DAILY MAINTENANCE P

1X 60 MW CPP KUTCH CHEMICALS INDUS

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 TG HOTT WELL PP-1
3 CHP BC-3
4 CHP OLD IDLER
5 CHP STREAM-1A
6 BOILER FIRE HYDRANT LINE
7 TG 5Mtr AHU
8 BOILER ID/SA FAN
9 BOP INST AIR COMP-1,2,3
10 BOILER ID/PA/SA-1

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOP AHU -5 Mtr
13 BOILER SPARE
14 CHP CRUSHER-1B
15 BOILER SPARE
16 BOP FIRE PP HOUSE
17 TG TG BUILDING
18 TG AHU
19 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
BC-3 RECEIVING CHUTE WELDING WORK
IMPACT IDLER REPAIRING WORK
PRIMARY SCREEN/CRUSHER/FLIP FLOW-1A PM
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
ALIGNMENT & TRIAL WORK
BEARING HOUSING AIR COOLING LINE FIXING WORK
SUCTION FILTER CLEANING WORK
GREASING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
5 mtr AHU blower base frame replacement.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
D, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
FITTER D
MRM/RS CONST D
FITTER D
AMRESH D
FITTER D
FITTER N
DAILY MAINTENANCE P
1X 60 MW CPP KUTCH CHEMICALS INDUS

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP SCREW COMP. 1A
3 CHP OLD IDLER
4 CHP STREAM-1B
5 BOILER FIRE HYDRANT LINE
6 CHP BELT
7 BOILER ID/PA/SA-2

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


A000Hrs RUNNING KIT REPLACEMENT WORK
IMPACT IDLER REPAIRING WORK
PRIMARY SCREEN/CRUSHER/FLIP FLOW-1B PM
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
BELT COILER MACHINE FABRICATION WORK
GREASING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
D, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
MRM/RS CONST D
ALPESH/AMRESH D
FITTER N
DAILY MAINTENANCE P
1X 60 MW CPP KUTCH CHEMICALS INDUS

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP SCREW COMP. 1A
3 CHP OLD IDLER
4 BOILER DAMPER
5 BOILER FIRE HYDRANT LINE
6 TG & BOILER HOUSE KEEPING
7 CHP BELT
8 BOP CT FAN-2

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


4000Hrs RUNNING KIT REPLACEMENT WORK
IMPACT IDLER REPAIRING WORK
ALL DAMPER BEARING GREASING WORK
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
HOUSE KEEPING
BELT COILER MACHINE FABRICATION WORK
PM

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
D, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
MRM/RS CONST D
FITTER/HELPER D
ALPESH/AMRESH D
FITTER N
DAILY MAINTENANCE P
1X 60 MW CPP KUTCH CHEMICALS INDUS

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP IAC-1
3 CHP COAL SHED
4 CHP BC-2&3
5 BOILER FIRE HYDRANT LINE
6 CHP BELT
7 TG & BOILER HOUSE KEEPING
8 ACC/BOP CEP/PROCESS LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


HP SIDE SHAFT GLAND REPLACEMENT
SPRINKLER BALL VALVE REMOVING WORK
VGT BOX TOP PLATE WELDING WORK
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
BELT COILER MACHINE FABRICATION WORK
HOUSE KEEPING
ONLINE LEACKAGE ARRESTING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
D, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
JANA D
MRM/RS CONST D
ALPESH/AMRESH D
FITTER/HELPER D/N
JANA/VENDOR D
DAILY MAINTENANCE P
1X 60 MW CPP KUTCH CHEMICALS INDUS

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOILER BED ASH COOLER-1&2
3 CHP BC-2&3
4 BOILER FIRE HYDRANT LINE
5 CHP BELT
6 TG & BOILER HOUSE KEEPING
7 ACC/BOP CEP/PROCESS LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SURGE HOPPER WINDOW FABRICATION FOR CLEANING PURPOSE
VGT BOX TOP PLATE WELDING WORK
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
BELT COILER MACHINE FABRICATION WORK
HOUSE KEEPING
ONLINE LEACKAGE ARRESTING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
D, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
MRM D
JANA D
MRM/RS CONST D
ALPESH/AMRESH D
FITTER/HELPER D/N
JANA/VENDOR D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOILER BED ASH COOLER-1&2
3 BOILER FIRE HYDRANT LINE
4 CHP BELT
5 TG & BOILER HOUSE KEEPING

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SURGE HOPPER WINDOW FIXING FOR CLEANING PURPOSE
BOILER AREA FIRE HYDRANT LINE FABRICATION WORK
BELT COILER MACHINE FABRICATION WORK
HOUSE KEEPING

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
MRM D
MRM/RS CONST D
ALPESH/AMRESH D
FITTER/HELPER/MRM/JANA D/N
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOILER BED ASH COOLER-1&2
3 CHP BC-1
4 BOILER ID/SA FAN
5 BOILER BED DRAIN
6 CHP BELT
7 TG & BOILER HOUSE KEEPING
8 TG TG BUILDING

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SURGE HOPPER WINDOW FIXING FOR CLEANING PURPOSE
PM
BEARING AIR COOLING LINE FIXING
AIR BLASTER SERVICE AIR HEADER FIXING WORK
BELT COILER MACHINE FABRICATION TRIAL WORK
HOUSE KEEPING
TG BUILDING WINDOW MESH FIXING

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
MRM D
FITTER D
MRM D
MRM D
ALPESH/AMRESH D
FITTER/HELPER/MRM/JANA D/N
JANA D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-2
3 CHP BC-1
BOP ACW-1
5 BOILER BED DRAIN
CHP BC-3
7 TG & BOILER HOUSE KEEPING
4 BOILER ID/SA FAN

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG TG BUILDING
17 TG AHU
18 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
PIN BUSH COUPLING REPLACEMENT & ALIGNMENT WORK
PM
AIR BLASTER SERVICE AIR HEADER FIXING WORK
RECEIVING CHUTE SPOOL PIECE FABRICATION WORK
HOUSE KEEPING
BEARING AIR COOLING LINE FIXING

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
TG building window mess fixing.
17 mtr Drain line replacement work.
17 mtr AHU door repairing work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
MRM D
JANA D
FITTER/HELPER/MRM/JANA D/N
MRM D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-3
3 CHP BC-2
4 BOP ACW-2
5 BOP RAW WATER PP-1
6 BOILER BED DRAIN
7 CHP BC-3
8 TG & BOILER HOUSE KEEPING
9 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
OLD BELT ROLLING WORK
PM
PM
AIR BLASTER SERVICE AIR HEADER FIXING WORK
RECEIVING CHUTE SPOOL PIECE FABRICATION WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
JANA D
FITTER D
FITTER D
MRM D
JANA D
FITTER/HELPER/MRM/JANA D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-4
3 CHP BC-2
4 BOP ACW-3
5 BOP RAW WATER PP-2
6 BOP FIRE HP-1
7 BOILER BED DRAIN
8 TG & BOILER HOUSE KEEPING
9 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
OLD BELT ROLLING WORK
PM
PM
NDE SIDE SLEEVE REPLACEMENT WORK
AIR BLASTER SERVICE AIR HEADER FIXING & TB MOUNTING FRAME FIXING WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
JANA D
FITTER D
FITTER D
FITTER D
MRM D
FITTER/HELPER/MRM/JANA D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-4
3 CHP STREAM-1A/1B
4 BOILER DCF-1,2,3
5 BOP RAW WATER PP-3
6 BOP FIRE HP-1
7 BOILER BED DRAIN
8 TG & BOILER HOUSE KEEPING
9 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
GREASING WORK
GREASING & CHAIN OILING WORK
PM
NDE SIDE SLEEVE REPLACEMENT WORK
AIR BLASTER SERVICE AIR HEADER FIXING & TB MOUNTING FRAME FIXING WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
FITTER D
FITTER D
MRM D
FITTER/HELPER/MRM/JANA D/N
RS CONST D
DAILY MAINTENAN
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-5
3 CHP BC-2
4 BOP DM TP-1 & 2
5 ACC 203-A & B
6 BOP FIRE HP-1
7 TG & BOILER HOUSE KEEPING
8 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
17 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
RETURNED SELF ALIGNMENT FRAME FIXING WORK
PM
BOTH FAN MIDDLE HOIST PLATEFORM FABRICATION WORK
NDE SIDE SLEEVE REPLACEMENT WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
MRM D
FITTER D
FITTER D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP RBF-1
3 CHP FF-1A
4 CHP BUNKER FLOOR
5 BOP FIRE HP-1
6 ELE ELE DEPT
7 TG & BOILER HOUSE KEEPING
8 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
17 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


CARRYING SIDE SELF ALIGNMENT FRAME FIXING WORK(HOT WORK)
INSPECTION WORK
HAND RAILLING FIXING WORK
NDE SIDE SLEEVE REPLACEMENT WORK
CABLE TRENCH COVERYING WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER/JANA D
VENDOR/FITTER D
JANA D
FITTER D
MRM D
FITTER D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP CLARIFIER WP-1
3 CHP FF-1A
4 CHP BC-6 & VF-4&5
5 BOP FIRE JP-1
6 ELE ELE DEPT
7 BOP CBM
8 TG & BOILER HOUSE KEEPING
9 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 BOP FIRE PP HOUSE
16 TG AHU
17 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
INSPECTION WORK
PM
SPIDER REPLACEMENT WORK
CABLE TRENCH COVERYING WORK
VIBRATION READING TAKEN
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
Fire HP pump sleeve replacement.
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
VENDOR/FITTER D
FITTER D
FITTER D
MRM D
D
FITTER D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP CLARIFIER WP-2
3 BOP DM TP-2
4 BOILER WALL SEAL BLOWER-2
5 BOP FIRE JP-1
6 ELE ELE DEPT
7 TG 5Mtr
8 ACC ACC FAN
9 TG & BOILER HOUSE KEEPING
10 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 TG TG BUILDING
8 BOILER WALL SEAL BLOWER
9 BOP BOP
10 BOILER BOILER
11 BOP AHU -17 Mtr
12 BOILER SPARE
13 CHP CRUSHER-1B
14 BOILER SPARE
15 TG AHU
16 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
INSPECTION WORK
PM
COUPLING REPLACEMENT & ALIGNMENT WORK
CABLE TRENCH COVERYING WORK
GUIDE IDLER FABRICATION WORK
FINS CLEANING WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Rain gutter joint fixing work in TG building.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
FITTER D
MRM D
FITTER D
FITTER N
FITTER D/N
RS CONST D
DAILY MAINTENANCE
1X 60 MW CPP KUTCH CHEMICALS IND

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 BOP CLARIFIER WP-3
3 BOP WASTE WATER PUMP
4 ELE ELE DEPT
5 TG 5MTR
6 TG & BOILER HOUSE KEEPING
7 BOILER FIRE LINE
8 BOILER SA FAN-1,2
9 CHP BC-4
10 AHP FLY ASH SILO

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 TG AHU
15 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
PM
CABLE TRENCH COVERING WORK
GUIDE IDLER FABRICATION WORK
HOUSE KEEPING
FIRE LINE MODIFICATION WORK
DE & NDE BEARING COOLING LINE FIXING WORK
BC-4 STRUCTURE TIE FABRICATION WORK
ASH CONDITIONER LINE PNEUMATIC VALVE FIXING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
NG
LTD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
MRM D
FITTER D
FITTER D/N
RS CONST D
MRM D
JANA D
JANA D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP BC-1F & 2F
3 AHP BIN VENT FILTER, BLOWER FILTER
4 BOP AIR DRYER-1
5 TG 5MTR
6 BOILER FIRE LINE
7 BOILER SA FAN-1,2
8 CHP BC-2
9 TURBINE HP HEATER-1
10 ELEC. DEPT. GIS

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 TG AHU
15 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
FILTER CLEANING WORK
FILTER CLEANING WORK
GUIDE IDLER FABRICATION WORK
FIRE LINE MODIFICATION WORK
DE & NDE BEARING COOLING LINE FIXING WORK
BC-3 TO BC-2 CHUTE SKIRT RUBBER MODIFICATION WORK
PRV PASSING CHECKING WORK
CABLE TRENCH COVER PLATE FIXING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
FITTER D
RS CONST D
MRM D
JANA/JADAV D
FITTER D
MRM D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP RBF-1 & 2
3 CHP FLIP FLOW-1A
4 TG 5MTR
5 BOILER FIRE LINE
6 ELEC. DEPT. GIS
7 BOP INST COMP.1,2,3
8 BOILER SPARE WALL SEAL BLOWER

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 TG DRAIN LINE
15 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


PM
NEW PU MAT FIXING TO CHECK
GUIDE IDLER FABRICATION WORK
FIRE LINE MODIFICATION WORK
CABLE TRENCH COVER PLATE FIXING WORK
SUCTION FILTER CLEANING WORK
DISMANTLING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
JADAV/TUSHAL D
FITTER D
RS CONST D
MRM D
FITTER D
ALPESH D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP OLD FLIP FLOW
3 BOILER FIRE LINE
4 ELEC. DEPT. GIS
5 CHP PRIMARY SCREEN-1A
6 BOILER SPARE WALL SEAL BLOWER
7 CHP BC-4
8 AHP FLY ASH SILO

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 TG DRAIN LINE
15 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SHAFT REMOVING WORK
FIRE LINE MODIFICATION WORK
CABLE TRENCH COVER PLATE FIXING WORK
SIDE SKIRT RUBBER FIXING & SIDE DOOR FIXING WORK
MAINTENANCE WORK
BEND PULLEY HUB COLLAR WELDING WORK
SPOUT CLOTH REPAIRING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
17 mtr Drain line replacement work.
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
RS CONST D
MRM D
JADAV/JANA D
FITTER D
JANA D
FITTER D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP OLD FLIP FLOW
3 BOILER FIRE LINE
4 TG 17 MTR. ALL DRAIN LINES
5 CHP ALL DEFECTS
6 BOILER SPARE WALL SEAL BLOWER
7 CHP BC-4
8 AHP FLY ASH SILO
9 BOP CT FAN-2

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SHAFT REMOVING WORK
FIRE LINE MODIFICATION WORK
DRAIN LINE MODIFICATION WORK
RECTIFICATION WORK
MAINTENANCE WORK
BEND PULLEY HUB COLLAR WELDING WORK
SPOUT CLOTH REPAIRING WORK
PM

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
RS CONST D
MRM D
FITTER D
FITTER D
SUDISH/JANA D
FITTER D
FITTER N
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP OLD FLIP FLOW
3 BOILER FIRE LINE
4 TG 17 MTR. ALL DRAIN LINES
5 CHP ALL DEFECTS
6 CHP STREAM-1A
7 AHP FLY ASH SILO
8 BOP CT FAN-3
9 BOP CLARIFIER PUMP-2
10 CHP PRIMARY SCREEN-1A & 1B

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOILER WALL SEAL BLOWER
8 BOP BOP
9 BOILER BOILER
10 BOP AHU -17 Mtr
11 BOILER SPARE
12 CHP CRUSHER-1B
13 BOILER SPARE
14 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SHAFT REMOVING WORK
FIRE LINE MODIFICATION WORK
DRAIN LINE MODIFICATION WORK
RECTIFICATION WORK
GREASING WORK
SPOUT CLOTH REPAIRING WORK
PM
ALIGNMENT CHECKING WORK
INSPECTION DOOR WELDING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
Wall seal blower gear box readiness work
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
RS CONST D
MRM D
FITTER D
FITTER D
FITTER D
FITTER N
ALPESH D
JANA D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP OLD FLIP FLOW
3 BOILER FIRE LINE
4 TG 17 MTR. ALL DRAIN LINES
5 CHP STREAM-1A
6 BOP CT FAN-3
7 BOP CLARIFIER PUMP-2
8 CHP RBF-1
9 CHP BC-1,2
10 BOP SCREW COMP. 1A
11 AHP ESP 1ST FIELD

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 BOILER APH
5 ACC ALL FAN
6 BOP RAW & CLARIFIER WP
7 BOP BOP
8 BOILER BOILER
9 BOP AHU -17 Mtr
10 BOILER SPARE
11 CHP CRUSHER-1B
12 BOILER SPARE
13 BOILER BUNKER FLOOR
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


BEARING REMOVING & SHAFT SHIFTING WORK
FIRE LINE MODIFICATION WORK
DRAIN LINE MODIFICATION WORK
GREASING WORK
PM
ALIGNMENT CHECKING WORK
COUPLING CHECKING
IMPACT & CARRYING ROLLER REPLACEMENT WORK
SUCTION FILTER, COOLER FINS CLEANING WORK
CONVEYING LINE BOOSTER VALVE FABRICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
BED ASH COOLER TO APH DUCT DAMPER AREA PLATEFORM FABRICATION
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
RS CONST D
MRM D
FITTER D
FITTER N
ALPESH D
FITTER D
FITTER D
FITTER D
MRM D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 TG BFP-2
3 TG BFP-3
4 ACC SPARE OIL PUMP
5 BOILER ID/PA/SA-1
6 AHP FLY ASH SILO
7 CHP BC-4
8 BOILER FIRE LINE

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 ACC ALL FAN
5 BOP RAW & CLARIFIER WP
6 BOP BOP
7 BOILER BOILER
8 BOP AHU -17 Mtr
9 BOILER SPARE
10 CHP CRUSHER-1B
11 BOILER SPARE
12 BOILER BUNKER FLOOR
13 BOP PH DOSING
14 AHP BED ASH SILO
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


BOTH OIL COOLER CLEANING WORK
UPPER OIL COOLER COOLING WATER LINE PIN HOLE LKG ARRESTING WORK
REDINESS WORK
GREASING WORK
OPERATING FLOOR PLATE FORM FABRICATION WORK
STRUCTURE FABRICATION WORK
FIRE LINE MODIFICATION WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
PH DOSING SYSTEM RE-LOCATING
SCREENING M/C FIXING WORK
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
MRM D
FITTER D
FITTER N
MRM D
JANA D
RS CONST D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 TG BFP-1
3 TG BFP-3
4 ACC SPARE OIL PUMP
5 BOILER ID/PA/SA-2
6 AHP FLY ASH SILO
7 CHP BC-4
8 BOILER FIRE LINE
9 BOILER DCF-1,2,3
10 CHP FLIP FLOW-1A

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 ACC ALL FAN
5 BOP RAW & CLARIFIER WP
6 BOP BOP
7 BOILER BOILER
8 BOP AHU -17 Mtr
9 BOILER SPARE
10 CHP CRUSHER-1B
11 BOILER SPARE
12 BOILER BUNKER FLOOR
13 BOP PH DOSING
14 AHP BED ASH SILO
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


BOTH OIL COOLER CLEANING WORK
UPPER OIL COOLER COOLING WATER LINE PIN HOLE LKG ARRESTING WORK
READINESS WORK
GREASING WORK
OPERATING FLOOR PLATE FORM FABRICATION WORK
STRUCTURE FABRICATION WORK
FIRE LINE MODIFICATION WORK
TAIL END BEARING GREASING & CHAIN OILING WORK
V-BELT REPLACEMENT WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
PH DOSING SYSTEM RE-LOCATING
SCREENING M/C FIXING WORK
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
MRM D
FITTER D
FITTER N
MRM D
JANA D
RS CONST D
FITTER D
FITTER D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 CHP STREAM-1A
3 BOP IAC-3
4 ACC SPARE OIL PUMP
5 AHP FLY ASH SILO
6 CHP BC-4
7 BOILER FIRE LINE
8 CHP PS-1A

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 ACC ALL FAN
5 BOP RAW & CLARIFIER WP
6 BOP BOP
7 BOILER BOILER
8 BOP AHU -17 Mtr
9 BOILER SPARE
10 CHP CRUSHER-1B
11 BOILER SPARE
12 BOILER BUNKER FLOOR
13 BOP PH DOSING
14 AHP BED ASH SILO
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


GREASING WORK
IAC OVER HAULING & AIR COOLER CLEANING WOK
READINESS WORK
OPERATING FLOOR PLATE FORM FABRICATION WORK
STRUCTURE FABRICATION WORK
FIRE LINE MODIFICATION WORK
DE BOTTOM SIDE SPRING REPLACEMENT WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
PH DOSING SYSTEM RE-LOCATING
SCREENING M/C FIXING WORK
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D
FITTER D
MRM D
JANA D
RS CONST D
FITTER D
DAILY MAINTENANC
1X 60 MW CPP KUTCH CHEMICALS IN

Sl. No. Area Name of Equipment

1 BOP SCREW COMP. 1A & 1B


2 TG SPARE
3 BOP IAC-2
4 CHP SPARE
5 AHP FLY ASH SILO
6 CHP BC-4
7 BOILER FIRE LINE
8 BOILER BUNKER FLOOR

Sl. No. Area Name of Equipment


1 BOP WASTE WATER
2 ACC ACC FINS
3 CHP BC-4
4 ACC ALL FAN
5 BOP RAW & CLARIFIER WP
6 BOP BOP
7 BOILER BOILER
8 BOP AHU -17 Mtr
9 BOILER SPARE
10 CHP CRUSHER-1B
11 BOILER SPARE
12 BOILER BUNKER FLOOR
13 BOP PH DOSING
14 AHP BED ASH SILO
DAILY MAINTENANCE PLANNING
1X 60 MW CPP KUTCH CHEMICALS INDUSTRIES LTD, GANDHIDHAM

Description of Maintenance Job

FILTER PANEL CLEANING WORK


SPARE ACC OIL PUMP REDINESS WORK
IAC OVER HAULING & AIR COOLER CLEANING WOK
SELF ALIGNMENT FRAME GUIDE ROLLER FABRICATION WORK
OPERATING FLOOR PLATE FORM FABRICATION WORK
STRUCTURE FABRICATION WORK
FIRE LINE MODIFICATION WORK
HAND RAILING PIPE WELDING WORK

List of Pending Jobs


WASTE WATER LINE NEAR ACC EXTENSION NEEDED
ACC LHS Area Spray Line Erection
BC-4 HEAD STRUCTURE TIE WORK
ALL FAN HUB BOTTOM GRATING WELDING WORK
Raw water pump and clarifier pump rubber bellow replacement work.
PAP condensate line insulation
COD vent valve replacement
17 mtr AHU leakage repairing.
SRSB gear box repair and readiness.
Crusher pulley balancing
PA and ID fan rotor repair and balancing
boiler bunker floor handrailing fixing work
PH DOSING SYSTEM RE-LOCATING
SCREENING M/C FIXING WORK
G
TD, GANDHIDHAM
Type of
Maintenance Job planned in Shift
Job
FITTER D
FITTER D
FITTER D/N
FITTER D
MRM D
JANA D
RS CONST D
MRM D