Professional Documents
Culture Documents
Contents
1. PURPOSE …………………………………………………………………………………. 1
2. SCOPE …………………………………………………………………………………….. 1
3. REFERENCE ……………………………………………………………………………… 1
4. DEFINITIONS …………………………………………………………………………….. 2
5. RESPONSIBILITIES ……………………………………………………………................. 3
6. INSPECTION PERSONNEL ……………………………………………………………... 4
7. PROCEDURES ……………………………………………………………………………. 4
7.1 Safety ………………………………………………………………………………... 4
7.2 Preparation and Planning …………………………………………………………... 4
7.3 External inspection ………………………………………...………………………... 4
7.4 Internal inspection ……………………...……………………...……………………...
7.5 Inspection of removed and replacement of vessel components ……...…………….. 4
7.6 Inspection and non-destructive testing……...……………...…………………............... 4
7.7 Pressure vessel repair and alternation……...…...………...……………………………... 4
7.8 Hydrostatic Pressure Testing……...……...………...…………………………... 4
7.9 Final inspection ……...………...………...………...………………………..................... 4
8. RECORDS AND DOCUMENTATION ………………………………………………….. 1
9. APPENDIX
8.1 APPENDIX A CORROSION RATE AND REMAINING LIFE CALCULATION……13
8.2 APPENDIX B MINIMUM RETIRED THICKNESS …………………………………15
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
1. PURPOSE
This procedure provides guidelines for both in-service and out-of-service inspection of various
types of pressure vessels such as separators, drum, columns, towers, and reactors etc. These can
vary greatly in design, fabrication complexity, working conditions and accessibility. However,
inspection frequency is based on risk-based inspection (RBI) criteria included several factors such
as service conditions, operational criticality and availability. The objective of inspection is to
confirm the mechanical integrity of the pressure vessel in order to ensure safe and reliable
operation.
2. SCOPE
This procedure defines inspection requirements and specific responsibilities for internal and
external inspection of existing pressure vessels including separators, drums, columns, towers, and
reactors etc. It applied for all pressure vessel of any metallic material which have been constructed
in accordance with a pressure vessel design code at Chevron Thailand Exploration and Production
Co., Ltd (CTEP) area of operations. The scope of this procedure applies for existing pressure
vessel installed and serviced in operation (Brown field); however, it does not apply for the new
construction (Green field). The inspection frequency of in-service and out-of-service inspection is
also outside the scope of this procedure. This procedure is not a detailed inspection manual, specific
location selective may change on case-by-case basis.
3. REFERENCES
4. DEFINITIONS
Column: Any vertical vessel containing trays, packing or other internals which is used to
separate product fractions.
Reactor: Any vessel containing beds of catalysts used to crack or improve the quality of the
feed product.
External Inspection: An assessment of the conditions of the vessel's external surfaces, such as:
insulation, fire proofing, painting and structures associated with the pressure vessel.
Internal Inspection: This normally refers to, but is not limited to, an assessment of the condition
of the vessel's internal surfaces and components, i.e. shells, heads, welds, internal parts, coating &
linings, cladding, anodes etc.
Condition Monitoring Location (CML): An area of a pressure vessel boundary surface which
has been selected and identified by monitoring shell, head and nozzles thicknesses. Previously,
they were normally referred to as “thickness monitoring location (CML).”
Corrosion Circuit (CC): A term used to describe a zone of a pressure vessel within which the
corrosive conditions are approximately equal, taking into account the corrosive environment
(internally and externally), temperature, pressure, and the constructed material. The Visions4
software also specifies corrosion circuits for inspection and monitoring.
Risk: A combination of the probability of occurrence of pressure vessel failure and magnitude of
the consequence of the failure.
Inspector: Pressure vessel inspectors shall be API 510 certified or authorized by company.
NDT Technician: NDE Technicians who are performing and interpreting non-destructive
examinations must be certified in the method(s) used by one of the following:
• ANST Level I, II or III
• ISO 9712 level I, II or III
• NDT techs pass a CVX test from Practice of NDT Personnel Qualification
Restricted interval (RI): A factor in company computerized inspection records system used
to shorten the length of the thickness measurement inspection interval when there is a potential
for uneven corrosion rates in the circuit/loops.
5. RESPONSIBILITIES
5.1.1 Responsible to implement of the Owner User Program and ensure that resources
are adequate.
5.1.2 Provide necessary qualified people and tools to execute inspection work to follow
the RBI programs.
5.1.3 Responsible for assuring the Authorized Inspector maintains the required
qualifications/certifications. Inspection and nondestructive examination personnel
who perform inspection tasks do not have to be company personnel.
5.1.1 Providing technical support and fit for purpose solutions to the corrosion, inspection,
repair method and integrity challenges.
5.1.2 Evaluating inspection findings and providing evaluation of potential repairs and
replacement.
5.3.1 Performing external and internal inspection of the piping and components in
accordance with this procedure.
5.3.5 Physically identifying CMLs and providing a sketch of the piping marked to indicate
inspection findings and the location of findings.
5.3.7 Providing an inspection report and anomaly report to meeting all requirements in this
procedure.
5.4.1 Maintaining static data, historical data and repair records in Visions4.
5.4.2 Running Visions4 for planning and scheduling of piping system. This will include
generate work order of both inspection and repair scope in CMMS.
5.4.3 Being focal point to conduct Risk Assessment with the RBI group and ETC
Version 0. Revised 17 July 2012 3
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
5.6 Field operation and maintenance (O&M), and Asset team shall be responsible for:
5.6.1 Providing preparation work for pressure vessel inspection such as vessel cleaning,
vessel isolation
5.6.2 Removing insulation for inspection and repairs and re-installing insulation after
inspection and repairs are completed.
5.6.3 Facilitating and Coordinating with all related parties to achieve repair work
efficiently.
6. INSPECTION PERSONNEL
Personnel performing inspection of pressure vessel and vessel components shall be certified in
accordance with Chevron’s written Practice of NDT Personnel Qualification in the SERIP Document.
They should also have at least 3 years of experience in design, construction, repair, operation or
inspection of vessel system and qualify at least level I or higher for UT and level II or higher for other
NDT techniques. API 510 Certified inspectors shall hold valid certificates and recognized by the
Company.
7. PROCEDURE
7.1 Safety
7.1.3 Adequate and proper ventilation, lighting and scaffolding should be provided.
7.1.5 The inspector and NDT examiner shall review the situation of vessel entry, and
follow the safety requirements for all necessary aspects related to the circumstances
of the inspection, including working in confined spaces, working at height,
precautions for H2S, etc.
7.1.6 For an internal inspection, positive isolation (blinds) from all sources of liquids,
gases or vapours shall isolate the vessel. The vessel should be cleaned, ventilated
and gas tested before it is entered. Particular attention should be given to areas
behind weir plates and inside drains and nozzles to ensure they are also thoroughly
drained prior to entry and inspection.
7.2.1 Prior to conducting inspection of pressure vessel, inspector should familiarize with
vessel design, service condition, operating experience and inspection history.
7.2.2 Prior to conducting internal inspection, inspector need to be ensure that proper
cleanliness needs to be carried out.
7.2.3 Besides the need for adequate cleaning of the metal surface, sufficient internal
lighting of the vessel is essential for proper and thorough visual inspection.
7.2.4 Examination/inspection must not take place when the preparation which provided
by Asset team is found to be inadequate.
7.2.6 Safe and adequate means of access to and into the equipment must be provided
7.2.7 It is the responsibility of the inspector to ensure that the vessel has been suitably
prepared for inspection. Particular attention should be given to vessel cleanliness,
access to all necessary locations, and insulation removal where required.
Assessing the condition of the vessel's external surfaces, such as fitting, protective devices,
protective painting, insulation, fire proofing, bolting, sign of leakage, bulging or excessive
dent and structures associated with the pressure by visual inspection
An external inspection of vessels should be carried out periodically whilst the vessel is in
service, preferably preceding a planned shutdown.
External corrosion can be a significant problem, particularly in any local areas where the
protective coating has broken down on uninsulated vessels or where water can
accumulate. Insulated vessels operating in the range -50 deg. C to 150 deg. C or in
intermittent service are particularly prone to external corrosion. For insulated vessels,
damaged or loose fitting insulation cladding will allow the ingress of water so that
corrosion may occur. Corrosion can also be experienced at locations where adequate
draining of any accumulated water in the insulation may not be possible.
A thorough visual inspection of all external surfaces shall be carried out as far as access
and insulation permits. Insulation should be removed in areas selected by the Inspector,
where accelerated corrosion can be anticipated. Known problem areas are at the junction
Version 0. Revised 17 July 2012 5
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
of supporting structures and cowling, insulation or vacuum rings, manholes and nozzles.
o Perform external visual inspection on all external surface of vessel and piping in
the skid as following below
2. Insulated vessel shall be installed inspection ports (IP) to prevent the ingress
of moisture under the insulation. The access port shall be defined as CML.
3. Within the area of CML vessel thickness shall be scanned to obtain the
minimum reading thickness. This reading shall then be recorded as the
thickness value for the CML in VISIONS4.
All internal surfaces, welded seams and heat affected zones including nozzle openings,
should be examined for any signs of discoloration, corrosion, erosion, pitting, cracking,
grooving, scale deposits, sludge accumulation or other defects. The general condition
must be recorded and any areas showing damage, leakage or deterioration must be
investigated and remedial action proposed where applicable.
The inspection should particularly include a re-check of any defects or repairs made
previously, as documented in previous inspection reports.
Any indication of a reduction in wall thickness of the pressure containing part of the
vessel shall be verified by ultrasonic or radiographic testing. The use of photography as a
means of permanently recording areas of interest is recommended. Samples of scale or
Version 0. Revised 17 July 2012 7
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
deposits should be obtained for analysis as and when judged necessary by the Inspector
or advised by the Corrosion Engineer.
Any local deformation of the vessel wall is most probably due to overstressing or
overloading of nozzles by connecting pipe work etc. Internals can be deformed for a
number of reasons, which may be related to the operating conditions.
Accessible surfaces should be checked for deformation or blistering. The primary method
for locating suspected deformation is to direct a flashlight beam parallel to the surface.
Shadows will appear in depressions and on the unlighted side of internal bulges.
Placing a straight edge parallel with the vessel axis against the vessel wall, and using a
steel rule to measure the extent of bulging can also measure local deformation.
The stress resulting from the sudden unequal expansion or contraction of the different parts
of a vessel may cause distortion that can result in cracking. This type of damage is more
likely to occur in austenitic materials such as stainless steel than in ferritic materials like
carbon steel or low alloy steel. If located, the extent and depth of cracking should be
established by NDT methods.
The location and form of any corrosion observed in the vessels should be clearly
identified. Corrosion damage can be classified as:-
b) Those, which can usually be positively identified only with the assistance of
supplementary methods of inspection or through microscopic examination.
• Cracking due to fatigue, creep or environment induced stress corrosion
cracking. These types of cracking are often associated with the weld
heat-affected zone.
• Intergranular corrosion, commonly experienced in stainless steels and
high nickel alloys, and often observed in the heat affected zones of
welds.
• Dealloying (graphite corrosion, dezincification of brass).
In particular, the type and appearance of any scale in the vessel should be noted, as a
possible indication of the type of corrosion damage that has occurred.
Where visual inspection has highlighted areas requiring a more thorough examination by
ultrasonic testing, these should be clearly marked up and reported.
All internal trays, support rings, support lugs, baffles, side sumps and nozzles welded to
the draw-off trays should be inspected for excessive bulges, depression, or any wear and
tear which may need repair. However, at the discretion of the Inspector, only a
representative number of each type of fittings can be selected for a more detailed
inspection. Complex internal fittings designed for specific purposes should be looked at
more critically for cracks and metal loss so that their strength is adequate for their
designated function.
5.3.7 Nozzles
The nozzles, flanged connections and bolting should be inspected for damage/corrosion.
The gasket faces of the flanges that are opened should be inspected to check that they are
in good condition.
Nozzles should be visually examined for bulging, excessive scaling and corrosion, internal
blockages and in particular, plugging in relief valve and instrument nozzles, where present.
Blind flanged nozzles (e.g. utility connection, vent nozzle etc) should be included in the
check for internal corrosion.
Note that nozzles attached to the equipment and water boots may be inspected on-stream
by means of radiography or ultrasonic thickness check, and should be included in the on-
stream inspection programme where appropriate.
Non-metallic coatings are applied to prevent internal corrosion of the vessel, but are
limited in their use by temperature and compatibility with some process fluids.
Metallic linings, in the form of integral cladding, strip lining or weld overlay with a more
corrosion resistant material may also be applied internally to protect the pressure vessel
from aggressive service conditions.
In the event of a coating or lining failure, the pressure vessel may be exposed to conditions
that it was not designed to withstand.
The coating or lining should therefore be carefully checked for any damage, particularly
due to thermal shock or temperature excursion, or separation from the parent metal,
particularly around nozzles and areas where there is a cross-section change. Metallic
corrosion-resistant linings should be examined using PT to check for cracking.
Internal refractory should be inspected for excessive erosion, wear, cracks and damage. If
Version 0. Revised 17 July 2012 9
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
o Clean internal vessel surfaces and vessel internal parts as needed prior to inspection
1) Scale, dirt, hydrocarbon deposits etc. shall be removed so that a thorough and
satisfactory inspection can be achieved.
2) Removal of internal coating, lining, obstructed parts may be required as necessary
o Perform internal visual inspection on all internal surface of vessel and piping in the
skid which includes an examination of all accessible surfaces of the vessel and all
internal parts.
7.5.1 General
A hydrostatic test shall be used to prove the integrity of pressure vessel after
repairs, provided the design of the vessel and supports can accommodate the test.
Hydrostatic testing should be applied carefully and with the knowledge of all
parties involved, since the vessel may be subjected to a stress exceeding its normal
operating stress.
8. Final Inspection
8.1 Upon completion of all required repair work, the vessel shall receive a re-inspection
to ensure the completeness and adequacy of repair and to verify vessel cleanliness prior to closing.
8.2 API Certified Inspector ensure all required inspection activities have been completed as
per inspection test plan (ITP)
The Inspector who has inspected the equipment shall record the findings in VISIONS4. In
this record, the following are required:
• Component history
• Corrosion rate (CR) and remaining life (RL)
• Highlights
• Recommendations, if any
• Thickness measurement, if any.
• All sketches, photographs results and reports of NDT and other
inspection activities
Attachments
Note:
1. UT all nozzle 2” and above
2. Nozzle size 4” & below - 1 Test point
3. Nozzle size above 4” - 2 Test points
4. UT should include level gauge and other appurtenances
Version 0. Revised 17 July 2012 12
CTEP - AIT-P-I-003: Inspection of Pressure Vessel
Examination Checklists
Pressure Vessels: (Including Columns, Reactors, Accumulators, Strippers, Filters, Pots, etc.)
1. Fouling
2. Dished heads
3. Shell
4. Boot
5. Nozzles (blockages)
6. Level gauge legs and other appurtenances.
7. Internals (Baffles, Coating, Cladding, Scallops Expansion rings, Centre screen,
Support rings, Trays, Tray support beams, Packing rings, demister pads, )
8. Welds (internal/external)
9. Vortex breaker (thickness)
10. Insulation
11. Insulation supports
12. Supporting structure
13. Skirts/saddles
14. Hold-down bolts
15. Earthing
16. Heating coils/elements
17. Gasket faces
18. Bolting
19. Ladders/Platforms/handrails
20. Welds (internal/external)
Note:
Delete what components are not applicable to Pressure Vessel being inspected.
Note: This checklist is an additional guide to external inspection covering items that should be
considered during inspection of pressure equipment. The list is not exhaustive, and the inspector
should apply knowledge and experience in the interpretation and application of the inspection
requirements.
Note: This checklist is an additional guide to internal inspection covering items that should be
considered during inspection of pressure equipment. The list is not exhaustive, and the inspector
should apply knowledge and experience in the interpretation and application of the inspection
requirements.
Internal Fouling?
Before cleaning: type
Location
After cleaning
Clad shell/heads:
General corrosion/pitting observed/measured -C.R.
DP inspected
Nozzles/manways:
All inspected
General corrosion/pitting observed/measured
Gasket face condition
Internals:
Trays and supports corroded/damaged
Tray caps corroded, damaged, in place
Demister pads displaced/corroded/fouled
Vessel appurtenances corroded/loose
Vessel packing intact/fouled
Impingement plates corroded/eroded – check welds for cracking
Internal lines hammer tested
Pressure test:
Statutory??
After repairs/modifications
Appendix III – Corrosion Rate (CR) and Remaining Life (RL) Calculation
tinitial −tlast
LT corrosion rate =
time (year)between tlast and tinitial
tprevious −tlast
ST Corrosion rate =
time (year)between tlast and tprevious
tlast −trequire
Remaining life =
Selected corrosion rate
The selected corrosion rate shall be determined from the maximum value whether LT or ST, that best
reflects the current process.
Where:
t initial = The piping original wall thickness before service.
t required = the greater value of the pressure design thickness (MAWP) or the structural
minimum thickness.
In case calculation sheet from manufacture is not available, simple formulas for calculation of wall
thicknesses of pressure vessel: Refer to construction codes
PRi
Cylindrical Shell t =
SE−0.6P
PDi
2:1 Ellipsoidal Head t =
2SE−0.2P
PR0
Cylindrical Shell t =
SE−0.4P
PD0
2:1 Ellipsoidal Head t =
2SE+1.8P
Where:
Weight of service fluid, weight vessel itself, and external load are not included in this calculation.
When calculate the wall thickness for any rejection of vessel, the inspector shall ensure that the
applicable code is correct to the year of construction and edition. Many factors have been revised for
each edition.
NOTE
If any suggestions from offshore inspectors and Asset Integrity Supervisors, let contact Asset
Integrity Team, Reliability Group, Facilities Engineering Department, Bangkok, Thailand
A1, A2, A3
B1, B2
C6