Professional Documents
Culture Documents
L
Page 1 of 15
(INTREX)
Tel: 23986748, 23988915 Fax No. 23986749 Date: 22.10.2020
TABLE OF CONTENTS
1.0 PURPOSE 2
2.0 SCOPE 2
3.0 DEFINITIONS 2
4.0 RESPONSIBILITIES 2
5.0 PROCEDURE 3
7.0 RECORDS 13
1.0 PURPOSE
1.1 The purpose of this standard operating procedure is to provide an approach for the
inspection of pressure vessels installed at the facilities of JO to ensure their
continued safe & efficient service.
2.0 SCOPE
2.1 Scope of this procedure is to provide instructions and establish techniques for the
maintenance inspection of all kind of pressure vessels in accordance with
requirements of the referenced codes or standards.
This procedure establishes and defines the standard requirement for inspection.
However, final Inspection methodology depends on the discretion of the
inspector.
3.0 DEFINITIONS
3.1 Alteration: A physical change in any component that has design implications that
affect the pressure containing capability of a pressure vessel.
3.2 Authorized Pressure Vessel Inspector: An employee of an authorized inspection
agency who is qualified and certified to perform inspection under the inspection
code.
3.3 Maximum Allowable Working Pressure: The maximum gauge pressure permitted
at the top of a pressure vessel in its operating position for a designated
temperature.
3.4 Minimum Allowable Shell Thickness: The thickness required for each element of
a vessel. The minimum allowable shell thickness is based on calculations that
consider temperature, pressure and all loadings.
3.5 Pressure Vessel: A container designed to withstand internal or external pressure.
3.6 Pressure Vessel Engineer: Shall be one or more persons, acceptable to the owner
user, who is knowledgeable and experienced in the engineering disciplines
associated with evaluating mechanical and material characteristics, which affect
the integrity and reliability of pressure vessels.
3.7 Repair: The work necessary to restore a vessel to a condition suitable for safe
operation at the design conditions.
3.8 Re-rating: A change in either the temperature ratings or the maximum allowable
working pressure rating of a vessel, or a change in both.
4.0 RESPONSIBILITIES
4.1 Overall responsibility for implementation of this SOP shall be with the concerned
INTREX Senior Engineer/Engineer.
4.2 Inspection activities and supervision of NDT/NDE shall be performed by the
approved INTREX personnel (Engineer/Senior Technician/Technician) or the JO
B authorized Contractor Personnel, who have appropriate qualification, skills,
experience and knowledge of relevant codes, standards and work practices.
4.3 NDT shall be performed by the INTREX Senior Technician/Technician who have
minimum ASNT Level-2 in accordance with “ASNT SNT-TC-1A” or as
approved by JO.
INTERNATIONAL INSPECTION CENTRE W.L.L
Page 3 of 15
(INTREX)
Tel: 23986748, 23988915 Fax No. 23986749 Date: 22.10.2020
5.0 PROCEDURE
5.1 Preparation Work & Other Requirements:
5.1.1 Review the vessel records and history of repairs, pressure relief protection,
etc. Upon receipt of equipment readiness information from the campaign
crew Plant Inspector shall study the inspection history files of the pressure
vessel thorough in order to know the previous thickness measurements
taken and find out the details of any major repairs carried out before and
any pending integrity issues from previous inspections. The inspector
shall make himself familiar with the operating conditions of the vessel
with the causes and characteristics of potential defects and deterioration
mechanisms.
5.1.2 The mandatory requirements for meaningful visual examination of the
vessel are a clean surface and good illumination of the vessel and the
working area. Adequate lighting shall be available in addition to hand held
flashlights. Surface preparation such as wire brushing, grit blast cleaning,
chipping, grinding or a combination of these preparations may be required.
5.1.3 External and internal coverings such as insulation, refractory, protective
linings, and corrosion resistant linings shall be examined to determine if
they are in good condition. Unless otherwise noted, small portions of the
coverings (insulation) may be removed to investigate their condition and
the condition of the metal underneath them. In case of internal
lining/coating, refractory etc., if it observed to be in good condition
satisfactory for further service till next inspection schedule, then its
removal is not required.
5.10.3 Wet fluorescent magnetic particle inspection (WFMPI) or dry method may
be deployed for inspection depending upon the sensitivity desired and site
conditions.
5.14.2 The pressure test shall be conducted at a pressure in accordance with the
construction code used for determining the maximum allowable working
pressure.
5.14.3 Pneumatic testing may be used when hydrostatic testing is impracticable.
Pneumatic testing shall be considered as “leak test” and should be made at
low pressure.
5.13.4 When a pressure test is to be conducted in which the test pressure will
exceed the set pressure of the safety relief valve with the lowest setting,
then the safety valve shall be removed. Other appurtenances, such as
gauge glasses, pressure gauges and rupture disks should be removed or
blanked off. When the pressure test has been completed, pressure relief
devices of the proper settings and other appurtenances shall be reinstalled
or reactivated.
5.17.2 The inspection shall determine the condition of the exterior surface, the
condition of the supports, the allowance for the expansion and the general
alignment of the vessel on its supports. The pressure temperature and level
gauges shall also be visually inspected and any malfunction or damage
reported.
5.17.3 Any signs of leakage should be investigated so that the sources can be
established.
5.17.4 Inspection for corrosion under insulation shall be considered and this may
require removal of some insulation. Jacketing shall be inspected during the
major surveys. Portions of the insulation shall be removed for inspecting
the metal substrate underneath. Select locations where condensation could
be expected or water from other sources could seep into the insulation.
5.17.5 Buried sections of vessels shall be monitored to determine their external
condition.
7.0 RECORDS
7.1 Pressure Vessels Inspection Checklist – Appendix A.
INTERNATIONAL INSPECTION CENTRE W.L.L
Page 14 of 15
(INTREX)
Tel: 23986748, 23988915 Fax No. 23986749 Date: 22.10.2020
Appendix A
Shell nozzles
1 Inspect shell nozzles for thinning and pitting.
2 Inspect hot tap nozzles for trimming of holes.
3 Identify type of shell nozzles.
Identify and describe internal piping, including
4
elbow up and elbow down types.
Drain Systems
1 Inspect for thinning and pitting.
2 Inspect protective coating
3 Inspect for damage to exterior of pipe.
4 Check for obstructions that pipe could catch on.