 20 Days from date of FOA
C. CIVIL WORK
1 Site Grading, Roads & Culverts 10 Days from date of FOA
7 Plain & Rein forced Cement Concrete Works 10 Days from date of FOA
8 False Calling, False Flooring, Under Deck Insulation Work 10 Days from date of FOA
C. ELECTRICAL WORK
1 Installation Testing & Commissioning of Electrical Work 10 Days from date of FOA
2 Installation Testing & Commissioning of Instruments Work 10 Days from date of FOA
3 Installation Testing & Commissioning of Fir & Gas detection and 10 Days from date of FOA
Fire Protection System Works