1. Background
a. Delay kedatangan Raw material
Original : Jumat, 9 December
Actual : Sabtu, 10 December
2. Recovery Plan
a. Catchup Delivery Schedule
16-Dec 17-Dec
11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00
Plan Prod 80 40 80 40 80 80 80 40 80 80 80 40 80
Act Prod
TMMIN 40 40 40 40 40 40
Del
ADM 40 40 40 40
b. Recovery Stock
17 18
TOTAL
D/S N/S D/S N/S Keep total safetyo stock FG min. 1 Shift volume
Stamping O O O O CONSUME Remain
TOTAL
Assy O O O O TMMIN ADM Stock