IT PROJECT CHARTER
1. General Project Information
* Project Name: Party Monsters Event Management System
Is this an Enterprise Project, i.e. does it have significant impact on 3 or more Yes
departments (Y/N)?
Document History
Version Date Author Reason for Change
* 1.0 * 09-07-18 * Moonlit System * Initial Draft
Solutions
* 1.1 * 10-18-18 * Moonlit System * Final Draft
Solutions
2. Stakeholders
1
Name Department Telephone E-mail
* Project Manager: Jia Matnog
* Tech Lead: Marco Jimenez
* Business Lead Qkuinzy Guingab
Alec Sison
Others: (e.g., those with a significant interest in this project)
Sponsor Party Monsters
3. Vendor Contacts
If a vendor is involved in development of this Charter, provide appropriate contact information
2
Name Company / Role Telephone E-mail
1
Include area code first (e.g., 919-555-1212).
2
Include area code first (e.g., 919-555-1212).
* Project Deliverables
The deliverables of these project is to produce a dyanamic website for the customers and administrator of the Party
Monsters.
* Project Success
1. Coordination of the development team.
2. Strictly following the given deadlines for specific tasks.
3. Listing all possible risks and giving them solutions.
4. The development team is highly skilled and specialized in their respective roles.
* Project Milestones
Proposed Date Milestone
September – October 2018 Planning for the System:
- Gather facts from Party Monsters
- Determining the system requirements.
October – December 2018 Designing the System:
- Use of different tools to identify or elaborate more the system
requirements
December 2018 – December 2019 Developing the System:
- Coding Phase
- Designing Phase
- Unit Testing
- Integration Phase
December 2019 Implementation and Evaluation of the System
December 2019 Deployment of the System
December 2019 - onwards Maintenance of the System
* Constraints
1. Lack of members and personnel.
2. Lack of time.
3. Shortage of Equipment
4. Limited data and information that is necessary for developing the system.
Funding Source Select one of the following: (Example: Operating Budget, Technology Fund, Grant, Other. (If Other,
please describe in the Notes section below.)
* Estimate of Implementation Cost Use Project Charter Budget Worksheet to calculate cost. If relevant, Include
both the cost of completing the project and the cost of not doing the project at all. If the project includes significant scope
options that will impact cost, include this information. For example, the cost of project with Option 1 only = $400,000 (range
$330,000 to $525,000). Cost of project with both Options 1 and 2 = $525,000 (range $430,000 to $650,000). Cost of not
doing the project = $120,000 per year in fines starting 2003 as a result of not meeting Federal Requirements X, Y, and Z.)
Create a Link_To_Project Charter Budget_Worksheet Implementation Cost in $U.S. (estimate with range, low to high):
$
Return-on-Investment (ROI) Data (include both Financial and non-Financial ROi estimates
Estimate time required of IT Department Staff (List each role and the number of hours required)
Database Administrator Throughout the designing and analyzation of the database for
the system (5 months)
Graphic Artist Throughout the developing phase for the front-end of the
system (3 months)
Tester For the integration and unit testing of the system (1 month)
8. Sign-off
Name Signature Date
(MM/DD/YYYY)
Project Manager Marco Robby Jimenez
Technical Writer Jia Claire Matnog
Database Administrator Qkuinzy Inochzim Guingab
Software Developer Alec Sison