Professional Documents
Culture Documents
PM-6000-7A2-23/FA
Project Budget
St.Francis college
To create a Gantt chart and determine how long the change approval process normally takes, we'll use the
provided activity list and their durations. A Gantt chart is a visual representation of a project schedule,
showing the start and end dates of each activity. We'll assume a five-day workweek, with no weekends or
holidays.
Step-by-step process to create the Gantt chart and calculate the duration:
Start Date: We'll assume a start date, let's say Monday, January 1, 2024, as a reference point.
Calculate the Start and End Dates for each subsequent activity based on its predecessors and duration.
• Activity 2: Start Date = End Date of Activity 1 + 1 day = January 3, 2024; End Date = Start Date + 2 days
= January 5, 2024
Continue this process for all activities. Here are the results:
• Activity 15 (Final Approval Decision): Start Date = March 17, 2024; End Date = March 18, 2024
• The total duration of the change approval process is the time between the start of Activity 1 and the end of
Activity 15.
3
• Calculate the total number of working days between January 1, 2024, and March 18, 2024, considering the
• The total duration of the change approval process is the number of working days between the start and end