Professional Documents
Culture Documents
POX DCS Operations
POX DCS Operations
1. General Knowledge
2. Performance of Main Activities
3. Troubleshooting Exercises
Main Activities
Competency Element Perfomance Criteria Skills and Knowledge
12. POX Feed Thickener Operation Key Can describe bed level Should know level of Density (40-45%)
Parameters Can describe optimum PH level (max-2.5 Should know when to run Floculant flow
pH, up to 3 pH will effect density) (in auto-cascade mode)
Can take action if deviation in PH level Should know the codes in the DCS screen
occurs (PIC, WIC, FIC, AI, HV, DI, XV, PU, AG, LI,
Can describe how parameters connect NI, ZI, TI)
with acidulation tank Should know the troubleshooting
Able to identify all parameters within procedures
feed thickener
13. Acidulation Feed and By-pass feed Can take necessary action if the carbon Should know where the pumps are
control level deviates leading and what are their speed &
Can change parameter of WIC current
(acidulation to pox feed tank – tph,spt) Should know if there is a deviation in
and inform the change to field operator carbon level of surge tank,
Can discuss with supervisor for the Should know how parameter change
decisions made & inform them about effects the other parameters
parameters Should explain the reason when there is
Can monitor level of pH in acidulation a issue or upset condition
tanks and agitator (vibration) level
Can run the pump for sulfuric acid
Can run the pump for scrubber
14. Throughput ramp up Can take action to increase tph, check Should know the limit of tph
heaters and increase the GEHO output Should know the limit of oxygen plant
manually & inform the supervisor Should know the differences between
Inform ramp-up to field operator and auto control pump and manual control
oxygen plant operator pump
Before taking actions inform US and DS Should know and able to explain the
operators about the ramp up connection when there is a change made
in parameters
15. Throughput ramp down Can describe the flow from POX surge Should know what problems would occur
tank to autoclave if no ramp down
Can describe how much amount of slurry Should know & describe why we need to
(tonnes per hour) should be decreased ramp down (pumps, downstream,
Upon instruction can decrease slurry in thickener etc.) and talk with supervisor
the feed pump (pump speed) manually to understand the reason
Communicate with 3rd party about ramp Should know and able to explain the
down (oxygen level) connection with oxygen mass flow
After decreasing the level in feed pump spreadsheet with ramp down process
and how much you should decrease
check the LT/HT levels and how the other Should know how much oxygen gotta be
pumps (LT/HT heater) react decreased
Decrease the pump level more (2% per
pump)
After decreasing the pump level (5 mins)
change the Oxygen set point parameter
accordingly
16. POX Shutdown for Hot Stand-by Refer to SOP No:.... (POX Shutdown for Should know the reason for shutdown
Autoclave Hot Standby) Should know all the procedure should be
Communicate with the field operators done one autoclave at a time (the
and vendors(3rd party if necessary) priority depends on supervision and
If Shutdown is 30 min above, prepare communication)
draining for HT heaters, LT heaters and Should know and explain the connection
HT & LT flash vessels with shutdown process and flash vessel
Prepare Autoclave level – 65-70% and Should know when to stop all the
can describe the purpose of level auxilaries pumps (gland water
arrangement distribution, hp water pump, purge
Venting the heaters and flash-vessels to water pump, flash trim pump)
atmospheric pressure
Open the drain valves of HT< heaters
and at the same time front-end pumps
(can describe why we do this)
Communicate with field operator to
lower the pressure by opening drain
valves HT< flash vessels, at the same
time depressurize the back-end pumps
Monitor all the parameters
17. POX Start-up from Autoclave Hot Refer to SOP No:.... (POX Start-up from Should know all the procedure should be
Standby Autoclave Hot Standby) done one autoclave at a time (the
Communicate with the field operators priority depends on supervision and
and vendors(3rd party if necessary) communication)
Confirm all the equipments/elements are Should know and explain the connection
ready and available with start-up process and flash vessel
Prepare a checklist for start-up process Should know when to start all the
auxilaries pumps (gland water
distribution, hp water pump, purge
water pump, flash trim pump)
Should know what equipments/elements
are needed for start-up
18. Autoclave heat up and start up from cold Refer to SOP No:.... (POX Start-up and Should know and explain when is needed
Heat-Up from empty state) start up process (shutdown,
There should be at least 2 DCS operators maintenance connected to autoclave –
during this period scrubber, flash vessel)
Communicate with the field operators Should know how much time needed to
and vendors(3rd party if necessary) do heat up (16-20 hours app)
Confirm all the equipments/elements are Should know the reason of close-open
ready and available valves / While closing drain valves, you
Prepare a checklist for start-up process open bleed valves (describe why we
Process start with boilers – make sure open these valves – air will come out)
you have all the parameters right (diesel, Should know and be able to describe why
demin water) and monitor the field operators open the steam line
parameters valves gradually – start slow with 20%
Refer to SOP No:....(Boiler start-up) (communicate with field operators
Check autoclave pressure level (can be continously)
close to zero) Should know temperature increase (10C
Communicate with field operator after increase per hour-why we need this slow
arranging Setpoint (SP) to make sure he process) and steam pressure / steam
does check the parameters in boiler and table excel control – kpag and
condensate the steam line traps temperature connection while doing
Pressurize the steam line spargers (6) by start-up.
opening the discharge valves – make Should know autoclave reach to
sure the oxygen and quench water valves optimum temperature (220C) then will
are closed (can describe why these check the parameters (steam flow,
valves would be open / interlocks) boiler, temperature).
Communicate with field operator to Should know the current boiler load
control the steam manual valve Should know when to fill-up the heaters
accordingly directed by control room Should know how long it will take for the
operator. reaction starts inside the autoclave
While doing heat-up , run the agitators Should know what is the target steam
(6) manually and check with field flow to the Autoclave and to its
operator to keep agitators run smoothly corresponding compartments.
(small valves should be open by them) Must know the correct Autoclave level
Ensure agitator speed at 50% prior to agitator start.
Monitor the quench water valve flow Should know why it needs to prime all
comes up to 0 (no water goes into Sparger (6).
autoclave discharge line) and wait
around 3 mins to make sure the line is
pressurized
Ensure pump drain and bleed valves are
closed (communicate with field operator)
Make sure all parameters are running
correctly before shift to auto-cascade
level
Increase the agitator speed to 95% for
first 3 then others are to 85%
Following the trend of autoclave
temperature (till oxygen-slurry reaction
starts)
Ensure the levels and parameters are
within range before discharge of slurry
(opening autoclave discharge valves)
Monitor the autoclave level to make sure
parameters are in range
Check flash tank level and open the flash
tank level control valve (between 2
tanks).
19. POX Start-up from Power Failure. Refer to SOP No:.... (POX Start-up from Should know and describe when to start
Power Failure) the POX from Power Failure.
Communicate with the Field operators Able to explain the importance of proper
which equipment to be started first for communication with Control Room
POX train start-up. (Instrumentation and Operator and Field Operator.
Electrical personnel must be within the Should know the priority equipment to
POX MCC Substation). start after power failure.
Confirm all the equipments/auxilliary Demostrate the importance of using SOP,
pumps are ready and available. Equipment checklist.
Prepare a checklist for start-up process Should know if the Autoclave
Check if Steam Generator (Boiler is temperature can sustain during POX start
needed to increase the Autoclave without starting steam generator.
temperature. Should know how long the Air Liquid can
Confirm to Air Liquid plant if O2 is supply O2 after the Power failure. (How
available after the Power Failure and many hours).
ready to supply. To know where to reset the Activated
Reset all the alarm in the DCS screen, INTERLOCK, HIS in the work station.
HIS, Console and ready to go.
20. POX Shutdown due to Power Failure Communicate with the Field operators, Should be able to identify which
Field Supervisor, Shift Engineer for equipment are connected to the
information dissemination. Emergency Generator.
Confirmed the Emergency Diesel Should be able to discuss why the
Generator are running. Autoclave Agitator is the most priority to
Start the Agitator seal water system as start.
soon as possible. Should know what pressure,
Can describe when the Autoclave need temperature, level of the Autoclave
to box-up. before to box-up.
Can describe the valve position should be Define the meaning of Fill-open, Fill-
during Power Failure. close, and Fill-last in the valve position
Determine what is the cause of Power during loss of instrument air of loss of
Failure and how long it takes before to power supply.
resume by informing the proper Should know all parameters are within
department. (Electrical, Contractor, the limit if Power resume.
Deputy Manager). Able to decide if heaters/flash vessels
level need to drop depending Power
availability.
21. Autoclave cool down and Refer to SOP No:.... (Autoclave cool down Should know the importance of using
depressurization to less than 100°C to less than 100°C). SOP, checklist in cooling the Autoclave.
Can figure out how many hours the Should know what is the cool down rate
depressurization and cooling of of Autoclave should be.
Autoclave takes until 80°C or 85°C. Define the importance of using the
Used the steam table when cooling or steam table while heating or cooling the
heating the Autoclave. Autoclave.
Prepare the Autoclave level while cooling Should know that Cooling down and
down as preparation for heating-up or decreasing level can be done via
dumping when External or Internal work Autoclave venting and discharging to
will carried out. High Pressure Flash vessels.
Can provide DCS trend showing the Should know how to open and inject
temperature decrease rate, pressure, Quench water to the Autoclave.
level. Able to determine which Autoclave
Quench water injection in each compartments needs to inject quench
compartment is used depending on water. (Current MOC required atleast
temperature decrease rate. 15°C increase or decrease rate in cooling
Stop the Autoclave all 6 Agitators when or heating).
level triggered low-low level setted at Should know the effect of running
30%. Autoclave agitator at below 30% level.
Oxygen line (spargers) must be flush with Should know the risk of not purging
quench water. (Mandatory). oxygen sparger with queach water after
used. (Line is pressurised with oxygen
(high concentration).
22. LT feed pumps changeover Can show where LT feed pumps located. There might be an issue with pump –
Speak with field operator first to confirm broken pump or under maintenance
if gland seal manual (on field) valve is We change-decrease the LL by 30%
open and manual drain valve is closed (force won’t be needed) – DCS operation
Choose either manual or sequence (auto) Preparation depends on the case
Manual process is chosen currently (maintenance or urgency)
Prepare LT Heater set point to 85% Stop the LT feed pump is around 1 min
because one pump will be in stand-by We stop one LT feed pump and start
Open the automatic suction valve other one which operates(called online)
Open the automatic gland seal valve Decrease LT Heater should be gradually
(control room) and check the flow switch around 20 min.
(should be on)
Switch from auto-cascade to manual
control (LT feed pump)
Decrease the speed of online LT feed
pump to 30% and stop the pump
manually
Start the stand-by LT feed pump and
open the automatic discharge valve
Increase the speed of online pump to
85% or the flow rate is greater than 30
cubic meter – it will be arranged
manually from the control room
Switch from manual to auto-cascade
control
Decrease LT Heater setpoint to 77%
gradually until see no fluctuation
23. HT feed pumps changeover Can show where HT feed pumps are There might be an issue with pump –
Speak with field operator first to confirm broken pump or under maintenance
if gland seal manual (on field) valve is We change-decrease the LL by 40%
open and manual drain valve is closed (force won’t be needed) – DCS operation
Choose either manual or sequence (auto) Preparation depends on the case
Manual process is chosen currently (maintenance or urgency)
Prepare HT Heater set point to 85% Stop the HT feed pump is around 1 min
because one group of pump will be in We stop one HT feed pump and start
stand-by other one which operates (called online)
Open the 2 automatic suction valves and Decrease HT Heater should be gradually
inlet discharge valve around 20 min
Open the 2 automatic gland seal valve
(control room) and check the flow
greater than 0.6
Switch from auto-cascade to manual
control (HT feed pump)
Decrease the speed of online HT feed
pump to 30% and stop the pumps
manually
Start the stand-by HT feed pumps and
open the outlet automatic discharge
valve
Increase the speed of online pump until
PDI shows greater than 220 or the flow
rate is greater than 20 cubic meter – it
will be arranged manually from the
control room
Switch from manual to auto-cascade
control
Decrease HT Heater setpoint to 77%
gradually until see no fluctuation
24. GEHO start up Refer to SOP No:.... (GEHO Priming) Should know the process of GEHO
Ensure that GEHO is primed Priming and how long it would take
Ensure front-end of the GEHO start-up Should know what is the use of GEHO
DCS operator can operate either in (GEHO – Autoclave feed pump (slurry))
manual or sequence (auto) (Manual Should know the sequence during start-
process is chosen currently) up process
Refer to SOP No:.... (GEHO Start-Up) Should know minimum seal water flow
Switch booster pump control from for all pumps is 0.6 m3/h
manual to auto-cascade Should know SPT for GEHO minimum
Set the GEHO speed to 5% and start the suction pressure 550
GEHO Start up means maintenance is finished /
Increase the GEHO speed by 2% troubleshooting is done
gradually until see no fluctuation Should know GEHO’s auxiliaries
equipment and purpose (lubrication
pump, propelling liquid pump, main
motor pump)
Should know and be able to explain what
the pumps are for and how field
operators check on the pumps (oil level,
flow level, warm-up and speed)
Should know the parameter limits for
GEHO operation
Should know the usage of booster pump
– supplying to GEHO (Maintenance can
be done in both GEHO and booster pump
together)
Should know what ‘no fluctuation means’
– LT and HT feed pump flows are stable,
GEHO discharge pressure is stable
25. GEHO shutdown Refer to SOP No:.... (GEHO Shutdown) Should know when needs shutdown
Decrease both GEHO speed by 2% (GEHO pump might be under
gradually (VSD Speed Setpoint) while maintenance, issue with the GEHO pump
decreasing oxygen flow according to or the booster pump) and how long it
demand (operator’s decision-checking will take
ratio) Should know the affects connected to DS
DCS should let HT & LT Heater levels and US areas (flash tanks, tailings,
reach LL before stop the system autoclave)
Make sure oxygen flow is cut after Choose auto or manual SPT based on the
burning out feed in autoclave case (system is put on auto system which
Should operate both in Control can catch up-by design)
shutdown (no fluctuation) or emergency Shutdown can take around 30-45 min
shutdown (immediate)
26. GEHO single to parallel operation Check if the priming in the field is done – Single operation: One GEHO works
speak with operator Parallel operation: 2 GEHO works
Speak with field operator first to confirm Single to parallel: Maintenance of GEHO
if gland seal manual (on field) valve on is finished (possible reason, GEHO
the booster pump is open and manual available)
drain valve is closed 4 MS GEHO – 3 DS GEHO
Choose either manual or sequence (auto) Routine maintenance – 8 hours for
Make sure seal water running (0.8 m3/h operation (from shutdown to start)
ideal) to pump before booster suction
valve is open.
Open the automatic gland seal valve
(booster pump) and check the flow
greater than 0.6 (match with above
explanation).
Open the 2 automatic suction valves and
inboard discharge valve (suction of
booster pump).
Pre-start GEHO
Switch from auto-cascade to manual
control
Set the speed of booster pump to 30%
and start the booster pump.
Increase the speed of booster pump until
SPT (set point) shows greater than 550 –
it will be arranged manually from the
control room (currenty LL is 150kpag).
Switch booster pump control from
manual to auto – manual set SPT (800)
Set the GEHO speed to 5% and start the
GEHO.
When GEHO discharge pressure reaches
same as Autoclave pressure, open
outboard automatic valve
Increase the GEHO speed by 2%
gradually until see no fluctuation (make
sure the GEHO speed is same for both)
27. GEHO parallel to single operation Speed up the GEHO which will be Maintenance or breakdown might be
running and decrease other one which reason for one GEHO to shutdown
will shutdown 2 works to 1 work
Gradually speed up by 2% and decrease Issue with the GEHO pump or the
other one by 2% (Ex: 85% SPT – 31% SPT booster pump
check both pumps level) Issue with downstream area from GEHO
Make sure no abnormalty in other (flash tanks, tailings, autoclave)
parameters (vibration etc. Field operator Control shutdown (no fluctuation) or
control) emergency shutdown (immediate)
When working GEHO reached certain
ideal speed level, continue decreasin
other GEHO till 5% (min.speed)
Adjust the oxygen flow per demand
while keeping the operation stable (by
checking other parameters)
Control stop the GEHO pump
28. Steam injection preparation and start up Make sure field operators start POX Steam is needed for heating-up
Boiler at Low Load (SPT 7 bar) autoclave
Drain condensate from supply header Steam is coming from POX steam-boilers
(manual valves checked by field (2) / one stand-by and one on duty
operator) (rarely both work together)
Make sure of starting pressurization at Boiler needs air receiver and diesel day
steam blowback vessel (pressure of tank to operator (demineralized water is
steam header line and blowback vessel needed because of heavy metal usage)
should be close to each other ex. 7 to 6.9 240-260C is needed for steam generation
bar) Demin water is put into the hotwell tank
Block valve before steam blowback and then it goes to boiler
should be open after pressure Field operators run & check the
equalization (done by DCS) equipments in this area and most are
Condensate from steam blowback vessel automatically run
(field operator) Field operator checks hotwell tank feed
Equalize the pressure of steam blowback water pump (3) / only one demin storage
vessel and header line after blowback tank
Condensate draining from the header Steam seperators (water and steam are
line after blowback seperated)
Block valve after steam blowback should Diesel tank is needed for firing the boiler
be open after pressure equalization Operations run in 2 different cases
(done by DCS) (complete shutdown-normal operation)
Increase the boiler SPT (pressure or load- Steam and oxygen cant be used in the
not fixed but according to demand – max same line (same for steam and quench
35 bar) water-safety reasons, flammable mix)
Normal operation steps: Bridge is needed when there is a change
Control room operator bridge steam between steam to oxygen
block valve Gradual valve opening is needed so that
Cut oxygen line to specific sparger (make interlock system wont be triggered
sure communicated with supplier)
Purge specific sparger with quench water
Check with field operator that all the
manual valves for oxygen-quench water
lines are closed
Ready for injection / check with field
operator to open hand valve and manual
valve of steam gradually till reaching the
demand required
Shutdown steps:
No changeover between oxygen to
steam (other steps are sames as normal
operation)
29. Steam shutdown Check all temperature are stable and Why shutdown – no steam needed
within range (autoclave compartment (autoclave temperature is within the
220 is target) range)
Ask field operator to close hand valve Whenever there is a shutdown or
and manual valve gradually maintenance we need the steam for
When the valves are closed, field heat-up
operator opens quench water manual Steam injection is one-time process (not
valves (communicated with DCS) continuous during normal operation)
Purge specific sparger with quench water Field operator should be aware of sounds
(no steam in the line) while cooling down of boiler
Ask field operator to open oxygen
manual valves (ready for O2 injection)
Initiate the pre-purge sequence for
steam boiler (gradual decrease and
automatic shutdown)
30. Safe changeover from Oxygen to steam Control room operator bridge steam Most preferred sparger is number 2
and steam to oxygen injection on same block valve (because we can make steam distribution
sparger Cut oxygen line to specific sparger (make easily)
sure communicated with supplier) Why using quench water? To clear
Purge specific sparger with quench water residual oxygen from the line (that’s the
Check with field operator that all the safe procedure)
manual valves for oxygen-quench water Why change from oxygen to steam?
lines are closed Needed for heat-up
Ready for injection / check with field
operator to open hand valve and manual
valve of steam gradually till reaching the
demand required
31. Oxygen injection start up DCS confirm oxygen plant is running and Why oxygen injection needed? Burn the
ready to supply sulphur sulphide in autoclave
Open the valve before oxygen outlet Oxygen is produced by Air Liquid plant
valve (oxygen supply equilisation valve) The pressure on the line should be low
gradually differential so that there will be no
Pressure equalisation – Before and after issue/reaction
Oxygen outlet valve (214XV1376)
Open the oxygen outlet valve and oxygen
goes through to blowback vessel
Pressure equalisation – between oxygen
supply and oxygen blowback (open
bypass valve)
Open the valve (143XV1977 – block valve
before oxygen blowback vessel)
Pressure equilisation – between
blowback and oxygen line header (open
the bypass valve)
Open the valve (143XV1986) – block
valve after blowback vessel)
Make sure of header lines are filled with
oxygen by checking pressure transmitter
(close to blowback pressure-ideal 34 bar)
Check with field operator if the oxygen
line and quench water lines are open /
steam lines are closed
Manual valves are open for quench and
oxygen / proceed with purging of all
spargers
Ready for oxygen injection
32. Oxygen injection shutdown Complete shutdown scenario: Why shutdown – autoclave shutdown
Make sure feed is completely stopped 2 scenarios – one is complete shutdown,
(GEHO pumps). second is changeover oxygen to steam
Make sure material in the autoclave Autoclave depressurize – remove all the
should be burnt out. fluids from the lines / takes 16 hours (10
Close all the oxygen block and flow degrees per hour)
valves.
Purge all spargers with quench water (no
oxygen should be left in the lines)
Injection Shutdown in 2 different ways:
Autoclave depressurize (depressurize
oxygen blowback and other all fluids by
closing/opening valves)
o Quench water – manual (close
quench water 2 isolation valves
and open bleed valve)
o Steam – manual (close 2 isolation
valves and open bleed valve)
o Oxygen – DCS (close block valve
VX1977 before oxygen blowback)
o Inform MS field workers about
start venting oxygen blowback
(evacuation) then opening
oxygen blowback vessel valve
PV1985 gradually until pressure
reaches zero
Autoclave box up (close all autoclave
feed line – slurry, oxygen, quench and
steam and outlet line – discharge lines)
33. Oxygen blowback vessel pressurization Refer to SOP No:.... (Oxygen blowback Should know the Oxygen Hazards when
and depressurization vessel pressurization and not properly handled.
depressurization). (Oxygen does not burn. It is not
Communicate with Field Personnel flammable, but it is an oxidizer. Oxygen
(Operation, Maintenance, Contractors) feeds fire, so it's dangerous to use
for the Pressurization activity. around something that is burning
Determine that no active activity, because it will help the fire burn much
isolation within the Oxygen blowback more quickly).
vessel and parts. Gradual pressurization in blowback
Identify which valve need to open during vessel is recommended via the bypass 1
pressurization. inch line.
Identify all the interlock in the DCS Oxygen Automated control valve cannot
Console and DCS Screen with regards to actuate if active interlock is/are active in
Oxygen Blowback vessel. the DCS.
Communicate with Field Supervisor that As per SOP, nobody inside the POX
no personnel inside the POX building building during O2 pressurization.
during O2 blowback pressurization.
34. Oxygen and steam injection on various Proper communication with Field Can describe the risk/hazards when
spargers at the same time Operator and Field Supervisor for proper operating steam/oxygen and quench
valve line-up. water.
Ensure to flush the spargers with quench (Steam and Quench water is unsafe)
water before introducing Oxygen. (Steam and Oxygen is unsafe)
Ensure to flush the spargers with quench (Oxygen and Quench water is safe)
water before introducing Steam. Should know the importance of flushing
Ensure the spargers are primed with the spargers with quench water prior to
quench water after maintenance work. inject steam nor Oxygen.
Bridge the Steam valve when injecting Should know the importance of priming
steam with approval from Shift Engineer. the spargers with quench water prior to
Boiler pressure vs Autoclave pressure inject steam nor Oxygen specially if from
should be monitored. maintenance work.
Boiler pressure vs Autoclave pressure Opening the steam valve without
must be monitored to avoid the Interlock bridging it can result to HIS interlock of
to activate. all Spargers to close.
Should know the PDI of boiler to
Autoclave pressure to avoid sudden
closing of Steam blowback dischage valve
due to activated interlock.
(PDI ≤300 kpag steam blowback vessel
oulet valve to close)
(Sudden pressure swing in main header
line ≥3700 kpag PSV of boiler released).
35. Mainstream water balance control Can described the water balance in Proper water usage in the Mainstream
mainstream area. contribute high efficiency in plant
Can described the effect of improper operation.
water usage in the system. Should know that proper water balance
contribute less consumption in-terms of
reagents consumption.
36. Decant thickener operation key Described the flocculant vs dilution water Understand the effect of over
parameters ratio. flocculation.
Can describe the thickener rake Should know the rake high limitation.
operation. Manage the rake mechanism movement
Can describe the Auto-cascade operation function: (forward-backward-down).
of Decant underflow pump. Explain the function of Semi-Auto, Auto,
Can balance the flow from decant Manual, Local/Remote, Int/Ext, Stop.
thickener overflow to acidulation tanks Understand the effect of low density and
and POX feed thickener overflow tanks. high density in downstream area.
Monitoring the Thickener underflow
density.
37. POX Shared Utilities Knowledge Describe the equipments in the POX Understand the requirements before to
shared utilities. start the Steam generator (boiler).
Communicate with Field Operator when Able to discuss the requirement of
to start the boiler. demineralised water into the boiler. (ph,
Can describe the function of Steam conductivity).
Generation in the POX operation. Know the function of Demin plant and
Can determine the level of uses in POX operation.
chemical/reagents use in Demin area. Understand the importance of
chemical/reagent in demin area.
38. Autoclave Agitator Seal System Start-up Communicate with Field Operator to Understand how the seal water system
check the line-up of Flush/Emergency works in the Autoclave agitators.
water system, Cooling water system, Understand the desired Flush seal
buffer fluid system. minimum flow on each agitators (0.28
Ensure that seal water tank level is l/min).
enough before starting the pump. Should know how the compensator
Advise to bleed all the compensator for works.
possible trap air.
39. Autoclave Agitator Seal System Communicate with Field Operator before Able to describe when to stop the seal
Shutdown to stop Agitator seal system. water system.
Can initiate agitator seal system Know how the buffer fluid refill system
shutdown safely. mixed. (glycerin + demi water)
40. POX Emergency Shutdown due to sudden Notes the closing of spargers and Fully understand the effect of Oxygen
loss of oxygen discharge valve of O2 blowback vessel. loss into the autoclave with respect to
Ramps down Trains to minimum temperature and pressure.
Advise Downstream Control Room Can communicate effectively with Air
Operator that throughput will be ramped Liquide for proper coordination.
down. Aware of the risks and hazards of venting
Call Air Liquide to get information on the Oxygen Blowback vessel.
when the O2 supply will come back. Knowledgeable on the purpose of
If O2 loss is unable to come back by 10 equalizing Oxygen line and blowback
minutes, decide to shutdown both pressure.
Trains.
Stops LT feed pumps, then stops HT feed
pumps and GEHOS on LL level interlocks.
Monitor flash vessel level and flash trim
flow.
Observe Autoclave level, if not holding,
box up by closing secondary MOGAS
discharge valve.
If Blowback vessel has high pressure
>3500kPag, gradually open vent to
equalize.
Constantly communicate with Air Liquide
for start up update.
41. POX Autoclave Discharge Line Checks that QW pumps are running with Can decide when there’s a need to
Pressurization enough pressure (at least ~300kPag pressurize autoclave discharge line.
greater than autoclave pressure). Able to do pre-checks of the essential
Communicate with Field Operator to valves and instruments involved prior to
open manual vent valve of the clave pressurization.
discharge line. Understands the hazards associated
Opens the auto vent valve in the DCS. during line pressurization.
Ensure drain manual valve is closed.
Understands why the line should be filled
Force interlocks on the QW injection
up and pressurized.
valves with the MOGAS discharge valves
Should be mindful enough on bridging
to allow water injection while the clave
discharge valves are in close position. and removing interlocks.
Inject water gradually with an initial
opening of 2%. Increase opening until
flow reaches 10m3/hr.
Confirm flow in the vent line.
Once flow is confirmed coming out of the
vent line, inform Field operator to close
discharge line vent manual valve.
Close QW auto and control valves in the
DCS.
Remove forced interlocks.
42. Manage Boiler Pressure Controller Communicate with Field Operator for the Able to set pressure controller based on
desired Boiler pressure. Autoclave pressure.
Can take action immediately when Understand how the pressure control
pressure abruptly increase. valve works.
Should know the limitation of pressure
controller based on PRV rated capacity.
43. Scrubber system operations Proper monitoring of scrubber system Aware of the pressure limitation in
and the water condition in Scrubber tank dampener to avoid shut of Oxygen flow
must be clear. valves.
Frequent stroking of the the dampener Understand the function of venturi
(1 x per shift including counter weight) scrubber.
Correct water flow setpoint in rod deck Understand the function of Safery
and venturi. scrubber.
Can take action immediately when
pressure increase in the Scrubbers.
44. Caldera Valve Control Can describes the power drive of Caldera Understand the Manual and Automatic
valve. operation of Caldera valve.
Can take action immediately when valve Can describe if the Caldera is working
is in stuck position. normal based in Output and valve
Can shows the Caldera valve trend in Feedback.
DCS. Understand the importance of Caldera
valve in the POX system and the severity
of damage during mis-operation.
Caldera valve operation is always in Auto
mode.
Understand the Caldera profile if the
plug is passing or broken.
45. Agitator Mechanical Seal System Ability to check the mechanical seal Should know the impact in Operation
temperature in the DCS. when Mechanical seals damaged.
Can describe the purpose of agitator Should know and understand the
mechanical seal system and its indication of mechanical seal failure.
subsystem (buffer fluid,flush/emergency Should know the potential effect on the
and cooling). agitators.
Can identify the importance and safety Should know how to respond,
issues of the agitator mechanical seal troubleshoot and interpret the alarm
system and its subsystem fault of agitator mechanical seal system
and its subsystem associated with the
procedures.
46. POX Ekato agitator system knowledge Manage the level of seal water tanks. Understand the Rated power of 6
Proper monitoring of seal flows in each agitators.
agitators. Should know the flow too-low limit of
Can take action if agitator HIGH vibration flush water in the agitators.
switch activited. Understand the purpose of Agitator in
Can describe the function of POX Ekato Autoclave operation.
agitator system. Understand the all the Interlocks and HIS
Can identify the importance and safety of Agitator.
issues of POX Ekato agitator system and Should understand the start up,
its subsystem (buffer operational and shutdwon procedures of
fluid,flush/emergency and cooling). Ekato agitator system.
Should know how to interpret the alarms
on level switches associated with
vendor’s manual.
Should understand how pressure
compensator works especially during
autoclave pressure fluctuations.
Should know when to use the manual fill
up through hand pump operation.
57. High pressure for HT and HP vessels Analyse the cause of high pressure in HT Should know the limitation of pressure in
Heater and HP Flash vessel. the heaters/flash vessels.
Can show the trend of Autoclave Know how to stabilize the pressure in the
pressure, HT Heaters, Flash vessel. system including levels of heaters.
Check the Autoclave discharge caldera Able to check the performance of the
valve position as a source of pressure double pumps, Autoclave feed pumps.
swing in the system. Able to check the design pressure
Check the LP Flash vessel Caldera valve setpoint in the system.
setpoint and valve feedback should be Able to check the pressure transmitter
the same. both in heaters/flash vessels must
Communicate to the Field Operator for working properly.
any abnormalities in field.
58. High Pressure for LT and LP vessels Can able to detect and respond any LT Should know LT Heater and LP Flash
Heater and LP Flash Vessel high pressure Vessel normal operating range pressure.
condition as quick as possible. Should know what are the implications if
Can able to determine the possible cause LT Heater and LP Flash Vessel pressure is
of the upset condition. higher than normal operating range such
Can able to direct Field Operator to as interlock activation, and equipment
conduct field verification regarding failure.
pressure transmitter readings, actual Should know pressure and temperature
scrubber rod deck dampener opening, relationships in closed vessel system.
actual condition of vent scrubber. Should know how pressure control works
Can able to direct field operator to in LT Heater and Flash Vessel.
conduct dampener stroking, to prevent Should know how to determine wether
any scale build up in scrubber pressure indicator gives true or false
dampeners. reading.
Can able to troubleshoot and regain
situation back within operating range by
adjusting scrubber rod deck dampener
opening.
59. High difference between OP and FBK for Check the DCS faceplate if it is in auto or Should know the condition or status of
Caldera Vent and Level valves local. the calderas in normal operation (in auto
Inform Field Operator to check the actual or local).
opening in field. Should know the normal opening of the
Advise field operator to check the alarm calderas for the specific tonnage.
in the panel and reset it. Ability to recognize the impact when the
Ask instrumentation personnel for calderas will suddenly close.
calderas calibration and stroking with Should know how to assist and advise
minimal effects in an operation. the instrumentation personnel for
Analize and check for possible line manual calibration without stroking the
blockage. calderas.
Reduce tonnage if necessary for trouble Should know how to operate in manual if
shooting. necessary.
60. High Scrubber Dampener differential Check any fluctuations of parameters in Should know how to identify and gather
pressure front-end, back-end and autoclave area. the data before declaring emergency
Check the trend for the abrupt increase shutdown.
of pressure and if the scrubber high level Should know the reliability of the presure
switch is activated. transmitters.
If activated, confirm to field operator the Should know the operating ranges of
scrubber status or condition and look for dampener differential pressure.
any leakages. İf unusual and quite, Should anticipate the increase of
baricade the area and escalate to dampener pressure may lead to increase
supervisors. of LT pressure thus HIS activation or
If confirm, Prepare for the emergency equipment failure if higher than normal
shutdown and advise to evacuate the operating pressure.
area.
If normal, advise field operator to
visiually check the actual dampener
opening and conduct dampener test.
Ask instrumentation personnel for
dampener calibration and transmitter
cleaning.
Ramp down operation and observe for
any changes of the dampener differential
pressure.
61. Low level of Clean Water Tanks Can able to determine and respond to Should know clean water tank normal
low level situation of Clean Water Tanks operating level range, low level value and
before any interlock condition activates. low low level value.
Can able to distinguish the reason for Should know the consequences once
upset condition. interlock is activated because of low low
Can able to direct Field Operator to level and what is it’s implication to
check filter system in Demin Water Plant eqipments.
as a source of the water going to clean Should know where is clean water source
water tank and restart the system. and where it will be used.
Can able to direct Field Operator to Should know how to determine wether
ensure all manual valves are open, level transmitter is giving correct reading
automatic valves working properly, lines or not.
are clear if there is no flow going to Clean
Water tanks after Demin Water Plant
Multimedia and Carbon filter is already
running.
Can able to determine the actual
consumption of clean water vis-a-vis the
actual supply.
62. Low EKATO cooling, flush, buffer fluid Advise field operator to check the line up Should be familiar the SOPs of vendor’s
tanks and verify the level in field. manual.
Choose either manual or auto fill up. Should know the DCS operating system;
In auto fill up refer to the vendors permissives, interlocks, level ranges and
manual refill system; alarms.
Refer to SOP no. ..for Buffer fluid refill Should aware the reliability of the level
system. transmitters.
Refer to SOP no. ..for Cooling water refill Should be familiar the line up in field
system. especially the additional modified pump
Refer to SOP no. ..for Flush and use to refill the buffer fluid tank.
Emergency refill system. Should know what to do incase no flow
during fill up of cooling and flushing
tanks due to common pipe and elevation.
63. Autoclave Agitators high vibration alarms Analyze the cause of alarms. Should know the DCS operating system;
Advise field operator to confirm in field. agitator permissives, interlocks, alarms
Decrease agitator speed and corrolate a and HIS system.
current, torque and power. Should know how to determine the
Ask mechanical personnel for the cause of alarms and the implications if
intensity and instrumentation personnel the alarms continue.
for the transmitter. Should aware the reliability of the
Reduce the oxygen, quench water or transmitters.
steam addition in the designated sparger Should know the incremental increase of
line. oxygen, quench water or steam addition
Close the designated automatic sparger and agitator speed in the designated
valve if necessary and check any sparger line.
changes.
Stop and restart agitator if necessary to
prevent bogged.
64. Low Raw Water tank level Check raw water transfer pumps and Should know the utilities which are
well water pumps. supplying the raw water.
Inform shift engineer and area supervisor Should know raw water users.
about the problem. Can lead troubleshooting of common
Inform raw water users to decrease raw water issues in DCS such as faulty
consumption wherever possible if level transmitter, high supply discharge
troubleshooting takes time. pressure, low raw water transfer
Temporarily change raw water users’ currents, etc.
supply from raw water to process water Should know the effect in the process
if possible. plant if cannot recover the level.
65. Low Raw Water transfer pumps Advise area supervisor to check in the Should know the possible causes and
discharge pressure field the status of the pumps and effects of raw water transfer pumps low
discharge lines. discharge pressures.
If no issues with the lines, advise the field Should know the HH and LL limits/
operator to gradually decrease discharge interlocks setting of the raw water
valves’ opening. pumps discharge pressure.
Monitor pumps’ current while
troubleshooting is on going.
66. Loss of flocculant supply for POX/Decant Check the cause of the loss of flocculant Should be familiar with the common
Thickener supply ( flocculant pump VFD fault, low causes of the loss of flocculant.
level of flocculant storage tanks, leak in Should know the importance of
the line). flocculant in the thickener.
Assess/estimate how long the flocculant Should be able to assess, react and
loss will be. decide accordingly with the time
If the loss of flocculant takes time, duration of the flocculant loss.
decrease to stop feeding into the
thickener.
Adjust underflow rates accordingly.
67. High bed level for POX/Decant Thickener Confirm with the field operator’s bed Should know the normal operating bed
level reading. level of the thickener.
Check torque, bed pressure, and Should know how to corollate the
densities reading. torque, bed pressure and densities,
Increase underflow rate if bed pressure, Should be familiar with mass balance
torque, and density are increasing. approach.
If torque and density are decreasing,
decrease feed flow and increase
flocculant.
68. High Torque but low density for POX Inform field operator to check the bed Should know the operating parameters
thickener level. of thickener rake mechanism and its
Check the flocculant ratio. limitation.
Inform the Field Supervisor if the Able to discuss the effect of low density
flocculant plant is working normal. and high density in the POX operation.
Inform Field operator to check the Should know the immediate action for
turbidity of overflow. the issue.
Check the Free-acid in the mixing tank. Know the mass balance of the thickener.
Check the ore feed analysis and inform (Feed tph vs Drawout tph).
Shift engineer in-charge.
Check the underflow pumps flowrate and
the density meter if same as the sample
density result.
Decrease the feed rate until the torque
back to normal while stabilising the
underflow density.
Frequent ask Field operator for the
feedback of thickener condition.
69. POX operations during carry over Check the level of heaters and flash Should know the operating parameters
vessels. of heaters and flash vessels.
Advise field operator to check the clarity Should know the Heaters and Flash
of water in the scrubber tank. vessels transmitters and calderas are
Advise field operator to distinguish the working properly.
carry over either oxidized or non- Should be certain that the carry over is
oxidized. oxidized or non oxidized.
İf non oxidized, divert sump pumps and Should know how to troubleshoot the
seal water return of double pumps to issue.
decant. Should know the consequences of the
İf oxidized, increase choke flow ratio and carry over in scrubber system.
trim flow ratio.
Reduce tonnages
Monitor the carry over frequently.
Competency Assessment