WCM BLITZ

Deployment Playbook

1
CONTENT

Playbook structure and


1 guidelines

2 WCM Blitz approach overview

3 WCM Blitz principles

4 Weekly plans

2
1. PLAYBOOK
STRUCTURE AND
GUIDELINES

3
Optional

1. PLAYBOOK STRUCTURE
AND GUIDELINES

4
VERSION CONTROL

Title WCM Blitz Deployment Playbook


Description 16 week deployment playbook for the WCM Blitz programme
Created By EY
Date Created 11 February 2019
Maintained By Zoe Platts (Unilever)

Version Number Modified By Modifications Made Date Modified Status


v1.0 Daniel Seeney (EY) First complete draft of playbook 27/02/2019 Master - Draft
Updated with:
- learnings from WCM Blitz deployment in Port
v2.0 Stan Simonski (EY) 28/02/2019 Master
Sunlight
- Feedback from Unilever Port Sunlight team

5
USING THE DEPLOYMENT PLAYBOOK
ABBREVIATIONS AND VOCABULARY INDEX
AM Autonomous Maintenance LS Line Settings
BDE Breakdown Elimination LT Line Team
CBP Current Best Practice LTC Line Team Coach
CI Continuous Improvement LTL Line Team Lead
CIL Clean, Inspect, Lubricate OEE Overall Equipment Effectiveness
CO Changeover OM Operations Manager
EM Engineering Manager PE Process Engineer
FD Factory Director PIL Process Improvement Lead
FI Focussed Improvement PM Professional Maintenance
FM Finance Manager SMED Single Minute Exchange of Dies
FT Focus Technician TM Tags Management
FV Factory Vision UL Unilever
EHS Environment, Health and Safety VR Volume Reliability
HC Health Check WCM World Class Manufacturing
HRM HR Manager WCM MGR WCM Manager
KPI Key Performance Indicator

6
THE PLAYBOOK PROVIDES CLEAR GUIDANCE ON THE WEEKLY
ACTIVITIES TO DEPLOY WCM BLITZ AND SUSTAIN THE RESULTS
1 Overview 3 Activities Planning Considerations

Provide week by week guidance for the deployment of WCM • Weekly drumbeat timings should be adjusted, in association
capabilities and tools within a 16-weeks ‘Blitz’ with the team, based on the local shift patterns - keeping to
The play book should be used together with the WCM Blitz the suggested structure as closely as possible
“Current Best Practice” guidebook • The deployment of Work Process and tools must occur within
the designated week. Any changes should be signed off by the
deployment leadership team
3 Structure • Conduct weekly Next Week Planning session with the
activities required based on staff availability
The Playbook consists of 16 weekly-plans defining the key
• The next week plan should be displayed in the daily meeting
activities that will take place in each week.
room
Each week has three sections:
• Promote and encourage attendance by the Senior Leadership
1. Overview showing what work processes and tools will be Team to open activities to develop their exposure and
introduced during the week knowledge of the Blitz approach and WCM
2. Detailed Work Plan lists:
• The activities to be planned in the week
• The type of coaching required
• Required supporting material
• Required attendees for the sessions
3. Weekly Drumbeat showing when activities should be planned,
this evolves throughout the Playbook as additional activities
are deployed

7
PLAYBOOK ASSUMPTIONS

Current Best Practice Factory Work Pattern

• The Playbook is the current leading practice • The Playbook timings are based on a Factory
for deploying the Blitz. with the following work pattern:
• The Playbook is designed to detail the type of • Line 9: 24 hours – 7 day a week operation
and timings for the activities required.
• Line 2: 24 hours – 7 day a week operation
• The daily timings of activities have been
• Line Team working hours of Monday to Friday
planned for the factory work pattern
5.30 to 18.30 to see all 3 shifts
described on this page.
• Two shifts:
• The implementation team should work with
the local factory team to adjust times to suit • Morning 6.00 to 18.00
their work pattern, but the timings should be
• Night 18.00 to 6.00
as close to those in the weekly drum beat as
possible. It is also recommended that the daily
and weekly order of events is preserved if any
adjustments to times are made. This is
especially true of the regular meetings and
Scheduled Stop timings

8
USING THE PLAYBOOK
WEEKLY DRUMBEAT TEMPLATE
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00

8.00 – 9.00

9.00 – 10.00

10.00 – 11.00

11.00 – 12.00

12.00 – 13.00

13.00 – 14.00

14.00 – 15.00

15.00 – 16.00

16.00 – 17.00

17.00 – 18.00

Night Shift

9
THE COACHING STRUCTURE WILL ENABLE THE SUCCESSFUL
AND SUSTAINABLE DEPLOYMENT OF THE WCM BLITZ
Deployment Coaching structure (to evolve over
Core Coaching Team
time)
1 Line Coaching Role
Factory
Each member of the Line Coaching Team will partner with Director
a member of the Line structure to: 2
Site
• Provide specific coaching and support
Engineering
• Provide advice on the SW owned by their Line Structure 4
Manager
partner
• Lead the SW Implementation Review session for the SW Central v
ManEX/
2 Senior coaches
Consultant
Factory Director and Engineering Manager act as senior Operations Factory
s WCM
coaches: Manager Engineering
1 Manager
(key coach) manager
• Provide specific coaching and support
• Lead ongoing health checks on SW

Auxiliary Coaching Team 3


PIL/AM
Site Pillar Process Focus
Pillar
3 SW coaching Leaders Engineer Technician
Owner
• Site pillar leaders provide expert advice on SW and tools
4 Accelerate progression
• Central ManEx team or consultants will be involved as
required to accelerate capability building or Enabled by Unilever coaching methodology
deployment activities.

10
2. BLITZ APPROACH
OVERVIEW

11
Optional

2. BLITZ APPROACH
OVERVIEW

12
HOLISTIC DEPLOYMENT PLAN ACROSS WORK PROCESS, TOOLS
AND LEADERSHIP TO ENABLE SUSTAINED RESULTS

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16

Health and Safety Standards

AM Standards - Line Settings and Scales

Daily Line Meeting

AM Standards - Clean, Inspect, Lubricate

Tags Management

Leadership Health Checks

PM Standards - Breakdown Elimination

PM Standards - Professional Maintenance

Changeover Standards and SMED

Link to Cost Deployment

Problem Solving (Kaizen, 5G, 5W 1H, Why Why etc.)

Rate Strategy

OEE Calculation

Unilever Leadership Capability

Key Work Process Tool Leadershi


process s p

13
3. BLITZ PRINCIPLES

14
Optional

3. BLITZ PRINCIPLES

15
THE BLITZ PRINCIPLES WILL GUIDE THE BLITZ APPROACH AND
THE DECISIONS TAKEN DURING THE DEPLOYMENT

1 Enhance focus on work processes

2 WCM is the way we manage operations, not additional work

3 The WCM Blitz is enabled and sustained by the Unilever leadership model

Work processes, tools and leadership capabilities should be developed consistently to drive sustainable
4
improvements

5 Clear ownership for the completion of each task

6 Each employee is empowered to make decisions within their own area and leadership to provide support

7 Zero loss mindset from site leadership to operators will be the norm, not the exception

8 Data will be the life blood of WCM Blitz

16
4. WEEKLY PLANS

17
Optional

4. WEEKLY PLANS

18
WEEKLY PLAN USE GUIDANCE

House Keeping Colour Coding Legend

• Only major planned activities have been captured in the We have used a consistent colour coding mechanism to
weekly deployment plans provide a clear line of sight between actions and the plan.
• Plans are indicative, and timings should be adapted to The coding is:
the schedule restrictions of those implementing Activity Description Color

• Plans are adapted to meet the needs of Port Sunlight Tool/Work Any activity where a new tool or
Factory 1, and therefore effective transfer to other Process Work Process is deployed for the
factories might require adjustments Deployment first time
• All terminology has been aligned with that used in WCM Work Any Work Process that is delivered
Best Practices, or within the PSL site. Any Process regularly as part of this deployment
misalignments or gaps should be consulted with UL Execution playbook
document owners Any training or learning for site
Training and
leadership, factory leadership , line
Learning
leadership, or operators
Any workshops or working sessions
Workshop/
used within the programme to
Working
develop specific outcomes in
Session
relation to programme goals
Periods within this playbook where
Line Stops
we will plan for the line to stop

19
PREPARATION

20
PREPARATION WEEK
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Baseline understanding of WCM deployment status, focus on AM Pillar and
• Factory Strategy and Vision (Prep)
Current State Assessment meetings structure
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) • Critical gaps identified
• KPI & Data (Prep) Line team roles activation • Line Team roles and coaches identified prior to launch
• Factory Leadership Training (wk1) Deployment team roles activation • Defined and identified support roles for the deployment team
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1) Tools Related and Other Tasks
• Rate Strategy (wk1) • Leadership has basic understanding of key Blitz concepts, the 16-week plan, and
• OEE Calculation (wk1) key SW and tools to be deployed
• Operator Blitz Kick-off (wk1) Leadership Introduction to Blitz
• Leadership has basic understanding of key Unilever leadership concepts, such as
• Health and Safety (wk1) servant leadership, and the role of leaders in WCM
• CIL Work Process preparation(wk1)
Factory Strategy and Vision • Understand current state of factory strategy, vision and objectives
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2) Fix line speed • Locked line speed agreed with factory
• Scheduled Stop (wk2) • Understand current state KPI
• Tags Management(wk3) KPIs
• Establish key KAI and KPIs to be tracked
• Leadership Coaching Zone (wk3)
• Obtain line data and related information for 3 to 6 months
• Shift Handover (wk4) Review line event data for gaps
• Unilever Problem Solving (wk4) • Initial data cleaning and understanding of potential gaps and current losses
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

21
PREPARATION WEEK
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Conduct Current State Deployment Shopfloor


Health Checks AM and daily meetings Health Checks 4-8 hours OM, WCM MGR, CI
Assessments/assessments Team health checks

Review current leadership FD, OM, EM, LT,


Deployment Working 90
standards/process & factory Working session Factory presentation LTC, WCM MGR,
Team session minutes
strategy HRM, FM

Review current state AM Pillar Deployment Working 120 AM Pillar Lead,


Working session WWCM Standards, Factory Processes and Standards
standards/deployment Team session minutes WCM MGR

Tools Related and Other


Activities

Establish Line Team, coaching


Deployment Working 90 FM, OM, EM, WCM
structure and extended Working session Roles Presentation, Roles descriptions
Team sessions minutes MGR, HRM
deployment team

Deployment Working 60 FM, EM, OM, WCM


Select lead line(s) Working session Blitz Overview Presentation
Team sessions minutes MGR, CI

Request initial data for lead Deployment Working 90 WCM MGR, Factory
Working session OEE calculation standards, Stops and MTBS calculation standard
line(s) Team sessions minutes data expert, CI

Factory data
Review LEDS data for gaps, Deployment Working 120
Working session OEE calculation standards Unilever and Reliability Engineering expert, CI, WCM
develop initial baseline Team sessions minutes
MGR

Deployment Working 90 FD, OM, CI, WCM


Confirm/establish locked rate Working session Rate Strategy Presentation
Team sessions minutes MGR, FT

Excel/physical PIL, WCM MGR,


Prepare Daily Meeting Board Prep Daily meeting board design and build Factory As needed
board Student support

Review relevant health and safety Working 60 EHS MGR, OM,


Prep Unilever health and safety tools and templates EHS manager
processes session minutes LTL, WCM MGR

22
PREP WEEK DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00

8.00 – 9.00

Current State Assessment


Current State Assessment
9.00 – 10.00 Preparation Week Kick-Off Daily Meeting Line Meetings (on the Preparation EHS
and Planning Session shopfloor)

10.00 – 11.00
Review current leadership Review LEDS data for
Prepare daily meeting
standards/process & gaps, develop initial
11.00 – 12.00 Establish Line Team and board
factory strategy baseline
coaching structure

12.00 – 13.00
Confirm Lead Line

13.00 – 14.00 Request initial data for Complete Current State Confirm/establish locked
lead line(s) Assessment activities on rate
14.00 – 15.00 the line
Current state assessment
AM Pillar Agree Daily Meeting Board
15.00 – 16.00 standards/deployment design

16.00 – 17.00

17.00 – 18.00

Night Shift

23
WEEK 1

24
WEEK 1
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Factory Strategy and Vision (Prep) • Introduce work processes and tools to Factory Leadership
Factory Leadership Training
• Daily Meeting Line Board (Prep) • Introduction to the Black Ops leadership
• Roles Activation (Prep) Validate daily meeting agenda and • Agree standard daily agenda for critical Daily Meeting activities for 16 Week
• KPI & Data (Prep) preparation process Schedule
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1) • Launch Line Daily Meeting meeting - Line Team review completion and
Line Daily Meeting deployment compliance of Work Process, previous 24 hour performance and create plan for
• Line Settings Work Process (wk1)
the day to prioritize corrective actions and allocate resources
• Rate Strategy (wk1)
• OEE Calculation (wk1) • Deploy process for managing line settings
• Operator Blitz Kick-off (wk1) Define Line Settings (LS) • Initial set of line settings for critical equipment
• Health and Safety (wk1) • Train operators in LS
• CIL Work Process preparation(wk1)
Rate Strategy • Deploy agreed locked rate from preparation week
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Introduce SW to Line Operators and Focused Technicians
• Scheduled Stop (wk2)
Operators Blitz Kick-Off • Introduction to 16-weeks Blitz plant
• Tags Management(wk3)
• Collect feedback on current issues
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4) • Training on H&S SW
• Unilever Problem Solving (wk4) Health and Safety • Soft launch of health and safety Work Process
• PM BD SW (wk5) • Agree on approach for embedding H&S work in AM and PM SW
• Weekly Meeting (wk6) Weekly Stops Planning and Preparation • Meeting to discuss plans for stops, and agree targets
• PM Professional Maintenance (wk7)
Tools Related and Other Tasks
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8) • Introduce Line Team to data analytics process and produce clean data set to be
Data analytics introduction
• SMED (wk9) used for developing initial OEE Calculation and stops data
• Continuation Planning (wk15) Unilever leadership • Start developing Unilever leadership capabilities within the Line Team

25
WEEK 1
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Daily Meeting Overview Trainings


& Exercises
FD, OM, LT, EM,
Playbook Overview Training & Factory Leadership Deployment HRM, MM, QM,
Exercise Leadership Introduction Presentation PowerPoint 60 Mins
Training Team HS&EM, FM, WCM
Data analytics MGR

AM, PM, FI Overview Training


Line Daily Meeting Overview Deployment PowerPoint,
Line team training Daily Meeting Process, Daily Meeting Health Check 30 Mins LT, OM, WCM MGR
Training Team Excel
Dry-run (s) of Line Daily Meeting Deployment
Execute Daily Work Line Daily Meeting Coaching Points PowerPoint 20 Mins LT, LTC, OM
exercise with live data Team
Work Process Deployment
Line Settings Training LS Process, LSS HC, LS Templates PowerPoint 60 Mins LT, WCM MGR
Training Team
Work Process Deployment
Line settings initial deployment LS templates Excel 30 Mins LT
deployment Team
H&S SW Training Leadership Training H&S WCM standards EHS Manager PowerPoint 30 Mins LT, WCM MGR
Tool/Work Process As per WCM
H&S SW Soft Launch H&S WCM Tools Leadership 30 Mins LT
Deployment Standard
Deployment
Operator Blitz Kick-Off Workshop Blitz Overview Presentation PowerPoint 60 Mins LT
Team
Deployment As per WCM
CIL prep Training CIL process, templates 60 Mins LT, WCM MGR
Team Standard
Initial Cleaning and Inspection Line Team
Planning Initial Cleaning and Inspection overview PowerPoint 60 mins LTL
Planning Lead
Tools Related and Other Activities
Deployment
Rate deployment Deployment Rate Strategy Presentation, Line performance PowerPoint 60 Mins LT
Team
Deployment
Data analytics Tool deployment WCM OEE Calculation standard, Daily meetings board design PowerPoint 60 Mins LT, WCM MGR
Team
Deployment FD, OM, WCM
Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

26
WEEK 1 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00

8.00 – 9.00 Lien Daily Meeting Dry


Lien Daily Meeting
Run
9.00 – 10.00 Operator Blitz Kick-Off
Factory Leadership
Training
Training: H&S Training
10.00 – 11.00
Data Analytics - OEE
Line Settings Calculation and Stops H&S Soft Launch
Deployment
Review data, develop
Training: Training:
11.00 – 12.00 Current State OEE
Line Daily Meeting Calculation CIL Preparation

12.00 – 13.00

Training: Preparation for Initial


13.00 – 14.00 Deploy fixed line rate
Line Settings & Scales Cleaning in week 2
Line daily meeting follow-up
14.00 – 15.00

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00
Operator Blitz Kick-Off
Night Shift

27
WEEK 2

28
WEEK 2
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Validate WCM CIL template
• Factory Strategy and Vision (Prep)
• Deploy CIL tasks on pilot equipment
• Daily Meeting Line Board (Prep) AM CIL Work Process
• Implement process for recording and managing CIL’s
• Roles Activation (Prep)
• Train operators in CIL process
• KPI & Data (Prep)
• Factory Leadership Training (wk1) • Validate WCM Health Check template
Leadership Health Checks on Work
• Line Daily Meeting (wk1) • Train and coach leadership on expectations and process for Health Checks
Process
• Line Settings Work Process (wk1) • Deploy Health Checks process
• Rate Strategy (wk1) AM Step 2 – Initial Cleaning and • Conduct initial cleaning on the line as per AM Step 2 standard from WCM
• OEE Calculation (wk1) Inspection • Involve leaders in the event (OM, FM, HRM, Finance, EM)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1) Tools Related and Other Tasks
• CIL Work Process preparation(wk1) • Train factory around the Scheduled Stop principal
• Leadership Health Checks (wk2) • Discuss timing of Scheduled Stops
• AM CIL Work Process (wk2) Scheduled Stop
• Deploy daily scheduled stops. Shiftly scheduled stops to be deployed 2-4 weeks
• Scheduled Stop (wk2) later
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

29
WEEK 2
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Line Daily Meeting coaching – Deployment In-meeting


Line Coaching Line Daily Meeting Coaching Points 30 Mins LT, LTC
(Narrow Focus Maturity) Team coaching
Health Check Deployment Excel LT, LTC, OM, EM,
Leadership Health Check Daily Meeting Process & Health Check Current Leading Practice 60 Mins
Deployment Team Checklist WCM MGR
Excel
Deployment LTC, OM, EM, WCM
Health Check Overview training Training Health Check Process, Health Check Template Checklist, 30 Mins
Team MGR
PowerPoint
Deployment
CIL Overview training Training CIL Presentation, CIL SW Process, CIL Health Check, CIL template, PowerPoint 60 Mins LT, WCM MGR, OM
Team
Weekly Stops Prep and Planning Line Team As per WCM
Deployment Weekly stops schedule 60 Mins LT, WCM MGR
Meeting Deployment Leader Standard
PM activities alignment to Focused FT, Maintenance
Working session Existing PM standards PM Standards 60
updated scheduled stop Technician Planner
Tools Related and Other
Activities
Scheduled Stop Presentation, Scheduled Stop Board, Scheduled Stop Deployment
Scheduled Stop Training PowerPoint 60 Mins LT, LTC
Definition Team
Line Team
Scheduled Stop Operator training Training Scheduled Stop Presentation PowerPoint 15 Mins LTL
Leader (LTL)

Line Team
Scheduled Stop Deployment Scheduled Stop Scheduled stop template, process Excel 30 Mins LT, EM
Leader (LTL)
LT, Selected
Line Team
Deep Clean & Inspection session Initial Cleaning Deployment Leading Practice – Scheduled Stop Checklist 240 Mins Factory Leaders,
Leader (LTL)
Engineers
Recurring Activities
Deployment FD, OM, WCM
Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM
Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team
Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team
30
WEEK 2 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
Operator scheduled Stop
8.00 – 9.00 and CIL Training

Scheduled stop Scheduled stop


9.00 – 10.00 CIL Overview training
Weekly Stops Prep and
Maintenance working
10.00 – 11.00 Planning Meeting
session
Deployment AM Step 2
Initial Cleaning
11.00 – 12.00

12.00 – 13.00
Health Check Training
Deploy Leadership Health
13.00 – 14.00
Check
Daily Meeting Follow-Up
14.00 – 15.00

Preparation reparation for Implement CIL Tracking


15.00 – 16.00
initial cleaning Process and Tool
Week Review and Next
16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift

31
WEEK 3

32
WEEK 3
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Deploy process for identifying and managing tags
• Factory Strategy and Vision (Prep)
Tags Management Work Process • Embed TM process into the daily line meeting
• Daily Meeting Line Board (Prep)
• Deploy Health Check monitoring process
• Roles Activation (Prep)
• KPI & Data (Prep) Tools Related and Other Tasks
• Factory Leadership Training (wk1)
• Allocate daily time for leadership, Line Team and other resources to engage the
• Line Daily Meeting (wk1) operators, coach on the floor, and embrace the servant leadership culture
Leadership Coaching Zone
• Line Settings Work Process (wk1) • Communicate Leadership Coaching Zone time to factory
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

33
WEEK 3
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tags Management Overview Deployment


Training TM overview, TM Process, TM Health Check Presentation 60 Mins LT, LTC
training (TM) Team

FT, LTL,
Focused Working
Deploy tags planning cycle Deployment TM TM Presentation, Unilever Maintenance Plan 60 mins Maintenance
Technician session
Planner

Tools Related and Other


Activities

Deployment FD, OM, WCM


Leadership Coaching Zone Training Unilever Leadership Presentation, Coaching on the Floor Presentation 30 Mins
Team MGR, EM, QM

Communicate Leadership Working FD, WCM MGR,


Deployment Communication mail template FD 60 Mins
Coaching Zone session OM, HRM

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

34
WEEK 3 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting

8.00 – 9.00
Scheduled stop
9.00 – 10.00

10.00 – 11.00 Training


Leadership Coaching Zone
Communication alignment
Training
11.00 – 12.00 on Leadership Coaching
TM Overview
Zone

12.00 – 13.00

Deploy weekly Tags


13.00 – 14.00 Management and PM Leadership Health Checks
planning
Daily Meeting Follow-Up
14.00 – 15.00

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift

35
WEEK 4

36
WEEK 4
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Factory Strategy and Vision (Prep) Shift handover Meeting • Launch Sift Handover Meeting between Supervisors
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1) • Train line team, engineers and line coaches on problem solving methodologies
Unilever Problem Solving and process
• Line Daily Meeting (wk1)
• Align problem solving triggers with current Breakdown Elimination process
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

37
WEEK 4
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Deployment
Shift Handover standard training Training Shift Handover Standard PowerPoint 30 Mins LTL, Supervisors
Team

Deploy Shift Handover Standard Deployment Shift Handover Standard LTL PowerPoint 30 Mins LTL, Supervisors

Tools Related and Other


Activities

PowerPoint,
problem
Unilever problem solving training Training Problem solving presentation/templets/examples UL Pillar Lead 60 Mins LT, LTC
solving board,
Excel

PowerPoint,
Problem solving deployment in Process problem
Deployment Problem solving presentation/templets/examples 60 Mins PE, WCM MGR
daily routine Engineer solving board,
Excel

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

38
WEEK 4 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting

8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00
Conduct first problem
Training Embed problem solving solving session
11.00 – 12.00
Problem Solving into daily routine

12.00 – 13.00

Training
Weekly Tags and PM Shift Handover
13.00 – 14.00 Leadership Health Checks
Planning Meeting Deployment Shift
Handover
Daily Meeting Follow-Up
14.00 – 15.00

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift

39
WEEK 5

40
WEEK 5
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Factory Strategy and Vision (Prep) CIL standards for night shift • Extend CIL standards to night shift
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) • Develop process to document all breakdowns
• KPI & Data (Prep) Breakdown Elimination SW • Establish breakdown trigger for in-depth analysis
• Factory Leadership Training (wk1) • Overview of breakdown elimination methodologies for line team
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1) Weekly meeting prep • Preparation session for weekly meeting
• Rate Strategy (wk1)
• OEE Calculation (wk1) Tools Related and Other Tasks
• Operator Blitz Kick-off (wk1)
Scheduled stop in night shift • Deploy scheduled stop in the night shift
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

41
WEEK 5
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Breakdown Elimination SW Deployment PowerPoint,


Training BD SW WCM Leading Practice 30 Mins LT, EM
Training Team Excel

Breakdown Elimination SW Deployment PowerPoint,


Deployment session Existing BDE material 90 Mins LT, EM
design Team Excel

Multiple
CIL Standards for night shift Deployment session CIL Leading Practice, Existing CIL standards LTL Excel LTL, Supervisors
sessions

Deployment PowerPoint,
Weekly meeting preparation Training Weekly meeting training, templates 60 Mins LT
Team Excel

Tools Related and Other


Activities

Scheduled Stope deployment Deployment Multiple


CIL Standard Supervisor Excel LTL, Supervisor
night shift sessions sessions

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

42
WEEK 5 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone
Scheduled stop
9.00 – 10.00

Training
Breakdown elimination Define night shift CIL
10.00 – 11.00
activities
Breakdown Elimination
Design Training
11.00 – 12.00
Weekly Meeting

12.00 – 13.00

Weekly Tags and PM


13.00 – 14.00 Leadership Health Checks
Planning Meeting
Daily Meeting Follow-Up
14.00 – 15.00

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Deploy planned stop

43
WEEK 6

44
WEEK 6
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Develop leadership Health Check checklist
• Factory Strategy and Vision (Prep)
PM Leadership Health Check • Train and coach leadership on expectations and process for Health Checks
• Daily Meeting Line Board (Prep)
• Deploy Health Checks on line
• Roles Activation (Prep)
• KPI & Data (Prep) Tools Related and Other Tasks
• Factory Leadership Training (wk1)
• Define terms of reference, attendees and inputs for weekly meeting
• Line Daily Meeting (wk1)
Weekly Meeting • Train teams on weekly meeting processes, per defined terms of reference
• Line Settings Work Process (wk1)
• Deploy weekly meeting
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

45
WEEK 6
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Deployment PowerPoint,
Weekly meeting deployment Deployment Session Weekly meeting WCM Leading Practice 240 Mins LT
Team Weekly Board

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

46
WEEK 6 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00
Weekly meeting Weekly meeting
preparation preparation
11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM


13.00 – 14.00 Leadership Health Checks
Planning Meeting
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

47
WEEK 7

48
WEEK 7
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Factory Strategy and Vision (Prep) • Updated maintenance standards
Professional maintenance
• Daily Meeting Line Board (Prep) • Professional maintenance fully integrated into the loss elimination cycle
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

49
WEEK 7
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

FT, EM,
Professional Maintenance Deployment
Training PM Training Powerpoint 30 Mins Maintenance
Training team
Planner

Professional Maintenance
Focused FT, Maintenance
Deployment Deployment work PM standards Excel, CMMS 240 mins
Technician Planner

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM
Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

50
WEEK 7 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00
Training:
PM overview

10.00 – 11.00
PM deployment – update PM Deployment – update
standards standards
11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

51
WEEK 8

52
WEEK 8
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Review changeover performance
• Factory Strategy and Vision (Prep)
Changeover SW • Training of operators on changeover standards
• Daily Meeting Line Board (Prep)
• Deploy changeover Work Process
• Roles Activation (Prep)
• KPI & Data (Prep) Tools Related and Other Tasks
• Factory Leadership Training (wk1)
Link to cost deployment plan • 90 day loss elimination plan for the line created
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

53
WEEK 8
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Changeover SW - Leadership and Deployment


Training Changeover CBP PowerPoint 60 Mins LT
Operator Training Team

Deployment Changeover
Changeover SW - Deployment Deployment Changeover CBP, Changeover templates and checklist 60 Mins PE
team template

Preparation for link to cost Deployment Powerpoint,


Working session 90-day plan training 120 mins LT
deployment team Excel

Deployment Powerpoint,
Link to cost deployment training Training 90-day plan training 30 mins LT
team Excel

Deployment Powerpoint,
Prepare 90-days plan Deployment 90-day plan training 120 mins LT
team Excel
Tools Related and Other
Activities
Process
Plan SMED workshop Working session SMED training Powerpoint 60 mins PE
Enginer

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team
Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist
Weekly Tags and Maintenance Weekly Maintenance Focused
Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team
Line Team LT, LTC, OM, FD,
Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Weekly meeting preparation Plan daily work KAI and KPI, problem statements
Line Team
Excel 60 mins LT 54
Lead
WEEK 8 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00
Training:
Link to Cost deployment

Training:
10.00 – 11.00 Plan SMED workshop Preparation for link to cost
Changeover
deployment: data Prepare 90-day plan
collection and analysis
11.00 – 12.00 Changeover deployment

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

55
WEEK 9

56
WEEK 9
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Factory Strategy and Vision (Prep)
• Daily Meeting Line Board (Prep)
Tools Related and Other Tasks
• Roles Activation (Prep)
• KPI & Data (Prep) • Review changeover performance post SW deployment
• Factory Leadership Training (wk1) SMED • Train leadership and operators on SMED (including case study/pilot example)
• Line Daily Meeting (wk1) • Conduct SMED workshop
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

57
WEEK 9
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

SMED - Leadership and Operator Deployment LT, SMED team


Training SMED CBA, Relevant SMED case study/example PowerPoint 60 Mins
Training Team members

LT, SMED team


SMED - Deployment Deployment SMED CBA, SMED Checklist Leadership N/A 60 Mins
members

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM
Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

58
WEEK 9 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

Training:
10.00 – 11.00
SMED

11.00 – 12.00 SMED Workshop SMED Workshop SMED Workshop


(time slot will vary (time slot will vary (time slot will vary
depending on changeover depending on changeover depending on changeover
12.00 – 13.00 timings) timings) timings)

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

59
WEEK 10

60
WEEK 10
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

61
WEEK 10
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

62
WEEK 10 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

63
WEEK 11

64
WEEK 11
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

65
WEEK 11
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

66
WEEK 11 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

67
WEEK 12

68
WEEK 12
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

69
WEEK 12
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

70
WEEK 12 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

71
WEEK 13

72
WEEK 13
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
Preparation for continuation planning
• Factory Leadership Training (wk1) • Data collection for continuation plan
workshop
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

73
WEEK 13
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Preparation for continuation Deployment


Working session Sample roadmaps Powerpoint 60 Mins WCM MGR, FD
planning team

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

74
WEEK 13 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

Preparation for
11.00 – 12.00
continuation planning

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

75
WEEK 14

76
WEEK 14
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
Preparation for continuation planning
• Factory Leadership Training (wk1) • Data collection for continuation plan
workshop
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

77
WEEK 14
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Preparation for continuation Deployment


Working session Sample roadmaps Powerpoint 60 Mins WCM MGR, FD
planning team

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

78
WEEK 14 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

Preparation for
11.00 – 12.00
continuation planning

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

79
WEEK 15

80
WEEK 15
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
Continuation planning workshop • Continuation roadmap in place
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

81
WEEK 15
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Factory
Continuation planning session Working session Sample roadmaps Powerpoint 60 Mins WCM MGR, FD
Director

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

82
WEEK 15 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

Continuation Planning
11.00 – 12.00
Session

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

83
WEEK 16

84
WEEK 16
OVERVIEW
Tool/Work Process Deployed Key Activities Introduced Outcomes

• Current State Assessment (Prep) Work Process Related


• Leadership Blitz Introduction (Prep)
• Continuous maturity increase of work processes
• Factory Strategy and Vision (Prep) Maturity of all work processes
• Preparation for self-sustaining organisation
• Daily Meeting Line Board (Prep)
• Roles Activation (Prep) Tools Related and Other Tasks
• KPI & Data (Prep)
• Factory Leadership Training (wk1)
• Line Daily Meeting (wk1)
• Line Settings Work Process (wk1)
• Rate Strategy (wk1)
• OEE Calculation (wk1)
• Operator Blitz Kick-off (wk1)
• Health and Safety (wk1)
• CIL Work Process preparation(wk1)
• Leadership Health Checks (wk2)
• AM CIL Work Process (wk2)
• Scheduled Stop (wk2)
• Tags Management(wk3)
• Leadership Coaching Zone (wk3)
• Shift Handover (wk4)
• Unilever Problem Solving (wk4)
• PM BD SW (wk5)
• Weekly Meeting (wk6)
• PM Professional Maintenance (wk7)
• Changeover SW (wk8)
• Quarterly Cost Deployment Plan (wk8)
• SMED (wk9)
• Continuation Planning (wk15)

85
WEEK 16
DETAILED WORK PLAN *Types
Tool/ Work
Process
Work Process Training and Workshop/workin
Line Stops
execution Learning g session
deployment
Work Process Related Activities Type* Material Lead Format Duration Core People

Tools Related and Other


Activities

Factory
Continuation planning session Working session Sample roadmaps Powerpoint 60 Mins WCM MGR, FD
Director

Recurring Activities

Deployment FD, OM, WCM


Weekly Deployment Review Progress Review Status Report PowerPoint 60 mins
Team MGR, EM

Deployment
Line Daily Meeting Execute Daily Work Line Daily Meeting Coaching Points Meeting board 30 Mins LT, LTC, OM
Team

Deployment
Line Daily Meeting Follow-Up Execute Daily Work Line Daily Meeting Coaching Points Meeting board 15 Mins LT
Team

Excel
Leadership Health Checks Health Check Health Checks Leadership 30 Mins LT, LTC
checklist

Weekly Tags and Maintenance Weekly Maintenance Focused


Weekly Maintenance Schedule, Tags log Excel 60 mins FT, MP
Planning Planning Technician

Line Team LT, LTC, Extended


Scheduled Stop SW Scheduled Stop Scheduled Stop SW Checklist 60 Mins
Lead deployment team

Line Team LT, LTC, OM, FD,


Weekly meeting Plan daily work KAI and KPI trends Excel 60 Mins
Lead EM

Line Team
Weekly meeting preparation Plan daily work KAI and KPI, problem statements Excel 60 mins LT
Lead

86
WEEK 16 DRUMBEAT
Tool/ Work
Work Process Training and Workshop/workin
*Types Process Line Stops
execution Learning g session
deployment
Monday Tuesday Wednesday Thursday Friday

7.00 – 8.00
Line Daily Meeting
8.00 – 9.00 Leadership coaching zone

Scheduled stop
9.00 – 10.00

10.00 – 11.00

11.00 – 12.00

12.00 – 13.00

Weekly Tags and PM Weekly meeting


13.00 – 14.00 Leadership Health Checks
Planning Meeting preparation
Daily Meeting Follow-Up Daily Meeting Follow-Up
14.00 – 15.00 Weekly meeting

15.00 – 16.00

Week Review and Next


16.00 – 17.00
Week Planning

17.00 – 18.00

Night Shift Night Shift Planned Stop

87
THANK YOU