ACTIVITIES AFTER RECEIPT OF FOA from Client

A. SATATUTORY ACTIVITIES
SL No DESCRIPTION TIMELINE REMARKS

1 Contract document between TGS and Client to be submitted to Client 07 days


2 Indemnity Bond beteen TGS and Client to be sumbitted to client 07 days
3 Indemnity Bond for FIM beteen TGS and Client to be sumbitted to client 07 days
4 Request letter for FORM-III 07 days
5 Erection Insurance Policy to be submitted to client 15 days
6 Insurance policy of FIM to be submitted to client 15 days
7 WCP (workmen compensation policy) to be submitted to client 15 days
8 BG (Bank Gurantee against execution) to be submitted to client 45 days
Agreement between TGS and Sub-Contractor
9 a)BG submission 15 days
b)Opening of ESCROW account

10 Apply for labour license & BOCW permission (After receipt of FORM-III) 02 days

B. CONTRACTOR'S PRIMARY ACTIVITIES


1 Submission of work Procedure & Approval As per Annexure-III
2 Deploymet of Manpower As per Annexure-II
3 Deploymet of Machinery As per Annexure-I
4 Tools & consumable procurement As per Annexure-I
5 Approval of specialized Agency (NDT, TCP, HDD, etc.) 10 Days From date of FOA

C. CONTRACTOR'S PROCUREMENT ACTIVITIES


1 On receipt of FOA/SOR , supply material list to be seggregated 03 days From date of FOA

2 Intimation by mail by TGS to all vendors for procurement of material 03 days After Seggregation
3 Rates to be taken from Vendors 04 days After Enquiry
After finalisation of rates
4 PO to be placed by subcontractor 7 days & vendors
Incase PO is not placed by subcontractor TGS would place the PO with After finalisation of rates
5 intimation to Sub contractor 10 Days & vendors
Material QAP/Data sheet to be obtained from competent vendor and After finalisation of rates
6 to be submitted to Client by TGS 7 days & vendors
After QAP approval, advance to be released by sub-contractor to
7 supplier 7 days After QAP Approval

In case Advanace after QAP is not released by sub-Contractor , TGS


8 would release adavance with intimation to sub-contractor . To be 8 days After QAP Approval
charged 20% extra on supply amount value

D. CONTRACTOR'S FIELD EXECUTION ACTIVITIES- PIPELINE


1 Store/office setup/guest house 15 days
2 Kick off meeting 07 days From FOA

After getting the approval


3 WPS & EQT conducting 07 days of PWPS & PEQT

4 Formal Permission from client 02 days From KOM


Route survey on available front for HDD,open tench,built up
5 surface/area 07 days From KOM
6 Chainage marking 03 days After Survey
7 Line pipe issuance/collection from Client 03 days On availability of Front
8 Grading 01 day After chainage
After getting the
Intimation to all Local Authority(police,traffic,telecom,water permission copy from
9 line,power) supported with client's data 02 days client. / Before the start of
work at site

10 Welder Qualification test 1 day After approval of WPS


11 PQR of NDT, Coating 1 day After approval of WPS
12 Stringing & Welding 2 day After approval of WPS
13 NDT activities 1 day After Welding
14 Joint Coating 01 day After clearance of NDT
15 Laying activities ( Trenching, lowering, backfilling, duct laying, HDD 01 day After clearance of
etc..) Pipebook
16 TCP activities 10 day After laying of pipeline
17 Installation of Markers 10 day After laying of pipeline
18 Duct connectivity & OFC blowing 10 day After laying of pipeline
After completion of entire
19 Mainline hydrotest 10day section
After completion of
20 SV & TP installation 10day mainline Hydrotest
After completion of SV &
21 Commissioning 05 day TP installation
22 ROW cleanup & Restoration 10 day After laying of pipeline
23
24 NOC from local authorities 20 day After laying of pipeline
After commissiong of
25 Submission of As-built drawings & NDT films 10 day pipeline
After commissiong of
26 Submission of final inspection reports & contract closing documents 10 day pipeline
After commissiong of
27 Material Reconcialation 10 day pipeline
28 Contract Closing
D. CONTRACTOR'S FIELD EXECUTION ACTIVITIES- TERMINAL WORKS
I. Boundary wall
After receiving the
1 Layout 2 Drawing
2 Excavation 1 After layout
3 Dressing & Compaction 1 After Excavation
4 PCC 1 After Dressing
5 Steel cutting & binding(As per approved BBS) 2 After PCC
6 Shuttering 1 After steel binding
7 RCC (Concrete) 1 After Shuttering
8 Steel Binding for column/ Wall(Up to sub structure) 2 After Casting
9 Shuttering 2 After Steel binding
10 RCC (Concrete) 1 After Shuttering
11 Deshuttring 1 After casting
12 Brick work 4 After Deshuttering
13 Steel Binding for Plinth beam or RCC band) 2 After Brick work
14 Shuttering 1 After Steel binding
15 RCC (Concrete) 1 After Shuttering
16 Deshuttering 1 After Casting
17 Steel Binding for column/ Wall(Up to Super structure) 2 After Deshuttering
18 Shuttering 2 After steel binding
19 RCC (Concrete) 1 After Shuttering
20 Deshuttering 1 After Casting
21 Brick work 4 After Deshuttering
22 Steel Binding for coping and top level beam 3 After Brick work
23 Shuttering 3 After steel binding
24 RCC (Concrete) 1 After Shuttering
25 Y-Angle Installation 2 After Casting
26 Plaster Work Outer side (NGL TO TOP LEVEL) 3 After Y angle instalation
27 Plaster Work Inner Side (FGL TO TOP LEVEL) 3 After inner side plaster
28 Concertina coil fixing 2 After Plaster
29 Bituminous Painting Inner side(NGL TO FGL) 1 Before Plot filling
30 Painting 3 After Plaster
II. Plot Devlopment After Boundary wall Complition
1 Drain 10 After Plot filling
2 Waterharvesting pit 7 After Plot filling
3 Road Work 7 After Plot filling
4 Septic & Soakpit tank 5 After Plot filling
5 Foundation for Highmast & Street pole 4 After Plot filling
6 Highmast & Street pole erection 1 After Foundation
III. CONTROL BUILDING
After receiving the
1 Layout for Control building 2 Drawing
2 Excavation 3 After layout
3 Dressing & Compaction 2 After Excavation
4 PCC 2 After Dressing
5 Steel cutting & binding(As per approved BBS) 4 After PCC
6 Shuttering 3 After steel binding
7 Footing casting (RCC) 1 After Shuttering
8 Steel Binding for column (Up to sub structure) 4 After Casting
9 Shuttering 4 After Steel binding
10 Column casting (below plinth beam) 4 After Shuttering
11 Deshuttring 1 After Casting
After Compaction &
12 Steel binding for Plinth beam 7 Shuttering
13 Shuttering of plinth beam 2 After steel binding
14 Plinth beam casting 1 After Plinth beam
shuttering

15 Cable trench work(After Compaction) 7 After Compaction


Note:- PCC, Steel binding, insert plate fixing, Angle fixing, wall casting,

16 Coumn stirups Binding(FGL to lintal beam 3 After Plinth beam casting


17 Shuttering of column 3 After stirups binding
18 Column casting (FGL to lintal beam 2 After shuttering
19 Steel binding for Lintel and chajja 2 After Dressing
21 Shuttering for lintel & Chajja 3 After steel binding
22 Lintel & Chajja casting(RCC) 1 After Shuttering
23 Shuttering of column(up to Roof beam Bottom) 4 After Casting
24 Column casting 3 After Steel binding
25 Shuttering of roof beam including slab 5 After Column Casting
26 Steel Binding for slab & roof beam 4 After shuttering
27 Slab Casting 1 After steel binding
28 Deshuttering of slab(Min. 15 Days) 3 After Casting
29 Block work 10 After Deshuttering
30 Outer Plaster 7 After Block work
Inner wall plaster
31 Note:- After plumbing & Conduit wiring compl. 9 After Block work
32 Flooring Work(After Compaction & Anti Termite Treatment 7 After Plaster
33 Tiles, Kota stone fixing 13 After Flooring
34 Door window fixing 4 After Tiles Fixing
35 Painting 7 After Door fixing
36 Water Proofing 5 After Block work
III. GUARD ROOM
After receiving the
1 Layout for guard room 1 Drawing
2 Excavation 1 After layout
3 Dressing & Compaction 1 After Excavation
4 PCC 1 After Dressing
5 Steel cutting & binding(As per approved BBS) 2 After PCC
6 Shuttering 2 After steel binding
7 Footing casting (RCC) 1 After Shuttering
8 Steel Binding for column (Up to sub structure) 1 After Casting
9 Shuttering 1 After Steel binding
10 Column casting (below plinth beam) 1 After Shuttering
11 Deshuttering 1 After Casting
After Compaction &
12 Steel binding for Plinth beam 2 Shuttering
13 Shuttering of plinth beam 2 After steel binding
14 Plinth beam casting 1 After shuttering
15 Column Stirups binding(FGL to Roof beam bottom ) 1 After casting
17 Shuttering of column(up to lintel level) 2 After Stirups binding
18 Column casting (below Lintel Level) 1 After shuttering
19 Steel binding for Lintel and chajja 2 After column casting
21 Shuttering for lintel & Chajja 2 After steel binding
22 Lintel & Chajja casting(RCC) 1 After shuttering
23 Shuttering of column(up to Roof beam Bottom) 3 After lintel casting
24 Column casting 3 After shuttering
25 Shuttering of roof beam including slab 5 After column casting
26 Steel Binding for slab & roof beam 4 After shuttering
27 Slab Casting 1 After steel binding
28 Deshuttering of slab(Min. 15 Days) 15 After casting
29 Block work 7 After Deshuttering
30 Outer Plaster 3 After Block work
31 Inner wall plaster 3 After block work
Note:- After plumbing & Conduit wiring compl.
32 Flooring Work(After Compaction & Anti Termite Treatment 4 After Plaster
33 Tiles, Kota stone fixing 4 After flooring
34 Sanatory works 2 after flooring
35 Door window fixing 2 After Tiles fixing
36 Painting 3 After Door fixing
37 Waterproofing 2 After Block work
38 Water tank installation 1 After slab casting
D. CONTRACTOR'S FIELD EXECUTION ACTIVITIES- ELECTRICAL / INSTRUMENTATION WORK
1 Vendor Finalization
2 Documents Submission for approval
3 Production
4 TPI / MECON inspection / MTC, Acceptance along with approved
documents
5 IMIR at Site
6 Installation Testing & Commissioning of Electrical Work
7 Installation Testing & Commissioning of Instruments Work
Installation Testing & Commissioning of Fir & Gas detection and Fire
8 Protection System Works
Annexure-I (for pipeline)
MINIMUM NUMBER OF MATERIAL LIST FOR 4''/6''/8'' X 5KM STEEL PIPELINE ( 1 SECTION)

SL NO. DESCRIPTION OF EQUIPMENT SIZE UOM QTY Timeline REMARKS

A Machinery
1 Hydra (8 – 10 MT) Nos 2 10 days from date of FOA
2 D.G. Sets : (inclusive of generators) 62.5 KVA to 200 KVA Nos 1 10 days from date of FOA
3 Air Compressor (300CFM) Nos 1 10 days from date of FOA
4 Excavator Nos 1 10 days from date of FOA
5 HDD Rig with All Equipments & Accessories (Cap. 32 T TO 150 T) Nos 1 As per site requirement
6 Pressurization Pump – Motorized 150 kg/cm2 Nos 1 As per site requirement
7 Pressurization Pump – Manual 100 Kg/Cm2 Nos 1 As per site requirement
8 Filling Pumps (400 TO 1000 M3/HR) Nos 1 10 days from date of FOA
9 Tractor with trolley Nos 1 10 days from date of FOA
10 Dewatering Pump Nos 1
B Welding Tools
1 Vehicle For Staff & Worker Nos 3 10 days from date of FOA
2 Tripod with 5 Tons Chain Pulley Block Nos 2 10 days from date of FOA
3 Choker Belt 5 mtr x10 ton Nos 3 10 days from date of FOA
4 Choker Belt 2 mtr x 5 ton Nos 3 10 days from date of FOA
5 Wire Rope(cilling) 16 MM Mtr 6.5 10 days from date of FOA
6 U Clamp Nos 5 10 days from date of FOA
7 D Cycle 3, 5 & 10 TON Nos Each 3 10 days from date of FOA
8 External Clamp As Per Pipe DIA Nos 1 10 days from date of FOA
9 Hydrolic Jack 5 Ton & 10 Ton Nos Each 1 10 days from date of FOA
10 Welding Machines 400 AMPS Nos 1 10 days from date of FOA
11 Grinding machine AG-5 Nos 1 10 days from date of FOA
12 Grinding machine AG-7 Nos 1 10 days from date of FOA
13 Grinding Wheel AG-7 Nos 100 10 days from date of FOA
14 Grinding Wheel AG-5 Nos 20 10 days from date of FOA
15 Cutting Wheel AG-7 Nos 50 10 days from date of FOA
16 Cutting Wheel AG-5 Nos 20 10 days from date of FOA
17 Grinding machine Cable Mtr 100 10 days from date of FOA
18 Welding Helmet Nos 1 10 days from date of FOA
19 Welding White Glass Nos 300 10 days from date of FOA
20 Welding Black Glass Nos 50 10 days from date of FOA
21 Grinding Helmet Nos 5 10 days from date of FOA
22 Leather Hand Gloves Pair 10 10 days from date of FOA
23 Hand Sleeve Pair 10 10 days from date of FOA
24 Welding Holder 1000 AMP Nos 5 10 days from date of FOA
25 Short Cable Mtr 30 10 days from date of FOA
26 Welding Cable Mtr 50 10 days from date of FOA
27 Cable Lock Nos 20 10 days from date of FOA
28 Halogen Lamp Set 500W Nos 2 10 days from date of FOA
29 Halogen Tube 500W Nos 10 10 days from date of FOA
30 Lamp 100W Nos 2 10 days from date of FOA
31 Safety Helmet Nos 20 10 days from date of FOA
32 Safety Shoes Nos 20 10 days from date of FOA
33 Safety Leg Guards Nos 20 10 days from date of FOA
34 Safety Apron Nos 20 10 days from date of FOA
35 Tool Box Nos 1 10 days from date of FOA
36 Measuring Tape 5MTR, 50MTR, 100MTR Nos EACH 1 10 days from date of FOA
37 Adjustable Wrinch 50MM Nos 1 10 days from date of FOA
38 Cutting Player Nos 1 10 days from date of FOA
39 Screw Driver Nos 1 10 days from date of FOA
40 Parmanent Marker Pkt 1 10 days from date of FOA
41 Yellow Cholk Pkt 2 10 days from date of FOA
42 Garden Umbrella Nos 1 10 days from date of FOA
43 Spanner Set Box 1 10 days from date of FOA
44 Allen Key Set Box 1 10 days from date of FOA
45 PVC Tape Nos 10 10 days from date of FOA
46 Teflon Tape Nos 20 10 days from date of FOA
47 MS Hammer 1kg & 2 Kg Nos Each 1 10 days from date of FOA
48 Wire Brush Nos 5 10 days from date of FOA
49 PVC Rope 12MM Roll 1 10 days from date of FOA
50 Welding Hood Nos 2 10 days from date of FOA
51 Wooden Set 1.5 mtr x 6inch Nos 50 10 days from date of FOA
52 Lifting Hook Nos 5 10 days from date of FOA
53 Electrical Tools Box 1 10 days from date of FOA
54 Industrial LPG Cylinder Nos 3 10 days from date of FOA
55 LPG Regulator Nos 3 10 days from date of FOA
56 L PG Torch Nos 2 10 days from date of FOA
57 LPG Hose Pipe Mtr 50 10 days from date of FOA
58 Sand Blasting Nosel Nos 2 10 days from date of FOA
59 Mobile Sand blasting equipment Nos 1 10 days from date of FOA
60 Hopper for Sand blasting Nos 1 10 days from date of FOA
61 Ring Clamp 2 inch Nos 10 10 days from date of FOA
62 Hose Pipe 2 inch Mtr 30 10 days from date of FOA
63 Nose Mask Nos 50 10 days from date of FOA
64 White Goggles Nos 20 10 days from date of FOA
65 Black Goggles Nos 20 10 days from date of FOA
66 Brass Hammer 1 Kg Nos 1 10 days from date of FOA
67 Wranning Tape 100 MTR Nos 10 10 days from date of FOA
68 Canvas Tarpaulin 18"X36" Nos 2 10 days from date of FOA
69 Right Angle Nos 1 10 days from date of FOA
70 Speed Level Tool Nos 1 10 days from date of FOA
71 File Nos 1 10 days from date of FOA
72 Blasting Helmet Nos 2 10 days from date of FOA
C Instruments
1 Holiday Detector Unit Nos 1 10 days from date of FOA
2 Portable Peel Gauge testers Nos 1 10 days from date of FOA
3 Coating Thickness Gauge Nos 1 10 days from date of FOA
4 Peel Test Kit Set 1 10 days from date of FOA
5 Wet Film Thickness Gauge Nos 1 10 days from date of FOA
6 Press-o-Film Box 5 10 days from date of FOA
7 Coat Meter Nos 1 10 days from date of FOA
8 Temparature Gun Nos 1 10 days from date of FOA
9 Weld Gauge Nos 1 10 days from date of FOA
10 Micro Meter Nos 1 10 days from date of FOA
11 Magnifying Glass Nos 1 10 days from date of FOA
12 Multi Meter Nos 1 10 days from date of FOA
13 Filler Gauge Nos 1 10 days from date of FOA
14 Clamp Meter Nos 1 10 days from date of FOA
15 Pressure Gauge 0-100 Kg/Cm2 Nos 4 10 days from date of FOA
D Consumable Materials
1 Perp-60 Roll 1 15 days from date of FOA
2 Perp-80 Roll 1 15 days from date of FOA
3 Applicator Pads Nos 200 15 days from date of FOA
4 Epoxy Hand Pump Nos 2 15 days from date of FOA
5 Mixing sticks, cups etc Nos 200 15 days from date of FOA
6 Rubber Hand Gloves Pair 2 15 days from date of FOA
7 Silicon Hand Roller (curved) Nos 2 15 days from date of FOA
8 Silicon Hand Roller (Straight) Nos 2 15 days from date of FOA
9 Copper Slag/Sand Ton 10 15 days from date of FOA
10 Normal Coating Sleeve As Per Requirement Nos 200 15 days from date of FOA
11 Dirax Coating Sleeve As Per Requirement Nos 100 15 days from date of FOA
12 Epoxy Part-A Drum 1 15 days from date of FOA
13 Epoxy Part-B Drum 1 15 days from date of FOA
14 LR Bends As Per Contract - As per SOR 25 days from date of FOA
15 Fittings & Flanges As Per Contract - As per SOR 25 days from date of FOA
16 HDPE Duct As Per Contract - As per SOR 25 days from date of FOA
17 OFC As Per Contract - As per SOR 25 days from date of FOA
18 Electrode As Per Contract - As per SOR 25 days from date of FOA
19 Casing & Conduit As Per Contract - As per SOR 25 days from date of FOA
20 Valves As Per Contract - As per SOR 25 days from date of FOA
21 Warnning Mat As Per Contract - As per SOR 25 days from date of FOA
Annexure-II (for pipeline)
MINIMUM NUMBER OF MANPOWER LIST FOR 4''/6''/8'' X 5KM STEEL PIPELINE ( 1 SECTION)
SL NO. DESCRIPTION QUALIFICATION & EXPERIENCE UOM QTY Timeline REMARKS
1 Construction Manager / Section In-charge B. Tech (Mech) & 7-10 Yr Nos 1 10 days from date of FOA
2 Planning engineer B. Tech (Mech) & 2-3 Yr Nos 1 10 days from date of FOA
3 QA/ QC engineer B. Tech (Mech), ASNT L-II & 3-5 Yr Nos 1 10 days from date of FOA
4 Safety officer Diploma in HSE & 2-3 Yr Nos 1 10 days from date of FOA
5 Account Officer B.Com Nos 1 10 days from date of FOA
6 Qualified Surveyor Diploma in Civil Nos 1 10 days from date of FOA
7 Welding/ NDT engineer Diploma in Mech, ASNT L-II & 2-3 Yr Nos 1 20 days from date of FOA
8 Discipline Engineer's (Civil/ Mech/ Elec) B.Tech in Civil/ Mech/ Elec Nos 1 10 days from date of FOA
9 Foreman / Supervisor Diploma in Mech & 2-3 Yr Nos 1 10 days from date of FOA
10 Civil surveyor / liaison team Diploma in Civil Nos 1 10 days from date of FOA
11 Document controller Nos 1 10 days from date of FOA
12 Store keeper / store in-charge Nos 1 10 days from date of FOA
13 Electrician / Machine mechanic Diploma/ITI Nos 1 10 days from date of FOA
14 ARC Welder (1G , 5G & 6G) As Per API 1104 Nos 1 10 days from date of FOA
15 Pipeline Fitter Nos 1 10 days from date of FOA
16 Grinder Nos 1 10 days from date of FOA
17 Welder Helper Nos 2 10 days from date of FOA
18 Rigger Nos 2 10 days from date of FOA
19 Sand Blaster Nos 1 10 days from date of FOA
20 Insulator Nos 2 10 days from date of FOA
21 Coating Helper Nos 2 10 days from date of FOA
22 OFC jointing crew Team 1 30 days from date of FOA
23 Hydrotesting crew Team 1 As per site requirement
24 HDD crew Team 1 As per site requirement
25 TCP crew Team 1 30 days from date of FOA
26 X-ray / Gamma Ray crew ASNT LEVEL-II Team 1 30 days from date of FOA
27 Unskilled workers Nos 10 10 days from date of FOA
28 Heavy duty driver Nos 1 10 days from date of FOA
Annexure-III
SL. NO DESCRIPTION OF PROCEDURES TIMELINE REMARK

A. MAINLINE
PROPOSED WELDING PROCEDURE SPECIFICATION – 01
1 7 Days from date of FOA
(MAIN LINE WELDING)
PROPOSED WELDING PROCEDURE
2 7 Days from date of FOA
SPECIFICATION – 02 (TIE-IN WELDING)
PROPOSED WELDING PROCEDURE SPECIFICATION – 03 (PARTIAL
3 7 Days from date of FOA
REPAIR)
PROPOSED WELDING PROCEDURE SPECIFICATION – 04
4 (THROUGH THICKNESS REPAIR) 7 Days from date of FOA
5 PROPOSED PROCEDURE FOR ELECTRODE QUALIFICATION TEST 7 Days from date of FOA
6 PIPE HANDLING, HAULING & STORAGE OF LINE PIPE 10 Days from date of FOA
7 SURVEY, CLEARING & GRADING OF ROW 10 Days from date of FOA
8 Incoming Material Inspection 10 Days from date of FOA
HEALTH, SAFEY AND ENVIRONMENT
9 10 Days from date of FOA
MANAGEMENT PLAN
10 Line pipe Stringing 10 Days from date of FOA
11 MAIN LINE WELDING PROCEDURE 10 Days from date of FOA
12 TIE- IN WELDING PROCEDURE 10 Days from date of FOA
13 Weld Joint Repair 10 Days from date of FOA
14 JOINT NUMBERING 10 Days from date of FOA
15 NDT Procedures (X-Ray) 10 Days from date of FOA
16 NDT Procedures (Gamma-Ray) 10 Days from date of FOA
17 Manual Ultrasonic Test 10 Days from date of FOA
18 Liquid Penetrant Test 10 Days from date of FOA
19 Field Joint Coating & Repair 10 Days from date of FOA
20 Cased Crossing by Boring, Open Cut and Minor Crossing 10 Days from date of FOA
21 HDD Crossing 10 Days from date of FOA
22 Pre-HydroTesting of Pipeline 10 Days from date of FOA
23 Trenching 10 Days from date of FOA
24 Lowering 10 Days from date of FOA
25 HDPE LAYING 10 Days from date of FOA
26 Backfilling 10 Days from date of FOA
27 Pipe Book 10 Days from date of FOA
28 OFC Drum testing 10 Days from date of FOA
29 Restoration 10 Days from date of FOA
30 Pipeline Marker Fabrication & Installation 10 Days from date of FOA
31 PENUMETIC TESTING 10 Days from date of FOA
32 WELDER QUALIFICATION TEST 10 Days from date of FOA
33 COLD FIELD BENDING 10 Days from date of FOA
34 ARC STRIKE REPAIR 10 Days from date of FOA
35 CONCRETE WEIGHT COATING 10 Days from date of FOA
36 MAJOR WATER CROSSINGS 10 Days from date of FOA
37 Mainline HydroTesting of Pipeline 10 Days from date of FOA
38 POST HYDRO TEST (FOR HDD CROSSING) 10 Days from date of FOA
FIELD JOINT COATING OF HDD SECTION
39 10 Days from date of FOA
(DIRAX SLEEVE)
40 DE-WATERING AND SWABBING 10 Days from date of FOA
41 HDD with Cassing 10 Days from date of FOA
42 MDPE PIPE LAYING 10 Days from date of FOA
43 Pre- Commisining & Commisining 10 Days from date of FOA
10 Days from date of FOA

B. STATION PIPING
1 EQT OF STATION PIPING 20 Days from date of FOA

2 WPS OF STATION PIPING 20 Days from date of FOA

3 Structural Steel Works 20 Days from date of FOA

4 Painting for Piping & Structure 20 Days from date of FOA

5 Hydro testing Piping 20 Days from date of FOA

6 NDT of piping 20 Days from date of FOA

7 Station piping Fabrication, welding & erection 20 Days from date of FOA

8 Penumetic Testing 20 Days from date of FOA

C. CIVIL WORK
1 Site Grading, Roads & Culverts 10 Days from date of FOA

2 Earth Works Excavation And Backfilling 10 Days from date of FOA

3 Brick Masonary Works 10 Days from date of FOA


Anti-Termite Treatment Micro Grading, Gravel Filling & Grouting
4 Works 10 Days from date of FOA

5 Topography Survey of Station Works 10 Days from date of FOA


Plastering /Pointing & White Color Washing and Distempering
6 Work 10 Days from date of FOA

7 Plain & Rein forced Cement Concrete Works 10 Days from date of FOA

8 False Calling, False Flooring, Under Deck Insulation Work 10 Days from date of FOA

9 Water Proofing Treatment 10 Days from date of FOA

10 Stone Masonary 10 Days from date of FOA

11 Structural Steel Works 10 Days from date of FOA

12 Chain link Fencing Works 10 Days from date of FOA

13 Architectural Works 10 Days from date of FOA

14 EXCAVATION 10 Days from date of FOA

15 Compound wall 10 Days from date of FOA

16 Installation of steel aluminium doors 10 Days from date of FOA

17 iInstalation of Bore Well 10 Days from date of FOA

18 Floor Finishing 10 Days from date of FOA

19 Plumbing & drainage 10 Days from date of FOA

20 Painting 10 Days from date of FOA

21 Strom Water Drain 10 Days from date of FOA

22 Valve pit 10 Days from date of FOA

23 Curve stone laying 10 Days from date of FOA

24 Pavement 10 Days from date of FOA

25 Lawn Development 10 Days from date of FOA


26 Piling 10 Days from date of FOA

C. ELECTRICAL WORK
1 Installation Testing & Commissioning of Electrical Work 10 Days from date of FOA

2 Installation Testing & Commissioning of Instruments Work 10 Days from date of FOA

3 Installation Testing & Commissioning of Fir & Gas detection and 10 Days from date of FOA
Fire Protection System Works