Professional Documents
Culture Documents
Music Recommendation
CODE: TEST PLAN
Date : February 26, 2023
Submitted by
Lam, Nguyen Viet Minh
Thi, Pham An
Thanh, Nguyen Tan
Huy, Chau Ngoc
Approved by Mentor
Man, Nguyen Duc PhD
PROJECT INFORMATION
Project acronym MR
Project Tittle Music Recommendation
Start Date 17 March 2023 End Date 20 May 2023
C2SE.23 TEAM 2
Test Plan Document | C2SE.23
Author(s) C2SE.23
Role C2SE.23-TestPlan
URL
REVISION HISTORY
Version Person(s) Date Description
C2SE.23 TEAM 3
Test Plan Document | C2SE.23
SIGNATURE
Document Approvals: The following signatures are required for approval of this
document.
Signature:
Mentor Man, Nguyen Duc, PhD
Date:
Signature:
Scrum master Lam, Nguyen Viet Minh
Date:
Signature:
Thi, Pham An
Date:
Team Signature:
Thanh, Nguyen Tan
member(s) Date:
Signature:
Huy, Chau Ngoc
Date:
C2SE.23 TEAM 4
Test Plan Document | C2SE.23
I. Introduction............................................................................................................7
1. Purpose................................................................................................................7
2. Scope....................................................................................................................7
3. Out of Scope:.......................................................................................................7
5. References...........................................................................................................8
1. Features to be Tested..........................................................................................8
3. Test Deliverables.................................................................................................9
1. Entry Criteria...................................................................................................17
2. Exit Criteria......................................................................................................17
C2SE.23 TEAM 5
Test Plan Document | C2SE.23
Table
Table 2: References 7
C2SE.23 TEAM 6
Test Plan Document | C2SE.23
I. Introduction
1. Purpose
The document provides an overview of the project includes the purpose and scope of
project.
Provide solution for business needs and give the overview of system architecture.
Provide overview about resources, schedule, solution and budget for the project.
2. Scope
This document provides a plan for each stage of software development process based
on Scrum process included: start time, end time and number of working days. This is
the general plan and will be updated with detail of the software development process
in the next document.
Proposal includes the introduction of solutions, determine the best way to develop
software that we make, the total estimated costs, payback period, break-even volume
for the project.
3. Out of Scope:
Security Testing
MR Music Recommendation
C2SE.23 TEAM 7
Test Plan Document | C2SE.23
5. References
https://scrum.org/resources/what-
1 Scrum Process
is-scrum
Proposal Document
Table 2: References
● Unit Testing
● Integration Testing
● System Testing
1. Features to be Tested
FE03: Register
FE04: Homepage
C2SE.23 TEAM 8
Test Plan Document | C2SE.23
FE10: Playlist
3. Test Deliverables
C2SE.23 TEAM 9
Test Plan Document | C2SE.23
Duration
No. Task Name Start Finish Resource
(Hour)
1 Sprint 1
1.3 Testing
C2SE.23 TEAM 10
Test Plan Document | C2SE.23
1.4 Re-Testing
C2SE.23 TEAM 11
Test Plan Document | C2SE.23
2 Sprint 2
C2SE.23 TEAM 12
Test Plan Document | C2SE.23
playlist”
2.3 Testing
Apr Huy
Test feature “Playlist” 2 Apr 14,2023
14,2023
2.4 Re-Testing
C2SE.23 TEAM 13
Test Plan Document | C2SE.23
3 Sprint 3
C2SE.23 TEAM 14
Test Plan Document | C2SE.23
3.3 Testing
C2SE.23 TEAM 15
Test Plan Document | C2SE.23
3.4 Re-Testing
C2SE.23 TEAM 16
Test Plan Document | C2SE.23
1. Entry Criteria
● All test hardware platforms must have been successfully installed, configured,
be available that will allow testers to operate the system and judge the correct
behavior.
● The test environment such as, lab, hardware, software, and system administration
2. Exit Criteria
● All high-risk areas have been fully tested, with only minor residual risks left
outstanding.
Roles Responsibilities
C2SE.23 TEAM 18
Test Plan Document | C2SE.23
Fix bugs.
Execute tests
Document defects
C2SE.23 TEAM 19