1. Objective
This method of statement outlines the procedures for the Addition DDC panel and Control module for BIP
and BEP Project work.
Interface with Existing Building work outlines the sequence and activities in preparation for the Installation
DDC panel and wiring work for the Tank equipment’s.
Before Commencement of work and interfacing with BMS, the DDC Panel and LMCP to be studied and
verified, this includes
a. Controls points
b. Controls functions
c. Sequences and staging
d. Hardware Contact
.
2.2 Programming and Sequence Walk-Through
Programming of the DDC controller and the residing system shall be programmed according to the As per
Client requested programming. There-after the application will do a sequence walk-through with the our site
engineers for;
Upon satisfactory verification of the application, the documents are to be produce and to be used during
Project Phase
a. The point check sheet, for the equipment
b. The control sequence check sheet base on the Function Diagram Schematic and application.
c. DDC point termination sheet.
Application and Site engineers jointly conduct a walk-through of the program with the project manager.
The project manager shall verify the application correctness. Simulation to be conducted where need be.
For critical plant, a walk-through of the operation of the equipment is to be conducted with facilities
management team in-charge of operating that equipment, to confirm final functions.
Testing and commissioning work for BIP and BEP Project work
The testing records and documents are to be organised and submitted, this included
Base on project reports, monitors and trend from central BMS computer;
Submit a final summary report of operation parameter (trend) upon completion of 1 cycle of operation.
1. Equipment did
not operate at 1. Trending of current equipment operation
correct timing. activities to identify sequence.
The affected
2. Missed Did not identify 2. Take down the equipment time program.
equipment
staging or the required
DDC control controls are not
sequencing. functions, 3. Check function against existing operation
functions. functioning in the
sequences or and maintenance manual.
right sequence,
3. Wrong staging time program.
stage
or sequencing 4. Verify equipment operation and function with
Facilities team in-charge of the particular
4. Operation equipment of system.
affected
5. Responsibility Matrix
I/O Summary
BMS Input / Output
Application Engineer Site Engineer
(I/O) Point DDC Sizing
Verification
System Architect
BMS System,
DDC Control Function Description Application Engineer Site Engineer Key and Main Plant
functions and Specification Control function
Sequences
Application Engineer
DDC Programming DDC control Site Engineer Key and Main Plant
and Application application database Control function
Testing and Application Engineer Site Engineer Key and Main Plant
Operating System
Commissioning Control function
Operation Trends
Follow-up and Application Engineer Site Engineer
Monitoring
Defects list clear
The check sheet and test procedure covers the following tests;
Point to point loop test provides the procedures for conducting point tests. Point test ensure that the point
interfaces, the connections and the inputs and outputs are correctly configure. Inputs that have direct
monitoring only, e.g. Trip alarm, and point that have direct output function only, e.g. Pump on/off control.
The Point to Point loop test procedure and check-sheet are as shown in Appendix A.
The Point to Point Check sheet is also use for recording of Each Individual system points, e.g., Tank
High/Low Feedback points.
Control loop test provides the procedures for conducting basic control loop associated with High / Low Level
Tanks feedback and Pump control logic. The test is standard for all equipments requiring such controls
function.
Sequence test are extension of the control loop test. The sequence test, verify the operation of a particular
system, whereby, the said system have to operate in a pre-determine sequence or staging, based on Tank
Level or Time of day. These sequences varies from equipment system to equipment systems
For AMAT, the equipment system that operated on some form of sequence are;
Sequence test check sheet are developed according to sequence studied and programming structure.
7. Appendices
The point to point loop test covers the test procedure for the input and output points of the DDCs
and together with the check sheet records the setting set-points and time program. The process
are;
SATP-001 Controller Digital Input or Binary Input (BI) Loop Check Verification Procedures
SATP-002 Controller Digital Output or Binary Output (BO) Loop Check Verification Procedures
Pre-requisite
Required Tools
Multi-meter
Thermometer
Short length of Jumper Cable
7.2 SATP-001: Controller Digital Input or Binary Input (BI) Loop Check Verification Procedures
SATP-001: Controller Digital Input or Binary Input (BI) Loop Check Verification
Description: Digital input senses a close or open voltage free contact state from field interface. The
contact may come from a switch device or a relay contact from equipment panels.
Responsibility: Honeywell
Acceptance Criteria: Controller digital input points are properly wired to the correct device and responded
correctly.
Procedure:
3. Close Contact State – Activate the end-device (e.g. start the fan or simulate close contact by placing
a wire jumper across the point terminals) to obtain a closed contact. Record the state of the point that
is displayed on EBI station.
4. Open Contact State – De-activate the end device to obtain an open contact. Record the state of the
point that is displayed on EBI station.
5. Test Result – Enter “Pass” or “Fail” to indicate if the actual result matches the expected result.
Signature section
7.3 SATP-002: Controller Digital Output or Binary Output (BO) Loop Check Verification Procedures
SATP-002: Controller Digital Output or Binary Output (BO) Loop Check Verification
Description: Digital Outputs sends a 24V signal to field relays of equipment panels; e.g. to Start Pumps
& Open/Close Motorized valve
Responsibility: Honeywell
Acceptance Criteria: Controller digital outputs are wired to the correct device.
Procedure:
3. Command on State: Actual – At the EBI station point display, set the digital output to on state.
Observed the physical state of the end-device or equipment. If end-device cannot be operated “live”,
measure voltage at interface terminal. The voltage should be 24V.
4. Command off State: Actual – At the EBI station point display, set the digital output to on state.
Observed the physical state of the end-device or equipment. If end-device cannot be operated “live”,
measure voltage at interface terminal. The voltage should be 0V.
5. Test Result – Enter “Pass” or “Fail” to indicate if the actual result matches the expected result.
Signature section
HONEYWELL
SL NO POINT NAME POINT DESCRIPTION POINT TYPE ONSITE VALUE STATUS REMARKS
5 L1_DOM_PUMP1_HIGHLEVEL HIGH LEVEL ALARM BINARY INPUT NORMAL / ALARM PASS / FAIL
6 L1_DOM_PUMP1_LOWLEVEL LOW LEVEL ALARM BINARY INPUT NORMAL / ALARM PASS / FAIL
7 L1_DOM_TANK_HIGHLEVEL HIGH LEVEL ALARM BINARY INPUT NORMAL / ALARM PASS / FAIL
8 L1_DOM_TANK_LOWLEVEL LOW LEVEL ALARM BINARY INPUT NORMAL / ALARM PASS / FAIL
Document No.: HPL/BIOPOLIS/BMS/MOS D-1 Issued Date: 6th MAY 2019 Rev.: 0