MINUTES OF PROGRESS MEETING SHORT SUPPLY D26 - SUPPORT RADIATOR LOWER D26

1. Background
a. Delay kedatangan Raw material
Original : Jumat, 9 December
Actual : Sabtu, 10 December

b. Stamping capacity issue, impact kondisi mesin tidak optimal

2. Recovery Plan
a. Catchup Delivery Schedule

16-Dec 17-Dec
11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00

Plan Prod 80 40 80 40 80 80 80 40 80 80 80 40 80

Act Prod

TMMIN 40 40 40 40 40 40
Del
ADM 40 40 40 40

Status : Closed delivery

b. Recovery Stock

17 18
TOTAL
D/S N/S D/S N/S Keep total safetyo stock FG min. 1 Shift volume
Stamping O O O O CONSUME Remain
TOTAL
Assy O O O O TMMIN ADM Stock

FG 460 460 460 460 1840 500 350 850 990

Attendance: ADM DPM


Mr. Deddy Rasidin Mr. Aang (Mkt.) Mr. Dede (PPC / Delivery)
Mr. Achmad Taufiq Mr. Arif (Mtc.) Mr. Nico (PPC / Delivery)
Mr. Parta Mr. Rizzal (PPC/ Delivery)