You are on page 1of 24

CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Chevron Thailand Exploration and Production


Requirements and Procedures For:

AIT-P-I-003 Inspection of Pressure Vessel

Revision Approval Description Prepared by Reviewed by Approved by


Date
0 Initial release for comment ITNN
1 Revised per Anuchai’s comments ATOH
2 Revised per Abie’s comments APZH

Version 0. Revised 26 October 2012


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Contents

1. PURPOSE …………………………………………………………………………………. 1
2. SCOPE …………………………………………………………………………………….. 1
3. REFERENCE ……………………………………………………………………………… 1
4. DEFINITIONS …………………………………………………………………………….. 2
5. RESPONSIBILITIES ……………………………………………………………................. 3
6. INSPECTION PERSONNEL ……………………………………………………………... 4
7. PROCEDURES ……………………………………………………………………………. 4
7.1 Safety ………………………………………………………………………………... 4
7.2 Preparation and Planning …………………………………………………………... 4
7.3 External inspection ………………………………………...………………………... 4
7.4 Internal inspection ……………………...……………………...……………………...
7.5 Inspection of removed and replacement of vessel components ……...…………….. 4
7.6 Inspection and non-destructive testing……...……………...…………………............... 4
7.7 Pressure vessel repair and alternation……...…...………...……………………………... 4
7.8 Hydrostatic Pressure Testing……...……...………...…………………………... 4
7.9 Final inspection ……...………...………...………...………………………..................... 4
8. RECORDS AND DOCUMENTATION ………………………………………………….. 1
9. APPENDIX
8.1 APPENDIX A CORROSION RATE AND REMAINING LIFE CALCULATION……13
8.2 APPENDIX B MINIMUM RETIRED THICKNESS …………………………………15
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

1. PURPOSE

This procedure provides guidelines for both in-service and out-of-service inspection of various
types of pressure vessels such as separators, drum, columns, towers, and reactors etc. These can
vary greatly in design, fabrication complexity, working conditions and accessibility. However,
inspection frequency is based on risk-based inspection (RBI) criteria included several factors such
as service conditions, operational criticality and availability. The objective of inspection is to
confirm the mechanical integrity of the pressure vessel in order to ensure safe and reliable
operation.

2. SCOPE

This procedure defines inspection requirements and specific responsibilities for internal and
external inspection of existing pressure vessels including separators, drums, columns, towers, and
reactors etc. It applied for all pressure vessel of any metallic material which have been constructed
in accordance with a pressure vessel design code at Chevron Thailand Exploration and Production
Co., Ltd (CTEP) area of operations. The scope of this procedure applies for existing pressure
vessel installed and serviced in operation (Brown field); however, it does not apply for the new
construction (Green field). The inspection frequency of in-service and out-of-service inspection is
also outside the scope of this procedure. This procedure is not a detailed inspection manual, specific
location selective may change on case-by-case basis.

3. REFERENCES

1. API STD 510 Pressure Vessel Inspection

2. API RP 571 Deterioration Mechanisms

3. API RP 572 Inspection of Pressure Vessels

4. API RP 579 Fit For Services

5. ASME Section V Non-destructive Testing

6. ASME Section VIII Div. 1 & 2 Unfired Pressure Vessels

7. Corrosion Prevention and Metallurgy Manual Volume I, II, III, ChevronTexaco


Energy Technology Co.

8. Pressure Vessel Manual, Section-700 In-Service Inspection, ChevronTexaco Energy


Technology Co.

9. Procedure of Asset Integrity Management (AIM) in SERIP document

Version 0. Revised 17 July 2012 1


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

4. DEFINITIONS

Vessel: A container designed to withstand internal or external pressure which is built to a


pressure vessel construction code (e.g. ASME, BS, JIS).

Column: Any vertical vessel containing trays, packing or other internals which is used to
separate product fractions.

Reactor: Any vessel containing beds of catalysts used to crack or improve the quality of the
feed product.

CMMS: Computerized Maintenance Management System.

External Thickness Monitoring: External thickness measurements normally performed with,


but not limited to, the NDE ultrasonic gauging instrument which may be performed while the
vessel either is in service or out of service. This definition coincides with the term "On-Stream
Inspection" used in API 510

External Inspection: An assessment of the conditions of the vessel's external surfaces, such as:
insulation, fire proofing, painting and structures associated with the pressure vessel.

Internal Inspection: This normally refers to, but is not limited to, an assessment of the condition
of the vessel's internal surfaces and components, i.e. shells, heads, welds, internal parts, coating &
linings, cladding, anodes etc.

Condition Monitoring Location (CML): An area of a pressure vessel boundary surface which
has been selected and identified by monitoring shell, head and nozzles thicknesses. Previously,
they were normally referred to as “thickness monitoring location (CML).”

Corrosion Circuit (CC): A term used to describe a zone of a pressure vessel within which the
corrosive conditions are approximately equal, taking into account the corrosive environment
(internally and externally), temperature, pressure, and the constructed material. The Visions4
software also specifies corrosion circuits for inspection and monitoring.

Risk: A combination of the probability of occurrence of pressure vessel failure and magnitude of
the consequence of the failure.

Inspector: Pressure vessel inspectors shall be API 510 certified or authorized by company.

NDT Technician: NDE Technicians who are performing and interpreting non-destructive
examinations must be certified in the method(s) used by one of the following:
• ANST Level I, II or III
• ISO 9712 level I, II or III
• NDT techs pass a CVX test from Practice of NDT Personnel Qualification

Restricted interval (RI): A factor in company computerized inspection records system used
to shorten the length of the thickness measurement inspection interval when there is a potential
for uneven corrosion rates in the circuit/loops.

Version 0. Revised 17 July 2012 2


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

5. RESPONSIBILITIES

5.1 Asset integrity program owner

5.1.1 Responsible to implement of the Owner User Program and ensure that resources
are adequate.

5.1.2 Provide necessary qualified people and tools to execute inspection work to follow
the RBI programs.

5.1.3 Responsible for assuring the Authorized Inspector maintains the required
qualifications/certifications. Inspection and nondestructive examination personnel
who perform inspection tasks do not have to be company personnel.

5.2 Asset integrity SME team shall be responsible for:

5.1.1 Providing technical support and fit for purpose solutions to the corrosion, inspection,
repair method and integrity challenges.

5.1.2 Evaluating inspection findings and providing evaluation of potential repairs and
replacement.

5.1.3 Preparing required inspection, replacement, and repair scopes

5.3 Asset integrity offshore execution team shall be responsible for:

5.3.1 Performing external and internal inspection of the piping and components in
accordance with this procedure.

5.3.2 Determining if cleaning is needed to achieve a satisfactory thorough inspection.

5.3.3 Establishing circuits and CMLs on-site.

5.3.4 Obtaining ultrasonic thickness readings of piping, valves, and fittings.

5.3.5 Physically identifying CMLs and providing a sketch of the piping marked to indicate
inspection findings and the location of findings.

5.3.6 Identifying the locations of repairs and replacements.

5.3.7 Providing an inspection report and anomaly report to meeting all requirements in this
procedure.

5.4 Asset integrity program shall be responsible for:

5.4.1 Maintaining static data, historical data and repair records in Visions4.

5.4.2 Running Visions4 for planning and scheduling of piping system. This will include
generate work order of both inspection and repair scope in CMMS.

5.4.3 Being focal point to conduct Risk Assessment with the RBI group and ETC
Version 0. Revised 17 July 2012 3
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

5.5 FE Construction Team shall be responsible for:

5.5.1 Replacing or repairing the deteriorated piping or components

5.5.2 Conducting Radiographic Examination.

5.6 Field operation and maintenance (O&M), and Asset team shall be responsible for:

5.6.1 Providing preparation work for pressure vessel inspection such as vessel cleaning,
vessel isolation

5.6.2 Removing insulation for inspection and repairs and re-installing insulation after
inspection and repairs are completed.

5.6.3 Facilitating and Coordinating with all related parties to achieve repair work
efficiently.

6. INSPECTION PERSONNEL

Personnel performing inspection of pressure vessel and vessel components shall be certified in
accordance with Chevron’s written Practice of NDT Personnel Qualification in the SERIP Document.
They should also have at least 3 years of experience in design, construction, repair, operation or
inspection of vessel system and qualify at least level I or higher for UT and level II or higher for other
NDT techniques. API 510 Certified inspectors shall hold valid certificates and recognized by the
Company.

7. PROCEDURE

7.1 Safety

7.1.1 All necessary permits/clearances in accordance with CTEP Safety Regulations


shall be obtained before commencement of inspection activities.

7.1.2 Appropriate Personal Protection Equipment shall be worn in accordance with


guidelines in the CTEP Safety Regulations or according to Permit to work
requirements.

7.1.3 Adequate and proper ventilation, lighting and scaffolding should be provided.

7.1.4 Proper safe access should be provided for inspection to be conducted.

7.1.5 The inspector and NDT examiner shall review the situation of vessel entry, and
follow the safety requirements for all necessary aspects related to the circumstances
of the inspection, including working in confined spaces, working at height,
precautions for H2S, etc.

7.1.6 For an internal inspection, positive isolation (blinds) from all sources of liquids,
gases or vapours shall isolate the vessel. The vessel should be cleaned, ventilated
and gas tested before it is entered. Particular attention should be given to areas

Version 0. Revised 17 July 2012 4


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

behind weir plates and inside drains and nozzles to ensure they are also thoroughly
drained prior to entry and inspection.

7.2 Preparation and Planning

7.2.1 Prior to conducting inspection of pressure vessel, inspector should familiarize with
vessel design, service condition, operating experience and inspection history.

7.2.2 Prior to conducting internal inspection, inspector need to be ensure that proper
cleanliness needs to be carried out.

7.2.3 Besides the need for adequate cleaning of the metal surface, sufficient internal
lighting of the vessel is essential for proper and thorough visual inspection.

7.2.4 Examination/inspection must not take place when the preparation which provided
by Asset team is found to be inadequate.

7.2.5 Internal inspection of large vessels may be constrained by accessibility. Prior to


inspection, Asset Integrity team should inform with maintenance and operations
department, the need for removal of trays and fittings or construction of internal
scaffolding and ladders to enable the necessary extent of inspection to be carried
out.

7.2.6 Safe and adequate means of access to and into the equipment must be provided

7.2.7 It is the responsibility of the inspector to ensure that the vessel has been suitably
prepared for inspection. Particular attention should be given to vessel cleanliness,
access to all necessary locations, and insulation removal where required.

7.3 External inspection of pressure vessel

7.3.1 Overview of external inspection

Assessing the condition of the vessel's external surfaces, such as fitting, protective devices,
protective painting, insulation, fire proofing, bolting, sign of leakage, bulging or excessive
dent and structures associated with the pressure by visual inspection

An external inspection of vessels should be carried out periodically whilst the vessel is in
service, preferably preceding a planned shutdown.

External corrosion can be a significant problem, particularly in any local areas where the
protective coating has broken down on uninsulated vessels or where water can
accumulate. Insulated vessels operating in the range -50 deg. C to 150 deg. C or in
intermittent service are particularly prone to external corrosion. For insulated vessels,
damaged or loose fitting insulation cladding will allow the ingress of water so that
corrosion may occur. Corrosion can also be experienced at locations where adequate
draining of any accumulated water in the insulation may not be possible.

A thorough visual inspection of all external surfaces shall be carried out as far as access
and insulation permits. Insulation should be removed in areas selected by the Inspector,
where accelerated corrosion can be anticipated. Known problem areas are at the junction
Version 0. Revised 17 July 2012 5
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

of supporting structures and cowling, insulation or vacuum rings, manholes and nozzles.

In determining the possible susceptibility of insulated vessels, columns and reactors to


external corrosion the Inspector shall take account of the actual operating temperature
and any temperature gradients which may exist over the equipment such as dead-legs

7.3.2 Guideline of external inspection

o Perform external visual inspection on all external surface of vessel and piping in
the skid as following below

1. Location of inspection : Entire external vessel


Inspection for :
• Distortion, bulging, blistering, cracking.
• Any sign of leakage.
• General and Pitting Corrosion.

2. Location of inspection : Protective coatings


Inspection for :
• Evidence of deterioration.

3. Location of inspection : Steel supports and skirts of vessel


Inspection for :
• Sign of corrosion, distortion, vibration and cracking for further proper
functioning.

4. Location of inspection : Ladder, walkways, platforms, grating and


stairways
Inspection for :
• Corroded, bent, broken, or missing structural parts.
• Loose or missing bolting.
• Worn stair treads and rungs.

5. Location of inspection : Insulated vessels


Inspection for :
• External evidence of corrosion under insulation (CUI).
• Loose, corroded, or deteriorated insulation support systems.
• Insulation jacket damage which would permit water to penetrate
• Check areas, particularly at joints or skirts where moisture can
penetrate and lead to corrosion of unprotected surfaces.
• Cold insulation should be checked for flaws in the vapour barrier.

6. Location of inspection : Level gauge legs and other appurtenances


Inspection for :
• External evidence of corrosion under insulation (CUI).
• Loose, corroded, or deteriorated insulation support systems.
• Insulation jacket damage which would permit water to penetrate
• UT is recommended ; however, RT maybe considered for small
bore or pitting type services.

Version 0. Revised 17 July 2012 6


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

7. Location of inspection : Small Branch Connections


Inspection for :
• PT is recommended if vibration is observe

o Perform external thickness monitoring inspection on located CML

1. Vessels constructed with corrosion resistant materials, including all internal


cladding may not require external thickness monitoring.

2. Insulated vessel shall be installed inspection ports (IP) to prevent the ingress
of moisture under the insulation. The access port shall be defined as CML.

3. Within the area of CML vessel thickness shall be scanned to obtain the
minimum reading thickness. This reading shall then be recorded as the
thickness value for the CML in VISIONS4.

4. If a large scatter in the thickness readings at a CML is experienced,


additional areas adjacent to the CML may need to be scanned until the
nature of the condition can be assessed. The verified minimum wall
thickness reading shall be recorded.
• Such conditions may require engineering evaluations or fitness for
service.
• All conditions of this sort shall be noted in the vessel inspection file.
• Thickness readings greater than previous readings for the CML which
are considered to be outside the acceptable instrument and/or operator
error shall be evaluated to determine the reason for the error. The
incorrect value shall be corrected and noted in the vessel inspection
file.

7.4 Internal inspection of pressure vessel

7.4.1 Overview of internal inspection

Vessels may be subjected to a range of service conditions, including regular changes of


contents, or unexpected traces of corrosive impurities and they may be constructed from
a range of materials to suit these service conditions. The defects to be inspected for will;
therefore, vary significantly according to the conditions that the vessels are exposed to
and the materials of construction.

All internal surfaces, welded seams and heat affected zones including nozzle openings,
should be examined for any signs of discoloration, corrosion, erosion, pitting, cracking,
grooving, scale deposits, sludge accumulation or other defects. The general condition
must be recorded and any areas showing damage, leakage or deterioration must be
investigated and remedial action proposed where applicable.

The inspection should particularly include a re-check of any defects or repairs made
previously, as documented in previous inspection reports.

Any indication of a reduction in wall thickness of the pressure containing part of the
vessel shall be verified by ultrasonic or radiographic testing. The use of photography as a
means of permanently recording areas of interest is recommended. Samples of scale or
Version 0. Revised 17 July 2012 7
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

deposits should be obtained for analysis as and when judged necessary by the Inspector
or advised by the Corrosion Engineer.

5.3.2 Local Deformation

Any local deformation of the vessel wall is most probably due to overstressing or
overloading of nozzles by connecting pipe work etc. Internals can be deformed for a
number of reasons, which may be related to the operating conditions.

In H2S-containing service, blistering of the vessel wall may be present.

Accessible surfaces should be checked for deformation or blistering. The primary method
for locating suspected deformation is to direct a flashlight beam parallel to the surface.
Shadows will appear in depressions and on the unlighted side of internal bulges.

Placing a straight edge parallel with the vessel axis against the vessel wall, and using a
steel rule to measure the extent of bulging can also measure local deformation.

5.3.3 Signs of Thermal Shock

The stress resulting from the sudden unequal expansion or contraction of the different parts
of a vessel may cause distortion that can result in cracking. This type of damage is more
likely to occur in austenitic materials such as stainless steel than in ferritic materials like
carbon steel or low alloy steel. If located, the extent and depth of cracking should be
established by NDT methods.

5.3.4 Corrosion Damage

The location and form of any corrosion observed in the vessels should be clearly
identified. Corrosion damage can be classified as:-

a) Those, which can be distinguished by visual examination.


• general or pitting corrosion
• localised corrosion
• galvanic corrosion
• velocity-related corrosion (e.g. erosion)

b) Those, which can usually be positively identified only with the assistance of
supplementary methods of inspection or through microscopic examination.
• Cracking due to fatigue, creep or environment induced stress corrosion
cracking. These types of cracking are often associated with the weld
heat-affected zone.
• Intergranular corrosion, commonly experienced in stainless steels and
high nickel alloys, and often observed in the heat affected zones of
welds.
• Dealloying (graphite corrosion, dezincification of brass).

In particular, the type and appearance of any scale in the vessel should be noted, as a
possible indication of the type of corrosion damage that has occurred.

Version 0. Revised 17 July 2012 8


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Where visual inspection has highlighted areas requiring a more thorough examination by
ultrasonic testing, these should be clearly marked up and reported.

5.3.6 Internal Fittings, Trays and Attachments

All internal trays, support rings, support lugs, baffles, side sumps and nozzles welded to
the draw-off trays should be inspected for excessive bulges, depression, or any wear and
tear which may need repair. However, at the discretion of the Inspector, only a
representative number of each type of fittings can be selected for a more detailed
inspection. Complex internal fittings designed for specific purposes should be looked at
more critically for cracks and metal loss so that their strength is adequate for their
designated function.

5.3.7 Nozzles

The nozzles, flanged connections and bolting should be inspected for damage/corrosion.
The gasket faces of the flanges that are opened should be inspected to check that they are
in good condition.

Visual inspection of small nozzles may be supplemented by use of a boroscope. Several


methods for the internal examination are also available using ultrasonic techniques,
radiography or internal calipers.

Nozzles should be visually examined for bulging, excessive scaling and corrosion, internal
blockages and in particular, plugging in relief valve and instrument nozzles, where present.

Blind flanged nozzles (e.g. utility connection, vent nozzle etc) should be included in the
check for internal corrosion.

Note that nozzles attached to the equipment and water boots may be inspected on-stream
by means of radiography or ultrasonic thickness check, and should be included in the on-
stream inspection programme where appropriate.

5.3.8 Internal Coatings, Lining or Cladding

Non-metallic coatings are applied to prevent internal corrosion of the vessel, but are
limited in their use by temperature and compatibility with some process fluids.

Metallic linings, in the form of integral cladding, strip lining or weld overlay with a more
corrosion resistant material may also be applied internally to protect the pressure vessel
from aggressive service conditions.

In the event of a coating or lining failure, the pressure vessel may be exposed to conditions
that it was not designed to withstand.

The coating or lining should therefore be carefully checked for any damage, particularly
due to thermal shock or temperature excursion, or separation from the parent metal,
particularly around nozzles and areas where there is a cross-section change. Metallic
corrosion-resistant linings should be examined using PT to check for cracking.

Internal refractory should be inspected for excessive erosion, wear, cracks and damage. If
Version 0. Revised 17 July 2012 9
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

required, the condition of the refractory-anchoring studs should also be checked.

7.4.2 Guideline of internal inspection

o Clean internal vessel surfaces and vessel internal parts as needed prior to inspection

1) Scale, dirt, hydrocarbon deposits etc. shall be removed so that a thorough and
satisfactory inspection can be achieved.
2) Removal of internal coating, lining, obstructed parts may be required as necessary

o Perform internal visual inspection on all internal surface of vessel and piping in the
skid which includes an examination of all accessible surfaces of the vessel and all
internal parts.

1. Location of inspection : Vessel shell, head, nozzles, and weld seams


Inspection for :
• General and localized corrosion, pitting, erosion, and impingement
damage
• Blistering, bulging, buckling, or distortion
• Cracking
• Pin-holes

2. Location of inspection : Internal part of vessel


Inspection for :
• Deterioration or cracking of trays, baffles, mist extractor, vane, piping
supports, internal stiffeners, and welds.
• Erosion of impingement plates.
• Distortion, bulging, blistering, or buckling of weirs, bucket, baffles,
trays, supports, and impingement plates.
• Missing, loose, or deteriorated bubble caps, weirs, chimney etc.
• Missing loose or deteriorated internal piping.
• Deteriorated, cracked, or damaged internal piping.
• Loose or missing bolting.
• damage, sagging, deflection, cracks or corrosion wastage.
• Any evidence of cracking at highly stressed areas such as stays and
braces on the column wall, support beams or rings damaged due to
effect of vibration or internal dynamic upset should be noted.

3. Location of inspection : Internal linings (both metallic and non-


metallic)
Inspection for :
• Sign of corrosion, pitting, cracking, spalling, and leakage

4. Location of inspection : Internal coating vessel


Inspection for :
• Evidence of deterioration

Version 0. Revised 17 July 2012 10


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

7.5 Hydrostatic Pressure Testing

7.5.1 General

A hydrostatic test shall be used to prove the integrity of pressure vessel after
repairs, provided the design of the vessel and supports can accommodate the test.
Hydrostatic testing should be applied carefully and with the knowledge of all
parties involved, since the vessel may be subjected to a stress exceeding its normal
operating stress.

Approval shall be obtained from Reliability Manager (add in role and


responsibility) if any requirement for hydrostatic pressure testing is to be waived.

7.5.2 Test Procedure

Details of the requirements for hydrostatic testing shall be followed hydrotest


procedure AIT-X-X-002. In case, any deviation from procedure require approval
by Reliability Manager (add in role and responsibility)

8. Final Inspection

8.1 Upon completion of all required repair work, the vessel shall receive a re-inspection
to ensure the completeness and adequacy of repair and to verify vessel cleanliness prior to closing.

8.2 API Certified Inspector ensure all required inspection activities have been completed as
per inspection test plan (ITP)

9. Records and documentation

The Inspector who has inspected the equipment shall record the findings in VISIONS4. In
this record, the following are required:
• Component history
• Corrosion rate (CR) and remaining life (RL)
• Highlights
• Recommendations, if any
• Thickness measurement, if any.
• All sketches, photographs results and reports of NDT and other
inspection activities

Attachments

a. Appendix I – CML for wall thickness gauging


b. Appendix II – Inspection checklist for pressure vessel
c. Appendix III – Corrosion Rate (CR) and Remaining Life (RL)
Calculation
d. Appendix IV - Wall Thickness Calculation

Version 0. Revised 17 July 2012 11


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Appendix I – CML for wall thickness gauging

Note:
1. UT all nozzle 2” and above
2. Nozzle size 4” & below - 1 Test point
3. Nozzle size above 4” - 2 Test points
4. UT should include level gauge and other appurtenances
Version 0. Revised 17 July 2012 12
CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Refer sheet 1 of 4 Note on nozzles

Appendix II – Inspection checklist for pressure vessel

Examination Checklists

Pressure Vessels: (Including Columns, Reactors, Accumulators, Strippers, Filters, Pots, etc.)

1. Fouling

Version 0. Revised 17 July 2012 13


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

2. Dished heads
3. Shell
4. Boot
5. Nozzles (blockages)
6. Level gauge legs and other appurtenances.
7. Internals (Baffles, Coating, Cladding, Scallops Expansion rings, Centre screen,
Support rings, Trays, Tray support beams, Packing rings, demister pads, )
8. Welds (internal/external)
9. Vortex breaker (thickness)
10. Insulation
11. Insulation supports
12. Supporting structure
13. Skirts/saddles
14. Hold-down bolts
15. Earthing
16. Heating coils/elements
17. Gasket faces
18. Bolting
19. Ladders/Platforms/handrails
20. Welds (internal/external)

Note:
Delete what components are not applicable to Pressure Vessel being inspected.

Note for Columns:


It is not unusual for the inspection of columns to be concentrated on part of the equipment
only. In that case, the boundaries of the examination must be clearly referenced and the
justification for the partial examination explained.

Version 0. Revised 17 July 2012 14


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Appendix II – Inspection checklist for pressure vessel

EXTERNAL INSPECTION GUIDE for VESSELS/COLUMNS/REACTORS

Note: This checklist is an additional guide to external inspection covering items that should be
considered during inspection of pressure equipment. The list is not exhaustive, and the inspector
should apply knowledge and experience in the interpretation and application of the inspection
requirements.

External condition (painting, lagging, fire-proofing, etc)


Support structure, skirt, ladders
Nozzles, water boots, (condition, UT/RT/??)
Flanges – free of leaks, bolt condition
Supports and saddles
Earthing
Sight glasses/fittings
Instrumentation
Small bore fittings (condition/design/vibration)
Relief valves
Bolt/nut condition (inc. hold-down bolts)
Clamps on lines
On-stream thickness gauging

Version 0. Revised 17 July 2012 15


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Appendix II – Inspection checklist for pressure vessel

INTERNAL INSPECTION GUIDE for VESSELS/COLUMNS/REACTORS

Note: This checklist is an additional guide to internal inspection covering items that should be
considered during inspection of pressure equipment. The list is not exhaustive, and the inspector
should apply knowledge and experience in the interpretation and application of the inspection
requirements.

Internal Fouling?
Before cleaning: type
Location

After cleaning

Unlined shell and heads:


General corrosion observed/measured - C.R. & R.L.
Pitting observed/measured
H2 blistering observed
Localised corrosion - downcomers, trays, welds, opposite nozzles, liquid
levels, etc
MPI checks in wet H2S, amines, deaerators, etc

Clad shell/heads:
General corrosion/pitting observed/measured -C.R.
DP inspected

Nozzles/manways:
All inspected
General corrosion/pitting observed/measured
Gasket face condition

Internals:
Trays and supports corroded/damaged
Tray caps corroded, damaged, in place
Demister pads displaced/corroded/fouled
Vessel appurtenances corroded/loose
Vessel packing intact/fouled
Impingement plates corroded/eroded – check welds for cracking
Internal lines hammer tested

Pressure test:
Statutory??
After repairs/modifications

Version 0. Revised 17 July 2012 16


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Appendix III – Corrosion Rate (CR) and Remaining Life (RL) Calculation

CORROSION RATE AND REMAINING LIFE CALCULATION

1. The long-term (LT) corrosion rate shall be calculated from

tinitial −tlast
LT corrosion rate =
time (year)between tlast and tinitial

2. The short-term (ST) corrosion rate shall be calculated from:

tprevious −tlast
ST Corrosion rate =
time (year)between tlast and tprevious

3. The remaining life of piping shall be calculated from:

tlast −trequire
Remaining life =
Selected corrosion rate

The selected corrosion rate shall be determined from the maximum value whether LT or ST, that best
reflects the current process.

Where:
t initial = The piping original wall thickness before service.

t last = The piping wall thickness at time of last inspection.

t previous = The piping wall thickness at time of previous inspection.

t required = the greater value of the pressure design thickness (MAWP) or the structural
minimum thickness.

Version 0. Revised 17 July 2012 17


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Appendix IV - Wall Thickness Calculation

WALL THICKNESS CALCULATION

In case calculation sheet from manufacture is not available, simple formulas for calculation of wall
thicknesses of pressure vessel: Refer to construction codes

Formulas in Terms of Inside Diameter:

PRi
Cylindrical Shell t =
SE−0.6P

PDi
2:1 Ellipsoidal Head t =
2SE−0.2P

Formulas in Terms of Outside Diameter :

PR0
Cylindrical Shell t =
SE−0.4P

PD0
2:1 Ellipsoidal Head t =
2SE+1.8P

Where:

P = Design Pressure or Maximum Allowable Operating Pressure, psig.


Ri = Inside Radius of Cylindrical Shell, inch. Plus corrosion allowance CA (if any)
Di = Inside Radius of 2:1 Ellipsoidal Head, inch.
Ro = Outside Radius of Cylindrical Shell, inch.
Do = Outside Radius of 2:1 Ellipsoidal Head, inch.
S = Maximum Allowable Stress, psi.
= 17,500 psi for A516 Gr. 70 Steel for year 1998 downward
= 20,000 psi for A516 Gr.70 steel for year 1999 upward
= 15,000 psi for A516 Gr. 60 Steel
E = Joint Efficiency.
= 1.00 for full radiographic tested weld vessels.
= 0.85 for spot radiographic tested weld vessels.
= 0.70 for non radiographic tested weld vessels.

Weight of service fluid, weight vessel itself, and external load are not included in this calculation.

When calculate the wall thickness for any rejection of vessel, the inspector shall ensure that the
applicable code is correct to the year of construction and edition. Many factors have been revised for
each edition.

NOTE
If any suggestions from offshore inspectors and Asset Integrity Supervisors, let contact Asset
Integrity Team, Reliability Group, Facilities Engineering Department, Bangkok, Thailand

Version 0. Revised 17 July 2012 18


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Version 0. Revised 17 July 2012 19


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

CML for pressure vessel

Version 0. Revised 17 July 2012 20


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

Vessel dia < 8 (

Typical Cleaning Standards

Class A – Special Inspection Clean.


The object is super cleaning for UT, ECT or MPI inspection. It will be accepted if all the
process fouling and all of the scale is 100% removed only at the position where the UT / ECT /
MPI is being conducted.
Inspection planner to specify these locations in ITP according to the following grades:
A1 Power brush at area required for Inspection
A2 Grit blasting at area required for Inspection
A3 Ultra-High Pressure Water jetting at area required for Inspection
A4 Mill scale removal by Chemical Cleaning at area required for Inspection

Class B – Visual Inspection Clean.


The object is cleaning for visual inspection. It will be accepted if the process fouling and the
scale is approximately 80 % removed
Inspection planner to identify locations required for visual inspection in ITP according to the
following grades:
B1 Hand Brush clean at area required for Visual Inspection
B2 Selective Hydro jetting at area required for Visual Inspection

Class C - Production Clean


The object is light cleaning for production to either clear a blockage or increase the available
flow area. It will be accepted if some mill scale (rust) or some hydrocarbon (coke) and process
fouling can still remain
Operations to specify cleaning requirements according to the following grades:
C1 Hand Brush clean
C2 Rag cleaning
C3 Vacuum Cleaning
C4 Volume water wash (using Fire Hose)
C5 Mechanical scrapers, hand tools
C6 Hydro jetting

Version 0. Revised 17 July 2012 21


CTEP - AIT-P-I-003: Inspection of Pressure Vessel

General Cleanliness Examples:

A1, A2, A3

B1, B2

C6

Version 0. Revised 17 July 2012 22

You might also like