Professional Documents
Culture Documents
Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
TABLE OF CONTENT
1. OBJECTIVE
2. SCOPE OF WORK
4. WORK METHODOLOGY
5. INSTALLATION
6. SYSTEM COMMISSIONING
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
1) OBJECTIVE
This method statement is to describe the method of which the Installation, Testing and
Commissioning of Fire Fighting System Work carried out for this project.
2) SCOPE
This procedure applies to project site, which requires Fire Fighting Services installation
work, which is carried out by the Company
EXECUTION OF WORKFLOW
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
Pipes with smaller diameter, full length or as required sizes will be shifted to
each floors through the designated staircase.
SAFETY MEASURES:
Workers assigned for material shifting will be equipped with necessary PPE’s
prior to start the work.
Assigned size of Rope will be used for lifting of pipe.
Flash back arrestor will be provided for oxyacetylene cutting set.
Pipe lifting inside the shafts shall be for main Sprinkler & Hydrant feeder.
Dia 150mm pipe will be cut into required size as the pipe can be pulled inside
the shaft manually through the Floor shaft entrance.
Pipe lifting and setting will be started from the bottom end of the shaft.
C- Channel supports will be fixed inside the shaft with 3mtrs interval with the
provision of holes for fixing the U- Bolt which holds the pipe.
Each piece of pipes will be jointed one and above until it attains the terrace.
Pipes will be fixed rigidly with C- Channel by means of respective size of U-
Bolts.
SAFETY MEASURES:
Workers assigned for material shifting will be equipped with necessary PPE’s
prior to start the work.
Necessary Shaft work permits will be taken prior to work start from the
respective PMC/ Client person.
Safety Belt and the appropriate ladders will be provided to work inside the
shaft.
Respiration availability will be checked prior to start the work.
IV. MARKING
Marking of Main header pipe and the Branches will be carried out as per the Shop
drawing which will be duly approved by the Consultant.
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
At changes of direction in either vertical or horizontal and point near the valve,
additional support shall be provided. However it may be omitted when coincidental
with required standard spacing location as described in figure below
a) Chamfering of pipes
For pipes with outside diameter 150 mm and greater shall be cut by
Oxyacetylene torch.
Bring lengths together leaving only a small welding gap. In normal practice, a
welding electrode of 2.4 mm Ø size, removed of its covering and bent in the
middle at an angle of 30° is inserted between the two pipes to obtain a perfect
welding gap.
Check for the levels.
Tack on both the sides, and rotate the pipe to 90⁰ and repeat the same
procedure.
As illustrate in the above figure, first a fill weld is carried out on the joint for the weld
to penetrate the inner surface of pipe. The flux has to be chipped off and the weld is
cleaned with the use of wire brush. A final weld is carried over the fill weld to
maintain the finishing and rigidity of the weld and the pipe joint.
a) Butt Welding
Butt welding practice is done to the pipes Of 65 mm dia and above. After the pipe to
Pipe fit-up is done the welding work is carried out.
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
b) Socket Welding
Socket weld is carried out on Lower dia pipes i.e. for 50 mm and below. This practice
is carried out for the following reasons.
Temporary tack welding is not needed for alignment, because in principle the
fitting ensures proper alignment.
The weld metal cannot penetrate into the bore of the pipe.
They can be used in place of threaded fittings, so the risk of leakage is much
smaller.
Construction costs are lower than with butt-welded joints due to the lack of
exacting fit-up requirements and elimination of special machining for butt weld
end preparation
c) Safety measures to be followed
When Welding or cutting near a hole in a wall or floor, a fire watch is required on
both sides of the wall or floor.
A Fire extinguisher shall be maintained in the area and the fire watch shall
understand how to use it
The area should be checked for at least an hour after the welding operation has
ceased to verify that no smoldering fire exist
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
sparks
I Intense light
irritation and
chemical burns
heat
burns
fires
X. Painting of pipes
All pipes will be cleaned inside and outside for removal of Dust and debris before
painting.
One coat of Approved Red-oxide Primer will be applied.
After drying, one coat of Approved Enamel Paint will be applied before
installation of Pipe.
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23
Finally one coat of Approved Enamel Paint Will be applied after hydraulic test
and in the final stages.
5) INSTALLATION
Once completion of welding branches with the main header pipe line Sprinkler head will be
installed. Sprinkler heads will be vary with the Temperature rating and the model according
the location of installation. Appropriate Temperature rating and model of sprinkler heads will
be installed with the base of Approved shop drawing. Sprinkler heads can be installed along
with Flexible drops to attain its location on the false ceiling. For the aesthetic view it will be
also installed with Rosette plate by tightening process.
6) SYSTEM COMMISSIONING
Equipment/Instruments to be used:
1. Adjustable Spanner.
2. Pressure Gauges.
3. Pipe Wrench.
a) Pre Commissioning
After piping is erected, all piping systems including main header line and branch
line will be cleaned to remove all mill, welding scale, oil, corrosion, and other
construction debris.
System will be flush cleaned and filled ready for service immediately after
cleaning.
Do not operate pumps or equipment until debris has been removed from the
respective system has been flushed out.
Flushing of the system can be done from a pumping source with minimum flow
rate to provide a velocity of 3 m/ sec.
Flush the piping system until all debris is removed and clean water comes out.
Automatic devices which can become clogged during the cleaning process will
be disconnected and will not be connected permanently until the cleaning
process is complete.
b) Commissioning:
The following are to be checked prior to handover of the Fire Sprinkler System to the
Clients/ End Users.
Project M/s.Suven Pharma
Location 2nd Floor, Aurobindo, Hyderabad
Vendor M/s. Centaur FSA Pvt.Ltd.
Document & Rev No: FPS Method Statement Rev 0 Date: 30.10.23