MINUTES OF MEETING

GROUP 9

ZIGURAT GLOBAL INSTITUTE OF TECHNOLOGY


PROJECT INFORMATION
Info Type Information Comment
Master _Global BIM
PDF Documents Final master thesis preparation for the first Delivery of Block 2
Management

A nine-story office building with a core tower, glass curtain


WeZIG Building ,
façade, and cantilever with a total gross area of
DWG Documents Located in Barcelona
approximately 2600 sqm. The 1st-floor level includes an extreme cantilever becoming the protection to the main
Spain
entrance and also generating a shading public area.

Revit Architecture, Structure , MEP in Revit of nine-story office building


Archicad Architecture, Structure , MEP in Archicad of nine-story office building
Pllannerly BEP Proposal for WeZig project
Trello Sprint boards related to the second delivery
BimSync Delivery of Block 2 and models uploaded

PROGRESS MEETING
Stage Main Topic Date Time Duration Venue
Review of the FMT second delivery and progress on the August 2nd 2022
Block 3- FD
third delivery 6:00 PM 7:30 PM ZOOM
ATTENDEES
Name Party Email Number
Mentor/
Jose Carlos Coya Zigurat josecarlos.coya@e-zigurat.com
Eskinder Fekade Lakew Group 9 eskifeke@gmail.com 0038762232953
Sneha Abhijit Laygude Kondhalkar Group 9 laygudesneha@gmail.cm 9860574427
Meme Hate Group 9 memehate02@yahoo.com 00355692165154
Avdija Hamzic Group 9 avdija.arh@gmail.com 0038762232953

APOLOGIES
Name Party Email / Reason for absence Number
All the partecipiant were present in online mode.

NEXT PROGRESS MEETING


Stage Main Topic Date Time Duration Venue
Block 3 ,Sprint planning,BEP update September 2022 7:00 PM 8:30 PM ZOOM
ATTENDEES
Name Party Email Number
To be deffine after communication in Slack channels
Stage Final Master Thesis -Block 3

Comment No. Responsible Description Status

BEP Proposal datas to be checked and added for the next


1 Group 9 TBC
delivery stage the datas to be edited:

-After choosing our bim uses agreed by all team members and
2 Group 9 after the confirmation with mentor. Is started the development of TBC
each of them updating dtas in the related platform, Plannerly,
Assigned to the team members to start working with the process
diagrams and IDMs of the Bim uses chosen

3 Group 9 -Edit of the status of the BEP sections , The BEP should answer TBC
the question of who as to do everything, when, how and where.
-BEP proposal will be update based on a chosen template by all
the team members, using as reference the EIR. Especially
4 Group 9 TBC
updating the naming convention for the metadata information for
the status of the documents.

-BimSync will be use as CDE, all the required models, native


format and Openbim format are uploaded and the missing ones
will be uploaded by the team members in the dedicated space.
5 Group 9 TBC
The models after the preconstruction phase will been updated in
our CDE. Completing also the necessary detail of classification
and level of information for this phase of design.

-Format and prepare the final models and 2D dwgs and pdfs. that
should be delivered as part of FMT project for this block, Using
6 Group 9 TBC
the authoring design software agreed during our first group set up.
Document shared in our CDE.

-Review Scrum planning for the work done in Trello for the Sprint
planning proposal for the design stage, the second delivery
7 Group 9 updating the dates of each sprint by changing the status of the TBC
each sprint. Updating the new board created for Block 3 with
respective information.

8 Group 9
-Prepare Sprint planning for all the tasks to be completed until the TBC
next delivery for the FMT, WeZig project.

-Start collecting information that will be part of our report that will
9 Group 9 be delivered for this block and use as part of the final report for TBC
the FMT. Prepare the report for the submission.

10 Group 9
-Concentrate our work also in developing the property sets of TBC
elements, necessary on the final report.

11 Group 9 -Prepare an agenda for next meeting. TBC

-Guides the team members more actively on the task they should
12 Mentor/Zigurat concentrate for the third Block Delivery of the Final Maser Thesis TBC
and think of e new way on managing the work for the next block.

NOTE
All concerned are requested to review the minutes and verify the points noted herein. If there is no comments received from any of the
concerned parties within 2 days of the issuance of this document, the points mentioned here shall be considered as true record of the meeting
held and as accepted by all attendees.