PRIMAVERA MID TERM EXAM – 25 marks

A) ACM– PRIMAVERA
 Create Project schedule using primavera for the data provided below
 Project Name: Construction of electrical building
 Project Id should be your Roll No. for Ex. AH23001, project Id should be 1
 Start date of project: 01/01/2023; 8.00 am
Create EPS, OBS, Project.
B) CALENDAR
 Assign project calendar with following data
o Working hours: 12 hrs
o 6 days working
o Work timings: 8 am to 8 pm, Lunch time 1.00 PM to 2.00 PM
o Holidays: 01/01/2023, 18/02/2022, 08/03/2023, 14/04/2023, 01/05/2023, 15/08/2023, and
02/10/2023 – Create a Global Calendar
o For calculation of Time Periods: Consider 25 working days per month

C) Resources: Assume the resources, create the resources and allocate them – Use any of the SOR
(Scheduled Rates) – any state. Create Baseline, and resource histogram

Create project report with columns - Activity Name, Actual Start, Actual Finish, Original Duration,
Budgeted Total Cost, Budgeted Labour Cost, Budgeted Material Cost, Budgeted Non-Labour Cost,