You are on page 1of 11

Solar Energy Vol. 62, No. 1, pp.

51–61, 1998
© 1997 Elsevier Science Ltd
PII: S0038-092X(97)00075-3 All rights reserved. Printed in Great Britain
0038-092X/98 $19.00+0.00

ECONOMIC EVALUATION OF SOLAR-ONLY AND HYBRID POWER


TOWERS USING MOLTEN-SALT TECHNOLOGY
GREGORY J. KOLB
Solar Thermal Technology Department, Sandia National Laboratories, MS 0703, Albuquerque,
NM 87185-5800, U.S.A.

Received 7 January 1997; revised version accepted 27 June 1997

Communicated by LORIN VANT-HULL

Abstract—Several hybrid and solar-only configurations for molten-salt power towers were evaluated with
a simple economic model, appropriate for screening analysis. The solar-specific aspects of these plants
were highlighted. In general, hybrid power towers were shown to be economically superior to solar-only
plants with the same field size. Furthermore, the power-booster hybrid approach was generally preferred
over the fuel-saver hybrid approach. Using today’s power tower technology, economic viability for the
solar power-boost occurs at fuel costs in the neighborhood of $8.90 to $15/MW h ($2.60 to $4.40/MBtu,
low heating value) depending on whether coal-based or gas-turbine-based technology is being offset.
These fuel prices exist today in certain areas of the world (e.g. India). The cost of CO avoidance was
2
also calculated for solar cases in which the fossil fuel cost was too low for solar to be economically viable.
The avoidance costs are competitive with other proposed methods of removing CO from fossil-fired
2
power plants and appear to be within the range of interest (<$29/mt) to environmental protection
organizations such as the Global Environmental Facility. © 1997 Elsevier Science Ltd.

1. INTRODUCTION properties, provides an efficient and low-cost


thermal storage medium and produces steam
The solar power tower concept of current inter-
temperatures that are compatible with high-
est in the United States is characterized by a
tower-mounted receiver that is cooled by molten efficiency Rankine-cycle turbines. Cost effective
salt. The receiver is heated by reflected energy storage allows the power plant to achieve high
from a field of sun-tracking mirrors, called annual capacity factors (>60%) and to dispatch
heliostats. Figure 1 shows a flow schematic of electricity to the grid when needed, even during
this system. Molten salt at 288°C (550°F ) is cloudy weather or at night.
pumped out of a ‘‘cold’’ storage tank to the In 1996, an industry/government consortium
receiver where it is heated to 565°C (1050°F ) led by Southern California Edison, initiated
and delivered to a ‘‘hot’’ storage tank. The hot startup of the Solar Two power plant (Fig. 2).
salt is then extracted for generation of 538°C The purpose of this 10 MW plant is to demon-
e
(1000°F ) steam in the steam generator. The strate the practicality of molten-salt power
steam powers the turbine to produce electricity. tower technology during a 3-year operating
Molten salt was chosen as the preferred heat- period (Prairie et al., 1996; Chavez et al., 1995).
transfer fluid because it has good heat-transfer Assuming success of Solar Two, it is currently

Fig. 1. Molten-salt power tower in a solar-only configuration.

51
52 G. J. Kolb

Fig. 2. The Solar Two power plant in operation. A fraction of heliostats are focused at their standby aimpoints, the rest
are heating salt in the receiver.

envisaged that the initial commercial-scale 200 to 400 MW range would likely become the
e
plants will be deployed within the U.S. Solar preferred method of technology deployment.
Enterprise Zone (southern Nevada) and within In this paper, the economic potential of vari-
developing nations such as India, Egypt and ous hybrid configurations that have been pro-
Mexico. posed for molten-salt power towers will be
The first commercial plants will be signifi- examined and compared to solar-only plants.
cantly larger than Solar Two, capable of pro- The analysis will highlight the solar-specific
ducing up to 100 MW . A large monetary aspects of these plants and will not blend the
e
investment will be required to build these plants costs of solar energy with fossil energy. When
and, since the power tower is a new generation costs are blended, identification of the preferred
technology, the financial risk will be perceived economic choice becomes difficult. Hybrid
to be high by potential investors. They will designs that are compatible with the needs of
require a high rate of return to balance the risk the huge international electricity market and
which could drive up the cost of solar power provide the most environmental benefits will be
beyond affordability. To reduce risk, the U.S. identified.
solar thermal community is currently promoting
a commercialization strategy in which the first
2. MARKET NEEDS FOR POWER TOWERS
power towers are hybridized with fossil fuels.
By designing a hybrid plant in which 10 to 30% The power towers analyzed herein are
of the annual electricity is derived from solar assumed to be exposed to insolation conditions
energy, financial risk is minimized because the similar to the good solar regions found in
majority of the electricity is derived from proven Rajasthan, India, or in Egypt. Marketing
fossil technology and steady payments for studies ( Utility Data Institute, 1994) suggest
power sales are assured. Furthermore, as will that for the foreseeable future, most new power
be shown in this paper, hybridization also sig- plants will be built within developing nations
nificantly reduces the cost of producing solar like India and Egypt. These countries were also
power. selected because they represent two distinctly
With today’s inexpensive fossil fuel, it is different power markets.
difficult for grid-connected solar plants to eco- Rajasthan is currently experiencing power
nomically compete with fossil plants; hybridiza- shortages at all times of the day and is in dire
tion will help close the gap. Eventually, as fossil need of base-load power. Rajasthan does not
fuel prices rise and more manufacturing experi- have access to a natural-gas-pipeline network
ence is gained resulting in a cost reduction for and future power plants are proposed to be
solar equipment, large solar-only plants in the fueled by coal, lignite and petroleum products.
Economic evaluation of solar-only and hybrid power towers using molten-salt technology 53

In many instances, these fuels will be costly is reduced when solar is available and electricity
because they will be brought to the plant site output is constant. In a Rankine-cycle applica-
from great distances by train or truck. tion, the solar steam generator can be sized to
Egypt, on the other hand, currently does not provide the entire input to the steam turbine or
have a power shortage and has an extensive a fractional amount. However, when hybridiz-
pipeline network. New natural-gas-fired power ing with a base-load fossil plant, it is perhaps
plants are under construction to meet the future preferred to contribute a fractional amount of
power needs of the country. Furthermore, heat from solar. This keeps the fossil boiler hot
energy resources are so prevalent (gas, solar, all the time and prevents daily startup losses
wind ) that Egypt wants to be an electricity and thermal cycles. In a combined-cycle applica-
exporter to the emerging international electricity tion, solar heat is added by preheating the inlet
grid. A significant demand for peak power air to the gas turbine via a salt-to-air heat
occurs after sunset in Egypt which is currently exchanger. Since the molten-salt operating tem-
being met with the Aswan hydroelectric project. perature is limited to less than 600°C and the
However, the need for peaking power is increas- inlet temperatures required by modern gas tur-
ing beyond the capabilities of Aswan and new bines are approaching 1400°C, the maximum
thermal plants must be built in the near future amount of fuel savings that is possible (using
to meet the evening peak (Geyer, 1996). an intercooled turbine similar to the
Because of the different needs for power and Westinghouse WR-21) is approximately 27%.
the variety of fossil fuels available, the hybrid In a ‘‘power booster’’ plant, fuel input to
power towers analyzed herein will provide peak- the plant is constant and additional electricity
ing power (i.e. low capacity factor) and near- is produced when solar heat is available.
base-load power (i.e. high capacity factor) and Additional electricity is produced by oversizing
will be interfaced with fossil plants that burn the steam turbine, contained within a pure
natural gas or coal. In addition, since fuel prices Rankine cycle or the bottoming portion of a
are expected to be high in certain regions of the combined cycle, so that it can operate on full
world, concepts with the primary purpose of fossil and solar energy when solar is available.
saving fuel will also be examined. And finally, Studies of this concept have typically oversized
because certain organizations (Anderson and the steam turbine from 25 to 50% beyond what
Ahmed, 1995; BMZ, 1992; World Bank, 1995) the turbine can produce in the fuel-only mode.
are willing to pay a premium for developing Oversizing beyond this range is not recom-
technologies that slow global warming, the cost- mended because the thermal-to-electric conver-
effectiveness of each of these solar concepts in sion efficiency will degrade when operating in
offsetting CO will be assessed. the fuel-only mode.
2
An advantage of a fuel saver over a power
booster plant is that a given amount of solar
3. HYBRID CONCEPTS
energy can be added to the grid for less cost
From a functional point of view, there are because additional steam turbine capacity does
two basic approaches to hybridizing a solar not have to be built. In addition, when perform-
power tower to a base-load fossil plant: fuel ing the fuel saving at the entrance to the gas
saver and power booster. The daily power pro- turbine within a combined cycle (Bechtel, 1979;
file for each concept is depicted in Fig. 3. Bohn et al., 1995), the solar energy is converted
In a ‘‘fuel-saver’’ plant, fuel input to the plant at a higher efficiency than when adding a power
boost to a pure Rankine cycle (e.g. 53% vs 40%).
The primary advantage of the power booster
is that the economic value of the solar energy
to the utility grid is greater than the fuel saver.
Thus, even though the cost of adding solar
energy to the grid is greater for the booster, the
increased value of the solar energy more than
compensates for the increased cost. In the next
Fig. 3. Daily power profile for hybrid power tower plants. section it will be shown that the increased value
If storage were added to the fuel saver ( left), the solar contri- will cause the power booster to be, in most
bution would look rectangular. In the power-booster profile
(right), it can be seen that storage is used to meet an cases, the preferred economic choice.
afternoon and early evening need. Simplified diagrams of hybrid power tower
54 G. J. Kolb

or coal-fired Rankine cycle that produces


350 MW when operating in a fossil-only mode.
e
Power boosters with low and high capacity
factors (CF ) for the solar portion (i.e. the
rectangle marked ‘‘solar’’ in Fig. 3) were devel-
oped to meet the different market needs. In all
cases, the base-load portion of the hybrid plant
was assumed to have an 80% CF.
Table 2 provides the design characteristics,
costs and annual performances of the solar-
only plants and the solar portion of the hybrid
(a)
plants. The assumed fossil competition for each
of the solar cases is also listed.
A few notes are in order regarding the data
presented in Table 2:
(1) Heliostats are assumed to cost slightly
under $100/m2. This value was obtained by
reducing a recent cost estimate (given a
production level of 2500 per year (Science
Applications, 1996)) for 150 m2 glass helio-
stats by 15% to account for construction in
a developing nation (Lewis, 1996). The
remaining costs were derived from previous
studies (Becker and Klimas, 1993).
Performance estimates were developed with
(b) the SOLERGY computer code (Stoddard
et al., 1987). Insolation levels were assumed
to be equivalent to the Mojave Desert.
Insolation similar to the Mojave can be
found in the desert regions throughout the
world.
(2) Fuel savers are shown to cost less than
power boosters with the same field/receiver
because a solar-specific increment to the
turbine does not have to be purchased. This
can be seen by comparing the installed cost
listed in column 1 to column 2 and column
3 to column 4.
(3) By comparing columns 1 and 2, it can be
seen that for a given solar field size, more
thermal storage is required for the
combined-cycle fuel saver than for the
(c)
combined-cycle power booster. This is be-
cause less peak solar thermal power can
Fig. 4. Molten-salt power towers in several hybrid configu- be accepted by the power block of the
rations. (a) Combined-cycle fuel saver; (b) combined-cycle
power booster; (c) coal fuel saver or power booster. fuel saver than the power booster (i.e.
171 MW vs 260 MW ) and thus more solar
t t
energy must be stored for later use.
plants in fuel saver and power booster configu- (4) Since a fuel saver reduces the fuel-heat
rations are depicted in Fig. 4. In order to com- input to the power block, levelized energy
pare the economics of the systems, a consistent costs (LEC ) are expressed per unit of heat.
set of conceptual designs were developed for Since a power booster adds additional
the hybrid power plants. From Table 1 it can electricity to the grid, LECs are expressed
be seen that in each design a solar field was per unit of electricity.
interfaced with a base-loaded combined cycle (5) An advanced solar-only case is given to
Economic evaluation of solar-only and hybrid power towers using molten-salt technology 55

Table 1. Characteristics of hybrid power plants

Gas turbine Steam turbine Total plant Annual solar


Hybrid plant description power† (MW ) power (MW ) power (MW ) fraction (%)
e e e
100 MW of Lo CF power boost to a N/A 450 450 12.9
base-loaded 350 MW coal plant
100 MW of Hi CF power boost to a N/A 450 450 18.8
base-loaded 350 MW coal plant
100 MW of Lo CF power boost to a 235 215 450 12.3
base-loaded 350 MW CC plant
100 MW of Hi CF power boost to a 235 215 450 18.1
base-loaded 350 MW CC plant
Fuel saver for a 350 MW 235 115 350 19.8
base-loaded CC plant
Fuel saver for a 350 MW N/A 350 350 23.3
base-loaded coal plant

†Gas turbine is assumed to be similar to a Westinghouse 701F gas turbine with an efficiency of 36.7% (heat rate of
9280 Btu/kW h), ( Turbine Systems Engineering Incorporated, 1996). For the combined-cycle fuel saver, an intercooler
is assumed to be installed (not available today for the 701F ).

illustrate what the next step in technology (1) Identification of non-solar competition.
development may look like beyond (2) Calculation of levelized solar-energy value.
hybridization. (3) Calculation of levelized solar-energy cost.
(6) To allow a comparison with photovoltaic (4) Determination of economic viability and
solar systems, installed costs are also CO avoidance cost.
expressed in units of $/watt (peak). To 2
Each of these steps is discussed in the ensuing
convert to peak values, the effect of thermal subsections, followed by an example calculation
storage must be removed. A first-order that displays the entire method. In the final
estimate can be obtained by dividing subsection, the results of the study are
installed costs by the solar multiple, presented.
e.g. for the low CF power booster
$1.57/W=$2.82×108/1×108 W/1.8. 4.1. Identification of non-solar competition
As stated earlier, hybridization significantly In order to evaluate the economic viability of
reduces the cost of producing solar power rela- the solar plants, one must first identify the non-
tive to a solar-only design. Table 2 indicates a
solar competition. Since the primary subject of
20 to 25% reduction. This can be seen by
this paper is hybrid solar plants, fossil fuel is
comparing the levelized energy costs in column
assumed to be available for delivery at the
2 to column 5 and column 3 to column 6. There
site and thus a comparison with coal-fired
are 3 reasons for this reduction: (1) reduced
and natural-gas-fired plants will be made.
capital costs for the 100 MW solar turbine
e Characteristics of the fossil technologies the
because only an increment on the base-load
fossil turbine must be purchased, (2) reduced solar plants are assumed to offset are listed at
O and M costs because only an increment the bottom of Table 2 and described more fully
beyond the base-load O and M staff and materi- in Table 3.
als must be used to maintain the solar-specific For market conditions requiring a high CF,
part of the plant, and (3) the solar plant pro- it is assumed that the technologies being offset
duces more electricity because the turbine is hot are either a pulverized coal Rankine cycle or a
all the time and daily startup losses incurred in natural-gas combined cycle. Rather than con-
a solar-only plant are avoided. structing a hybrid plant by adding a 100 MW
e
The economic viability of the solar plants solar increment, the lowest-cost fossil alterna-
presented in Table 2 will be assessed in the tive would be to add a 100 MW fossil increment
next section. to the plant. The incremental capital and O and
M costs are listed in Table 3; capital costs
associated with increasing the fossil plants from
4. ECONOMIC EVALUATION OF HYBRID
350 to 450 MW were derived from information
AND SOLAR-ONLY CONCEPTS e
presented in Fig. 5 and incremental O and M
The method used to evaluate the economics costs were calculated from EPRI (1993).
of the solar plants involved the 4 steps listed For market conditions requiring a low CF, it
below: is assumed that a stand-alone 100 MW gas-
e
56 G. J. Kolb

Table 2. Characteristics and costs of solar increment

Lo CF, Hi CF,
CC or CC or
coal coal
CC fuel- power- power- Coal fuel- Lo CF Hi CF Advanced
saver booster booster saver solar solar solar
hybrid hybrid hybrid hybrid only only only

Solar characteristics
Collector size (m2) 883000 883000 1350000 1350000 883000 1350000 2477000
Receiver power (MW ) 470 470 715 715 470 715 1400
t
Process power (MW ) 171 260 260 260 260 260 520
t
Solar multiple† 2.7 1.8 2.7 2.7 1.8 2.7 2.7
Turbine power (MW ) – 100 100 – 100 100 200
e
Storage size (h) 14 6 13 13 6 13 13
Storage size (MW h ) 2400 1600 3400 3400 1600 3400 6800
t
Annual energy (GW h) 914 th 362 el‡ 569 el‡ 1472 th 340 el 535 el 1100 el
Parasitics (GW h ) 17 – – 27 – – –
e
Solar-specific costs ($M )
Site improvements 6 6 8 8 6 8 10
Heliostats 87 87 132 132 87 132 241
Receiver/tower 26 26 35 35 26 35 50
Thermal storage 32 24 44 44 24 44 60
Steam generator 0 11 11 11 11 11 17
Air heat exchanger 11 0 0 0 0 0 0
Master control 1 1 1 1 3 3 3
Turbine 0 27 27 0 54 54 80
Total direct costs 163 182 258 231 211 287 461
Indirect multiplier 1.55 1.55 1.55 1.55 1.55 1.55 1.37
Installed capital costs 253 282 400 358 327 445 632
Installed cost ($/W ) 1.57 1.48 1.82 1.65 1.17
peak
1st Year O and M costs 2.3 2.3 3 3 4.6 5.6 6
30-yr Lev. O and M costs 3.5 3.5 4.5 4.5 6.9 8.4 9
Levelized energy cost§
Fuel savers $/MW h ($/MBtu)
Capital 27.30 (8.0) 24.22 (7.1)
O and M 3.75 (1.1) 3.07 (0.9)
Parasitics 1.35 (0.4) 1.35 (0.4)
Total 32.40 (9.5) 28.64 (8.4)
Power boosters and solar only ($/kW h )
e
Capital 0.078 0.070 0.097 0.082 0.057
O and M 0.009 0.008 0.020 0.016 0.008
Total 0.087 0.078 0.117 0.098 0.065
Fossil competition Natural Gas Increment Coal Gas Increment Combined-
gas turbine to CC or fuel turbine to CC or cycle
fuel plant coal plant plant coal plant plant

†Solar multiple is the ratio of the above 2 rows. Excess energy produced by the receiver is sent to the thermal storage tank
for later use.
‡The annual energies shown are applicable to a power boost on a coal plant. These energies should be reduced by 5% for
a power boost on a combined-cycle plant due to the lower Rankine efficiency.
§This is a 30-yr ‘‘current’’ dollar estimate which includes the effects of inflation. See paper for explanation of economic
assumptions.

turbine plant will be offset by the 100 MW 4.2. Calculation of levelized solar-energy value
e
solar power boost to the coal or combined-cycle The next step in assessing economic viability
plant. The installed cost listed in Table 3 was is to determine the value (i.e. the price to be
derived by multiplying the manufacturers list paid) for the solar energy produced. This should
price for a 100 MW gas turbine (Siemens V84.2) be equal to the avoided cost of producing the
by the indirects/installation factor presented for equivalent energy with the fossil competition
gas turbines ( EPRI, 1993). described above. Avoided costs are comprised
After market entry is complete using the of 3 components: capital construction, O and
hybrid approach, large solar-only plants may M, and fuel expense.
be preferred. When this occurs, stand-alone The avoided cost of capital is typically
combined-cycle plants with ratings of 200 MW expressed as the annualized payment needed to
or more could be offset. This is the reason for amortize the construction loan during a period
including the last column in Table 3. that is equal to the life of the plant. On a
Economic evaluation of solar-only and hybrid power towers using molten-salt technology 57

Table 3. Characteristics of fossil technologies being offset by solar power towers

Stand-alone
Incremental Incremental combined
pulverized coal combined cycle Stand-alone cycle
with FGD natural gas gas turbine natural gas

Type and size of 100 MW 100 MW 100 MW 200 MW


fossil addition increment increment stand-alone stand-alone
between between power plant power plant
350 and 450 MW 350 and 450 MW
Installed cost ($/kW ) 1140 290 410 800
e
1st yr O and M cost ($/kW h ) 0.0052 0.0025 0.0040 0.0030
e
30-yr Lev. O and M cost 0.0078 0.0038 0.0060 0.0045
Fossil plant net efficiency 35 53 33 53
(Annual, LHV†) (%)
Capacity factor (%) 80 80 40 80
CO emissions (g/kW h ) 909 345 554 345
2 e
Capacity value ($/kW -yr)‡ 183 46 66 128
e
O and M value ($/kW h )‡ 0.0078 0.0038 0.006 0.0045
e
Fuel value ($/kW h )‡given
e
1st yr fuel cost (LHV )
3.4$/MW h (1$/MBtu) 0.0148 – – –
6.8$/MW h (2$/MBtu) 0.0296 0.0193 0.0310 0.0193
10.2$/MW h (3$/MBtu) 0.0444 0.0290 0.0465 0.0290
13.6$/MW h (4$/MBtu) 0.0592 0.0386 0.0620 0.0386
17.1$/MW h (5$/MBtu) – 0.0483 0.0775 0.0483
20.5$/MW h (6$/MBtu) – 0.0579 0.0931 0.0579

†LHV – low heating value for fuel.


‡These are 30-year levelized values. See paper for explanation of economic assumptions.

economic assumptions‡: 30-yr plant life, 10%


discount rate, 4% annual inflation, 1% annual
property insurance, 40% tax bracket, 15-yr
depreciation life, 1% annual property tax.
The capacity values listed in Table 3 were
calculated with eqn (1) and a 16% fixed
charge rate.
The avoided cost of O and M, on a 30-yr
levelized basis, is equal to 1.5 times the O and
M cost for the first year of plant operation. The
Fig. 5. Installed capital costs of coal-fired (EPRI, 1993), factor 1.5 converts 30 years of O and M costs,
combined-cycle (Spencer Management Associates, 1994 and that increase at the inflation rate, to the equiva-
extrapolation by author) and gas-turbine ( EPRI, 1993; lent levelized cost given a 10% discount rate.
Turbine Systems Engineering Incorporated, 1996) power
plants. The O and M costs (values) listed in Table 3
have been divided by the annual electricity
produced by the fossil plant and thus have units
of $/kW h . (The electricity produced is defined
levelized basis, this payment is e
by the capacity factors listed in the table.)
Annual capital costs=fixed charge rate The avoided cost of fuel, on a 30-yr levelized
×installed cost. (1) basis, is also equal to 1.5 times the first-year
fuel cost. Thus fuel is assumed to escalate at
Since fixed charge rate (also called capital the inflation rate and the discount rate is
carrying charge) represents the fraction of capi-
tal paid per year and installed cost has units of
‡These economic assumptions do not apply to plants built
$/kW, the levelized annual capital costs (also in developing nations like India or Egypt. The evalua-
called capacity value) has units of $/kW-yr. The tion of the appropriate economic factors for these coun-
fixed charge rate for an investor-owned utility tries is beyond the scope of this analysis. In addition,
the economic model employed in this paper is admittedly
within the US is approximately 16% and is simple and is only appropriate for the screening type of
calculated (Doane, 1976) given the following analysis contained herein.
58 G. J. Kolb

assumed to be 10%. Annual fuel costs (values) plant is a power booster or fuel saver, respec-
listed in Table 3 are a function of the plant fuel- tively. Electric parasitics required to run the
conversion efficiencies listed in the table and solar equipment have been subtracted from
have also been divided by the annual electricity. electric energy produced by the booster.
Since fuel cost is highly uncertain, fuel values However, because the product of the fuel saver
are given for a variety of first-year fuel costs. is thermal energy, electric parasitics have been
The next step in determining economic via- listed separately for this case and treated as an
bility of the solar plants is to assign the appro- O and M expense.
priate value to the energy that the solar plants The economic assumptions used to calculate
add to the grid. For a fuel saver plant it is the fixed charge rate and the levelized energy
logical to assign only the avoided cost of fuel costs for the solar cases were the same as
that is saved. For a power booster plant, the described for the fossil competition except for
value of the solar energy is increased because it the following taxation parameters: 5-yr depreci-
not only offsets fuel but also the cost of building ation life, 0% annual property tax, 20% invest-
new power plant capacity either onsite or some- ment tax credit.
where else on the utility grid and the O and M Recent studies indicate that if solar plants
associated with that new capacity. Thus, the are taxed at the same rate as fossil plants, the
value of energy produced by the power booster solar plant will pay much more tax per kilowatt
is equivalent to the full avoided cost. However, hour during its lifetime. Selection of the above
to realize this full value the power boost must taxation parameters have been shown to be one
meet a dispatchability requirement that is method of achieving tax equity between solar
roughly equivalent to the fossil plant it is offset- and fossil generated electricity for plants built
ting. The dispatchability requirement for peak- in California, U.S.A. (Nathan and Chapman,
ing power plants in the Mojave Desert is that 1994). Achieving tax equity causes a very sig-
they demonstrate greater than an 80% CF from nificant reduction in the fixed charge rate
noon to 6 P.M., Monday through Friday, from (reduced from 16 to 10%) and levelized energy
June through September. Studies have shown cost for solar plants. In this economic analysis,
that a molten-salt power tower with 6 hours of it is assumed tax equity has been achieved and
thermal storage will meet this dispatchability thus a fixed charge rate of 10% was used to
requirement (Chiang, 1987; PG and E, 1988). calculate the solar LECs listed in Table 2.
It should be emphasized that the dispatchability
requirement is totally dependent on the local 4.4. Determination of economic viability and
power needs and must be investigated on a case CO avoidance cost (example calculation)
2
by case basis. For example, because of their As stated previously, economic viability
evening peak, Egypt might require the plant to occurs if value exceeds costs. If cost of produc-
demonstrate a high availability during the 4 ing solar energy exceeds the value, then we must
hours after sunset. It is assumed here that the justify why we are willing to pay more for solar
power boosters and solar-only plants meet the power. Here, it was assumed that we are willing
dispatchability requirement. to pay more for power that produces less CO
2
and quantify how much we are paying to do
4.3. Calculation of levelized solar-energy cost this. An example calculation that demonstrates
If the value of the solar energy is greater than the analysis methodology is presented next.
the cost of producing it, economic viability is 4.4.1. Define case. Assess the economic via-
achieved. The levelized energy costs for the bility of 100 MW (Hi CF ) power boost to a
solar increments and solar-only plants presented 350 MW base-loaded coal plant. The power
in Table 2 were calculated with the following boost produces 569 GW h /yr (column 3,
e
equation: Table 2). The coal is assumed to cost
LEC=(annualized capital costs+O and M $6.80/MW h ($2/MBtu) in the first year and
costs)/(annual energy). escalate at the inflation rate.
As stated previously, annualized capital cost 4.4.2. Determine value. The high CF power
is the product of the fixed charge rate times the booster is assumed to meet the dispatchability
installed capital costs. The capital costs, 30-yr requirement and thus qualify for the capacity,
levelized O and M costs, and annual energy are O and M, and fuel values listed in column 1 of
all listed in Table 2. Annual energy is either Table 3. The annual levelized value is calculated
electric or thermal, depending on whether the to be:
Economic evaluation of solar-only and hybrid power towers using molten-salt technology 59

Capacity value=$183/kW-yr×100,000 kW= (1) Cases that offset coal (A, B, C ) have a
18.3$M/yr lower CO avoidance cost and have a
2
O and M value=$0.0078/kW h×569E6 different slope than those that offset gas
kW h=4.4$M/yr (D–I ). There are 2 reasons for this: (1)
Fuel value=$0.0296/kW h×569E6 kW h= much higher amounts of CO are produced
2
16.8$M/yr by burning coal than natural gas, and (2)
Total levelized value=39.6$M/yr. the value of the solar energy is greater
4.4.3. Determine cost. From column 3 of because the avoided cost of offsetting coal
Table 2, the LEC is $0.078/kW h. The annual plants is higher than offsetting gas-fired
levelized cost is thus plants (i.e. the capacity and O and M values
Total levelized cost=$0.078/kW h×569E6 listed in Table 3 are higher for coal ).
kW h=44.4$M/yr. (2) The economics of case A (coal power
4.4.4. Determine economic viability and CO booster) and case B (solar-only that offsets
2
avoidance cost. It can be seen that levelized a coal increment) are superior to case C
costs exceed levelized payments by 4.8$M/yr. (coal fuel saver). This is because in the
However, the solar boost avoids 5.17E5 mt former cases the value of solar energy is
(5.62E5 U.S. ton) of CO /yr: greater and equal to the full avoided cost,
2
569E6 kW h/yr×909 g/kW h=5.2E8 kg/yr whereas the fuel saver only receives the
=5.17E5 mt/yr. value of the fuel.
The levelized CO avoidance cost is thus (3) Case E (combined-cycle power booster that
2
4.8$M/5.17E5 mt=$9.28/mt ($8.54/U.S. ton). offsets a gas-turbine plant), case F (solar-
4.5. Results of evaluation only that offsets a gas-turbine plant) and
case G (combined-cycle fuel saver), all have
Similar calculations to those presented in the same field size but the economics of
Section 4.4 were performed for each of the case E are superior to cases F and G, which
hybrid and solar-only cases over the full range are shown to be approximately equal. Case
of expected fuel costs. The results of these
E beats case F because the LEC of case E
calculations are plotted in Fig. 6 (the asterisk
is lower than F, yet case E receives about
represents the example calculation presented in
the same value. Case E beats case G because
Section 4.4). When the avoidance cost is zero,
of the higher avoided cost payment that is
the solar plants achieve economically viability.
received for the energy produced.
Major insights are annotated below:
(4) The economics of case G (combined-cycle
fuel saver) is shown to be superior to case
H (combined-cycle power booster that off-
sets a combined-cycle increment) and case
I (solar-only plant that offsets a combined-
cycle increment). The capacity and O and
M values ($46/kW yr and $0.0038/kW h in
Table 3) received by cases H and I are too
low to compensate for the increased capital
costs of these systems.
(5) The coal fuel saver (C ) achieves economic
viability at a slightly lower fuel cost than
the combined-cycle fuel saver (G), i.e. $20.5
vs $22.2/MW h ($6.00 vs $6.50/MBtu). The
only reason this occurs is because case C
has a lower LEC due its larger solar field
and improved economy of scale.
(6) Because of the very high fuel costs required,
the economics of offsetting a combined-
cycle increment with current-generation
power towers are unfavorable (cases H and
Fig. 6. CO avoidance cost for solar options. Economic via- I ). However, the advanced solar-only case
2
bility occurs when CO avoidance cost is zero.
2
(D) shows some hope. Besides using
60 G. J. Kolb

advanced technology, case D is improved Environmental Facility which is providing


because the solar plant is larger (200 MW financial support to technologies that reduce
vs 100 MW ) and is capable of offsetting an global warming. The CO avoidance costs also
2
entire combined-cycle plant rather than just appear to be competitive with other proposed
an increment. This significantly increases methods of removing CO from fossil-fired
2
the capacity and O and M value for the power plants and other industrial processes
electricity produced. (Farla et al., 1995).

REFERENCES
5. CONCLUSIONS Anderson D. and Ahmed K. (1995) The Case for Solar
Energy Investments. World Bank Technical Paper
This paper has examined the economic poten- Number 279, ISBN 0-8213-3196-5. World Bank, Wash-
tial of various hybrid and solar-only configura- ington, DC.
tions for molten-salt power towers. The focus Bechtel National Incorporated (1979) Combined Cycle Solar
Central Receiver Hybrid Power System. DOE/ET/
of the analysis was the solar-specific aspects of 21050-1, Washington, DC.
these plants. The value of the solar energy Becker M. and Klimas P. (Eds) (1993) Second Generation
produced was not blended with fossil energy so Central Receiver Technologies. ISBN 3-7880-7482-5,
Verlag C.F. Muller Karlsruhe, Germany.
that clear economic comparisons could be BMZ – Federal Ministry for Economic Co-operation and
made. Development (1992) Concept for Development
In general, hybrid power towers were shown Co-operation with Asia. Technical paper, contact Dr
Lotz, Bonn, Germany.
to be economically superior to solar-only plants Bohn M., Williams T. and Price H. (1995) Combined cycle
with the same field size. Furthermore, the power tower. In Solar Engineering 1995, ASME Interna-
power-booster hybrid approach was generally tional Solar Energy Conference, Stine W. et al. ( Eds),
Maui, Hawaii, pp. 597–606.
preferred over the fuel-saver hybrid approach Chavez J., Reilly H., Kolb G., Gould B., Zavoico A. and
because the economic value assigned to the Sutherland P. (1995) The Solar Two Power Tower Pro-
booster is the sum of ‘‘capacity, O and M, and ject: a 10 MW Power Plant. IECEC Paper Number
e
RE-357, American Society of Mechanical Engineers,
fuel’’, rather than just ‘‘fuel’’. In order for the New York, NY.
booster to qualify for these additional pay- Chiang C. J. (1987) SUNBURN: A Computer Code for
ments, the dispatchability requirement estab- Evaluating the Economic Viability of Hybrid Solar
Central Receiver Electric Power Plants. SAND86-2165,
lished by the electric utility which is purchasing Sandia National Laboratories, Albuquerque, NM.
the power must be met. If the dispatchability Doane J. W. (1976) The Cost of Energy from Utility Owned
requirement cannot be met, a different conclu- Solar Electric Systems. ERDA/JPL 1012-76/3, Washing-
ton, DC.
sion regarding the preferred system might be EPRI – Electric Power Research Institute (1993) TAG@ –
appropriate. Technical Assistance Guide Volume 1: Electricity Supply
The hybrid cases showing the most promising – 1993. TR-102276-Vol. 1, Palo Alto, CA.
Farla J., Hendriks C. and Blok K. (1995) Carbon dioxide
economic potential are a power boost to a coal recovery from industrial processes. In Proceedings of
plant and a power boost to a combined-cycle Conference on Climate Change, ISSN/ISBN: 0165-0009,
plant. However, in order for the latter case to 29, number 4, Netherlands, pp. 439–461.
Geyer M. (1996) IEA SolarPACES START Mission to
be attractive, the solar boost must offset the Egypt. Deutsche Forschungsanstalt fur Luft-und Raum-
construction of a new gas-turbine plant. Given fahrt (DLR), Cologne, Germany.
the economic assumptions presented in this Lewis E. (1996) India’s refining prospects linked to eco-
nomic growth (1996) June 10, 1996, Oil and Gas Journal.
paper, economic viability for the coal boost Nathan N. H. and Chapman R. A. (1994) Tax equity –
occurs at a fuel cost ( low heating value) of solar electric power plants. Report prepared for Alec
$8.90/MW h ($2.60/MBtu). Viability for the Jenkins, California Energy Commission, Sacramento,
CA.
combined-cycle boost occurs at a fuel cost of PG and E – Pacific Gas and Electric Company (1988) Solar
$15/MW h ($4.40/MBtu). These fuel prices exist central receiver technology advancement for electric uti-
today in certain areas of the world (e.g. lity applications, phase 1. Topical Report, Report
No. 007.2-88.2, San Francisco, CA.
Rajasthan, India). Prairie M. J., Pacheco J. and Kolb G. (1996) Solar central
The cost of CO avoidance was also calcu- receiver technology: the Solar Two project. AIChE Sym-
2 posium Series 310, 92, 229–233.
lated for solar cases in which the fuel cost was
Science Applications International Corporation (1996)
too low for solar to be economically viable. Heliostat manufacturing for near-term markets, phase 1
Solar cases that offset coal plants were shown summary report. Energy Products Division, Golden,
to have the lowest CO avoidance cost. The CO.
2 Spencer Management Associates (1994) Integrated Solar
avoidance costs appear to be within the Combined Cycle Systems (ISCCS) Using Solar Parabolic
range of interest (<$29/mt) to the Global Trough Technology. Diablo, CA.
Economic evaluation of solar-only and hybrid power towers using molten-salt technology 61

Stoddard M. C., Faas S. E., Chiang J. A. and Dirks J. A. wide website http://www.gas-turbines.com/TRADER/
(1987) SOLERGY – A Computer Code for Calculating Manprice.htm.
the Annual Energy from Central Receiver Power Plants. Utility Data Institute (1994) World Directory of New
SAND86-8060, Sandia National Laboratories, Liver- Electric Power Plants. UDI-2460-94, Washington, DC.
more, CA. World Bank (1995) The Solar Initiative. IEN publications
Turbine Systems Engineering Incorporated (1996) World- clerk, G5-100, Washington, DC.

You might also like