3. Which steps to be followed during installation of panels ? (1 Point)

Before installation check the switchgear room dimensions.

Check the Panel installation floor level.

Remove the breaker trolley from panel and then install the panels.

All above.

4. According to operation manual, what is straightness tolerance required ? (1 Point)

2mm within 1meter measured length

1mm within 1meter measured length & 2mm over entire switchboard length.

5. For Panel installation when should be the withdrawable part (VCB / Contactor / PT trollies)
removed? (1 Point)

Before shifting of Panels on foundation


After shifting of panels on foundation

6. Which lubrication should be used for busbar joints ? (1 Point)

Shell Vaseline, which is transparent, colorless & odorless

Molykote® Longterm 2 plus, which is black in color & sticky

soflex Topas L32, which is yellow in color & sticky

7. Which of the following torque values are correct for tightening of Busbar & any Insert
(Bushing / CT)? (1 Point)

Tightening torques 40Nm for M10 bolt & 70Nm for M12 bolt

Tightening torques 30Nm for M10 bolt & 50Nm for M12 bolt

8. Is there any interlock provided to avoid opening of HV door when the withdrawable part (VCB
/ Contactor / PT trollies) is in service condition ? (1 Point)

No such interlock is provided

Yes, door cannot be open when withdrawable part is in service condition

9. Can the cable earthing switch be switched ON with VCB in service position ? (1 Point)

Yes, earthing switch can be operated hassle free in all conditions irrespective of VCB position

No, earthing switches can be operated only when VCB is in test condition

10. Which lubricant should be used for earthing switch blades & tulip contacts on switching
device? (1 Point)

Thin film of Molykote® Longterm 2 plus


Thin film of Vaseline

11. During Maintenance all insulating components must be clean with? (1 Point)

small brushes and dusters

Chemical solvents such as CTC(Carbon, Tetra Chloride), trichloroethane

Vacuum cleaner

Clean cloth

12. Where are panel rating plate & CT/VT rating plate stickers stuck on panel ? (1 Point)

Outside of HV door

Inside of HV door

Inside of LV door

13. HV door can be opened in which condition ? (1 Point)

When switching device is in service condition

When switching device is in test condition

14. When can we provide Padlock facility for shutter mechanism in panels ? (1 Point)

Shutters can be padlocked in closed & open conditions both

When they are in closed condition only

When they are in open condition only


15. How to measure contact resistance of circuit breaker? (1 Point)

Breaker in OFF condition with 33kV source

Breaker in ON condition with 100A DC source

16. At site HV test is conducted at …. % of rated test voltage ? (1 Point)

50% of rated test voltage

75% of rated test voltage

80% of rated test voltage

100% of rated test voltage

17. Ingress protection of IP4X means…. ? (1 Point)

Object more then 1mm should not enter and touch the live parts

Object more then 2.5mm should not enter and touch the live parts

Object more then 50mm should not enter and touch the live parts

Object more then 12.5mm should not enter and touch the live parts

18. Circuit Breaker is rated for ------- mechanical operations at rated current? (1 Point)

100000 operations

10000 operations

2000 operations

5000 operations
19. Shrouding of main bus bar joints for NXAIR H (36kV) ? (1 Point)

Is provided by default

Is provided as optional feature

20. Shrouding of main bus bar joints for NXAIR (12kV) ? (1 Point)

Is provided by default

Is provided as optional feature

21. Internal arc classification IAC A FLR means? (1 Point)

Internal arc protection at Panel front

Internal arc protection at Panel rear

Internal arc protection at Panel front, sides and rear

Internal arc protection at Panel sides

22. Limits of Circuit Breaker closing and opening timings are …..? (1 Point)

<45ms and <25ms

<80ms and <65ms

<90ms and <70ms

23. Panel enclosure is having Ingress protection of …. ? (1 Point)

IP 2x

IP 4x
IP 3x

IP 55

24. Panel to panel coupling bolts for NXAIR (12kV) provided at ................. ? (1 Point)

At Pressure Release Compartment (PRC)

At rear side with ledges

All above

At front CB and LV chambers

25. Which size of Allen key to be use for NXAIR (12kV) door defeat interlock .......? (1 Point)

M6

M4

M5

M3

This content is created by the owner of the form. The data you submit will be sent to the form owner. Microsoft is not responsible for
the privacy or security practices of its customers, including those of this form owner. Never give out your password.

Powered by Microsoft Forms | Privacy and cookies | Terms of use

You might also like