Professional Documents
Culture Documents
i
Table of Contents
1 Introduction......................................................................................................................................... 1
2 Project planning................................................................................................................................... 2
2.1 Project Approach..........................................................................................................................................2
2.2 Goals and objectives.....................................................................................................................................2
2.3 Scope............................................................................................................................................................2
2.4 M&E..............................................................................................................................................................3
2.5 Management and Governance structure......................................................................................................4
2.5.1 Project roles and responsibilities.............................................................................................................4
2.5.3 Project timeline........................................................................................................................................5
2.5.4 Risk Assessment.......................................................................................................................................6
2.5.5 Cluster manager deliverables and timeline..............................................................................................7
2.5.6 Change management............................................................................................................................8
2.5.7 Communications Plan..............................................................................................................................9
ii
Table of Figures
Table 1 WBS..................................................................................................................................................................1
Table 2: Outline for the M&E System...........................................................................................................................3
Table 4 Project roles and responsibilities.....................................................................................................................4
Table 5 Project timeline................................................................................................................................................5
Table 3 Initial risk assessment.....................................................................................................................................6
Table 6 Cluster manger deliverables, deadline and payment schedule.......................................................................7
Table 8: How previous WPs feed into WP4................................................................................................................14
Table 9: Procedure for establishing the number of disclosures that can enter WP4, alternative allocations of
resources.....................................................................................................................................................................14
iii
1 Introduction
The document at hand is the detailed work plan including the narrative report for the project:
“CNFA”. This project aims to provide technical support to civil society organizations with
regard to sustainable organizational capacity. It is designed to unify and strengthen the
cluster’s stakeholders and national partners behind an excellent tourism destination
promotion campaign.
The Report is key in this project, because it sets the frame for all activities that will take place
until January 2023. It details all the activities to be undertaken as well as our approach and
project management strategy.
This document is structured in line with the project. It describes deliverables, the
corresponding activities and includes tasks and subtasks. The document is based on the
Work Breakdown Structure (WBS) outlined in figure 1.
4.2 Upgrading
1.2 Participate in 2.2 Strenghten 3.2Engage cluster
agrotourism
tourism fairs local MSME's players
facilities - Katwijk
Table 1 WBS
The project planning described in this paragraph provides the framework for execution of the
project. It details the approach, goals and objectives, scope, M&E and the management and
governance structure.
These phases are not all sequential, as some will start before the previous phase is
completed. The above mention phases are a generalized approach to the project. For the
implementation roll out of the WBS described in figure 1 will be leading.
2.3 Scope
The project scope is well defined in the Cluster manager responsibilities in relation to
reaching project objectives.
The responsibilities that best describe the project scope are:
- Develop a Strategic Plan for CNFA - Vision and Mission Statement, Guiding
Principles, Strategic Domains, Enabling Actions
- Develop an Operational Plan for CNFA for the next calendar year following the
guidance of the Strategic Plan developed in Activity #1 .
- Develop the By-laws of CNFA to inform the organization's legal registration process
- Support CNFA to meet the requirements for legal registration.
- Draft and develop the operations manual for CNFA to include all relevant policies,
membership code of conduct, and other Standard Operating Procedures .
Goal 2
Output 2
Outcome 2
1.2 Participate in tourism fairs 115 days? Tue 9/10/19 Mon 2/17/20
1.3 Organize Fam trip CARICOM 90 days Mon 1/20/20 Fri 5/22/20
1.4 Organize Fam trips Europe 120 days Wed 3/24/21 Tue 9/7/21
3.1 Coordinate planned activities 494 days? Mon 1/20/20 Thu 12/9/21
3.2 Engage cluster players 494 days? Mon 1/20/20 Thu 12/9/21
4.1 Bakkie facilities upgrade and renovation 60 days Mon 2/10/20 Fri 5/1/20
4.2 Upgrading agro tourism facilities - Katwijk 65 days Mon 5/11/20 Fri 8/7/20
4.3 Upgrading heritage trails 120 days Wed 8/19/20 Tue 2/2/21
All deliverables will be reviewed by the CUS and project steering committee and must be
approved by Compete Caribbean prior to payment. In addition to monthly updates and
quarterly progress reports, the consultant will submit the following deliverables (the
consultant is expected to make timely project progress reports for every three-month period
of implementation using the template provided):
The information contained within the Project Plan will likely change as the project
progresses. While change is both certain and required, it is important to note that any
changes to the Project Plan will impact at least one of three critical success factors:
Available Time, Available Resources (Financial, Personnel), or Project Quality. The
decision by which to make modifications to the Project Plan (including project scope
and resources) should be coordinated using the following process:
Step 1: As soon as a change which affects project scope, schedule, or spending is identified,
the Project Manager will document the issue.
Step 2: The Project Manager will review the change and determine the associated impact to
the project and will forward the issue, along with a recommendation, to the Steering
Committee and CUS for review and decision.
Step 3: Upon receipt, the Steering Committee and CUS should reach a consensus opinion on
whether to approve, reject or modify the request based upon the information contained within
the CDP, the Project Manager’s recommendation and their own judgment. Any change
request deemed ‘major’ by the CUS will be forwarded to Compete Caribbean. Also if should
the Steering Committee and CUS be unable to reach consensus on the approval or denial of
a change, the issue will be forwarded to Compete Caribbean, with a written summation of the
issue, for ultimate resolution.
Step 4: If required under the decision matrix or due to a lack of consensus, the Project
Sponsor shall review the issue(s) and render a final decision on the approval or denial of a
change.
Step 5: Following an approval or denial (by the Steering Committee or Project Sponsor), the
Project Manager will notify the cluster of the action taken. There is no appeal process.
The above mentioned process will be updated when necessary so it is always in compliance
with Compete Caribbean and CUS regulations.
This plan provides a framework for informing, involving, and obtaining buy-in from all
stakeholders throughout the duration of the project.
Project Sponsor
CUS
Steering Committee
Cluster members
Project Manager
Consultants
The following is a list of communication events that are established for this project:
Ad-hoc Communication
Communication with individual cluster members and with the CUS will be constant as major
milestones or changes, are reached and communicated irrespective of above-mentioned
scheduled meetings.
The cluster’s overarching goal is to market North Commewijne Tourism area as high value
and high-quality tourism experience centered on the unique characteristics of the culture,
nature, heritage, history and Asian and Indian selling points to penetrate the tourism market
segments in the Netherlands and Caribbean.
Deliverable 1 is the most critical deliverable in the project as it is directly connected to the
overarching goal of the project. Parts of the activities have already started before the
completion of the detailed work plan because of time constraints and important opportunities
for marketing in the Dutch market being seasonal and limited.
The project efforts to increase international visitors and tourism sales for the North
Commewijne area will not have an immediate visible impact as especially Dutch tourist plan
their vacation at least one year in advance. A steady and significant increase starting in late
2021 is to be expected as a result of the activities that come forth from deliverable 1.
The activities are further elaborated in sub activities. Because activity 1.1 “marketing and
branding strategy development and implementation” is at the bases of the other activities in
this deliverable, they can not be detailed as they are subject to recommendation from the
strategy developed in activity 1.1.
3.1 Activity 1.1 Marketing and branding strategy development and implementation
First activity relates to all the tasks of hiring a consultant, in accordance to IBD's procedure.
This consultant will carry out the subtasks specified for this activity and will advise on the
tasks 1.2, 1.3 and 1.4.
The sub activities to be undertaken for activity 1.1 are:
12
3.2 Activity 1.2 Participate in tourism fairs
The vacation fair in Utrecht is by far the biggest of its sort in Holland, Suriname’s most
important tourism market. That is why participation in this fair is of utmost importance for the
Cluster.
This activity is scheduled to take place in January 2020 and January 2021. The fair for 2020
was from January 15 to January 19. The exact dates for 2021 are not yet published. As
before mentioned the Cluster has already participated in the 2020 fair under this project.
It is important to do the planning and reservations for the fairs long ahead of time, as flight
availability decreases and prices skyrocket due the January rush of tourist going back to
Holland after the December holidays. The planning outlined in the schedule will reflect
inclusion of this concern. The sub-activities undertaken for the 2020 fair or stated below.
These same sub-activities are projected for participation in the 2021 fair.
Sub activities:
1.2.1 Procure flights and booth
1.2.2 Prepare material for booth
1.2.3 Participate in Fair
This activity focuses on attracting tourist from the Caribbean and is dependent on the
completion of sub-activity 1.1.2 ‘Design branding Strategy and implementation’ for detailed
elaboration. This sub-activity entails organizing a trip for tour operators from the Caribbean to
experience the North Commewijne tourism activities so they can better sell the product. It is
however subject to change in approach, so it is scheduled but not detailed. In the schedule, it
is one of the last activities to take place, because improvements in the tourism product under
this project need to be completed in order the showcase the product as intended.
This activity is planned as the last major activity in the project as it the culmination of all the
efforts and lessons learned to promote and enhance the North Commewijne Tourism Area.
The Familiarization trip for European tour operators will be further detailed after completion of
sub-activity 1.1.2.
13
4 Deliverable 2: Compose Bylaws and operational manual
To build capacity amongst Cluster members and local MSME’s a mix of cluster, CUS,
compete Caribbean as well as consultants will be utilized. Therefore, this activity will extend
beyond drafting a TOR and leasing with consultants and stakeholders, the Cluster manager
will be very actively involved in the execution.
In this deliverable special attention will be paid to the strengthening and involvement of
female and local participation in the project. This to position them to benefit optimally from
the expected increase in tourist visits. In the ToR of the consultants to be hired to execute
the activities this will be highlighted as one of the major outcomes.
This deliverable is aimed at enhancing local tourism skills and capacities to increase the
value of the tourism experience in North Commewijne. The goal is to raise standards for all
suppliers to minimum international standards. To achieve this goal the following activities will
be undertaken:
2.1 Local guides tourism training and awareness
2.2 Strengthen local MSME's
2.3 Cluster firm training
14
5 Deliverable 3: Provide road map and technical reports
The Cluster Manager, in coordination with the CUS, Compete Caribbean and the steering
committee will oversee and support the successful implementation of the cluster initiative.
The Cluster Manager will maintain the overall focus of the cluster and ensure that the cluster
activities are in accordance with the established plan of operations and contribute towards
the overall objectives of the cluster initiative. Specifically, the Cluster Manager will oversee
on-site implementation, support and motivate cluster members to collaborate around the
cluster initiative and identify and transfer knowledge necessary to successfully implement
and sustain the cluster initiative post project.
15